This document contains a solicitation for a Digital Signal Processor (DSP) Inverter procurement. The Naval Air Systems Command (NAVAIR) H-1 Upgrades Program Office (PMA-276) intends to award a firm fixed price contract for the design, development, testing, certification, and production of DSP Inverters for the UH-1Y aircraft. The base contract will include non-recurring engineering costs along with the delivery of flight test and verification assets. Option years are contemplated for additional low-rate initial production quantities in FY2021 and FY2022, as well as spares packages and potential foreign military sales. Offerors must submit any questions by August 5, 2019, and contract award is targeted for the second quarter of FY2020.
Attachment L-3
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0002.docx | DOCX document | |
| Questions_and_Answers_Rev1_22_Aug_2019.xlsx | XLSX spreadsheet | |
| Questions_and_Answers.xlsx | XLSX spreadsheet | |
| Amendment_0001.docx | DOCX document | |
| L-3_Vol_3_Price_Summary_Revision.xlsx | XLSX spreadsheet | |
| L-4_Vol_3_GFE_Summary.xlsx | XLSX spreadsheet | |
| L-1_Vol_1_ES_Tables.xlsx | XLSX spreadsheet | |
| L-2_Vol_2_T-1_SB_Goals.xlsx | XLSX spreadsheet | |
| RFP_N00019-19-R-0030.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet2
| Section L Cost - Attachment L-3 | |||||||||||||||
| Price Summary Table | |||||||||||||||
| DIRECT LABOR | MATERIAL | ODC | SUBCONTRACT | ||||||||||||
| CLIN | HRS | COST | O/H | SUBTL | COST | O/H | SUBTL | SUBTL | SUBTL | SUBTL | G&A | TOTAL | FCCM | FEE | Est. PRICE |
| CLIN 0001 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| CLIN 0002 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| CLIN 0003 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| CLIN 0004 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| CLIN 1001 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| CLIN 2001 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| CLIN 2002 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Qty 60-80 Unit Price | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| Qty 81-100 Unit Price | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| CLIN 3001 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Qty 15-25 Unit Price | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Calcualted Fields, please do not change
Sheet1
| Section L Cost - Attachment L-3 | ||||||||||||||||
| Cost Summary Table | ||||||||||||||||
| DIRECT LABOR | MATERIAL | ODC | SUBCONTRACT | |||||||||||||
| WBS | Nomenclature | HRS | COST | O/H | SUBTL | COST | O/H | SUBTL | SUBTL | SUBTL | SUBTL | G&A | TOTAL | FCCM | FEE | Est. PRICE |
| 1.0 | UH-1Y DSP Inverter Redesign | 0 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0.00 | 0 | 0 | 0.00 |
| 1.1 | DSP Inverter | 0 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0.00 | 0 | 0 | 0.00 |
| 1.1.1 | Integration, Assembly, Test, and Checkout | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.1.2 | Hardware | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.1.3 | Firmware | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.2 | Platform Integration, Assembly, Test, and Checkout | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.3 | Systems Engineering | 0 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0.00 | 0 | 0 | 0.00 |
| 1.3.1 | Integrated Logistics Support (ILS) Systems Engineering | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.3.2 | Core Systems Engineering | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.4 | Program Management | 0 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0.00 | 0 | 0 | 0.00 |
| 1.4.1 | Integrated Logistics Support (ILS) Program Management | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.4.2 | Core Program Management | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.5 | System Test and Evaluation | 0 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0.00 | 0 | 0 | 0.00 |
| 1.5.1 | Development Test and Evaluation | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.5.2 | Operational Test and Evaluation | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.5.3 | Test and Evaluation Support | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.5.4 | Test Facilities | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.6 | Training | 0 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0.00 | 0 | 0 | 0.00 |
| 1.6.1 | Equipment | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.6.2 | Services | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.7 | Data | 0 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0.00 | 0 | 0 | 0.00 |
| 1.7.1 | Data Deliverables CDRL A001-A009, A00A-A00H, A00J-A00N,A00P-A00W | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.7.2 | Data Repository | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.7.3 | Data Rights 1...n (Specify) | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.8 | Peculiar Support Equipment | 0 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0.00 | 0 | 0 | 0.00 |
| 1.8.1 | Test and Measurement Equipment | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.8.2 | Support and Handling Equipment | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.9 | Common Support Equipment | 0 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0 | 0.00 | 0 | 0.00 | 0 | 0 | 0.00 |
| 1.9.1 | Test and Measurement Equipment | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.9.2 | Support and Handling Equipment | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.10 | Operational/Site Activation by Site 1...n (Specify) | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.11 | Contractor Logistics Support (CLS) | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.12 | Industrial Facilities | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | ||||||||||
| 1.13 | Initial Spares and Repair Parts | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |