About this file
This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract (Amendment 0002) for solicitation N6264925RA038, issued by NAVSUP Fleet Logistics Center Yokosuka for maintenance work on the PSNS Barge YR-85. The amendment extends the proposal submission due date from 14 April 2025 to 22 April 2025, both at 1000 Japan Standard Time, and provides an updated Task Group Instruction (TGI) in response to a contractor's question about a specific location number or notation.
The amendment includes modifications to Section J, listing updated Task Group Instructions for Corrective Maintenance (CM) and Preventative Maintenance (PM) Work, with numerous document codes being updated or revised. The solicitation is specifically for maintenance work to be performed from 3 June 2025 through 30 September 2025 at a government facility, and is restricted to sources authorized to operate and do business in Japan. Potential offerors must request access to the detailed work specification package through DoD SAFE by 27 March 2025, with access links valid for 14 days after issuance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6264925RA038-0001.pdf | ||
| Attachment IV Contract Data Sheet.pdf | ||
| Attachment III Request for Information Form.pdf | ||
| Attachment II Proposal Breakdown Form N6264925RA038.xlsx | XLSX spreadsheet | |
| N6264925RA038.pdf | ||
| Attachment V GFP-GFM listings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N6275825RCBYR85
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of AMENDMENT 0002 is described below :
1. To provide updated TGI 38HVA51202A01-c1v0 as a government's response to the contractor's question regarding this RFP. Please refer to the continuation page and attached updated TGI for details.
2. To extend proposal submission due date from 14 Apr 2025, 1000 Japan Standard time to 22 Apr 2025, 1000 Japan Standard time.
All other information remains unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 11-Apr-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6264925RA038
X 9B. DATED (SEE ITEM 11)
13-Mar-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
11-Apr-2025
CODE
NAVSUP FLC YOKOSUKA
(CODE 200)
CONTRACTING DEPARTMENT
PSC 473 BOX 11
FPO AP 96349-0011
N62649 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6264925RA038
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTION AND ANSWER
Below is the question received and the response:
Question) 38HVA51202A01 para 1.3.1.9 indicates ES 01-48-2 ... Frame 48 Stbd.
We think either location number or "Stbd" is incorrect.
Is it possible to confirm?
Government Answer) Please see updated TGI 38HVA51202A01-c1v0 as a government respose.
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 14-Apr-2025 10:00 AM to 22-Apr-2025 10:00 AM.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been modified:
SECTION J
SECTION J
SECTION EXHIBITS AND OTHER ATTACHMENTS
Attachment (I) TGI (Task Group Instructions)
CORRECTIVE MAINTENANCE (CM) WORK
38HVA16702A01_c0v0 38HVA51406A01_c1v1 38HVA53301A01_c0v1
38HVA17902A03_c2v2 38HVA51407T01_c0v0 38HVA58202A01_c0v0
38HVA51404A01_c0v0 38HVA51407A01_c0v0 38HVA61202A01_c0v0
38HVA51406T01_c0v0 38HVA53301T01_c0v0 38HVA63101A01_c0v0
PREVENTATIVE MAINTENANCE (PM) WORK
38HVA16701A01_c0v0 38HVA51201A01_c1v1 38HVA55102A01_c0v0
38HVA17901A01_c0v0 38HVA51202A01_c1v0 38HVA55301A01_c1v1
N6264925RA038
38HVA32101A01_c0v0 38HVA51203A01_c0v0 38HVA55302A02_c1v1
38HVA32102A01_c0v0 38HVA51204A01_c0v0 38HVA55502A01_c0v0
38HVA32402A01_c0v0 38HVA51401A01_c1v1 38HVA58201A01_c0v0
38HVA43601A01_c0v0 38HVA51402A01_c1v1 38HVA61201A01_c0v0
38HVA43602A01_c0v0 38HVA52801A01_c0v0 38HVA62301A01_c0v0
38HVA43603A01_c0v0 38HVA52802A01_c0v0
Attachment (II) Proposal Breakdown Form (Contractor Response Required) Attachment (III) Request for Information Form Attachment (IV) Contract Data Sheet
Attachment (V) Government Furnished Property (GFP-GFM listings)
EXHIBIT (A) Contract Data Requirements List (CDRL)
(End of Summary of Changes)