N6893618R0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 23-Jul-2018 03:00 PM to 30-Jul-2018 03:00 PM.
The following have been added by full text:
AMENDMENT 03 COMMENT
Upon reviewing the specifications, the following drawings/documents were inadvertently omitted:
| Item |
| Drawing Number |
| Description |
| 2 |
| 1609AS102 |
| EXTRUSION, LOWER, SIDE |
| 19 |
| 1609AS130 |
| EXTRUSION, UPPER |
| 4 |
| 3145AS121 |
| EXTRUSION, I-BEAM |
| 104 |
| 3145AS125 |
| SCREW, SPECIAL |
| 96 |
| 3145AS129 |
| MOUNTING PLATE |
| 13 |
| 3931AS104 |
| BLOCK, GROUND |
| 64 |
| 3931AS115 |
| CUSHION, SIDE, CENTER |
Amendment 03 adds the above documents to the solicitation and extends the deadline for proposals to 30 July 2018 at 3:00 pm (Pacific). Please note that Section J Attachment 2- Combined Sub-Component Drawings (Rev 01) now has 71 pages and previously had 51 pages.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been modified:
ATTACHMENTS
Exhibit/Attachment Table of Contents
| DOCUMENT TYPE | | DESCRIPTION | | PAGES | DATE |
| Exhibit A | CDRLs | 2 | 5/29/2018 | | |
| Attachment 1 | 3941AS100H Drawing | 12 | 5/9/2018 | | |
| Attachment 2 | Combined Sub-Component | 71 | 7/17/2018 | | |
Drawings (Rev 01)
Attachment 3 Tech Spec-PHST-185 10 5/9/2018
Attachment 4 Missile Containers- Spares 1 5/14/2018 Breakdown