ATTACHMENT 4 - Submittal Register.xls

XLS spreadsheet 67 KB Posted

Attached to
Extend ASW Header PNSY-DD1 Federal contract opportunity
Solicitation number
N4008520B2541
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This submittal register outlines requirements for 82 submissions related to a project to extend ASW piping at Portsmouth Naval Shipyard Dry Dock 1. Key submissions include an accident prevention plan, construction schedule, quality control plan, traffic control plan, welding procedures and qualifications, pressure and leak test reports, operation and maintenance manuals, and record drawings. Submissions are due prior to construction, during construction, and for closeout. The contractor must allow two weeks' notice prior to final piping connection to coordinate with Code 984 and Dry Dock operations.

View the file

Other files for this federal contract opportunity

Other files attached to Extend ASW Header PNSY-DD1, newest first.
File Type Posted
Amendment 2 WD Update.pdf PDF
Amendment 1.pdf PDF
ATTACHMENT 3 - Technical Specifications.pdf PDF
N4008520B2541 Solicitation.pdf PDF
1583452 - Scope of Work.pdf PDF
ATTACHMENT 5 - Drawings.pdf PDF
ATTACHMENT 2 - Division 1 Specifications.pdf PDF
ATTACHMENT 1 - Bid Form.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal Register

TITLE:ATTACHMENT 4 - SUBMITTAL REGISTERSUBMITTAL REGISTER
JOB NAME:Extend ASW Header PNSY-DD1
LOCATION:Portsmouth Naval Shipyard, Dry Dock 1
CONTRACT NO:
CONTRACTOR:
CONTRACTOR SCHEDULE DATESCONTRACTOR ACTIONAPPROVING AUTHORITY
LineAct-ivity #Trans-mittal #Specification SectionSD #SD DescriptionItem SubmittedParagraph #Classi-fication: GOVT or A/E RevwrSubmitApproval Needed ByMaterial Needed ByAction CodeDate Of ActionDate FWD to APPR / Auth - Date RCD From CONTRDate FWD To Other RevwrDate RCD From Other RevwrAction CodeDate Of ActionMailed To CONTR/ Date RCD From APPR AuthorityRemarks
101 14 00.00 2201Preconstruction SubmittalsList of Contact Personnel1.5.1G
201 20 00.00 2201Preconstruction SubmittalsSchedule of Prices1.3G
301 30 00.00 2201Preconstruction SubmittalsNAVFAC Red Zone Checklist0G
401 30 00.00 2201Preconstruction SubmittalsNAVFAC PWD ME Follow-on Services List1.8G
501 31 23.13 2001Preconstruction SubmittalsList of Contractor's Personnel1.4.2G
601 32 16.00 2001Preconstruction SubmittalsConstruction Schedule1.2G
701 32 16.00 2007CertificatesMonthly Updates1.4
801 33 0001Preconstruction SubmittalsSubmittal Register1.5G
901 33 10.05 2001Preconstruction SubmittalsConsolidated RFP Documents2.1G
1001 33 10.05 2001Preconstruction SubmittalsSubmittal Register1.5.5G
1101 33 10.05 2005Design DataDesign Drawings1.7G
1201 33 10.05 2005Design DataSpecifications1.8G
1301 33 10.05 2005Design DataDesign Analysis1.9G
1401 33 10.05 2005Design DataDesign Submittals2.2G
1501 33 10.05 2011Closeout SubmittalsRecord Documents0G
1601 33 10.05 2011Closeout SubmittalsDD Form 13540G
1701 35 26.00 2201Preconstruction SubmittalsAccident Prevention Plan (APP)1.7G
1801 35 26.00 2206Test ReportsMonthly Exposure Reports1.4
1901 35 26.00 2206Test ReportsNotifications and Reports1.12
2001 35 26.00 2206Test ReportsAccident Reports1.12.2G
2101 35 26.00 2206Test ReportsLHE Inspection Reports1.12.3
2201 35 26.00 2207CertificatesCrane Operators/Riggers1.6.1.5
2301 35 26.00 2207CertificatesStandard Lift Plan1.7.2.2G
2401 35 26.00 2207CertificatesCritical Lift Plan1.7.2.3G
2501 35 26.00 2207CertificatesNaval Architecture Analysis1.7.2.3G
2601 35 26.00 2207CertificatesActivity Hazard Analysis (AHA)1.8
2701 35 26.00 2207CertificatesConfined Space Entry Permit1.9.1
2801 35 26.00 2207CertificatesHot Work Permit1.9.1
2901 35 26.00 2207CertificatesCertificate of Compliance1.12.4
3001 35 26.00 2207CertificatesThird Party Certification of Barge-Mounted Mobile Cranes0
3101 35 26.00 2207CertificatesLicense Certificates1.14
3201 35 26.00 2207CertificatesRadiography Operation Planning Work Sheet1.14.1G
3301 45 00.10 2201Preconstruction SubmittalsQC Plan1.6G
3401 50 00.00 2201Preconstruction SubmittalsConstruction site plan1.4G
3501 50 00.00 2201Preconstruction SubmittalsTraffic control plan3.3.1G
3601 50 00.00 2206Test ReportsBackflow Preventer Tests2.2.5G
3701 50 00.00 2207CertificatesBackflow Tester1.5.1G
3801 50 00.00 2207CertificatesBackflow Preventers1.5G
3901 57 19.00 2201Preconstruction SubmittalsPreconstruction Survey1.5.1G
4001 57 19.00 2201Preconstruction SubmittalsSolid Waste Management Plan3.4G
4101 57 19.00 2201Preconstruction SubmittalsRegulatory Notifications1.5.2G
4201 57 19.00 2201Preconstruction SubmittalsEnvironmental Management Plan (EMP)3.1G
4301 57 19.00 2201Preconstruction SubmittalsDirt and Dust Control Plan3.14.1G
4401 57 19.00 2201Preconstruction SubmittalsContractor Hazardous Material Inventory Log3.6G
4501 57 19.00 2201Preconstruction SubmittalsStorm Water Management/Erosion and Sedimentation Control Plan3.2.1G
4601 57 19.00 2206Test ReportsLaboratory Analysis3.13.4.2G
4701 57 19.00 2206Test ReportsDisposal Requirements3.15.2G
4801 57 19.00 2206Test ReportsErosion and Sediment Control Inspection Reports3.2.4G
4901 57 19.00 2206Test ReportsSolid Waste Management Report3.4.1G
5001 57 19.00 2211Closeout SubmittalsStorm Water Management and Erosion Control Compliance Notebook3.2.1G
5101 57 19.00 2211Closeout SubmittalsWaste Determination Documentation3.5G
5201 57 19.00 2211Closeout SubmittalsDisposal Documentation for Hazardous and Regulated Waste3.13.4.4G
5301 57 19.00 2211Closeout SubmittalsContractor 40 CFR Employee Training Records1.5.5G
5401 57 19.00 2211Closeout SubmittalsSolid Waste Management Report3.4.1G
5501 57 19.00 2211Closeout SubmittalsContractor Hazardous Material Inventory Log3.6G
5601 57 19.00 2211Closeout SubmittalsHazardous Waste/Debris Management3.13.4G
5701 57 19.00 2211Closeout SubmittalsRegulatory Notifications1.5.2G
5801 74 19.00 2201Preconstruction SubmittalsWaste Management Plan1.3G
5901 74 19.00 2211Closeout SubmittalsRecords1.4G
6001 78 00.00 2203Product DataAs-Built Record of Equipment and Materials1.3.2G
6101 78 00.00 2203Product DataWarranty Management Plan1.7.1G
6201 78 00.00 2203Product DataWarranty Tags1.7.4G
6301 78 00.00 2203Product DataFinal Cleaning0G
6401 78 00.00 2203Product DataSpare Parts Data1.4G
6501 78 00.00 2208Manufacturer’s InstructionsPreventative Maintenance1.5G
6601 78 00.00 2208Manufacturer’s InstructionsCondition Monitoring (Predictive Testing)1.5G
6701 78 00.00 2208Manufacturer’s InstructionsInspection1.5G
6801 78 00.00 2208Manufacturer’s InstructionsInstructions1.7.1G
6901 78 00.00 2210Operation and Maintenance DataOperation and Maintenance Manuals1.9G
7001 78 00.00 2211Closeout SubmittalsRecord Drawings1.3.1G
7101 78 00.00 2211Closeout SubmittalsCertification of EPA Designated Items1.6G
7201 78 00.00 2211Closeout SubmittalsCertification of EPA Designated Items1.6G
7301 78 00.00 2211Closeout SubmittalsRed Zone Documents1.3.6G
7401 78 2310Operation and Maintenance DataO&M Database0G
7501 78 2310Operation and Maintenance DataTraining Plan3.1.1G
7601 78 2310Operation and Maintenance DataTraining Outline3.1.3G
7701 78 2310Operation and Maintenance DataTraining Content3.1.2G
7801 78 2311Closeout SubmittalsTraining Video Recording3.1.4G
7901 78 2311Closeout SubmittalsValidation of Training Completion3.1.6G
8001 78 24.00 2211Closeout SubmittalseOMSI, Progress Submittal1.4.1G
8101 78 24.00 2211Closeout SubmittalseOMSI, Prefinal Submittal1.4.2G
8201 78 24.00 2211Closeout SubmittalseOMSI, Final Submittal1.4.3G
8323 64 2603Product DataGrooved Mechanical Connections For SteelG
8423 64 2603Product DataGrooved Mechanical Connections For CopperG
8523 64 2603Product DataCalibrated Balancing ValvesG
8623 64 2603Product DataAutomatic Flow Control ValvesG
8723 64 2603Product DataPump Discharge Valve
8823 64 2603Product DataWater Temperature Mixing ValveG
8923 64 2603Product DataWater Temperature Regulating ValvesG
9023 64 2603Product DataWater Pressure Reducing Valve
9123 64 2603Product DataPressure Relief Valve
9223 64 2603Product DataCombination Pressure and Temperature Relief Valves
9323 64 2603Product DataExpansion Joints2.4.2G
9423 64 2603Product DataPumpsG
9523 64 2603Product DataCombination Strainer and Pump Suction Diffuser
9623 64 2603Product DataExpansion Tanks
9723 64 2603Product DataAir Separator Tanks
9823 64 2603Product DataWater Treatment SystemsG
9923 64 2606Test ReportsPiping Welds NDE Report
10023 64 2606Test ReportsPressure Tests Reports3.4.2G
10123 64 2606Test ReportsCondenser Water Quality Test ReportsG
10223 64 2606Test ReportsOne-Year Inspection Report For Cooling WaterG
10323 64 2607CertificatesEmployer's Record Documents (For Welding)
10423 64 2607CertificatesWelding Procedures and Qualifications
10523 64 2608Manufacturer’s InstructionsLesson plan for the Instruction Course3.5G
10623 64 2610Operation and Maintenance DataWater Treatment SystemsG
10723 64 2610Operation and Maintenance DataCalibrated Balancing ValvesG
10823 64 2610Operation and Maintenance DataAutomatic Flow Control ValvesG
10923 64 2610Operation and Maintenance DataPump Discharge ValveG
11023 64 2610Operation and Maintenance DataWater Temperature Mixing ValveG
11123 64 2610Operation and Maintenance DataWater Temperature Regulating ValvesG
11223 64 2610Operation and Maintenance DataWater Pressure Reducing ValveG
11323 64 2610Operation and Maintenance DataPressure Relief ValveG
11423 64 2610Operation and Maintenance DataCombination Pressure and Temperature Relief ValvesG
11523 64 2610Operation and Maintenance DataExpansion Joints2.4.2G
11623 64 2610Operation and Maintenance DataPumpsG
11723 64 2610Operation and Maintenance DataCombination Strainer and Pump Suction DiffuserG
11823 64 2610Operation and Maintenance DataExpansion TanksG
11923 64 2610Operation and Maintenance DataAir Separator TanksG