This is a Request for Proposals (RFP) issued by Maynard Public Schools in Massachusetts for a comprehensive Facility Condition Assessment (FCA) and the development of a Twenty-Year Capital Improvement Plan covering all District-owned school facilities and associated site infrastructure. The District is seeking qualified consulting firms capable of evaluating the physical condition of its buildings and grounds, identifying capital needs, and creating a strategic long-term plan for facility improvements and maintenance. The proposal must include detailed assessments of structural integrity, mechanical and electrical systems, accessibility compliance, and site conditions across all school properties. Interested firms must submit proposals by the specified deadline, with the District planning to conduct site visits and a bidders' conference to allow proposers to examine facilities and clarify requirements. The successful consultant will be selected based on qualifications, experience with similar projects, and proposed methodology, with the contract term extending twenty years to align with the planning horizon.
Specific pricing terms, budget allocations, and funding sources should be detailed in the RFP document, along with any requirements for insurance, bonding, or professional certifications. The District may have established set-asides for minority-owned or women-owned businesses as applicable under Massachusetts procurement regulations. Award of contract will be contingent upon the selected firm's ability to deliver comprehensive assessment reports, capital planning documentation, and recommendations for phased improvements. The consultant's work product will serve as the foundation for the District's facility investment decisions over the twenty-year planning period and may inform future bond referendums or grant applications for capital funding.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP 27-03 questions and responses Amendment 3.docx | DOCX document | |
| RFP 27-03 questions and responses.docx | DOCX document | |
| Amendment 1 RFP 27-03.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAYNARD PUBLIC SCHOOLS
REQUEST FOR PROPOSALS (RFP) #27-03
DISTRICT-WIDE FACILITY CONDITION ASSESSMENT AND
TWENTY-YEAR CAPITAL IMPROVEMENT PLAN
Issued Pursuant to Massachusetts General Laws Chapter 30B, Section 6
Issued By:
Maynard Public Schools
3-R Tiger Drive
Maynard, MA 01754
RFP Schedule
Event Date
Request for Proposals Issued 08/12/2026
Optional Pre-Proposal Site Visit
08/24/2026 @ 10AM
3Tiger Drive, Maynard, MA
Deadline for Questions 08/25/2026 @12 PM
Responses to Questions Issued 08/26/2026
Proposal Submission Deadline 09/02/2026 @2 PM
Anticipated Award Within 30 Days of Opening
Contact Person
All communications regarding this Request for Proposals shall be directed to:
Michelle Resendes
Director of Finance
Maynard Public Schools
3-R Tiger Drive
Maynard, MA 01754
Email: Mresendes@Maynard.k12.ma.us
Telephone: 978-897-8251 X4002
No interpretation of the meaning of the Request for Proposals shall be made orally. All questions regarding this solicitation shall be submitted in writing by the deadline indicated above.
Responses to questions will be issued by written addendum to all known proposers.
TABLE OF CONTENTS
1. Background and Project Overview
2. District Facilities
3. Scope of Services
4. Deliverables
5. Proposal Submission Requirements
6. Minimum Qualifications
7. Comparative Evaluation Criteria
8. Award of Contract
9. Procurement Schedule
10. Optional Pre-Proposal Site Visit
11. Questions and Addenda
Appendix A – Non-Collusion and Tax Compliance Certification
Appendix B – Price Proposal Form
Appendix C – Evaluation Committee Score Sheet
Appendix D – Reference Form
1. BACKGROUND AND PROJECT OVERVIEW
The Maynard Public Schools ("District") is seeking proposals from qualified consulting firms to conduct a comprehensive Facility Condition Assessment (FCA) and develop a Twenty-Year
Capital Improvement Plan for all District-owned school facilities and associated site infrastructure.
The purpose of this project is to provide the District with a comprehensive evaluation of the condition of its educational facilities and grounds while establishing a long-range capital planning document that will assist the School Committee, Superintendent, Town Administration, and Capital Planning Committee in making informed decisions regarding future capital investments.
The selected consultant shall perform a comprehensive visual assessment of each school building and associated site improvements, identify existing deficiencies, evaluate the remaining useful life of major building systems, provide budgetary cost estimates for recommended capital improvements, and prepare a prioritized twenty-year capital improvement plan.
The completed assessment will serve as a planning tool for:
• Annual capital budget development;
• Long-range financial planning;
• Capital Improvement Planning;
• Preventive maintenance planning;
• Asset preservation;
• Future grant opportunities;
• Future Massachusetts School Building Authority (MSBA) planning initiatives; and
• Ongoing facility management.
The District intends to select a consultant with demonstrated experience performing similar facility condition assessments and long-range capital planning studies for Massachusetts public school districts.
The successful proposer shall furnish all labor, supervision, equipment, materials, transportation, and professional services necessary to complete the work described in this Request for Proposals.
2. DISTRICT FACILITIES
The assessment shall include the following facilities and associated grounds.
Facility Approximate Square Footage
Maynard High School 107,500 SF
Fowler School 128,000 SF
Green Meadow School 90,525 SF
Total Building Area: Approximately 326,025 square feet
The assessment shall include all associated site improvements and infrastructure serving the above facilities, including but not limited to:
• Parking lots and driveways
• Sidewalks and pedestrian pathways
• Athletic fields and athletic facilities
• Playgrounds
• Site drainage systems
• Exterior lighting
• Landscaping
• Retaining walls
• Fencing
• Site utilities
• Exterior signage
• Loading areas
• Other exterior improvements owned and maintained by the District
The District reserves the right to include additional related facilities or site improvements of a similar nature if determined necessary during the course of the project.
3. SCOPE OF SERVICES
The Maynard Public Schools is seeking professional consulting services to perform a comprehensive Facility Condition Assessment (FCA) and develop a Twenty-Year Capital
Improvement Plan for all District-owned school buildings and associated grounds.
The selected consultant shall furnish all labor, supervision, equipment, transportation, materials, and professional services necessary to complete the assessment and prepare the required reports.
The assessment shall be based on a visual inspection of the facilities and shall include interviews with District personnel, review of available facility documentation, and other investigative efforts deemed appropriate by the consultant to prepare a comprehensive capital improvement plan.
The consultant shall evaluate the current condition of the District's facilities and provide recommendations for repair, replacement, or improvement based on observed conditions, remaining useful life, and industry standards.
At a minimum, the assessment shall include the following:
A. Building Envelope
Evaluate the condition of:
• Roof systems
• Exterior walls
• Windows
• Exterior doors
• Masonry
• Building foundations (visual observations only)
• Exterior sealants
• Waterproofing systems
• Building façade components
The consultant shall identify observed deficiencies, deferred maintenance items, and anticipated replacement needs.
B. Structural Systems
Evaluate the observable condition of:
• Structural framing
• Floor systems
• Roof framing
• Foundations (visual observations)
• Signs of settlement
• Signs of structural deterioration
This assessment shall be visual in nature and shall not include destructive testing or structural calculations unless specifically authorized by the District.
C. Mechanical Systems
Review the condition of:
• Heating systems
• Ventilation systems
• Air conditioning systems
• Boilers
• Chillers (if applicable)
• Rooftop units
• Heat pumps
• Building automation systems
• Temperature controls
• Pumps
• Domestic hot water systems
• Plumbing distribution systems
D. Electrical Systems
Review the condition of:
• Main electrical service
• Electrical distribution equipment
• Panelboards
• Lighting systems
• Emergency lighting
• Exit lighting
• Emergency generators (if applicable)
• Fire alarm systems
• Security systems
• Access control systems
E. Interior Building Components
Review the condition of:
• Floors
• Walls
• Ceilings
• Interior doors
• Hardware
• Casework
• Restrooms
• Painting
• General interior finishes
F. Site Improvements
Review the condition of:
• Parking lots
• Sidewalks
• Curbing
• Site drainage
• Retaining walls
• Exterior stairs
• Loading areas
• Site utilities
• Exterior lighting
• Fencing
• Signage
G. Athletic and Recreational Facilities
Evaluate:
• Athletic fields
• Tennis courts
• Playgrounds
• Outdoor recreation areas
• Bleachers
• Athletic support facilities
H. Accessibility
Provide general observations regarding compliance with the Americans with Disabilities Act
(ADA) and identify readily observable accessibility deficiencies.
This review is intended as a planning tool only and is not intended to constitute a comprehensive
ADA compliance audit.
I. Capital Improvement Plan
Based upon the assessment, the consultant shall prepare a Twenty-Year Capital Improvement
Plan identifying anticipated capital projects and estimated replacement timeframes.
The Capital Improvement Plan shall include:
• Description of each recommended project
• General project location
• Estimated year of replacement or repair
• Budgetary opinion of probable cost
• Recommended project priority
• General description of the recommended work
J. Meetings
The consultant shall attend meetings as necessary throughout the project, including:
• Project kickoff meeting
• Progress meeting(s), as required
• Presentation of draft findings
• Presentation of the final report to the School Committee and/or other designated Town officials
4. DELIVERABLES
Upon completion of the project, the selected consultant shall provide the District with a comprehensive Facility Condition Assessment and Twenty-Year Capital Improvement Plan.
At a minimum, the final deliverables shall include:
A. Existing Conditions Report
A written report summarizing the existing condition of each facility and associated site improvements evaluated as part of this project.
The report shall identify observed deficiencies, deferred maintenance items, and recommendations for repair or replacement of major building systems and site infrastructure.
B. Twenty-Year Capital Improvement Plan
A comprehensive capital improvement plan identifying recommended capital projects over a twenty-year planning horizon.
Each recommended project shall include, at a minimum:
• Description of the recommended improvement
• Building or site location
• Recommended timeframe
• Budgetary opinion of probable cost
• Project priority
C. Cost Estimates
Provide budgetary opinions of probable cost for recommended capital improvements using current industry standards and generally accepted estimating practices.
Cost estimates are intended solely for long-range capital planning purposes and are not intended for bidding or construction.
D. Executive Summary
Provide a concise Executive Summary highlighting:
• Overall condition of District facilities
• Significant capital needs
• Immediate priorities
• Short-term planning considerations
• Long-term planning considerations
The Executive Summary should be suitable for presentation to the School Committee, Town
Administration, and Capital Planning Committee.
E. Electronic Deliverables
Provide the following electronic files:
• Searchable PDF of the complete report
• Microsoft Excel file containing the capital improvement plan and cost estimates
• Any photographs used to document significant deficiencies
Electronic files shall become the property of the Maynard Public Schools.
F. Presentation
The consultant shall present the completed report and recommendations at a meeting of the
School Committee and/or other designated Town officials.
5. PROPOSAL SUBMISSION REQUIREMENTS
Proposals shall be submitted in accordance with M.G.L. c. 30B, Section 6, and shall consist of two separately sealed proposals.
Envelope A – Technical Proposal
The Technical Proposal shall include:
1. Letter of Transmittal
2. Company Profile
3. Firm Qualifications
4. Project Team o Identify the Project Manager.
o Identify key personnel assigned to the project.
o Include resumes of principal staff.
5. Relevant Experience o Describe experience performing similar work for Massachusetts public school districts or municipalities.
o Include a minimum of three (3) comparable projects completed within the last five years.
6. Project Approach o Describe the firm's proposed methodology.
o Describe the proposed work plan.
o Include a proposed project schedule.
7. Sample Report o Submit one sample Facility Condition Assessment or Capital Needs Assessment completed for a public-sector client.
8. References o Complete the Reference Form included as Appendix D.
9. Required Certifications o Non-Collusion Certification o Tax Compliance Certification
Envelope B – Price Proposal
The Price Proposal shall be submitted in a separately sealed envelope clearly marked:
PRICE PROPOSAL – DISTRICT-WIDE FACILITY CONDITION ASSESSMENT AND
TWENTY-YEAR CAPITAL IMPROVEMENT PLAN
The Price Proposal shall include:
• Completed Price Proposal Form (Appendix B)
• Lump Sum Fee
• Hourly Rates for Additional Services (if requested)
6. MINIMUM QUALIFICATIONS
The following minimum qualifications must be met for a proposal to be considered responsive.
Failure to satisfy any of the minimum requirements may result in rejection of the proposal without further evaluation.
Minimum Requirements (Pass/Fail)
Requirement Meets Requirement
(Yes/No)
Page #
Proposal received by the submission deadline
Technical Proposal submitted in accordance with the RFP
Price Proposal submitted separately as required
Completed Non-Collusion Certification included
Completed Tax Compliance Certification included
Firm has a minimum of five (5) years of experience performing facility condition assessments or capital planning studies for public agencies
Firm has completed at least three (3) comparable public school or municipal projects within the past five (5) years
Proposal includes a proposed Project Manager and key project personnel
Proposal includes a proposed project schedule
Proposal includes the required references
Any proposal determined to be non-responsive may be rejected and may not receive further evaluation.
7. COMPARATIVE EVALUATION CRITERIA
Responsive proposals will be evaluated in accordance with M.G.L. Chapter 30B, Section 6.
The District will evaluate each proposal using the criteria below.
Evaluation
Criteria
Highly Advantageous (3
Points)
Advantageous (2
Points)
Not Advantageous
(1 Point)
Relevant
Experience
Five (5) or more comparable
K-12 public school or municipal facility assessments completed within the past five years
Two (2) to four (4) comparable projects
Limited or no comparable experience
Project Team
Project team includes licensed professionals with extensive experience performing school facility assessments and capital planning
Qualified personnel with relevant municipal or commercial experience
Limited relevant experience
Project
Understanding &
Methodology
Proposal demonstrates a thorough understanding of the District's needs and presents a clear, comprehensive work plan
Proposal adequately addresses the scope of services
Proposal lacks detail or demonstrates limited understanding
Project Schedule
Schedule is clear, realistic, and demonstrates the ability to complete the work within the requested timeframe
Schedule is acceptable
Schedule is incomplete or unrealistic
References
Excellent references from comparable Massachusetts public school or municipal projects
Satisfactory references
Weak or unavailable references
Technical Evaluation Scoring
Criteria Maximum Points
Relevant Experience 3
Project Team 3
Project Understanding & Methodology 3
Project Schedule 3
References 3
Maximum Technical Score 15 Points
The Evaluation Committee shall independently evaluate each responsive Technical Proposal.
Following completion of the technical evaluation, the committee shall review the Price Proposals and determine the proposal that is most advantageous to the District, taking into consideration both price and the evaluation criteria set forth in this Request for Proposals.
8. AWARD OF CONTRACT
The contract shall be awarded to the responsive and responsible proposer whose proposal is determined to be the most advantageous to the Maynard Public Schools, taking into consideration both price and the comparative evaluation criteria established in this Request for
Proposals, pursuant to M.G.L. Chapter 30B, Section 6.
The District reserves the right to:
• Reject any or all proposals.
• Waive minor informalities or irregularities when determined to be in the best interest of the District.
• Request clarification or additional information from any proposer.
• Negotiate with the highest-ranked proposer, if appropriate.
• Award a contract in the manner determined to be in the best interest of the District.
The District reserves the right not to award a contract if it determines that doing so would not be in the best interest of the Maynard Public Schools.
9. PROCUREMENT SCHEDULE
The anticipated procurement schedule is as follows. The District reserves the right to revise this schedule by written addendum.
Event Date
Request for Proposals Issued 08/12/2026
Optional Pre-Proposal Site Visit 08/18/2026
Deadline for Questions 08/20/2026
Responses to Questions Issued 08/24/2026
Proposal Submission Deadline 09/02/2026 @10AM
Public Opening of Price Proposals 09/08/2026 @ 2 PM
Anticipated Award Within 30 Days of Opening
10. OPTIONAL PRE-PROPOSAL SITE VISIT
An optional pre-proposal site visit may be conducted to familiarize prospective proposers with the District's facilities and project requirements.
Attendance is not mandatory and is not a condition for submitting a proposal.
Should a site visit be scheduled, the date, time, and meeting location will be identified in the
Procurement Schedule or by written addendum.
Questions arising during the site visit shall not be answered verbally unless they are administrative in nature. All substantive questions shall be submitted in writing in accordance with Section 11. Responses will be issued only through written addendum.
11. QUESTIONS AND ADDENDA
Questions regarding this Request for Proposals shall be submitted in writing to the contact person identified in this solicitation no later than the date identified in the Procurement Schedule.
Questions received after the deadline may not be answered.
Responses to questions and any modifications to this Request for Proposals shall be issued by written addendum. Addenda shall become part of this Request for Proposals and shall be binding upon all proposers.
Proposers are responsible for acknowledging receipt of all addenda and incorporating any revisions into their proposals.
Verbal interpretations or statements shall not be considered binding.
12. RESERVATION OF RIGHTS
The Maynard Public Schools reserves the right to:
• Reject any or all proposals.
• Waive minor informalities or irregularities when determined to be in the best interest of the District.
• Request clarification of any proposal.
• Request additional information from any proposer.
• Verify references and qualifications.
• Conduct interviews with one or more proposers, if determined to be in the best interest of the District.
• Negotiate final contract terms with the selected proposer, consistent with M.G.L. Chapter
30B.
• Cancel this procurement at any time prior to contract execution if determined to be in the best interest of the District.
The District shall not be liable for any costs incurred by proposers in preparing or submitting proposals.
13. CONTRACT TERM
The anticipated contract shall commence upon execution by both parties and shall remain in effect until completion of all required services, unless terminated in accordance with the terms of the agreement.
The District anticipates completion of the project within approximately 120 calendar days following issuance of the Notice to Proceed, unless otherwise agreed upon by the parties.
APPENDIX A
NON-COLLUSION CERTIFICATION AND TAX COMPLIANCE CERTIFICATION
Non-Collusion Certification
The undersigned certifies under penalties of perjury that this proposal has been made and submitted in good faith and without collusion or fraud with any other person. As used in this certification, the word "person" shall mean any natural person, business, partnership, corporation, union, committee, club, or other organization, entity, or group of individuals.
The undersigned further certifies that he/she is duly authorized to bind the proposer contractually.
Tax Compliance Certification
Pursuant to M.G.L. Chapter 62C, Section 49A, the undersigned certifies under penalties of perjury that, to the best of his/her knowledge and belief, the proposer has filed all state tax returns and paid all state taxes required under Massachusetts law.
Firm Name __________________________
Authorized Signature __________________________
Printed Name __________________________
Title __________________________
Date __________________________
APPENDIX B
PRICE PROPOSAL FORM
DISTRICT-WIDE FACILITY CONDITION ASSESSMENT AND TWENTY-YEAR
CAPITAL IMPROVEMENT PLAN
Proposer Name:
The undersigned proposes to furnish all labor, supervision, equipment, transportation, and professional services necessary to complete the work described in the Request for Proposals for the following firm fixed price.
Description Lump Sum Cost
Facility Condition Assessment $____________
Twenty-Year Capital Improvement Plan $____________
Final Report and Presentation $____________
TOTAL LUMP SUM PRICE $____________
Hourly Rate for Additional Services (if requested by the District):
$______________/Hour
The undersigned acknowledges that this price shall remain valid for 60 days following the proposal opening.
Authorized Signature ________________________
Printed Name ________________________
Title ________________________
Date ________________________
APPENDIX C
EVALUATION COMMITTEE SCORE SHEET
Proposer Information
Proposer _________________________
Evaluator _________________________
Date _________________________
Minimum Qualifications (Pass / Fail)
Requirement Yes No
Proposal submitted by deadline ☐ ☐
Technical Proposal complete ☐ ☐
Price Proposal submitted separately ☐ ☐
Non-Collusion Certification included ☐ ☐
Tax Compliance Certification included ☐ ☐
Minimum experience requirements met ☐ ☐
References included ☐ ☐
If any required item is marked No, the proposal may be deemed non-responsive.
Comparative Evaluation
Criteria Highly
Advantageous (3)
Advantageous
(2)
Not Advantageous
(1) Score
Relevant Experience ☐ ☐ ☐ _____
Project Team ☐ ☐ ☐ _____
Understanding of the
Project
Proposed Methodology ☐ ☐ ☐ _____
References ☐ ☐ ☐ _____
Total Technical Score
_______ / 15
Evaluator Comments
Strengths
Weaknesses
Overall Recommendation
☐ Highly Recommended
☐ Recommended
☐ Recommended with Reservations
☐ Not Recommended
Evaluator Signature
APPENDIX D
REFERENCE FORM
Please provide information for three (3) comparable projects completed within the past five (5) years.
Reference No. 1
Client
Project
Facility Size
Completion Date
Contact Person
Title
Telephone
Reference No. 2
Facility Size
Completion Date
Contact Person
Title
Telephone
Reference No. 3
Facility Size
Completion Date
Contact Person
Title
Telephone
File details come from the government source that posted it. Updated .