Past Performance Survey

View the file

Other files for this federal contract opportunity

Other files attached to Aegis Ballistic Missile Defense Engineering Services, newest first.
File Type Posted
14-R-0025-0001_RFP_Solicitation_Amendment.docx DOCX document
14-R-0025_RFQ_Solicitation.docx DOCX document
Government_Furnished_Property_Spreadsheet.xlsx XLSX spreadsheet
Contract_Data_Requirements_List.docx DOCX document
Workforce_Qualifications_Spreadsheet.xls XLS spreadsheet
Government_Furnished_Property_List.pdf PDF
Cost_Summary_Format.xls XLS spreadsheet
NAVAIR_Standard_Labor_Categories.pdf PDF
CPARS_Update_Questionnaire.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N68936-14-R-0025

Past Performance Survey Attachment (8)

PAST PERFORMANCE SURVEY COVER SHEET

Name of offeror survey is being completed for: _________________________________________________

Name of company (Contracting Officer) completing survey: ________________________________________

Contract Number: _________________________________________________________________________

Name, title and phone number of person completing survey: _______________________________________

Length of time your company has been involved with the offeror: __________________________________

SUBMIT PAST PERFORMANCE COVER SHEET AND SURVEY BY: (provided by offeror) __________________________________________________________________________________________

SCOPE OF INFORMATION TECHNOLOGY/CYBER SECURITY FOLLOW-ON CONTRACT

The scope of this effort encompasses engineering services to be provided to the Naval Air Warfare Center Weapons Division (NAWCWD), Point Mugu, CA. The contractor shall provide support for Test and Evaluation (T&E) and systems engineering activities related to Aegis Ballistic Missile Defense (BMD) Program. Tasking includes Operations Research Support, Physics Analysis, Test Plans and Procedures, Test Data Collection Analysis and Test Data Review, Test Monitoring and Real-Time Mission Conduct Support, Technical Management Support, technical reports and briefing preparations.

PAST PERFORMANCE SURVEY RATING SHEET

RATING SCALE

Please use the following ratings to answer the questions. If you are unable to rate an item because it was not a requirement, never an issue, or you have no knowledge of the item in question, then you should mark Neutral.

EVALUATION CRITERIA

Very Low (VL): Based on the offeror's experience or past performance, essentially no doubt exists that the offeror will successfully perform the required effort.

Low (L): Based on the offeror's experience or past performance, little doubt exists that the offeror will successfully perform the required effort.

Moderate (M): Based on the offeror's experience or past performance, some doubt exists that the offeror will successfully perform the required effort.

High (H): Based on the offeror's experience or past performance, substantial doubt exists that the offeror will successfully perform the required effort.

Very High (VH): Based on the offeror's experience or past performance, extreme doubt exists that the offeror will successfully perform the required effort.

Unknown (UNK): No performance record identifiable. This only applies to past performance.

NOTE:

For statements indicating “Very High” or “Very Low”, please provide a brief explanation in the comments section of the survey.

RATING
FACTOR

1. RELEVANCY

a. Did the Contractor successfully perform on similar contracts with respect to scope and complexity?

b. Did the Contractor maintain continuity of key personnel?

c. Did the Contractor maintain continuity of technical personnel?

d. Did the Contractor maintain continuity of teaming arrangements and subcontractors?

e. Did the Contractor implement controls and systemic improvements to resolve previous or present problems? If so, please provide an example.

2. PRODUCT AND SERVICE QUALITY:

a. Did the Contractor continuously exceed service requirements?

b. Did the Contractor utilize personnel that were appropriate to the effort performed?

c. Did the Contractor comply with technical or functional requirements? If not discuss systemic improvements or actions taken to improve quality.

d. Did the Contractor demonstrate effective management over the effort performed?

e. Did the Contractor demonstrate quality acquisition management (e.g., purchasing system)?

f. Did the Contractor hire and retain a quality overhead support staff?

RATING
FACTOR

3. PRODUCT AND SERVICE PERFORMANCE:

a. Did the Contractor perform the effort within established contract requirements, level-of effort, specifications, and standards?

b. Rate the Contractor’s performance in supporting integration and/or testing on new hardware and software into an existing environment.

c. Rate the Contractor’s performance in the following areas:

1. Studies, Analyses and Assessments

2. Project Planning, Technical Reviews, and Documentation for Information Technology (IT) Systems

3. Software Development

4. Information Technology Services

5. Data and Information Handling, Data Management, and Administration

6. Configuration/Data Management and IT Systems

7. Quality Assurance/Quality Control of IT Systems

8. Corporate Business Services

9. Test Support Services

10. Management of Sensitive and Secure Data and Systems

d. Did the Contractor maintain an effective small/small disadvantaged business subcontracting program?

e. Did the Contractor present information and correspondence in a clear, concise, and businesslike manner?

4. DELIVERY SCHEDULE PERFORMANCE:

a. Were the products and/or services required completed in a timely manner and in accordance with delivery schedules/period of performance of the orders/contract? If not, explain systemic improvement actions taken to correct the problem/s.

b. Was the Contractor was responsive to technical and/or contractual direction?

c. Did the Contractor submit data deliverables on a timely basis? If not, please explain.

d. Did the Contractor submit accurate invoices on a timely basis? If not, please explain.

e. Did the Contractor make timely award to, and demonstrate effective management of its subcontractors?

RATING
FACTOR

5. COST/PRICE PERFORMANCE:

a. Did the Contractor estimate and perform efforts within contract costs?

b. Were the Contractor’s rates competitive to market prices for the duration of the order/contract?

c. Did the Contractor demonstrate cost efficiencies in performing the required effort?

d. Did the actual costs/rates realized closely reflect the negotiated costs/rates?

e. Did the Contractor submit accurate and timely cost/price reports?

f. Did the Contractor effectively control indirect costs? If not, explain.

g. If costs were exceeded or prices adjusted, were there systemic improvement actions taken and current controls now in place to prevent future recurrences?

6. SYSTEMIC IMPROVEMENT:

a. Did the Government benefit from the Contractor’s systemic approach to supply quality products/services and did they make continuous improvements to the critical process of the organization.

b. Did the Contractor provide timely and accurate problem tracking, reporting, and maintenance documentation?

c. Did the Contractor cooperate with the Government in providing flexible, proactive, and effective recommended solutions to critical issues?

d. Did the Contractor maintain an open line of communication so that the Government was apprised of technical, cost, and schedule issues?

e. Was the Contractor able to perform with minimal or no direction from the Government?

RATING
FACTOR

7. Customer Satisfaction:

a. The products/services provided adequately met the needs of the program.

b. The Contractor was able to perform with minimal or no direction from the COR or the TPOC.

c. I am satisfied with the performance of the Contractor under this effort.

8. Key Personnel:

a. The labor turnover in key personnel labor categories was minimal and did not adversely affect Contractor performance.

b. The Contractor proposed qualified personnel to fulfill the requirements of the contract.

ADDITIONAL COMMENTS: