MFL Solicitation.pdf
PDF 628 KB Posted
- Attached to
- Multnomah Falls Lodge Electrical Upgrades
- Solicitation number
- 1240BH21R0011
About this file
This Request for Proposals from the USDA Forest Service seeks electrical upgrades at the Multnomah Falls Lodge. The project scope includes replacing all electric panels, installing an automatic transfer switch, emergency shut-off switch and strobe lights, as well as new distribution panels, a main switchboard, lighting and other electrical equipment. Site work is required for installation of the main switchboard and automatic transfer switch. The project is located approximately 33 miles east of Portland, Oregon with an estimated value between $1,000,000 to $5,000,000 including optional items. A mandatory site visit is scheduled for April 28, 2021 and a pre-proposal conference call is scheduled for May 4, 2021. Prospective offerors must be registered in SAM and maintain registration through award and performance. The closing date for proposals was not provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF24-Bid Bond Form.pdf | ||
| Wage Determination.pdf | ||
| MultnomahLodge-DWGS-22x36-20210122.pdf | ||
| MFL Electrical Specs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OMB APPROVAL NO. 2700-0042
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
1240BH21R0011
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED
04/14/2021
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
6. PROJECT NO.
7. ISSUED BY CODE 8. ADDRESS OFFER TO
Procurement & Property Services NW Zone CSA 6 – Construction & AE Group 1220 SW 3rd Avenue Portland, OR. 97204
Email Submission Only Note: Due to COVID-19, all proposal documents must be emailed to leslie.solberg@usda.gov
9. FOR INFORMATION
CALL:
A. NAME
Leslie Solberg
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS) 503-668-1667
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
Electrical renovation of the Multnomah Falls Lodge, Bridal Veil, Oregon
This is a set-aside for Total Small Business – Contractors must be registered in SAM
NAICS code: 238210 (Electrical Contractors and Other Wiring Installation Contractors)
Price Range (FAR 36.204) The Government's estimate is between $1,000,000 and $5,000,000 (Base and Option Items)
Proposal due on 05/14/2021 by 4pm (PST) Emailed to block #8
See page 39 for required documents to be submitted for evaluation
11. The Contractor shall begin performance within 10 calendar days and complete it within 200 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See .)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
YES NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and -0- copies to perform the work required are due at the place specified in Item 8 by 4pm(PST) local time 05/14/2021. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e) mailto:leslie.solberg@usda.gov
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14)
CODE FACILITY CODE
17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract.
The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED
TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS
Bid Item Description Quantity Unit Total Cost
Base Bid Items 01 Multnomah Falls Electrical System - Base Bid 1 LS $ Bid Options
02 BO 1 - Install Panel C 1 LS $ 03 BO 2 - Install Panel H 1 LS $ 04 BO 3 - Install Panel M 1 LS $ 05 BO 4 - Install Panel SB1 1 LS $ 06 BO 5 - Install Panel SB2 1 LS $ 07 BO 6 - Install Panel SB3 1 LS $ 08 BO 7 - Install Panel N 1 LS $ 09 BO 8 - Install Panel R 1 LS $ 10 BO 9 - Install Panel J 1 LS $ 11 BO 10 - Install Panel Q 1 LS $ 12 BO 11 - Replace Outlet Receptacles 1 LS $ 13 BO 12 - Install New HVAC Disconnects 1 LS $
14 BO 13 - Benson Park Standby Generator System Not In
Contract
15 BO 14 - Multnomah Falls Standby Generator System Not In
Contact Total All Bid Options $ Total Base Bid Plus Bid Options $
LS = Lump Sum
All items are described in detail in Section C of this document. While the schedule above provides for a lump sum price, the Government will require a detailed price breakdown for each item as part of the Schedule of Values.
The Contractor shall bid on all items, including the option items. Any of the Option Items may be awarded if the Government decides to accept the option item. The Government is not obligated to award any of the option items.
Note: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed- Price Construction Contracts, shall not be in additions to the contract price. Include bond payments under Mobilization.
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
The purpose of this contract is to demolish and install electric components at Multnomah Falls Lodge. The work will include replacing all electric panels, installation of ATS, emergency shut-off switch and strobe; installation of new distribution panels, main switch board, panelboard T, lighting and other electrical equipment to make the electrical improvements complete. There is site work included with the installation of the main switch board and ATS.
C.2 PROJECT LOCATION
Bridal Veil, OR. The project is located approximately 33 miles east of Portland, OR on Highway I-84.
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
Price Range (FAR 36.204) The Government’s estimate is between $1,000,00 and $5,000,00 (including optional items)
C.4 AGAR 452.211-72 STATEMENT OF WORK/SPECIFICATIONS (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
C.5 AGAR 452.211-73 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS
(FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
C.6 BIOBASED PROGRAM REQUIREMENTS
The Contractor must comply with Section 9002 of the Farm Security and Rural Investment Act of 2002 (FSRIA), Executive Order (EO) 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” and the Federal Acquisition Regulation to provide biobased products.
The Contractor shall utilize products and material made from biobased materials (e.g., insulating foam, composite panels, and concrete and asphalt release fluids) to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR).
The following is an example list of products that may be used in this contract for minor construction for which biobased products are available. The list is not all inclusive. It is desirable that vendors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.
Graffiti and grease removers Insulation foam Concrete and asphalt release fluids Fluid-filled transformers Wood and concrete sealers Composite panels Adhesive and mastic removers Carpets Roof coating Hydraulic fluid Diesel fuel additives Greases
Dust suppressant 2-cycle engine oil Absorbents
Biobased products that are designated for preferred procurement under USDA’s BioPreferred program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov. The Contractor should provide data for their biobased products such as biobased content and source of biobased material
In addition to the biobased products designated by the U.S. Department of Agriculture in the BioPreferred Program, the Contractor is encouraged to use other commercially available biobased products.
The awarded Contractor on each anniversary date of the contract shall compile a complete list of biobased products, including the information above, purchased to carry out the contract requirements. The Contractor shall list volume to be used and total cost for each individual product. This information will be used for reporting purposes.
The Contractor shall comply with the provision at FAR 52.223-1, Biobased Product Certification.
The Contractor shall comply with the clause at FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
SECTION D--PACKAGING AND MARKING
{For this Solicitation, there are NO clauses in this Section}
SECTION E--INSPECTION AND ACCEPTANCE
E.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/?q=browsefar
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996) 52.246-13 Inspection—Dismantling, Demolition, or Removal of Improvements (AUG 1996)
E.2 AGAR 452.246-70 INSPECTION AND ACCEPTANCE (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at the project site.
E.3 INSPECTION AND TESTING PERFORMED BY GOVERNMENT
The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Special Project Specifications.
E.4 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.
https://www.acquisition.gov/?q=browsefar
SECTION F--DELIVERIES OR PERFORMANCE
F.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.211-13 Time Extensions (SEP 2000) 52.242-14 Suspension of Work (APR 1984)
F.2 FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 200 days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
http://www.arnet.gov/far/
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and he within 30 days after the date of contract award. The conference will be held at the Multnomah Falls Lodge, located approximately 33 miles east of Portland, OR on Highway I-84, or virtually through Teams.
G.2 DESIGNATION OF CONTRACTING OFFICER’S REPRESENTATIVE
The Contracting Officer will designate a Contracting Officer's Representative (COR) at the time of contract award.
The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract).
On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
G.3 CONTRACT RELEASE
When submitting final payment, Contractor shall provide a signed and dated contract release that includes the following information: "In consideration of receipt of final payment in the amount of $__________ Contractor hereby releases the United States of America from any and all obligations arising under this contract and any modifications thereof except as reserved herein.
Reservations:______________"
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,
EQUIPMENT, UTILITIES, AND IMPROVEMENTS (APR 1984)
(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work sites, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workman, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by Contracting Officer.
(b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the location of which are made know to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor
H.2 AGAR 452.237-74 KEY PERSONNEL (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel: Project Manager
(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutions, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
H-3. Conformity with Drawings and Specifications
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.
A. Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
B. The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
C. Government inspections and tests are for the sole benefit of the Government and do not--
1. Relieve the Contractor of responsibility for providing adequate quality control measures;
2. Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
3. Constitute or imply acceptance; or
4. Affect the continuing rights of the Government after acceptance of the completed work under paragraph (I) below.
D. The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
E. The Contractor shall promptly furnish, without additional charge, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
F. The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
G. If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or (2) terminate for default the Contractor's right to proceed.
H. If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
I. Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
H-4. Product Substitution
Any modification of other items, designs, materials, products or equipment (including Government-furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.
H-5. Contractor’s Representation & Responsibility
A. In making formal request for substitution the Contractor represents he/she:
1. Have investigated proposed product and determined that it is equal to or superior in all respects to that originally specified.
2. Will provide same warranties and bond for substitute as for originally specified product.
3. Will coordinate installation of accepted substitution into the work, and will make such changes as may be required for the work to be complete in all respects.
4. Will waive claims for additional costs caused by substitution, which may subsequently become apparent.
5. Cost data is complete and includes related costs under the contract, but not:
a. Costs under separate contracts.
b. Contracting Officer costs for redesign or revision of contract documents.
B. The Contractor assumes full responsibility that the substitution and/or alternate items or procedures proposed will meet the job requirements.
C. The Contractor is solely responsible for the cost of redesign and modifications to this and other parts of the work caused by the substitutions or alternates furnished.
H-6. Traffic Control
The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagman and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
The Contractor shall furnish, erect, maintain, and remove when notified any project identification signs shown on the drawings
Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.
H-7. Safety
Identify inherently hazardous conditions that could lead to serious injury or loss of life.
Identify and describe inherently hazardous conditions.
Recognize hazards when contracting for inherently hazardous working conditions.
When inherently hazardous conditions exist, the contract should require a written, job-specific safety plan for information and discussion at the post award meeting.
Plan to reduce safety hazards and the costs of litigation.
Make sure that inherently hazardous conditions are documented and are written up in a job-specific Job Hazard Analysis (JHA) for Forest Service employees involved. This will help identify hazards involved in the job.
For each contract evaluate working conditions to determine if specific inherently hazardous conditions will be encountered as part of the needed construction work. If these conditions do exist, they need to be listed in the contract.
H-8. Additional Requirements or Restrictions
Contract work on this project will not begin until this Fall, 2021
H-9. Suspensions for Other Than Government’s Convenience
The Contracting Officer may issue orders to suspend the work wholly or in part for such period of time as deemed necessary because of: (1) Weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project, or adjacent property. Such action would include but not be limited to instances such as siltation of streams, damage to access roads, rutting of project roads which causes otherwise suitable soils to become muddy or unsuitable; or (2) Failure of the Contractor to comply with Specifications such as but not limited to placement of frozen material in fills, placing of asphalts at temperatures lower than those specified, performing work prior to prerequisite approvals, operating equipment not meeting fire requirements, or when conditions exist which do not meet safety requirements. Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by his/her operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR 52.242-14, Suspension of Work, and shall not qualify for equitable adjustment.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.dm.usda.gov/procurement/policy/agar.html
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-13 Contractor Code of Business Ethics and Conduct (JUN 2020)
52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (JUN 2020)
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreement or Statements (JAN 2017)
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper |
(MAY 2011)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
(JUN 2020)
52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016)
52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or
Provided by Kaspersky Lab and Other Covered Entities (JUL 2018) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video
Surveillance Services or Equipment (AUG 2020) 52.204-22 Alternative Line Item Proposal (JAN 2017) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors
Debarred, Suspended, or Proposed for Debarment (JUN 2020) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
(OCT 2018)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.215-8 Order of Precedence – Uniform Contract Format (OCT 1997) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020)
52.219-8 Utilization of Small Business Concerns (OCT 2018) 52.219-9 Small Business Subcontracting Plan (JUN 2020) Alternate II (NOV 2016)
52.219-14 Limitations on Subcontracting (JAN 2017) 52.219-28 Post-Award Small Business Program Representation (NOV 2020) 52.222-3 Convict Labor (JUNE 2003) 52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation
(MAY 2018)
52.222-6 Construction Wage Rate Requirements (AUG 2018)
52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (AUG 2018) 52.222-9 Apprentices and Trainees (JULY 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations
(MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000
(MAY 2014)
52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (SEPT 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020)
52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employees Rights Under the National Labor Relations Act
(DEC 2010)
52.222-50 Combating Trafficking in Persons (OCT 2020) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.222-55 Minimum Wages Under Executive Order 13658 (NOV 2020)
52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction
Contracts (SEP 2013) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy-Consuming Products (MAY 2020) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction
Contracts (AUG 2018) 52.223-18 Encouraging Contractor Policies to Ban Test Messaging While Driving
(JUN 2020)
52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997)
52.228-5 Insurance—Work on a Government Installation (JAN 1997) 52.228-11 Individual Surety-Pledges of Assets (FEB 2021) (DEVIATION APR 2020)
52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds – Construction (JUN 2020)(DEVIATION APR
2020) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014)
52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management
(OCT 2018)
52.232-39 Unenforceability of Unauthorized Obligations (JUNE 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)
52.233-1 Disputes (MAY 2014) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984)
52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984)
52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995)
52.242-5 Payment to Small Business Subcontractors (JAN 2017) 52.242-13 Bankruptcy (JULY 1995) 52.243-4 Changes (JUNE 2007) 52.244-6 Subcontracts for Commercial Items (NOV 2017)
52.245-1 Government Property (JAN 2017) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994) Alternate I (MAR 1994)
52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)--
Alternate I (SEP 1996) 52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, Or
Removal of Improvements (APR 2012) 52.249-10 Default (Fixed-Price Construction) (APR 1984)
52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts
(NOV 1996)
452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)
I-2. FAR 52.217-7 Option for Increased Quantity—Separately Priced Line Item (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 180 days. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
I.3 FAR 52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (FEB 2021)
(a) Definitions. As used in this clause—
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
https://acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508 http://uscode.house.gov/
“Cost of components” means—
(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which non availability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: None
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
http://uscode.house.gov/ http://uscode.house.gov/ https://acquisition.gov/far/current/html/Subpart%2012_5.html#wp1077123
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material.
However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
FOREIGN AND DOMESTIC CONSTRUCTION MATERIALS PRICE COMPARISON
Construction Material Description Unit of Measure Quantity Price (Dollars)* Item 1:
Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2: _______ _______ Foreign construction material _______ _______ _______ Domestic construction material
I.4 FAR 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –
(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION APR 2020)
(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond -
(1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and
(2) Standard Form 28, Affidavit of Individual Surety, [except that the words “being duly sworn, depose and say” on the Standard Form 28 are replaced with the word “affirm” and the Standard Form 28 is not required to be sworn and notarized in block 12].
(b)The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained—
(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.
(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.
https://www.acquisition.gov/far/part-28#FAR_28_203_1
(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.
(c)A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a Federal district court judgment, or a sworn statement by the subcontractor or supplier that the claim is correct along with a notarized authorization of the release by the surety stating that it approves of such release. The security interest on the individual surety's assets in support of a payment bond shall be maintained—
(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds (40 U.S.C. 3131). For 1 year following final payment, or until resolution of all pending claims filed against the payment bond during the 1-year period following final payment, whichever is later.
(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.
(3) Other contracts not subject to the requirements of paragraph (c)(1) of this clause. For 90 days following final payment.
(d)The Contracting Officer may allow the Contractor to substitute an individual surety, for a performance or payment bond, after contract award. The Contractor shall comply with the requirements of paragraph (a) of this clause within the timeframe established by the Contracting Officer.
52.228-15 Performance and Payment Bonds -- Construction (JUN 2020) (DEVIATION APR 2020)
(a)Definitions. As used in this clause -- “Original contract price” means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance Bonds (Standard Form 25, EXCEPT THAT A SEAL IS NOT REQUIRED).
The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25-A, EXCEPT THAT A SEAL IS NOT REQUIRED).
The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection.
(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
https://www.acquisition.gov/far/part-28#FAR_28_102_1
(c) Furnishing executed bonds. The Contractor shall furnish…
This is the start of the file's text. The full file is on GovTribe.