This document contains an amendment to a solicitation and responses to questions regarding a federal contract opportunity. The opportunity involves extending an existing anti-submarine warfare piping system at Portsmouth Naval Shipyard by running piping around a dry dock service tunnel and installing two branch lines to service balconies on the south side. The piping will be fused polypropylene SDR-11 pipe compatible with the existing system. Valves, hangers, and expansion joints made of 316 stainless steel will also be provided. The amendment changes the bid opening time and provides responses to questions on technical specifications and the scope of work, clarifying piping and fitting types, valve and expansion joint requirements, and testing and training needs.

View the file

Other files for this federal contract opportunity

Other files attached to Extend ASW Header PNSY-DD1, newest first.
File Type Posted
Amendment 2 WD Update.pdf PDF
N4008520B2541 Solicitation.pdf PDF
1583452 - Scope of Work.pdf PDF
ATTACHMENT 5 - Drawings.pdf PDF
ATTACHMENT 4 - Submittal Register.xls XLS spreadsheet
ATTACHMENT 2 - Division 1 Specifications.pdf PDF
ATTACHMENT 1 - Bid Form.pdf PDF
ATTACHMENT 3 - Technical Specifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACQR5503627

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of Amendment 1 is the follow ing:

1. Provide Government responses to RFI questions received as of 17 July 2020. See SF30 continuation page.

2. To change the bid opening from 31 July 2020, 2:30 PM EST to 31 July 2020, 3:00 PM EST.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008520B2541

X 9B. DATED (SEE ITEM 11)

29-Jun-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

21-Jul-2020

CODE

NAVFAC MID ATLANTIC

PWD MAINE - FEAD PORTSMOUTH

PORTSMOUTH NAVAL SHIPYARD

BLDG 59

PORTSMOUTH NH 03801-2032

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008520B2541

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 1 RFI RESPONSES

TECHNICAL SPECIFICATIONS, ATTACHMENT 3:

1.3 SUBMITTALS:

1. There are many items in this section which are not a requirement for the project, nor are being supplied, are we to ignore those which do not apply?

Items not referenced in the scope of work or drawings can be ignored.

2. In particular:

“Proposed water treatment plan including a layout, control scheme, a list of existing make-up water conditions including the items listed in paragraph WATER ANALYSIS", a list of chemicals, the proportion of chemicals to be added, the final treated water conditions, and a description of environmental concerns for handling the chemicals.”

Water treatment plan and associated sections are not required.

3. SD-06 Does this apply?

“One-Year Inspection Report For Cooling Water; G

At the completion of one year of service, in bound 8-1/2 by 11 inch booklets. In the report, identify the condition of each cooling tower and condenser. Include a comparison of the condition of the cooling tower and condenser with the manufacturer's recommended operating conditions. Identify all actions taken by the Contractor and manufacturer to correct deficiencies during the first year of service.”

This section is not required.

4. SD-08, manufacturer’s instructions, are we to provide training?

This section is not required.

2.2 POLYPROPYLENE PIPING

5. 2.2.1 Pipe: “Polypropylene pipe shall be Schedule 40”

Is this a correct statement or is the pipe to be SDR 11?

Refer to piping material requirements in the Scope of Work document:

“The basis of design piping is Aquatherm brand, blue pipe SDR-11 faser composite PP-R pipe. This is the existing type of piping and this project shall be compatible with this type of piping.”

6. 2.2.2 Fitting:

Fittings shall meet ASTM F2389 and NSF/ANSI 14 and shall be NSF listed for the service intended. Plastic pipe, fittings, and solvent cement shall bear the NSF seal "NSF- PW." Polypropylene fittings shall conform to dimensional requirements of Schedule 40. Polypropylene piping that will be exposed to UV light shall be provided with a Factory applied UV resistant coating.

a. Are the fittings to be sch. 40 or SDR 7.9?

b. Solvent welded or Fusion bonded as per section 3.2.2?

Fittings are to be SDR 11. Joints shall be fusion bonded. Reference SOW Section 1 under Piping Installation section 1.3 for more detail.

7. 2.3.1 Gate Valves:

The specification is calling for OS & Y valves, with bronze trim, is this correct or are we wo utilize knife gate valves? Please provide appropriate specification.

Valves shall be 150# class, 316 stainless steel knife gate valves.

8. 2.3.3 Butterfly Valves:

Are the valves to be lug or wafer style, the specification allows for both. Existing valves have gear operators, the specification calls for lever type on smaller than 8”.

Butterfly valves shall be 150# class, lug style, 316 stainless steel with gear operators.

9. 2.4.2 Expansion Joints:

We do not believe this specification section supports the type of expansion joints for this system, please review and advise.

See below for expansion joint requirements.

10. 3.1.1 Functional Requirements:

States that the piping to be pitched at a rate of 1” in 40’, please advise if this requirement applies.

Yes, the intent is to be able to drain the piping at the end of the line.

SCOPE OF WORK:

11. 1.2 Expansion joints:

Indicates that the joints shall comply with Spec Section 23 64 26, this section does not call out a requirement for rubber expansion joints that we found. This section also indicates that these joints shall be sized for expansion based on a 75 degree delta in the event of a steam leak indicating calculations are required, SOW section 6.0 Design states NOT APPLICABLE, please advise on basis of design for expansion joints.

Basis of design for the expansion joints are Metraflex DSEE1000 with the root ring primed and protected with epoxy paint to prevent corrosion. Expansion joints shall be capable of allowing at least 2.375” compressive axial movement.

12. 1.6 The existing system does not utilize stainless steel rings, are epoxy coated acceptable?

Yes that is acceptable as long as epoxy is compatible with pipe material.

13. 1.7 hangers and anchors, we do not know of a roller support as depicted on the drawings as being available in 316 stainless, is galvanized acceptable on the roller assembly?

Yes that is acceptable.

14. 28.0 Training; is training required for the piping system installed?

Training is required as described in this section.

(End of Summary of Changes)