About this file

This document contains a Contract Data Requirements List (CDRL) and related federal contract opportunity solicitation. The CDRL outlines requirements for a Test/Inspection Report to document testing and inspection results for a shielded shipping cask. It specifies the format, content, and delivery requirements for test data including void space calculations and shielding performance testing. The related opportunity is a small business set-aside solicitation seeking proposals for CASK Containers. It will be awarded as a single, firm-fixed-price commercial contract under FAR Part 12. The period of performance includes a base year and three option years. The NAICS code is 332439. The soliciting agency is the Department of the Navy Naval Supply Systems Command.

View the file

Other files for this federal contract opportunity

Other files attached to CASK Containers, newest first.
File Type Posted
Questions and Anwsers..pdf PDF
Attachment 2 - 9274V000-00646-ITEMDOC NEW C OF C, Instructions, Certs required.doc DOC document
Attachement 1 - 9274V000-00646-Distro A Performance Specification Rev C cask.pdf PDF
9274V000-00646-CDRL A002-Calculations.doc DOC document
9274V000-00646-CDRL A015-Technical Documentation.doc DOC document
9274V000-00646-CDRL A013-Technical Documentation Rev A.doc DOC document
9274V000-00646-CDRL A010 - Certifications.doc DOC document
9274V000-00646-CDRL A001- Product Data -Gasket.doc DOC document
9274V000-00646-CDRL A006 - Lift Sketch.doc DOC document
9274V000-00646-CDRL A008-Measured Weight Report.doc DOC document
Attachment 4 - J5 Previous Efforts Form.doc DOC document
Combind Synopsis Solicitation.docx DOCX document
9274V000-00646-CDRL A009-Load Test Report.doc DOC document
9274V000-00646-CDRL A005-Stress analysis.doc DOC document
Section L Instructions with M.docx DOCX document
Attachment 3 - Table 2 Summary of Deliverables for ALL OPTION YEARS.doc DOC document
9274V000-00646-CDRL A012- Test Report Cask Tipping.doc DOC document
9274V000-00646-CDRL A011 49 CFR.doc DOC document
9274V000-00646-CDRL A004 - Certifications.doc DOC document
9274V000-00646-CDRL A007 - Certification of compliance.doc DOC document
9274V000-00646-CDRL A003-Shipping Plan.doc DOC document
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SHIPYARD ENGINEERING AND PLANNING PROCEDURES MANUALADVANCE \D 3.60

ADVANCE \D 9.35

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved

OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington VA 22202-4302. Please DO NOT RETURN your form to either of these address. Send completed form to the Government issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
TBD
A
TDF TM OTHER X NDTI

D. SYSTEM/ITEM

SHIELDED SHIPPING CASK

E. CONTRACT/PR NO.

N4523A9274V000

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A014

2. TITLE OF DATA ITEM

TEST/INSPECTION REPORT

3. SUBTITLE

TEST REPORT

4. AUTHORITY (Data Acquisition Document No.)

DI-NDTI-80809B

5. CONTRACT REFERENCE

SOW

6. REQUIRING OFFICE

PSNS & IMF C/2310.3

7. DD 250 REQ

N/A

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

ASREQ

12. DATE OF FIRST

SUBMISSION

SEE BLK 16

14. DISTRIBUTION

b. COPIES

8. APP CODE

A

*
11. AS OF DATE

SEE BLK 16

13. DATE OF SUBSEQUENT SUBMISSION

N/A

A. ADDRESSEE

Final

Draft
Reg
Repro

16.

Block 3: THE CONTRACTOR SHALL PROVIDE IN THE CONTRACTOR’S FORMAT:

A. TOTAL CALCULATED VOID SPACE IN SHIELDING MATERIALS REQUIRED PER SPECIFICATION PARAGRAPH 3.2.4.3.6, B. RESULTS OF SHIELDING PERFORMANCE TESTING REQUIRED PER SPECIFICATION PARAGRAPH 4.3.1.2 Block 8: THE TOTAL CALCULATED VOID SPACE IN SHIELDING MATERIALS REQUIRED PER SPECIFICATION PARAGRAPH 3.2.4.3.6, AND RESULTS OF SHIELDING PERFORMANCE TESTING REQUIRED PER SPECIFICATION PARAGRAPH 4.3.1.2 SHALL BE SUBMITTED FOR GOVERNMENT APPROVAL. Approval will be based on tehnical content and compliance with requirements. THE GOVERNMENT WILL HAVE 10 WORKING DAYS FOR REVIEW. THE CONTRACTOR SHALL HAVE 10 WORKING DAYS TO REVISE (IF REQUIRED) AND RESUBMIT FOR A NEW REVIEW.

BLOCKS 11 & 12: THE CONTRACTOR SHALL PROVIDE TOTAL CALCULATED VOID SPACE IN SHIELDING MATERIALS REQUIRED PER SPECIFICATION PARAGRAPH 3.2.4.3.6, AND RESULTS OF SHIELDING PERFORMANCE TESTING REQUIRED PER SPECIFICATION PARAGRAPH 4.3.1.2 WITH DELIVERY OF THE SHIELDED SHIPPING CASK TO PSNS.

BLOCK 14: THE CONTRACTOR SHALL PROVIDE ONE COPY OF THETOTAL CALCULATED VOID SPACE IN SHIELDING MATERIALS REQUIRED PER SPECIFICATION PARAGRAPH 3.2.4.3.6, AND RESULTS OF SHIELDING PERFORMANCE TESTING REQUIRED PER SPECIFICATION PARAGRAPH 4.3.1.2 IN ELECTRONIC UNPROTECTED SEACHABLE PDF FORMAT TO THE GOVERNMENT TECHNICAL POINT OF CONTACT (BELOW).

JERRY NAHRING

C/2310.3, PSNS & IMF

Jerry.nahring@navy.mil

PSNS C/2310.3
1
1
0
TOTAL
1
1
0
G. PREPARED BY
H. DATE
H. APPROVED BY
J. DATE
Mike Baker
9 September, 2019
Rich Balter
10 September, 2019

DD Form 1423-1, FEB 2001 Previous edition may be used.

Page 1 of 4 Pages

DATA ITEM DESCRIPTION

Title: Test/Inspection Report

Number: DI-NDTI-80809B Approval date: 970124 AMSC Number: N/A Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility: F/AFMC-DOP Applicable Forms: N/A

Distribution Statement A: Approved for public release. Distribution is unlimited.

Description/Purpose: The test/inspection report is used to document test/inspection results, findings, and analyses that will enable the Government or Contracting Agency to evaluate compliance with system requirements, performance objectives, specifications, and test/inspection plans.

Application/interrelationship: This Data Item Description (DID) contains the format and content preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.

This DID is applicable to engineering (developmental), preliminary qualification, qualification, and acceptance testing.

Requirements:

1 Format. Contractor format is acceptable. Organize the information required by paragraph 2 and its subparagraphs in a manner that facilitates presentation and understanding.

2 Content. The test/inspection report shall contain the following information, as applicable.

2.1 The following information shall appear on the outside front cover and title page:

a. Report date

b. Report number (contractor or Government)

c. Contractor’s name, address, and commercial and Government code

d. Contract number and contract line item number or sequence number (if applicable)

e. Type of test/inspection (for example, first article acceptance test, quality performance inspection, developmental test, qualification test, environmental test)

f. Identification of item tested/inspected

g. Date or period of test/inspection

h. Name and address of requiring Government activity

i. Security classification, downgrading and declassifying information, if applicable

2.2 Table of Contents. The table of contents shall identify the following:

a. The title and starting page of each major section, paragraph, and appendix of report

b. The page, identifying number, and title of each illustration (for example; figure, table, photograph, chart, drawing, etc.)

2.3 Introduction. The introduction shall include the following information:

2.3.1 Test/inspection objective(s). The specific test/inspection objective(s) as specified in the contract tasking document.

2.3.2 Item(s) tested/inspected. Complete identification of the item(s) tested/inspected including the following:

a. Nomenclature

b. National stock number

c. Model number, part number, and serial number

d. Type of item (for example; prototype, production item, laboratory model)

e. Serial or lot number

f. Applicable engineering changes

g. Production item specification, if applicable

h. Date of manufacture

2.3.3 Test/inspection requirements. Complete identification of the test/inspection requirements correlated to contractual requirements including the following:

a. Required test/inspection parameters

b. Performance requirements, acceptance or compliance limits, and environmental criteria

2.4 Summary. Complete test/inspection report summary including the following:

a. A brief discussion of the significant test/inspection results, observations, conclusions, and recommendations covered in greater detail elsewhere in the report

b. Proposed corrective actions and schedules for failures or problems encountered

c. Identification of deviations, departures, or limitations encountered, referenced to the contract requirements

d. Tables, graphs, illustrations, or charts as appropriate to simplify the summary data

2.5 Referenced documents. Complete identification of all documents referenced in the test/inspection report including the following, as applicable:

a. Prior test/inspection reports on the same item

b. Test/inspection plans and procedure documents

c. Prior certifications of compliance

d. Contractor’s file designation where test/inspection records are maintained

e. Input parameters used

Note: The applicable issue of the documents cited therein, including their approval dates and dates of any applicable amendments, notices, and revisions, shall be as specified in the contract.

2.6 Body of report. The body of the test/inspection report shall be as follows:

2.6.1 Test equipment identification. Complete identification of each item of test equipment used in the test/inspection including the following:

a. Nomenclature

b. Model number

c. Serial number

d. Manufacture

e. Calibration status

f. Accuracy data

g. Comments, if applicable

2.6.2 Test/inspection facility installation and set-up. Complete description of the physical set-up used in conducting the test/inspection to include the following:

a. Location or orientation of the item

b. Location, orientation, or settings of test equipment and instrumentation

c. Location, orientation, or settings of sensors and probes

d. Location or orientation of interconnections, cables, and hoop-ups

e. Electrical power, pneumatic, fluidic, and hydraulic requirements

Drawings, illustrations, and photographs may be used for clarification

2.6.3 Test/inspection procedures. Complete description of the procedures used in conducting the test/inspection to include the following:

a. Item selection and inspection that verified suitability for test/inspection

b. Summarized sequence of testing/inspection steps, including a description of how the item was operated during the test/inspection, and any control condition imposed

2.6.4 Test/inspection results and analysis. A copy of all test/inspection results and analysis to include the following:

2.6.4.1 Recorded data. The actual recorded data (for example, log book entries, oscillographs, instrument readings, plotter graphs). If the recorded data is extensive, it shall be provided in an appendix.

2.6.4.2 Test/inspection results. Identification of all test/inspection results to include the following:

a. Matrices comparing results achieved against test/inspection objectives or requirements

b. A discussion of these matrices as to their significance, and how they compare to any prior test/inspection

c. Calculation examples

d. Discussion of any anomalies, deviations, discrepancies, or failures including their impact, causes, and proposed corrective actions. The discussion shall address discrepancies between design requirements and the tested/inspected configuration.

2.6.5 Conclusions. Test/inspection conclusions distinguished between objective and subjective to include the following:

a. The effectiveness of the test/inspection procedures in measuring item performance

b. The success or failure of the item to meet required test/inspection objectives

c. The need for repeat, additional, or alternative tests/inspections

d. The need for item redesign or further development

e. The need for improved test/inspection procedures, techniques, or facilities

f. The adequacy and completeness of the test/inspection requirements

2.6.6 Recommendations. Recommendations appropriate to the test/inspection results and conclusions including the following:

a. Acceptability of the item tested/inspected (pass or fail)

b. Additional testing/inspection required

c. Redesign required

d. Problem resolution

e. Test/inspection procedure or facility improvements

f. Disposition of items tested/inspected

g. Documentation changes required

h. Testing/inspection improvements

2.7 Authentication. The following certifications shall be included, as applicable:

2.7.1 Authentication of test/inspection results. A statement that the test/inspection was performed in accordance with applicable test/inspection plans and procedures, and that the results are true and accurate. The authentication shall include the signature of the contractor personnel that performed the test(s)/inspection(s), a contractor representative authorized to make such certification.

2.7.2 Authentication of prior validation. A statement identifying those requirements not tested/inspected or measured that were previously validated. Include identification of the data and method employed for such validation (for example, prior to test/inspection, analytical verification, equivalent item, etc.). The authentication shall include the signature of a contractor representative authorized to make such authentication.

2.7.3 Authentication of acceptability. A statement that the item tested/inspected either passed or failed item acceptability requirements. This authentication shall include the signature of a contractor representative authorized to make such authentication.

2.8 Appendices. Appendices shall be used to append detailed test/inspection data, drawings, photographs, or other documentation too voluminous to include in the main body of the report. This includes referenced documentation not previously provided by the Government, and test/inspection reports from any associated test/inspection activity that may have performed some of the testing/inspecting requirements.

3 End of DI-NDTI-80809B