Amendment 0001.docx
DOCX document 31 KB Posted
- Attached to
- Midterm Availability (MTA) on the USNS ROBERT E. PEARY (T-AKE 9) Federal contract opportunity
- Solicitation number
- N3220522R4035
About this file
This document contains an amendment to a solicitation for ship repair and maintenance services on the USNS ROBERT E. PEARY. Key details include:
-
The amendment provides responses to contractor questions to clarify work item numbering and descriptions. It also revises estimated electrical usage and updates references in various work items.
-
The original solicitation seeks proposals for midterm repair and maintenance availability on the USNS ROBERT E. PEARY beginning August 9, 2022 for 46 days. Estimated electrical usage was revised from 60 to 46 days.
-
The Navy will release solicitation N3220522R4035 on or around February 23, 2022. Proposals are due by February 24, 2022. The contract period of performance is August 9 to September 23, 2022.
-
The work will be awarded competitively under FAR Part 15 to contractors in the Gulf and East Coast regions of the United States. No set-aside status applies. The Military Sealift Command and Department of the Navy are the contracting agencies.
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N3220522R4035
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION J - LIST OF DOCUMENTS, EXHIBITS & OTHER ATTACHMENTS
The following have been added by full text:
RFC RESPONSES AMENDMENT 0001
MILITARY SEALIFT COMMAND
N3220521R4035
Request for Clarification
SPECIFICATION ITEM NO.: 502
PARAGRAPH / SECTION NO: NA
TITLE: JP5 SYSTEM FUEL FLOW METER INSTALLATION (T-ALT 322)
QUESTION: Work Item 502 is listed on the Work Item Index and the J-2 Category A pricing sheet, but individual work item is titled “503”. Please clarify.
ANSWER: Labeling Error. Work item 502 is JP5 SYSTEM FUEL FLOW METER INSTALLATION (T-ALT 322). Please see revised work item.
SPECIFICATION ITEM NO.: 503
TITLE: CARGO AND AC PLANT INSP AND GROOM
QUESTION: Work Item 503 is listed on the Work Item Index and the J-2 Category A pricing sheet, but individual work item is titled “521”. Please clarify.
ANSWER: Labeling Error. Work item 503 is Cargo and AC Plant Insp and Groom. Please see revised work item.
Changes to include
011 - Revised estimate in Section 7.2.A to read as follows:
The contractor will base its offer on providing 29,000 KWH per day for 46 days, 1,334,000 KWH total.
0502 – Revised title block and footer to reflect 0502
0503 - Revised title block and footer to reflect 0503
Changes made before 1/6/2022
0302 – Updated references to include Peary’s specific drawings
090 – MSC Covid policy changed. Therefore revised work item sent to correctly follow MSC Covid Policies 0413 – MSC N6 Revised Scope of work section 7 to correctly identify scope of work as well as what testing is to be conducted.
SPECIFICATION ITEM NO.: 011
PARAGRAPH / SECTION NO: 7.2a
TITLE: GENERAL SERVICES FOR SHIP REV
QUESTION: Para. 7.2a states 60 days for kwh. Period of performance is 46 days. Please clarify.
ANSWER: Yes Period of performance in 46 days. Revised work item to read:
The contractor will base its offer on providing 29,000 KWH per day for 46 days, 1,334,000 KWH total.
SPECIFICATION ITEM NO.: 021
TITLE: CLEAN AND GAS FREE TANKS VOIDS COFFERDAMS AND SPACES - 02APR2021
QUESTION: Please confirm one tank is to be cleaned with this work item.
ANSWER: Yes, this work item is only One (1) tank. This is to support work item 0209
SPECIFICATION ITEM NO.: 030 “B”
PARAGRAPH / SECTION NO: 7.6, 7.7, AND 7.8.13
TITLE: CONTINUATION OF SERVICES REV – 02APR2021
QUESTION: For paragraphs 7.6, 7.7, and 7.8, J-3 Category “B” and work item specification do not match. Please clarify.
ANSWER: Please see revised J-3
SPECIFICATION ITEM NO.: 0503 & 0521
TITLE: DISCREPANCY IN WORK ITEM NUMBERING
QUESTION: After reviewing the individual work items the following was noted. WI-0503 is listed as Work Item 0502 on index. Work item Cargo and AC Plant Insp and Groom is titled Work Item 0521 but is listed as WI-0503 on index. Work Item 0521 is not listed as an item on the index.
ANSWER: Labeling Error. Work item 502 is JP5 SYSTEM FUEL FLOW METER INSTALLATION (T-ALT 322). Please see revised work item.
Labeling Error. Work item 503 is Cargo and AC Plant Insp and Groom. Please see revised work item.
SPECIFICATION ITEM NO.: WORK PACKAGE
TITLE: WORK PACKAGE
QUESTION: Please advise what work items have been revised with the new work item package received 1/26/22.
There are various work items such as items 090 and 413 that have been revised without mention. Additionally, it was stated that there was a numbering issue, and the package was being resent with those work items, but the entire work package was resent without clarification. Work items have gone out to subcontractors and changes to the package must be known.
ANSWER: Zip file “REP MTA 22 Work Items 01.25.2022” is the compiled work items to be used.
Changes to include
011 - Revised estimate in Section 7.2.A to read as follows:
The contractor will base its offer on providing 29,000 KWH per day for 46 days, 1,334,000 KWH total.
0502 – Revised title block and footer to reflect 0502
0503 - Revised title block and footer to reflect 0503
Changes made before 1/6/2022
0302 – Updated references to include Peary’s specific drawings
090 – MSC Covid policy changed. Therefore revised work item sent to correctly follow MSC Covid Policies
0413 – MSC N6 Revised Scope of work section 7 to correctly identify scope of work as well as what testing is to be conducted.
SPECIFICATION ITEM NO.: J-2
PARAGRAPH / SECTION NO: N/A
TITLE: J-2
QUESTION: Provided J-2 has two sections for 1000 work items. Additionally, work item 661 is listed on the J-2 under section 1000 but was not provided with the work package, please clarify if it is to be provided.
ANSWER: J-2 has a 0000 section and 1000. No work item 0661 is listed in J-2 or work items.
(End of Summary of Changes) image1.wmf