Solicitation N4523A20R1307 Questions and Responses.docx
DOCX document 12 KB Posted
- Attached to
- Boom and Aerial Work Platform (AWP) Leases
- Solicitation number
- N4523A20R1307
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N4523A20R1307 Combined Synopsis Solicitation.docx | DOCX document | |
| Attachment A 52.212-1_.docx | DOCX document | |
| Attachment E PWS Solicitation AWP_Rqt 2_CLINs 0005_0006.doc | DOC document | |
| Attachment B 52.212-2_.docx | DOCX document | |
| Attachment C 52.212-5 Clauses_.docx | DOCX document | |
| Attachment D PWS Solicitation Boom and AWP_Requirement 1 CLIN0001-0004.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Questions and Responses Question 1: Do we email the quote to you directly?
Government Answer: Per the instructions on the last page of the solicitation, proposals must be submitted via email to jacquelyn.schmid@navvy.mil and ianthe.stevens-ford@navy.mil by 12:00 pm Pacific Standard Time on 13 July 2020.
Question 2: Are we ok to quote telescopic/straight booms across the board or are you in need of any articulating booms?
Government Answer: Quotes should be for the equipment listed in section 1.3 in Attachment D PWS Solicitation Boom and AWP_Requirement 1 CLIN0001-0004. The requirement is for a 55’ telescopic forklift (high reach) or equivalent.