SOUTHWEST REGIONAL MAINTENANCE CENTER
CODE 410 3755 BRINSER STREET, STE 1
SAN DIEGO CA 92136-5205
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
REF: ARCO (ARDM-5)
SEE CONTINUATION PAGE
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-Jun-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N55236-15-Q-0131
X 9B. DATED (SEE ITEM 11)
17-Jun-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-Jun-2015
CODE
SOUTHWEST REGIONAL MAINTENANCE CENTER
CODE 410 3755 BRINSER STREET, STE 1
SAN DIEGO CA 92136
N55236 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE N55236
FACILITY CODECODE
roderick.rioveros@navy.milEMAIL:(619) 556-2309TEL:
CODE 410B - RODERICK RIOVEROS / CONTRACTING OFFICER
N55236-15-Q-0131
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0001 (CONTINUED)
REQUEST FOR SPECIFICATION CLARIFICATIONS:
1.QUESTION: WORK ITEM 179-00-001, PARAGRAPH 3.5 Contractor understands after review of work item that only paragraph 3.5 remains to accomplish non-skid requirements. Reference 4802179 is difficult to read.
Please provide approximate square footage of area that requires new non-skid.
ANSWER: The dock ramp is available for ship check. The Government estimates the size of the ramp surface as approximately 20 feet by 70 feet (1400 square feet) including all three sections. The Government does not guarantee the accuracy of this estimate; for a more precise estimate it is recommended that the contractor come to Arco and accomplish a ship check of the work required.
2. QUESTION: WORK ITEM 514-31-501, PARAGRAPH 1.3.2 Contractor has determined that requested replacement unit in paragraph 1.3.2 is long lead time material with an EDD of late August 2015, well after the current period of performance. Should contractor price in requested unit and recommend possible suitable substitute, if available, after contract award?
ANSWER: The contract will be modified to reflect an extended timeline for this specific work item to compensate for the lead time requirements of the material.
3. QUESTION: WORK ITEM 529-10-001, PARAGRAPH 1.3.1 Please clarify approximate wall height of drip pans. Please clarify size diameter and length of hose fitting required at bottom of drip pan.
ANSWER: Ship’s force has a sample drip pan available for ship check. To the best of the Government’s knowledge the hose fitting dimensions are ¾ inch diameter and ¾ inch long (sized to fit common garden type hose.
The Government does not guarantee the accuracy of this estimate; it is recommended that the contractor accomplish a ship check of Arco to verify the exact sizes and dimensions of the drip pan.
4. WORK ITEM: 589-21-001 FOR CLARIFICATION PURPOSES: The intention of the work item is to provide and install new pointer devices that attach to the pivot point of the boom and indicate degree of elevation on the boom attachment plate. The plate with the angle indications does not get replaced.
(End of Summary of Changes)