N6945022Q0005U0002 - RFQ Harlingen NOSC Amendment.pdf

PDF 113 KB Posted

Attached to
NOSC Harlingen Hurricane Damage Repairs
Solicitation number
N6945022Q0005
Issued by

View the file

Other files

File Type Posted
U0002- RFQ Harlingen NOSC PPI.pdf PDF
U0002 - RFQ Harlingen NOSC SOW PICTs Added.pdf PDF
PH 26 Harlingen.jpg JPG image
Combined Utilities.pdf PDF
PH 25 Harlingen.jpg JPG image
PH 09 Harlingen.jpg JPG image
PH 12 Harlingen.jpg JPG image
Water.pdf PDF
Wastewater.pdf PDF
PH 16 Harlingen.jpg JPG image
Electrical.pdf PDF
PH 23 Harlingen.jpg JPG image
PH 22 Harlingen.jpg JPG image
PH 01 Harlingen.jpg JPG image
PH 08 Harlingen.jpg JPG image
PH 02 Harlingen.jpg JPG image
PH 17 Harlingen.jpg JPG image
PH 15 Harlingen.jpg JPG image
Natural Gas.pdf PDF
PH 04 Harlingen.jpg JPG image
PH 27 Harlingen.jpg JPG image
PH 05 Harlingen.jpg JPG image
PH 13 Harlingen.jpg JPG image
PH 24 Harlingen.jpg JPG image
PH 21 Harlingen.jpg JPG image
PH 19 Harlingen.jpg JPG image
PH 11 Harlingen.jpg JPG image
PH 28 Harlingen.jpg JPG image
PH 14 Harlingen.jpg JPG image
PH 03 Harlingen.jpg JPG image
N6945022Q0005U0001 RFQ Harlingen NOSC Amendment .pdf PDF
PH 18 Harlingen.jpg JPG image
PH 20 Harlingen.jpg JPG image
PH 06 Harlingen.jpg JPG image
PH 10 Harlingen.jpg JPG image
PH 07 Harlingen.jpg JPG image
N6945022Q0005 NOSC Harlingen Hurricane Repairs.pdf PDF
N6945022Q0005 NOSC Harlingen Hurricane Repairs_All Attachments Combined A_ H_12JUL2021.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5901605

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The reason for this amendment is to:

1.) Include the government’s response to RFI’s / PPI’s

2.) Provide additional pictures as requested

3.) Provide an extension date on the RFQ to 25 FEB 22 Close of Business (COB) 1700 Eastern Standard Time (EST)

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 17-Feb-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6945022Q0005

X 9B. DATED (SEE ITEM 11)

05-Jan-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-Feb-2022

CODE

NAVFAC ENGINEERING SYSTEMS COMMAND SE

PWD CORPUS CHRISTI

8851 OCEAN DRIVE, BLDG 19

CORPUS CHRISTI TX 78419-5021

N69450 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

kimberly.drymala@navy.milEMAIL:(504)862-1214TEL:

KIMBERLY DRYMALA / CONTRACT SPECIALIST

N6945022Q0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

(End of Summary of Changes)