Amendment 01 RFI LOG-Solicitation-Repair Bldg 888.pdf
PDF 110 KB Posted
- Attached to
- W50S8P-20-B-0003 NLZG142008 Repair Bldg 888 Federal contract opportunity
- Solicitation number
- NLZG142008
- Issued by
- Department of the Army National Guard
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name: Repair Bldg 888 Project No. NLZG142008 RFI Log-Solicitation Date: 11-Sep-20
RFI NO. DATE RECEIVED BY EFT SPEC SECTION DESCRIPTION
DATE TO
ENG./OWNER
DATE FROM
ENG./OWNER
DATE TO
CONTRACTOR COMMENTS
001 8/18/2020 061000
On sheets A-102B, A-102C, A-102E, & A-102F, there are numerous metal partition walls that do not have call outs for wall types. What are we to assume these are? 6/21/2018 8/20/2020
Refer to drawing sheets A-102A, A-102B, A-102C, A-102D, A-102E, A-102F, A- 105 (Annotation Floor Plans) and ADD the following FLOOR PLAN GENERAL
NOTES:
1. Refer to Enlarged Floor Plans for additional interior partition type tags.
2. Interior partitions shall be Type A unless otherwise indicated.
3. Interior partitions framed with metal studs (width of 3-5/8” or greater) shall be installed with sound attenuation batt insulation (SAB) for the full height of the stud (Types A, A2, A3, B, B2, C2, C3, D, S, T, U).
002 8/20/2020
Currently, this solicitation is scheduled to be delivered as a hard copy. Given the current COVID-19 social distancing restrictions and couriers not guaranteeing overnight delivery of non-essential packages, would it be acceptable to submit our proposal, including bid bond, electronically? Attached is Class Deviation 2020-O0016. 8/20/2020
We will be having a live bid opening. We have the room to allow 1 representative from each company bring in the bids. The bid bond is still required, it just doesn't need to be notarized or have a seal on the day of bid opening and it can be electronically signed.
003 8/20/2020
If a hard copy of the bid bond is still required, can our proposal be submitted electronically with the original bid bond being delivered within 72 hours of the bid date? 8/20/2020
All Proposals/bid will need to be hard copy in person. Bid bond is still required, just doesn't need to be notarized or have a seal on the day of bid opening and it can be electronically signed.
004 8/20/2020 Please confirm the documents uploaded to beta.sam on 29 July 2020 are the final specs and drawings. 8/20/2020 8/21/2020
The drawings and specs posted on 26JUL20 are the same as what was officially posted on 17AUG20.
005 8/21/2020 01 11 00
Specifications section 01 11 00, 1.8 states that the “Government will install all communication wiring and terminal devices in the existing building”. However, there is a bid breakdown for the installation of communication wiring. Can you please clarify if we need to install the communication wiring?
8/21/2020 8/21/2020
Spec 01 11 00, 1.8 refers to base bid items only such as telecom pathways - ABI-1 Option for Telecommunication Scope includes communications wiring - refer to division 27
006 8/21/2020
01 91 00 Please clarify who is responsible for the commissioning of this project. If the contractor is responsible for the commissioning, please provide specification 01 91 00.15.
8/21/2020 9/4/2020
Bottom line, the GC is responsible for carrying commissioning costs. Our Type C services will include our commissioning agent to help the government facilitate/coordinate the plan of execution as well as to observe the GC’s efforts and to evaluate the performance they deliver. Refer to newly issued Specifications Section 01 91 00.15 provided with this response.
007 8/27/2020
WILL CONRACTORS BE REQUIRED TO GO THROUGH FRONT GATE
SECURITY ON A DAILY BASIS? IF SO, WILL VEHICLES, TRAILERS,
TOOLS PASSING THROUGH THE FRONG GATE BE INSPECTED DAILY?
HOME MUCH GATE CHECK-IN TIME SHOULD BE CONSIDERED ON A
DAILY BASIS? 8/27/2020 8/27/2020
Yes, all contractors are required to enter through the contractor gate and have the vehicles inspected. Daily time will change dependending on how many contractors are working on base. Times vary from 15 min to 1.5 hr in the morning depending o the number of contractors.
008 8/27/2020
WILL WORKER BE ABLE TO LEAVE AND RE-ENER THE BASE
THROUGHOUT THE DAY? IF SO WILL THEY BE SUBJECT TO
REPEATING THE FRONT GATE CHECK-IN PROCESS? 8/27/2020 8/27/2020
Yes the workers are able to leave and re-enter the base throughout the day.
Contractor lane is open between the hours of 7:00 AM to 3:00 PM. Always required to repeat the check-in process. Times should be 15 minutes or less after 08:30 AM for check-in.
009 8/27/2020 0 14 00
WILL ANY AREAS OF THE BUILDING BE ACCUPIED DURING
SCHEDULED CONSTRUCTION? IF SO, WHICH AREAS WILL BE
OCCUPIED AND DURING WHAT TIMES? 8/27/2020 8/27/2020
See spec section 0 14 00 1.2 paragraph b. The areas listed as not in scope on drawing A-100 in areas "A" and D" will be occupied for the duration of construction during normal business hours.
010 8/27/2020
CLINs 0003 and 0004 states the following “Paragraphs noted below are inclusive of all subparts unless otherwise noted.” There are no paragraphs following that sentence for either CLIN. Please provide the paragraphs for both CLINs. 8/27/2020
No addiitonal info availiable. Chart of included specification are given, if additional clarification is needed please ask.
011 9/2/2020
Level 1 Antiterrorism Awareness Training Will this training be required for all workers on the site?
How much time is allotted for the training and what will the cost be?
9/2/2020 9/2/2020 Training is required for all workers. Training is on-line and takes about an hour. No cost for training.
Prepared by EFT Architects, Inc. Page No.1
RFI Log-Solicitation Date: 11-Sep-20
RFI NO. DATE RECEIVED BY EFT SPEC SECTION DESCRIPTION
DATE TO
ENG./OWNER
DATE FROM
ENG./OWNER
DATE TO
CONTRACTOR COMMENTS
012 9/2/2020
Do we provide our own background checks and submit the results, or do they need to be completed at Rickenbacker?
If they are completed at Rickenbacker, what is the cost for the background check?
9/2/2020 9/2/2020
No cost for background checks. Will be provided a form to be filled out with Name, SS#, and Driver Licence #, that will be sent to our local Security Forces who will perform the NCIC background check.
013 9/2/2020
Sheet A-202 C2 & B2, at the new louvres to be cut in L-1 thru L-8, clarify the wa composition.
S101B and S101E both call for new louvres in existing CMU above Sheet A-351 cuts A4 reflects existing masonry to the height of 16’ 10”, cut A3 & A5 reflects no masonry
9/2/2020 9/2/2020 See Original 1953 Drawing A-6 and S-16 for elevations. These drawings are acurate showing structural steel, masonry and windows.
014 9/4/2020 23 09 23 Who is the controls manufacturer. DWGs M-701 thru M-801 9/4/2020 9/4/2020
Manufacturer will be decided by the building management controls sub-contractor's submittal. It shall meet the requirements in Spec section 23 09 23. The current Base wide system is Johnson Control's which the new system will need to integrate with. Drawing M-001 notes 53 and 54.
015 9/4/2020 Drawing MH101D Note #13 calls for an HVAC emergency shutdown switch. Is this part of controls? 9/4/2020 9/4/2020
Yes the automatic shutdown is part of the control contractor's responsibilty.
Besides the loation on drawing MH101D they should be located as described in the following. See FA drawings for LOC locations.
Locate the shutoff switch (or switches) to be easily accessible by building occupant by locating them similarly to building mass notification system (MNS) local operating consoles (LOC) (see UFC 4-021-01 for additional information on MNS LOCS) so that the travel distance to the nearest shutoff switch will not be in excess of 200 ft. (61 m). Ensure that the shutoff switches are well labeled, and of a different color than fire alarm pull stations.
016 9/4/2020 Detail A1 on M-503, what matereial is the fume hood made of? 9/4/2020 9/4/2020 16 ga steel, continuous welded seems, all fume hood exhaust ductwork to hav continuous welded seams.
017 9/4/2020
On the drawing sheet T-101E, on key # T20 it references SIPR (under th specifications legend it requires SC Fiber optic jack). Does that mean T20 on sheet T101E will require fiber drop along with 2 data and 1 voice? 9/4/2020 9/4/2020 Provide (4) Cat6 data drops only. Red Cat6 cable for SIPR.
018 9/4/2020 27 10 00 All the outlets that require fiber drops, what type of fiber are required? 9/4/2020 9/4/2020 Delete fiber drops, and add Red Cat6 cable drops instead.
019 8-Sep-20 Drawing E-601 Electrical-One-Line Diagram-Rev.0
On drawing E-601 Electrical-One-Line-Diagram-Rev.0 there is a designation for Panel LP2C, but there is no panel schedule listed on the panel schedule drawings. Please provide panel schedule for panel LP2C. 9/9/2020
020 8-Sep-20 Drawing E-601 Electrical-One-Line Diagram-Rev.1 Please provide a circuit schedule for the central inverter. 9/9/2020
021 8-Sep-20 Drawing E-601 Electrical-One-Line Diagram-Rev.2
Please provide location for the “MTS” 200A Heavy Duty Double-Throw Fused disconnect. 9/9/2020
022 8-Sep-20 Drawing E-601 Electrical-One-Line Diagram-Rev.3 Please provide location for the Generator Connection Box. 9/9/2020
023 8-Sep-20
ES101-ELECTRICAL-SITE-
PLAN-Rev.0
Key Note E50 states “Reconnect power to existing break area.” What is required for this? Does this location have a number designation? 9/9/2020
This is an outdoor pavillion with outlets, lights, and ceiling fans. There is no numbe designation for the pavillion. There are (3) 120V 20A circuits.
024 8-Sep-20 Key Note E49 states “Reconnect power to this existing building.” Please provide location of the existing power conduit and or disconnect for this building. 9/9/2020
There is an existing pull box on the outside of building 888 directly across from the building in question. It has a 3PH 208/120V 200A panel.
025 8-Sep-20 26 51 00
The following drawings have key notes that refer to flood lighting controls. What is required for these controls? EL101A-FIRST-FLOOR-ELECTRICAL- LIGHTING-PLAN---AREA-A-Rev.0 EL101F-FIRST-FLOOR-ELECTRICAL-LIGHTING-PLAN---AREA-F-Rev.0 – Key note L8 refers to the location, but I cannot find the location on the drawing.
9/9/2020
These will require bi-level controls. Low level lighting when no occupancy detection/ high level when ocupancy detected. Connected to Building Automation System for time control and also a photo-cell. Refer to Spec section 26 51 00 subsection 2.5 for lighting controls.
Prepared by EFT Architects, Inc. Page No.2
RFI Log-Solicitation Date: 11-Sep-20
RFI NO. DATE RECEIVED BY EFT SPEC SECTION DESCRIPTION
DATE TO
ENG./OWNER
DATE FROM
ENG./OWNER
DATE TO
CONTRACTOR COMMENTS
026 8-Sep-20
The following drawings all have key notes that state that we are supposed to provide new homerun conductors and install a GTD-20 transfer switch for each circuit to accommodate the new inverter circuits.
EL101A-FIRST-FLOOR-ELECTRICAL-LIGHTING-PLAN---AREA-A-Rev.0 EL101B-FIRST-FLOOR-ELECTRICAL-LIGHTING-PLAN---AREA-B-Rev.0 EL101C-FIRST-FLOOR-ELECTRICAL-LIGHTING-PLAN---AREA-C-Rev.0 EL101D-FIRST-FLOOR-ELECTRICAL-LIGHTING-PLAN---AREA-D-Rev.0 EL101E-FIRST-FLOOR-ELECTRICAL-LIGHTING-PLAN---AREA-E-Rev.0 How many circuits are there? 9/9/2020
EL101A (2) 2-pole 208v circuits EL101B (1) 2-pole 208v circuit EL101C (3) 277v circuits EL101D(3) 277v circuits EL101E Same circuits as EL101C
027 8-Sep-20 23 09 00
Currently Rickenabcker ANG buildings utilize Johnson Controls for temperature controls and tie to a JCI Metasys server for monitoring. Current spec calls for Tridium which would allow for 888 to have a temperature controls installation different from other locations in the base complex.
Please confirm Tridium is acceptable?
11-Sep-20 9/11/2020 Yes, Tridium or one of it's licensed vendors is acceptable and required by the Specifications.
028 8-Sep-20 M-001 If acceptable, is a tie in required from the Tridium system at the 888 location to the existing JCI Metasys server? 9/11/2020 9/11/2020
Per drawing M-001 general note 53 the BAS system at Building 888 needs to communicate with the JCI front end.
029 10-Sep-20 M-001
Who is the current EMCS provider and what type of front-end is it? The spec calls for a Niagara system but on Sheet M-001 General Note 53 says we need to integrate to the JCI Front End.
11-Sep-20 9/11/2020 The new BAS system for Buildg 888 needs to tie into the Johnson's Control Metasys front end.
030 10-Sep-20 23 09 00/ 23 09 23.02
How should the system be integrated – do we need to serve the points via BACnet/IP and leave out the graphics or include the graphics, who will bring our controls into the front end? For example (if it is JCI) do we need to hire them to integrate the front end or get a quote for them to do the graphics?
11-Sep-20 9/11/2020
The BAS controls system at Building 888 should be able to act as a stand alone system; graphics will be loaded on the Niagra (Tridium) system. The Controls contractor is responsible for connecting the BAS for Building 888 to the front end.
Refer to the specifications 23 09 00 and 23 09 23.02 on what is required to be seen on the front end. The Government does not have input as to what contractor is hired to do the work.
031 07 05 23
Specification section 07 05 23 specifies air barrier testing. Specification Section 07 27 10.00 10 is the specification section for the air barrier system but there is no air barrier system specified. The words “air barrier” are not shown on the drawings and the details don’t show a continuous air-tight system. Please indicate on the drawings what the air barrier system consists of and change details to provide a continuous air barrier system or remove the air barrier testing requirements from the specifications.
032 10-Sep-02 09 06 00 Section 09 06 00, paragraph 2.2.1.1 says the wall panels are to match existing What is existing? 11-Sep-20 9/11/2020
There is no available information on the existing exterior wall panels. Pictures wer allowed during the pre-bid site visit.
033 10-Sep-20 01 32 01
Project specifications make references to building commissioning (01 32 01.00 10 par. 3.3.4.j, 01 33 29 par. 1.6.1, 14 24 23 par. 3.3, for example); however, no commissioning specifications are provided. If commissioning is to be performed, please provide commissioning specifications. 11-Sep-20 9/11/2020 See RFI 006 response
034 11-Sep-20
• Who is the current EMCS (BAS) provider and what type of front-end is it? The spec calls for a Niagara system but Sheet M-001 General Note 53 says we need to integrate to the JCI Front End. If it is a JCI front end is it FX (Niagara) or Metasys? 11-Sep-20 The EMCS is Johnson's Controls Metasys
Prepared by EFT Architects, Inc. Page No.3
RFI Log-Solicitation Date: 11-Sep-20
RFI NO. DATE RECEIVED BY EFT SPEC SECTION DESCRIPTION
DATE TO
ENG./OWNER
DATE FROM
ENG./OWNER
DATE TO
CONTRACTOR COMMENTS
035 11-Sep-20 23 09 00 / 23 09 23.02
• How should the system be integrated – do we need to serve the points via BACnet/IP and leave out the graphics? Or do we include the graphics? We have the capability to integrate to an open Niagara Supervisor (Front End) but if it is Metasys then we would need JCI to bring in the controls and most likely do the graphics. 11-Sep-20
The graphics are required on the Niagra system. Refer to the specifications 23 09 00 and 23 09 23.02 on what is required to be seen on the front end.
Prepared by EFT Architects, Inc. Page No.4