N00173-13-R-PW10-0005.pdf

PDF 1 MB Posted

Attached to
Subsystems and Modules for Radio Frequency Distribution System
Solicitation number
N00173-13-R-PW10
Issued by

About this file

Amendment 0005

View the file

Other files

File Type Posted
N00173-13-R-PW10-0007.pdf PDF
N00173-13-R-PW10-0006.pdf PDF
N00173-13-R-PW10-0004.pdf PDF
N00173-13-R-PW10-0003.pdf PDF
N00173-13-R-PW10-0002.pdf PDF
N00173-13-R-PW10-0001.pdf PDF
Attachment_1.pdf PDF
Attachment_2.xlsx XLSX spreadsheet
ExhibitB.pdf PDF
N00173-13-R-PW10.pdf PDF
ExhibitA.pdf PDF
ExhibitD.pdf PDF
N00173-13-R-PW10_draft.pdf PDF
Attachment_2.xlsx XLSX spreadsheet
ExhibitA.pdf PDF
ExhibitD.pdf PDF
ExhibitB_draft.pdf PDF
Attachment_1.pdf PDF
http //heron.nrl.navy.mil/contracts/13PW10.html HTML file
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N00173-13-R-PW10-0005

The purpose of this amendment is to answer a question from a potential offeror.

1. The following is the answer to a question received from a vendor. The numbering of the questions is continued from the previous amendment.

Q. 26. Would NRL entertain a bid for hardware only and not the OCONUS/CONUS Support Services?

A. 26. No. FAR 52.215-1, included in the solicitation by reference, at (c)(4) states that “Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items” [emphasis added].

Section L-8 of the solicitation states that “The proposal shall be a complete response to the statement of work and the requirements of this RFP, taking into consideration required production quantities and delivery schedules specified in this solicitation.

“Alternate proposals that depart from stated requirements will not be considered and shall not be submitted. The offeror may submit multiple proposals that offer different approaches to meet the stated requirements.”

The language cited above from the last paragraph in L-8 otherwise specifies, per FAR FAR 215-1(c)(4), that alternate proposals will not be accepted.