This is a Pre-Bid Meeting Summary and Addendum #1 for the O'Neil Building Chiller Replacement project issued by the State of Delaware, Office of Management and Budget (OMB), Division of Facilities Management. The project involves the complete demolition and replacement of an existing chiller system serving the Margaret M. O'Neil Building and Supreme Court Clerk buildings located at 410 Federal Street in Dover, Delaware, in Kent County. The scope includes HVAC systems, electrical work, concrete work, and commissioning activities. A mandatory pre-bid meeting was held on May 27, 2026, at 9:30 a.m. at the Haslet Armory, Room 133, in Dover, with a building walkthrough conducted immediately following the meeting. Sealed bids are due electronically through the Bonfire Portal by 1:00 p.m. on June 18, 2026, with public bid opening at 2:00 p.m. that same day. Written questions must be submitted by 4:00 p.m. on Monday, June 8, 2026. The contract will be awarded to the lowest qualified bidder and executed on the AIA Document A101-2017 standard form agreement supplemented by state-specific modifications.

Each bidder must include a signed Affidavit for Bidder certifying compliance with OMB Regulation 4104 regarding mandatory drug testing programs for employees on large public works projects. Bids must be accompanied by bid security equal to ten percent of the bid amount plus all additive alternates, and the successful bidder must furnish performance and payment bonds each equal to 100 percent of the contract price upon execution. Contract documents are available from DEDC, LLC for a non-refundable fee of $100.00 per paper set or $25.00 per electronic set. The project includes a $20,000 contingency allowance for miscellaneous items discovered during construction, with remaining funds credited to the Owner at closeout. Bidders must identify three subcontractor categories—Mechanical, Electrical, and Controls—with full names and addresses on the bid form; no substitutions are permitted without written consent from the awarding agency. All bidders must comply with Delaware prevailing wage requirements for Kent County, and the General Contractor must provide a full-time superintendent or working foreman throughout construction. Progress meetings will be held every two weeks, with contractors required to submit a full schedule before work begins and a three-week look-ahead schedule at each meeting.

View the file

Other files

File Type Posted
OMB-MC1002000958-wages.pdf PDF
OMB-MC1002000958-rfp.pdf PDF
OMB-MC1002000958-dwgs..pdf PDF
OMB-MC1002000958-specs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-BID MEETING SUMMARY

O’NEIL BUILDING

CHILLER REPLACEMENT

OMB/DFM# MC1002000958

ADDENDUM #1

ATTENDEES:

See attached sign in sheet.

GENERAL STATEMENT:

A. The Mandatory Pre-bid meeting was held at the Haslet Armory in Rm. 133 at 122 Martin Luther King

Blvd. S., Dover, DE 19901, at 9:30 AM on Wednesday May 27, 2026.

ITEMS DISCUSSED:

A. Key dates

1. Bid Due – June 18, 2026 at 1:00 P.M. by way of the Bonfire Portal as described in the invitation to bid.

2. Bid Opening – June 18, 2026 June 18, 2026 at 2:00 p.m. in the Haslet Armory, 122 Martin

Luther King Jr. Blvd. South in Conference Room 133.

3. Questions deadline is Monday June 8, 2026 at 4:00 PM. All questions must be submitted in writing and E-mailed to mlano@dedc-eng.com and bkrinsky@dedc-eng.com. Phone calls will not be accepted.

B. Key topics

1. Bids

a. The contractor must use the bid bond and bid form supplied in the project manual.

b. Each bidder shall include a signed Affidavit for the Bidder certifying compliance with

OMB Regulation 4104 - “Regulations for the Drug Testing of Contractor and Subcontractor Employees Working on “Large Public Works Projects.” “Large Public Works” is based upon the current threshold required for bidding Public Works as set by the Purchasing and Contracting Advisory Council.

c. Contract documents may be obtained at the office of DEDC, LLC, 315 S. Chapel Street Newark, Delaware 19711, phone 302-738-7172, upon receipt of the $100.00 per paper set or $25.00 per electronic set, both non-refundable. Checks are to be made payable to

“DEDC, LLC”.

d. There is a $20,000 allowance to be included in the base bid for use upon the owner’s instructions for any miscellaneous items found during construction. This allowance may only be billed against with the owner’s written approval.

2. Building Access

a. A walkthrough will be conducted immediately following the pre bid.

b. The building will be occupied throughout this project

3. Clarifications

a. All permits required for this effort to be obtained by the contractor.

b. The General Contractor who is bidding the project shall have a full-time superintendent or working foreman during the duration of construction.

c. This is a Delaware Prevailing Wage project (Kent County).

d. There are (3) three subcontractor listings on this project: Mechanical, Electrical, and

Controls. These Subcontractors are identified on the revised bid form included with this addendum.

e. Be sure to list your company name if your company is performing this work.

f. All companies listed must be registered in the State of Delaware to perform this work.

g. Normal work hours are 8:00 a.m. to 4:30 p.m. during the week. Off hours will need to be coordinated with DFM/OMB.

C. Meetings/Scheduling/Shutdowns

1. There will be progress meetings on this project every 2 weeks on a specific day and time, to be determined at the kickoff meeting.

2. Contractor to provide a full schedule before the project is to begin. It is the contractor’s responsibility to ensure all equipment/material lead times meet the project schedule.

3. Contractors shall provide 3 – week look ahead schedule at each meeting to indicate work areas and shutdowns.

4. Any building systems shutdowns must be requested with at least 14 calendar days written request. The State will make every effort to coordinate a reasonable time for shutdowns based on coordination of manpower and critical State Agency activity schedules.

5. For the purpose of providing notice to building occupants, as the work progresses, at least 7 days written notice to the DFM Project Manager is required when the contractor intends to mobilize, re-mobilize, close any area of the building or access to any areas, and/or transition to and/or perform work in a new area of the building. The written notification must include details such as: When will the work start? Where/what areas of the building will be affected?

How long will the area be affected? When will the work in this new area be complete?

D. Addendum #1

1. Pre-Bid Meeting Summary (this document) (2 pages)

2. Sign-In Sheet (2 pages)

3. Revised Bid Form (8 pages)

Summarized By: DEDC, LLC Ben Krinsky Date: May 27, 2026

O’NEIL BUILDING CHILLER REPLACEMENT

MAY 2026 OMB/DFM# MC1002000958

DEDC, LLC BID FORM

24P231 00 41 13 - 1

SECTION 00 41 13

BID FORM

For Bids Due: June 18th 2026 (1:00 p.m.) To: Mr. Glenn Lowman Construction Projects Manager State of Delaware Office of Management and Budget Haslet Armory, 122 Martin Luther King Jr. Blvd. South Dover, Delaware 19901

Name of Bidder:

Delaware Business License No.: Taxpayer ID No.:

(Other License Nos.):

Phone No.: ( ) - Fax No.: ( ) -

The undersigned, representing that he has read and understands the Bidding Documents and that this bid is made in accordance therewith, that he has visited the site and has familiarized himself with the local conditions under which the Work is to be performed, and that his bid is based upon the materials, systems and equipment described in the Bidding Documents without exception, hereby proposes and agrees to provide all labor, materials, plant, equipment, supplies, transport and other facilities required to execute the work described by the aforesaid documents for the lump sum itemized below:

ALLOWANCE

A $20,000 twenty-thousand-dollar allowance shall be provided as part of the base bid of this project to cover miscellaneous items found during construction. Contractor shall use Allowance Authorization Form to document any allowance change orders. At closeout of the Contract, funds remaining in the Contingency allowance will be credited to Owner by Change Order.

Confirmed: __________________________________________________

(Signature)

CHILLER REPLACEMENT O’NEIL BUILDING

OMB/DFM# MC1002000958 MAY 2026

BID FORM DEDC, LLC

00 41 13 - 2 24P231

BID FORM

I/We acknowledge Addendums numbered and the price(s) submitted include any cost/schedule impact they may have.

This bid shall remain valid and cannot be withdrawn for thirty (30) days from the date of opening of bids (60 days for School Districts and Department of Education), and the undersigned shall abide by the Bid Security forfeiture provisions. Bid Security is attached to this Bid.

The Owner shall have the right to reject any or all bids, and to waive any informality or irregularity in any bid received.

This bid is based upon work being accomplished by the Sub-Contractors named on the list attached to this bid.

Should I/We be awarded this contract, I/We pledge to achieve substantial completion of all the work within calendar days of the Notice to Proceed.

The undersigned represents and warrants that he has complied and shall comply with all requirements of local, state, and national laws; that no legal requirement has been or shall be violated in making or accepting this bid, in awarding the contract to him or in the prosecution of the work required; that the bid is legal and firm; that he has not, directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken action in restraint of free competitive bidding.

Upon receipt of written notice of the acceptance of this Bid, the Bidder shall, within twenty (20) calendar days, execute the agreement in the required form and deliver the Contract Bonds, and Insurance Certificates, required by the Contract Documents.

I am / We are an Individual / a Partnership / a Corporation

By Trading as (Individual’s / General Partner’s / Corporate Name)

(State of Corporation)

Business Address:

Witness: By:

( Authorized Signature )

(SEAL)

( Title ) Date:

ATTACHMENTS

Sub-Contractor List Non-Collusion Statement Affidavit of Employee Drug Testing Program Affidavit of Contractor Qualifications Bid Security (Others as Required by Project Manuals)

24P231 00 41 13 - 3

BID FORM

SUBCONTRACTOR LIST

In accordance with Title 29, Chapter 69, Section 6962(d)(10)b of the Delaware Code, the following subcontractor listing must accompany any bid submittal. The bidder must list in each category the full name and address (City & State) of the sub-contractor that the bidder will be using to perform the work and provide material for that subcontractor category. Should the bidder’s listed subcontractor intend to provide any of their subcontractor category of work through a third-tier contractor, the bidder shall list that third-tier contractor’s full name and address (City & State). If the bidder intends to perform any category of work itself, it must list its full name and address. For clarification, if the bidder intends to perform the work themselves, the bidder may not insert “not applicable”, “N/A”, “self” or anything other than its own full name and address (City & State). To do so shall cause the bid to be rejected. In addition, the failure to produce a completed subcontractor list with the bid submittal shall cause the bid to be rejected. If you have more than three (3) third-tier contractors to report in any subcontractor category, print out additional page(s) containing the appropriate category, complete the rest of your list of third-tier contractors for that category, notate the addition in parentheses as (CONTINUATION) next to the subcontractor category and an asterisk (*) next to any additional third-tier contractors, and submit it with your bid.

Subcontractor Category Subcontractor Address (City & State) Subcontractors tax-payer ID # or Delaware Business license #

1.Mechanical

A.

B.

C.

2.Electrical

00 41 13 - 4 24P231

BID FORM (Continued)

3.Controls

24P231 00 41 13 - 5

BID FORM

NON-COLLUSION STATEMENT

This is to certify that the undersigned bidder has neither directly nor indirectly, entered into any agreement, participated in any collusion or otherwise taken any action in restraint of free competitive bidding in connection with this proposal submitted this date to the Office of Management and Budget, Division of Facilities Management.

All the terms and conditions of OMB/DFM# MC1002000958 been thoroughly examined and are understood.

NAME OF BIDDER:

AUTHORIZED REPRESENTATIVE

(TYPED):

AUTHORIZED REPRESENTATIVE

(SIGNATURE):

TITLE:

ADDRESS OF BIDDER:

E-MAIL: ______________________________________________________________

PHONE NUMBER:

Sworn to and Subscribed before me this day of 20 .

My Commission expires . NOTARY PUBLIC .

THIS PAGE MUST BE SIGNED AND NOTARIZED FOR YOUR BID TO BE CONSIDERED.

00 41 13 - 6 24P231

AFFIDAVIT

OF

EMPLOYEE DRUG TESTING PROGRAM

4104 Regulations for the Drug Testing of Contractor and Subcontractor Employees Working on Large Public Works Projects requires that Contractors and Subcontractors implement a program of mandatory drug testing for Employees who work on Large Public Works Contracts funded all or in part with public funds.

We hereby certify that we have in place or will implement during the entire term of the contract a Mandatory Drug Testing Program for our employees on the jobsite, including subcontractors, that complies with this regulation:

Contractor/Subcontractor Name:

Contractor/Subcontractor Address:

Authorized Representative (typed or printed):

Authorized Representative (signature):

Title:

24P231 00 41 13 - 7

AFFIDAVIT

OF

CONTRACTOR QUALIFICATIONS

We hereby certify that we will abide by the contractor’s qualifications outlined in the construction bid specifications for the duration of the contract term.

In accordance with Title 29, Chapter 69, Section 6962(d)(10)b.3 of the Delaware Code, after a contract has been awarded the successful bidder shall not substitute another subcontractor whose name was submitted on the Subcontractor Form except for the reasons in the statute and not without written consent from the awarding agency. Failure to utilize the subcontractors on the list will subject the successful bidder to penalties as outlined in the General Requirements Section 5.2 of the contract.

Contractor Name:

Contractor Address:

Authorized Representative (typed or printed):

Authorized Representative (signature):

Title:

00 41 13 - 8 24P231

THIS PAGE INTENTIONALLY LEFT BLANK

24P231 - Pre Bid Meeting Summary
Bid Results
00 41 13 - Bid Form-2017 Rev 07-21-2020

File details come from the government source that posted it. Updated .