ArcoCM-WorkPackage.pdf

PDF 432 KB Posted

Attached to
ARCO (ARDM-5); Continuous Maintenance Availability Federal contract opportunity
Solicitation number
N55236-15-Q-0131
Issued by
Department of the Navy Naval Sea Systems Command

View the file

Other files for this federal contract opportunity

Other files attached to ARCO (ARDM-5); Continuous Maintenance Availability, newest first.
File Type Posted
N55236-15-Q-0131_ARCO_(ARDM-5)_0002.pdf PDF
N55236-15-Q-0131_ARCO_(ARDM-5)_0001.pdf PDF
Attachment_2_-_Request_for_Specification_Clarification_Form.docx DOCX document
Errata01-018-15.pdf PDF
N55236-15-Q-0131_ARCO_(ARDM-5).pdf PDF
Attachment_1_SSSD_018-15_ArcoCM-WorkPackage.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE NAVY

SPECIFICATIONS FOR WORK TO BE ACCOMPLISHED

SPECIFICATION NUMBER:

SHIP CHARACTERISTICS

FEET INCHESLENGTH OVERALL

FEET INCHESMAX. BEAM AT DESIGN WATERLINE

FEET INCHESEXTREME BEAM INCLUDING APPENDAGES

FEET INCHESDRAFT (MAX. NAVIGABLE) (FWD.)

FEET INCHESDRAFT (MAX. NAVIGABLE) (AFT.)

LONG TONLIGHT DISPLACEMENT

LONG TONFULL LOAD DISPLACEMENT

INCHESFEETHEIGHT OF MAST ABOVE DESIGN WATERLINE

INCLUDES ALL CHANGES THROUGH 6/5/2015

INDEX

SHIP: ARCO (CNRMC 5) SSSD-018-15

ITEMS THAT ARE STRUCK OUT IN THIS INDEX DO NOT APPLY TO THIS CONTRACT.

CATEGORY I. FY-15 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE.

ITEM_NO. TITLE DATE

009-01 General Criteria; accomplish 11/07/2013

009-02 Environmental Compliance Reports for Material Usage at Naval Facilities; provide 07/29/2011

009-03 Toxic and Hazardous Substances; control 01/17/2013

009-04 Quality Management System; provide 11/07/2013

009-05 Temporary Accesses; provide 01/17/2013

009-06 Maintaining Protection and Cleanliness from Non-Radioactive Operations;

accomplish

06/10/2014

009-07 Confined Space Entry, Certification, Fire Prevention and Housekeeping; accomplish 06/10/2014

009-08 Fire Protection at Contractor's Facility; accomplish 06/10/2014

009-10 Shipboard Asbestos-Containing Material (ACM); control 07/29/2011

009-18 Magnetic Material; control 01/17/2013

009-19 Provisioning Technical Documentation (PTD); provide 07/29/2011

009-20 Government Property; control 01/17/2013

009-21 Logistics and Technical Data; provide 07/29/2011

009-23 Interferences; remove and install 01/17/2013

009-24 Authorization, Control, Isolation, Blanking, and Tagging Requirements; accomplish 01/17/2013

009-28 Fire Prevention Requirements; accomplish 06/10/2014

009-29 Asbestos-Free Pipe Hanger Liner Material; install 07/29/2004

009-34 Fire Protection of Unmanned Vessels at Contractor's Facility; provide 01/17/2013

009-35 Confined Space Entry, Certification, Fire Prevention Utilizing Military Fire Watches, and Housekeeping; accomplish

06/10/2014

009-39 Technical Manual Contract Requirement (TMCR) for New Technical Manuals for Commercial Equipment/ Component; provide

07/19/2007

009-40 Requirements for Contractor Cranes, Multi-Purpose Machines and Material Handling Equipment at Naval Facilities; accomplish

07/29/2011

009-59 Organotin Antifouling Material; control 07/29/2011

009-60 Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration;

provide and manage

11/07/2013

009-61 Shipboard Use of Fluorocarbons; control 01/17/2013

009-64 Synthetic Fire-Resistant Hydraulic Fluid; control 07/29/2011

009-65 Polychlorinated Biphenyls (PCBs); control 07/29/2011

009-67 Integrated Total Ship Testing; manage 01/17/2013

009-69 Heavy Weather Plan; provide 11/07/2013

009-70 Confined Space Entry, Certification, Fire Prevention and Housekeeping for Unmanned Vessels; accomplish

06/10/2014

009-72 Physical Security at Private Contractor's Facility; accomplish 01/17/2013

009-73 Shipboard Electrical/Electronic/Fiber Optic Cable; remove, relocate, repair, and install 11/07/2013

Page 1 of 4 PLANNED WORK

ITEM_NO. TITLE DATE

009-74 Occupational, Safety and Health Requirements; accomplish 06/10/2014

009-77 Cofferdam Requirements; accomplish 01/17/2013

009-79 Government Owned Material (GOM); status reporting 07/29/2011

009-80 Ship's Facilities; provide 07/29/2011

009-81 Compartment Closeout; accomplish 01/17/2013

009-82 Data Requirements When Installing an Equal Component Vice Specified Component;

provide

07/29/2011

009-83 Wire Rope Fitting Verification; provide 01/17/2013

009-84 Accountability of Temporary Fasteners; provide 01/17/2013

009-86 Recovery of Chlorofluorocarbon (CFC) Refrigerants and Fire Suppressant Halon (H) Materials; accomplish

08/01/2008

009-87 Chemical Disinfection Procedures; accomplish 01/17/2013

009-88 Collection, Holding and Transfer (CHT) and Mogas Tanks, Spaces, and Piping, including Sewage or Mogas-Contaminated Tanks, Spaces, and Piping; certify

07/29/2011

009-89 Purchase and Inspection Requirements for Contractor Furnished Anodes;

accomplish

07/29/2011

009-93 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution Prevention Act (PPA) Information; provide

01/17/2013

009-94 General Environmental Requirements for Work at Contractor's Facility; accomplish 01/17/2013

009-95 Mechanically Attached Fittings (MAF's) for Piping Systems; install 01/17/2013

009-97 Shipbuilding and Ship Repair Operations National Emission Standard for Hazardous Air Pollutants (NESHAPS) for Surface Coating Information; provide

01/17/2013

009-99 Ship Departure Report; provide 01/17/2013

009-100 Ship's Stability Process Control Procedure (PCP); maintain 07/30/2010

009-101 Requirements for Mooring, Entry to and Departure from Contractor's Facility;

accomplish

01/17/2013

009-102 Alteration Verification; provide 07/29/2011

009-103 Weight and Moment Change Data; provide 07/29/2011

009-106 Work Authorization Form Coordinator (WAFCOR); provide 01/06/2014

009-108 Aircraft Carrier Requirements for Mooring, Entry to, Movement within, and Departure from Contractor's Facility; accomplish

07/29/2011

009-109 Special Requirements for Non-SUBSAFE Work on SUBSAFE-Certified Vessels;

accomplish

07/29/2011

009-110 Special Requirements for Non-Nuclear Work on Nuclear Vessels; accomplish 07/29/2011

009-111 Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration;

provide and manage

11/07/2013

009-112 Prevention of Radiographic-Inspection Ionizing-Radiation Hazards; accomplish 07/29/2011

009-117 AEGIS Light Off (ALO) Support for AEGIS Weapons Systems Assessments (AWSA);

provide

01/06/2014

009-118 CG Deck Loading; accomplish 01/17/2013

009-120 Fact Finding and Critique of Unplanned Events; manage 01/06/2014

009-121 Ship Assessment/Inspection Requirements; provide 01/06/2014

Page 2 of 4 PLANNED WORK

DATETITLEITEM NO.

CATEGORY II. FY-15 STANDARD ITEMS WHICH MAY BE INVOKED IN THE WORK ITEMS OF THIS JOB ORDER

009-11 Insulation and Lagging Requirements; accomplish 17-Jan-13

009-12 Welding, Fabrication, and Inspection Requirements;

accomplish

07-Nov-13

009-26 Deck Covering Requirements; accomplish 17-Jan-13

009-32 Cleaning and Painting Requirements; accomplish 07-Nov-13

Page 3 of 4 PLANNED WORK

ITEM NO. TITLE

Dock Ramp and Ramp Extension Plate Assembly; repair179-00-001

Lagging and Insulation; repair508-10-501

Air Conditioning Unit; replace514-31-501

Deballast Pump Drip Pans; manufacture529-10-001

Deballast Valve;replace529-10-002

Boom Angle Indicator; manufacture and install589-21-001

Polymeric Deck Covering; Resurface634-11-001

Page 4 of 4 PLANNED WORK

SHIP: ARCO (CNRMC 5) ITEM NO: 179-00-001

COAR: 28 PCN: DA01-0935

DA01-0004

CSWT FILE NO: 130-007 CMP: NONE

REVISED: 16 Jun 2014 PLANNER: GREEN, DONALD

SSP: SSSD-018-15 1 of 2 ITEM NO: 179-00-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Dock Ramp and Ramp Extension Plate Assembly; repair

1.2 Location of Work:

1.2.1 Dock Access Ramp and Onboard Ramp Extension in Dock Basin

1.3 Identification:

1.3.1 Quantity (One) each Dock Access Ramp, Sliding Plate, Screwed Plate and Extension Ramp Assembly

2. REFERENCES:

2.1 Standard Items

2.2 4802179, Rev C, Pontoon Structure

3. REQUIREMENTS:

3.1 Remove each ramp sliding plate, screwed down extension plate and each dock basin extension ramp using 2.2 as guidance.

3.2 Weld buildup and machine 8 each bolt holes to accommodate new fasteners. Four each deck tabs and four each foundation bolt holes.

3.3 Remove existing and install new the end of extension ramp flat bar assuring it's level to dock basin with no uplift using 2.2 as guidance.

3.4 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column A, Lines One through 7.

3.5 Accomplish the requirements of 009-32 of 2.1, including Table 2, Line 28, columns A through E for new non-skid on access ramp, sliding plate, screwed down plate and dock extension ramp.

3.6 Accomplish the requirements of 009-32 of 2.1, including Table 2, Line 12, Column A through E, for drydock deck areas under the extension ramp.

3.7 Install each sliding plate, screwed plate and extension dock ramp to their respective locations.

3.7.1 Install new 44 each CRES 304 flat head slotted hold down screws for the screwed down plate and 4 each CRES 304, Bolt, washer and nuts for the extension ramp hold down tabs using existing for dimensional requirements and using 2.2 as guidance.

3.7.1.1 Align ramp prior to tightening.

3.8 Accomplish the requirements of 009-32 of 2.1 for new and disturbed surfaces.

4. NOTES:

4.1 None.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

SHIP: ARCO (CNRMC 5)

SSP: SSSD-018-15 2 of 2 ITEM NO: 179-00-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

5.3 KITTED MATERIAL:

1. None.

SHIP: ARCO (CNRMC 5) ITEM NO: 508-10-501

COAR: 28 PCN: ERMC-Q571

CSWT FILE NO: 508-001 CMP: NONE

REVISED: 16 Jun 2014 PLANNER: STOUT, MICHAEL

SSP: SSSD-018-15 1 of 1 ITEM NO: 508-10-501

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Lagging and Insulation; repair

1.2 Location of Work:

1.2.1 Electrical Shop, (2-276-2-Q)

1.2.1.1 Quantity (26 LF), 4", 6" and 8" Seawater Pipe Lagging.

1.2.2 Deck Lounge (Operations Classroom), (2-66-1-Q)

1.2.2.1 Quantity (20 SF), 2 Inch Bulkhead Insulation

1.3 Identification:

1.3.1 Not Applicable

2. REFERENCES:

2.1 Standard Items

2.2 S9086-RK-STM-010/CH-505,, Piping Systems

3. REQUIREMENTS:

3.1 Remove damaged and deteriorated insulation and install new on equipment at location in 1.2.2.

3.1.1 Verify location of insulation being replaced with ship's force

3.1.2 Accomplish the requirements of 009-11 of 2.1.

3.2 Install new lagging on piping located in 1.2.1 using 2.2 as guidance.

3.2.1 Verify location of lagging being installed with ships force.

3.2.2 Accomplish the requirements of 009-11 of 2.1.

3.3 Accomplish the requirements of 009-32 of 2.1 for new and disturbed surfaces.

4. NOTES:

4.1 None.

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

SHIP: ARCO (CNRMC 5) ITEM NO: 514-31-501

COAR: 28 PCN: EA01-0089

EA01-0101

CMP: NONE

PLANNER: STOUT, MICHAEL

SSP: SSSD-018-15 1 of 2 ITEM NO: 514-31-501

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Air Conditioning Unit; replace

1.2 Location of Work:

1.2.1 Main Deck, Port Side,(1-120-2)

1.2.2 Admin Office,(2-120-2-Q)

1.2.3 Main Deck, Port Side,(1-396-2)

1.2.4 HT/DC SHOP(Supply Room),(2-396-2)

1.3 Identification:

1.3.1 Quantity (One) ea., York Condensing Unit; Model H4DB060S25A 208-230V, Serial No.WGMM049174, 300-350 PSIG.

1.3.1.1 Quantity (One) ea., York Furnace; Model G2FD060H24A, Serial No.(S)XALS010659,350 PSIG (MAX).

1.3.2 Quantity (One) each, Air Conditioner and condensing unit, Model #WHP30D020AA000C , NSN No.4120-01-529-0459

2. REFERENCES:

2.1 Standard Items

3. REQUIREMENTS:

3.1 Remove existing, and install new the equipment identified in 1.3.1, located and 1.3.2, using existing for guidance.

3.1.1 Repair/service the equipment listed in 1.3.1.1, located in 1.2.2, for the equipment identified in 1.3.1, located at 1.2.1.

3.2 Remove existing and install new, the equipment identified in 1.3.2, located in 1.2.3 and 1.2.4, using existing as guidance.

3.2.1 Recover refrigerant out of existing A/C unit and dispose of as per EPA guidelines.

3.3 Remove existing, template, and install new each foundation to fit new equipment located in 1.2.1, 1.2.3, and 1.2.4.

3.3.1 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column A, Lines One through 7, for new mounting foundations and deck below condensing unit and standing pipes and deck.

3.3.2 Accomplish the requirements of 009-32 of 2.1 for the new foundation.

(V)(G) "OPERATIONAL TEST"

3.4 Test each newly installed equipment listed in 1.3.1. 1.3.11, AND

1.3.2 through all phases of normal operation in compliance with OEM Specifications.

SSP: SSSD-018-15 2 of 2 ITEM NO: 514-31-501

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

3.5 Accomplish the requirements of 009-11, for new and disturbed lagging.

3.6 Accomplish the requirements of 009-32 of 2.1 for new and disturbed surfaces.

4. NOTES:

4.1 Shipboard point of contact is CHENG, Phil Delaventura.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

SHIP: ARCO (CNRMC 5) ITEM NO: 529-10-001

COAR: 28 PCN: EA01-0028

BWST FILE NO: 000-001 CMP: NONE

REVISED: 11 Dec 2014 PLANNER: GREEN, DONALD

SSP: SSSD-018-15 1 of 1 ITEM NO: 529-10-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Deballast Pump Drip Pans; manufacture

1.2 Location of Work:

1.2.1 None

1.3 Identification:

1.3.1 Quantity (10) ea., Deballast Pump CRES Drip Pans, Approx.

Size: 10 1/2 inch by 24 Inches long with Drain Discharge for Hose Fitting

2. REFERENCES:

2.1 None

3. REQUIREMENTS:

3.1 Receive from ships force sample drip pan.

3.2 Manufacture as per sample each drip pan listed in 1.3.1 using CRES 304 material to include hose fitting in bottom and attachment straps.

3.3 Deliver drip pans to ship's force upon completion.

3.3.1 Submit one legible copy, in electronic media, of a report including printed name, title and signature of person receiving each pan to the SUPERVISOR.

4. NOTES:

4.1 Shipboard contact: ENS Deshane/Young.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

SHIP: ARCO (CNRMC 5) ITEM NO: 529-10-002

COAR: 28 PCN: EA01-0110

BWST FILE NO: 000-001 CMP: NONE

REVISED: 11 Dec 2014 PLANNER: STOUT, MICHAEL

GREEN, DONALD

SSP: SSSD-018-15 1 of 2 ITEM NO: 529-10-002

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Deballast Valve;replace

1.2 Location of Work:

1.2.1 Pump Room Number 2, (4-120-0-E)

1.3 Identification:

1.3.1 Quantity (One) ea., #3 Deballast Pump Discharge, 14 Inch, Gate Knife, w/v Orfice, Flanged, Air Operated

2. REFERENCES:

2.1 Standard Items

2.2 D-76-084, Rev -, Cast 14 Inch Disk Valve

2.3 4802132, Rev C, Ballast & Deballast Sys. ARRGT & DETS

3. REQUIREMENTS:

3.1 Remove existing and install new the equipment listed in 1.3.1, located in 1.2.1, using 2.2 and 2.3 as guidance.

3.1.1 Install new each gasket and fastener found beyond economical use.

(V)(G) "OPERATIONAL TEST"

3.2 Accomplish an operational test of the new valve. Operate through 3 complete cycles, with no sticking or binding permitted.

(V)(G) "OPERATIONAL TEST"

3.3 Accomplish an operational and tightness test of new valve , and inspect for leaks, proper operation, and unobstructed flow. Allowable leakage: None.

3.4 Accomplish the requirements of 009-11 of 2.1 for new and disturbed lagging.

3.5 Accomplish the requirements of 009-32 of 2.1 for new and disturbed surfaces.

4. NOTES:

4.1 Possible Source: Engineered Valves, LLC. Phone: 662-256-7185 Web site: https://engvalves.com/core/medialibrary/engvalves/website/Tools- Resources/Brochures/FabriValve/fabricf37.pdf?ext=.pdf

Valves shown here.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

SSP: SSSD-018-15 2 of 2 ITEM NO: 529-10-002

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. None.

5.2 PUSH MATERIAL:

1. None.

SHIP: ARCO (CNRMC 5) ITEM NO: 589-21-001

COAR: 28 PCN: DA01-0057

BWST FILE NO: 000-001 CMP: NONE

REVISED: 11 Dec 2014 PLANNER: GREEN, DONALD

SSP: SSSD-018-15 1 of 1 ITEM NO: 589-21-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Boom Angle Indicator; manufacture and install

1.2 Location of Work:

1.2.1 Crane Boom, Port and Starboard

1.3 Identification:

1.3.1 Quantity (4) ea., Boom Angle Indicator Devices, (2) ea., Port and (2) ea., Starboard Crane Boom Indicators

2. REFERENCES:

2.1 None

3. REQUIREMENTS:

3.1 Remove existing, template, manufacture new each equipment listed in

1.3.1 using existing as guidance.

3.1.1 Accomplish the requirements of 009-32 of 2.1 for new

surfaces.

3.1.2 Confirm with ship's force as to required colors.

3.2 Install each equipment on each crane to respective location using new fasteners and using existing as guidance.

3.3 Accomplish the requirements of 009-32 of 2.1 for new and disturbed surfaces.

4. NOTES:

4.1 None.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

SHIP: ARCO (CNRMC 5) ITEM NO: 634-11-001

COAR: 28 PCN: DA01-0932

DA01-0930

DA01-0931

DA01-0933

BWST FILE NO: 000-001 CMP: NONE

REVISED: 11 Dec 2014 PLANNER: STOUT, MICHAEL

GREEN, DONALD

SSP: SSSD-018-15 1 of 2 ITEM NO: 634-11-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

1. SCOPE:

1.1 Title: Polymeric Deck Covering; Resurface

1.2 Location of Work:

1.2.1 (2-36-1-L) Passageway

1.2.2 (2-0-1-Q) First Lt. Office

1.2.3 (2-40-1-L) Unisex WR/WC

1.2.4 (2-6-1-Q) Deck Office

1.3 Identification:

1.3.1 Quantity 257 sq. ft., Polymeric Deck Covering

1.3.2 Quantity 75 sq. ft., Polymeric Deck Covering

1.3.3 Quantity 45 sq. ft., Polymeric Deck Covering

1.3.4 Quantity 360 sq. ft., Polymeric Deck Covering

2. REFERENCES:

2.1 Standard Items

2.2 101-4802175, Rev D, Compartment & Access Decks

3. REQUIREMENTS:

3.1 Accomplish the requirements of 009-26 of 1.2, including Attachment C, Paragraph F and G, for resurfacing of each deck, in each location listed in 1.2.1 through 1.2.4.

3.1.1 Submit one legible copy, in hard copy or approved

transferrable media, of a report listing the results of 3.1 to the SUPERVISOR at the completion of work.

4. NOTES:

4.1 Primary point of contact is Ship Building Specialist Michael Stout, Cell # 619-726-5753.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

SSP: SSSD-018-15 2 of 2 ITEM NO: 634-11-001

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

File details come from the government source that posted it. Updated .