This document contains a risk assessment template and example for a Navy program called Sailor 2025 - Ready Relevant Learning. The risk assessment identifies insufficient access to fleet and schoolhouse subject matter experts during analysis, design, development, and testing phases as a key risk that could result in delayed contractor deliverables, analysis outputs, and content conversion. The risk is rated as high likelihood and moderate consequence initially. Plans to mitigate the risk include coordinating with schoolhouse staff and fleet experts before and during acquisition phases, as well as holding risk working group meetings. The Naval Air Warfare Center Training Systems Division is listed as the risk owner.

View the file

Other files for this federal contract opportunity

Other files attached to FY21 Content Conversion Draft Solicitation, newest first.
File Type Posted
Atch (1)_APPENDIX H Sailor 2025 RRL Use of Blooms Taxonomy Action Verbs - 06 Dec 2019.odt ODT document
Atch (L-7) DO Pricing Form.xlsx XLSX spreadsheet
Atch (1)_APPENDIX G Sailor 2025 RRL Operational Engaging Instructional Strategies - 06 Dec 2019.docx DOCX document
Atch (1)_APPENDIX C Terms and Definitions - 16 Jan 2020.docx DOCX document
Exhibit F_FY21 RRL CONTENT CONVERSION (F00X) Training CDRLs - Draft 10 Feb 2020.odt ODT document
Atch (1)_APPENDIX K S2025 xAPI Requirements - 06 Dec 2019.docx DOCX document
Atch (1)_APPENDIX I Sailor 2025 RRL Content Conversion Media Type Characteristics - 06 Dec 2019.odt ODT document
Atch (L-2) Vol 1 T-1 SB Goals.xlsx XLSX spreadsheet
Draft N61340-20-R-0037.docx DOCX document
Atch (1)_APPENDIX M NETC RRL Video Streaming Guidance - 06 Dec 2019.odt ODT document
Atch (1)_APPENDIX L NETC RRL Single User Gaming and Simulation Guidance - 06 Dec 2019.odt ODT document
Atch (L-8)_Past_Performance_Acknowledgement.docx DOCX document
Atch (L-1) Q&A Form_21Mar2019.xlsx XLSX spreadsheet
Exhibit B_FY21 RRL CONTENT CONVERSION (B00X) Admin CDRLS - Draft 10 Feb 2020.docx DOCX document
Exhibit A_FY21 RRL CONTENT CONVERSION (A00X) Engineering CDRLs - Draft 16 Jan 2020.docx DOCX document
Atch (1)_APPENDIX F Sailor 2025 RRL Content Delivery Modes - 06 Dec 2019.odt ODT document
Atch (L-4)_Contractor Performance Assessment Questionaire(CPAQ).docx DOCX document
Atch (L-5)_Relevancy_Information_of_the_PP_Contract_FINAL_28Jun19.docx DOCX document
Atch (1)_APPENDIX D CDRL List - 22 Jan 2020.docx DOCX document
Attachment (2) - Draft FY21 CC MA Rating DO - 10 Feb 2020.docx DOCX document
Atch (L-3)_PastPerformanceContractReferenceWorksheet.docx DOCX document
Attachment (1) - FY21CC IDIQ SOW - Draft RFP - 10 Feb 2020.docx DOCX document
Atch (1)_APPENDIX J Mobile Learning Roadmap - 06 Dec 2019.docx DOCX document
Atch (L-6) CLIN Pricing Form.xlsx XLSX spreadsheet
Atch (1)_APPENDIX B Acronym List - 03 Feb 2020.docx DOCX document
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DISTRIBUTION A. Approved for public release. Distribution is unlimited.

APPENDIX E: Risk Assessment Example Format 06 Dec 2019

Sailor 2025 – Ready Relevant Learning (RRL) Risk Assessment

Likelihood [5] Near Certainty (~90%)

[4] Highly Likely (~70%)

1
[3] Likely

(~50%)

[2] Low Likelihood (~30%)

[1] Not Likely (~10%)

Consequence[1]
Minimal[2]
Minor[3]
Moderate[4]
Major[5]

Unaccept-able

O

- Original X

- Current Low Moderate High

Consequence Likelihood

Action/Event Date Schd.

ECD

Act.

Current Status Risk Level if Successful C L Suc.

Comments Plan:

T

- Target New Plan - Current Plan Current Original Risk Level N/A N/A

1. Coordinate with schoolhouse staff and TYCOMs for SMEs.

10/1/16 1/26/17 1/26/17 Coordinating with schoolhouse and TYCOMs for SMEs.

Y

2. Coordinate with fleet SMEs prior to and during the acquisition phases.

1/2/17 05/10/17 5/10/17 Continuing coordination with schoolhouse and SMEs.

Y

8/14/17 8/14/17 8/14/17 Continue to coordinate with schoolhouse staff and fleet SMEs prior to and during the acquisition phases.

Y

Risk Status:

Open

Risk Type (Check one in each area Technical Schedule Cost Risk Summary Worksheet Team: Sailor 2025 Risk Owner: NAWCTSD Date Opened: 01 Oct 2016 Updated: 14 Aug 2017 Risk Title: Sufficient Access to Fleet and Schoolhouse SMEs Risk #: 1 Description of Risk: If sufficient access to fleet and schoolhouse Subject Matter Experts (SMEs) is not available during analysis, design, development, and testing, for each wave, then contractor deliverables, the analysis output, and content conversion may be late.

Root Cause: Fleet and schoolhouse SMEs are busy working and teaching classes and have limited availability for RRL visits.

Consequence: Contractor deliverables, the analysis output, and content conversion may be late.

X O X

3. Risk working group meeting

Action/Event Date Schd.

ECD

Act.

Success Criteria L C Suc.

Comments Risk Level if Successful

Plan:

New Plan - Current Plan Current

Team: Sailor 2025 Risk Owner: NAWCTSD Date Opened: 01 Oct 2016 Updated: 14 Aug 2017 Risk Title: Sufficient Access to Fleet and Schoolhouse SMEs Risk #: 1 Risk Summary Worksheet

Backup Information

Program Risk Assessment

Not Likely:

Low Likelihood:

Likely:

Highly Likely:

Near Certainty:

...Will effectively avoid or mitigate this risk based on standard practices ~10% ...Have usually mitigated this type of risk with minimal oversight in similar cases ~30% ...May mitigate this risk, but workarounds will be required ~50% ...Cannot mitigate this risk, but a different approach might ~70% ...Cannot mitigate this type of risk; no known processes or workarounds are available ~90%

Determination of consequence for Schedule and Cost are program Specific.

Consequence

HIGH

MEDIUM

LOW

LevelTechnical PerformanceScheduleCost
1Minimal or no consequence to technical performanceMinimal or no impactMinimal or no impact
2Minor reduction in technical performance or supportability, can be tolerated with little or no impact on program; same approach retainedAdditional activities required, able to meet key dates.
Slip <___Month(s)Cost increase or unit production cost increases

< 1_% of budget

3Moderate reduction in technical performance or supportability with limited impact on program objectives; workarounds availableMinor schedule slip, no impact to key milestones
Slip < __ month(s) plus available float of critical path. Sub-system slip > __ month(s) plus available float. Slip <__Month(s)Cost increase or unit production cost increase

<___ 5% of budget

4Significant degradation in technical performance or major shortfall in supportability; may jeopardize program success; workarounds may not be available or may have negative consequencesPrgm critical path affected, all sched float assoc. w/key MS exhausted
Slip <__ MonthsCost increase or unit production cost increase

<____ 10% of budget

5Severe degradation in technical performance; Cannot meet KPP or Key technical/supportabilility threshold; will jeopardize program success; no workarounds availableCannot meet key program milestones
Slip >___ MonthsExceeds APBA threshold

> ____ 10% of budget

Consequence Level Probability of Occurrence image1.bin image2.emf