The file's text, extracted by GovTribe without its formatting.
Table 1 Attachment 17
| Question 1 | | | ANSWERS |
| Document/Section | Paragraph | Question/Issue/Concern | |
| Performance Work Statement | 3.5.1.1 Joint Mobilization Inspection | This paragraph mentions Acceptance Test Procedures (ATP) and Trainer Test Procedures, can the government provide a copy of these documents? | Revised Section 3.5.1.1 Joint Mobilization Inspection section to address written System Test Procedures - added Attachment 14. |
| Question 2 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| Performance Work Statement | 3.6 System Operation | All of these paragraphs mention Original Equipment Manufacturer (OEM) Maintenance Manuals and OEM operations/user manuals. The OEM Manuals provided in Attachment 4 is the "Link 108348 SEA MK-LV2 Manuals". Can the government provide the manuals for the rest of the training devices? | Additional manuals are provided with Amendment 0002, in an update to Attachment 4. |
| 3.6.1 System Functionality | | |
| 3.9.1 Maintenance Support Plan | | |
| 3.9.2 Preventive Maintenance | | |
| Question 3 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| Performance Work Statement | 3.7.5 Practical Device Utilization | Can the government provide historical copies of CDRL F001? | Usage history for the MEAT, SVET, and SWET has been provided under Attachment 16 |
| Question 4 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| Performance Work Statement | 3.9.5 Trainer Maintenance Certifications | This paragraph states "The contractor shall ensure that the load tests are conducted at a minimum of every two (2) years, or as required by the base if less than (2) years", can the government provide a copy of any base requirements that differ from the standard 2 year requirement? Can the government provide the dates when each trainer was last load tested? | The requirement is every two years from date of last inspection by location. Camp Pendleton, 11 March 2016 Camp Lejeune 08 April 2016, Kaneohe Bay 8 January 2016 and Okinawa 29 July 2016. |
Section 3.9.5 has been revised to change the certification requirement to account for natural disasters or equipment failure, otherwise the 2 year certification requirement is in place.
| Question 5 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| Performance Work Statement | 3.10.4.1 SEBD Bottles | Can the government provide an updated list of SEBD Bottles inventory that lists the dates when the bottles were last requalified? | The contractor shall perform an annual visual inspection of the cylinder according to the Compressed Gas Association (CGA) standards. The contractor is not responsible for performing hydrostatic testing on any cylinder not exceeding two inches outside diameter and less than two feet in length. This recommendation is in accordance with the Department Of Transportation (DOT) Title 49 CFR Ch-1 (10-1-01) Section 173.34, Qualification, maintenance and use of cylinders, Table “Retest and Inspection of Cylinders1”. |
| Question 6 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| Solicitation | Section M & PPQ Attachment 12 | Section M states that after relevancy has been established CPARS and PPQs will be used to assess the offeror’s ability to meet scheduled requirements But the PPQ doesn’t ask the agency to give any comments on “Schedule.” “Schedule” is not one of the areas for input. The evaluation criteria outlined in Section M are not in alignment with the information the PPQ is submitting. How will the USMC assess our ability to meet scheduled deadlines if the PPQ doesn’t ask about schedule? | Schedule is addressed in PPQ, paragraph 12, sections G and H, that request information regarding the schedule in past performance contracts. Also, paragraph 13 allows for additional comments. |
| Question 7 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| Solicitation | N/A | The government did not apply the Service Contract Act to this Solicitation. No Wage Determinations were provided nor can references be found that direct compliance. Can the government confirm that the applicable site employees are not subject to the Service Contract Act, with the exception of Okinawa Employees (SOFA)? | The solicitation has been Amended to include "52.222-41 -- Service Contract Labor Standards". In addition, the Government has attached the applicable Wage Determinations. |
| Question 8 | | |
| Document/Section | Paragraph | Question/Issue/Concern |
| Solicitation/L.5.1 Section 1: Recent and Relevant Past Performance ); and M.5.3 Past Performance Confidence Assessment Rating, and Table 3 | First complete paragraph of L.5.1/page 83 of 91; and first paragraph and Table 3 of M.5.3/page 90 of 91 | Question: The Section L reference uses the term “Offeror” to indicate who is allowed to submit up to three citations (past performance contracts). Additionally, the reference states that each principal subcontractor can submit up to two citations each. |
It is not clear, however, whether the term “Offeror” refers to the Prime only, as implied in Section L.5.1, Section 1, or to the entire proposing team (as implied in Section M.5.3 and Table 3).
If the Prime Offeror is unable to submit past performance citations, but at least one principal subcontractor can submit one or more citations, does the entire proposal receive a neutral confidence assessment rating? If an Offeror is unable to submit Past Performance, but at least one Principal Subcontractor can, the entire proposal does not necessarily receive a “Neutral Confidence” Past Performance Confidence Assessment rating.
The definition of “Neutral Confidence” in Section M.5.3 (Table 3) is as follows:
“No recent/relevant performance record is available or the Offeror's performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The Offeror may not be evaluated favorably or unfavorably on the factor of past performance.”
The definition does not depend on whether the past performance is submitted; rather, the definition states that no recent/relevant performance record is available or the Offeror's perform and record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.
Pursuant to Section L.5.1., Past Performance may be submitted for an Offeror or a Principal Subcontractor. Both the Offeror’s and Principal Subcontractor’s submitted past performance will be evaluated.
Please be advised that the Government has amended the solicitation, Section M.5.3. to include “In assessing confidence, the Government will assign greater weight to the Offeror’s past performance than to a Principal Subcontractor, and will assign greater weight to an Offeror’s performance as a Prime Contractor than as a subcontractor.”
| Question 9 | | |
| Document/Section | Paragraph | Question/Issue/Concern |
| Solicitation/Section I (eye), Contract Clauses | First paragraph of Full Text clause 52.204-8, Annual Representations and Certifications (Apr 2016)/page 57 of 91 | Question: On 15 March 2017 PM TRASYS issued an amendment to the UET Solicitation changing the NAICS from 561210 to 611699. |
Would PM TRASYS consider changing the NAICS back to 561210 to better align the NAICS with the size, scope, and complexity of UET CLS for UET facility operation, maintenance, and training?
NAICS 561210 is “Facilities Support Services.” The UET Contract is a “Contractor Logistics Support (CLS)” contract. NAICS 561210 accommodates all aspects of CLS, and with a $38.5 Million Dollar Small Business Size Standard, provides for increased small business competition.
The newly assigned 611699 NAICS code does not accommodate CLS, rather miscellaneous training or instruction only, and would not cover UET facility maintenance. Section 1.3 of the PWS includes all UET CLS scope under “logistical support,” including maintenance, inventory management and control, and warranty management, all typically associated with CLS contracts. NAICS 611699 does not account for this CLS scope. After careful review and consideration, PM TRASYS has determined that, notwithstanding the reference to Contractor Logistics Support in the PWS, the principle purpose of this contract is to provide instruction to Marines. Among the mission goals, PWS Section 1.1 states the contractor will “train Marines and other authorized personnel how to egress sinking or submerged platforms (i.e., aircraft, amphibious, and ground vehicles), including the use of life support equipment, e.g., Supplemental Emergency Breathing Devices (SEBDs) and Life Preserver Units (LPUs) to increase survival rates.” As such, PM TRASYS will not change the NAICS code back to 561210.
| Question 10 | | |
| Document/Section | Paragraph | Question/Issue/Concern |
| RFP | L.4.3 | |
| M.4.3 | L.4.3 states that Offerors shall "propose their technical approach to academic training that maximizes through-put of the practical devices." | | |
M.4.3 mentions nothing about "academic training" per se, however. Instead, M.4.3 merely indicates that the requirement in L.4.3 will be assessed to determine whether or not an Offeror "Demonstrates a realistic and efficient approach that maximizing [sic.] Marine through-put of the practical devices."
Question: Would the Government please clarify if Offerors are to demonstrate how their approach in general maximizes Marine through-put of the practical devices, or if they are to demonstrate how their approach to academic training maximizes Marine through-put of the practical devices? update L.4.3 "propose their technical approach to academic training that maximizes Marine through-put on the practical devices."
M.4.3. to state:
"Demonstrates a realistic and efficient approach to academic training that maximizes Marine through-put on the practical devices"
| Question 11 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| RFP | PWS - Appendix A | Appendix A appears to be incomplete. For starters, it only outlines student:instructor ratios for some of the POIs detailed in PWS Attachment 3, but not all of them. Additionally, the final page of the document (page 41) seems to abruptly end after subparagraph "a." Will the Government please confirm if Appendix A is correctly represented in its entirty in the current PWS? If not, will the Government please provide a fully fleshed out copy of Appendix A - Minimum Training Standards for Personnel Ratios? | Appendix A has been revised to reflect the Student to Instructor and Instructor to platform type safety position requirements. |
| Question 12 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Contract Administration | 2.3.3 | paragraph 2 states "The contractor shall provide the necessary…audiovisual and other equipment…to maintain administrative offices and training materials." Please confirm that the contractor is only required to provide support for ASSIGNED training spaces and there is no need to provide mobile audiovisual support to train in other than assigned spaces? | The contractor is responsible per PWS Section 2.3.3 to provide all equipment necessary to maintain administrative offices and training materials within their assigned space. |
| Question 13 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Contractor Personnel Training | 2.3.5 | states "The contractor shall ensure currency and proficiency in program prerequisite position qualifications by providing initial and refresher training during Mobilization, training resulting from Government/contractor changes/modifications, and training of replacement personnel." Can the Government please confirm that the Government will provide time, on a local coordinated level, for refresher/sustainment and new training as needed. | It is incumbent upon the contractor to manage their manpower and training requirements without interference or impact to scheduled onsite training. |
| Question 14 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Transportation | 2.3.8 | states "The contractor shall be responsible for furnishing all local transportation for ..material between all points of business…(e.g. relocation of SWET chair)." Please define the "local transportation." | Section 2.3.8, the word "local" has been removed. It is the contractor's responsibility to provide all transportation for the contractor (including subcontractor) personnel and material between all points of business requiring the contractor’s services in the execution of this PWS |
| Question 15 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Health and Safety Plan | 3.2 | The last paragraph states "The contractor shall utilize the Government provided topside communication GFP as the primary source of communication while conducting in water training." Will two divers be required to utilize this equipment during training? With only two sets of GFP diver comms per site, training would need to be suspended if one set was inoperable. Repair is available only through the OEM. (B) Additionally, if local conditions preclude the use of the topside comms, will training need to be suspended (For Example: The helo pad at Camp Hansen Okinawa is directly adjacent to the UET training site, and during the frequent flight ops training at Camp Hansen communication is often done using hand and arm signals.) | The Government identifies the topside communication GFP as the primary source, but does not preclude the contractor from utilizing an alternate/secondary source for communication when necessary. |
| Question 16 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Transition Out Plan | 3.4 | The last paragraph states "...the contractor shall provide Government approved Train the Instructor(s), Operator(s), Maintainer(s) POI training to the successor staff at no additional cost to the Government." Is this expected to be done on a not-to-interfere basis, and if so how will that be accomplished in the event of full training schedules? | The contractor shall provide reasonable and cooperative support within to the successor contractor to ensure an orderly transition, while minimizing impact to the operational readiness of UET training systems and meeting all training requirements. The Government expects this to be able to be completed with relative low risk of "full training schedules" within the 60 days Transition out period. |
| Question 17 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Joint Mobilization Inspection | 3.5.1.1 | Paragraph 2 states "Written test procedures will be utilized, which may include Acceptance Test Procedures (ATP), Trainer Test Procedures…" Please provide copies of these procedures. | See Government Response to Question #1 |
| Question 18 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, System Functionality | 3.6.1 | states "Any cost must be approved by the COR prior to incurring them in order to be reimbursed by the government." What third-party repair costs might reasonably be expected to be reimbursed by the government? | Third party repair costs that have been approved by the COR would be expected to be reimbursed. Additional CLINs (0019, 1019, 2019, 3019, and 4019) have been provided as NTE for any such approved repairs |
| Question 19 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Normal Operating Window | 3.6.2 | Can the Government clarify this requirement (40 hours in a 7 day week) for operations in California where any work over an 8 hour day incurs overtime pay? (B) Can the contractor turn a unit away if the late arrival causes the contractor to work beyond the 8 hour day? | PWS has been updated |
| Question 20 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Training Curricula | 3.7.1 | states "The contractor shall be required to operate the SWET in conjunction with the MAET/SVET simultaneously pending pool size limitations…" Will all SWET devices at a site be required to be operated simultaneously with the MAET/SVET? | No, the trainers will be utilized based on training throughput requirements and instructor availability to optimize training efficiency. |
| Question 21 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Scheduling | 3.7.2 | states "The designated local Government representative will provide the contractor with a practical device initial training schedule at each location by close of business on Tuesday of the prior work week..." Will this supersede local installation practices and base directives (Camp Lejeune) currently in place at the different installations, and if so, who will be the designated representative for each base that will assume this new duty? | PWS Section 3.7.2 Scheduling has been revised. |
| Question 22 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Academic Training | 3.7.3 | states "There is no limit to class size for the academic portion." If the academic class size exceeds the max capacity of the assigned contractor spaces, who is responsible for coordinating a larger facility and all the required technical support necessary to teach and test the government provided curriculum? | This is a performance based requirement, the contractor will need to coordinate with the designated Government Site Representative. |
| Question 23 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Academic Training | 3.7.3 | states "The Government reserves the right to modify deliver method of academic training in order to increase practical training throughput (e.g., computer based training)." Who specifically within the Government has authority to modify the delivery method? (B) Can each installation modify delivery method or only PM TRASYS? (C) How much advance notice will the contractor be given for changes to the delivery method? | The Contracting Officer is the only individual authorized to make changes to the scope of the contract. Any change in delivery method will be accomplished through a contract modification action. The Government is unable to provide "how much advance notice", but any modification to the terms and conditions of a contract will require bi-laterally approval. |
| Question 24 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Trainee Readiness | 3.7.4 | paragraph 1 states "It is up to the training unit representative if to allow a trainee to drop the course during training." In almost every case, the unit representative will have a rudimentary knowledge at best, of the complexities of the training. In the interest of safety, will the senior UET instructor present be allowed to override the unit rep? | It is up to the training unit representative to allow a trainee to drop the course during training unless it’s a health or safety risk. PWS has been updated. |
| Question 25 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Trainee Readiness | 3.7.4 | paragraph 1 states "It is up to the training unit representative if to allow a trainee to drop the course during training." Will the contractors be required to take unwilling students into the MAET/SVET if the unit rep refuses to let them drop? | Contractors shall not required to physically force any unwilling student into the any practical device. Should a student physically refuse, the contractor shall notify the training unit representative. PWS has been updated. |
| Question 26 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Trainee Readiness | 3.7.4 | paragraph 2 states "Prior to practical device training, the contractor shall verify that each student…possess a valid, current Marine Corps Water Survival Training Program (MCWSTP) Water Survival Basic qualification." No one who is not a Marine, such as other services (for example, corpsman) or foreign nationals will have this swim qualification. Who will be responsible for turning away these individuals and notifying the unit that they cannot be trained? | Non-USMC Military Personnel and Foreign Militaries shall be responsible for ensuring their trainees can meet their units designated swimming qualification and requirements. The designated onsite Government Representative will be responsible to determine if Non-USMC personnel will be unable to train. PWS has been updated |
| Question 27 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Trainee Readiness | 3.7.4 | paragraph 2 states "The contractor shall not allow any personnel to participate in any training conducted within the pool if a valid and current MCWSTO WSB qualifications cannot be verified by the training unit." To preclude any questions or issues arising from "verbal" confirmation, can the individual Swim Qualification be added to Enclosure 6 to be verified in writing by the unit? | It is the designated unit resprsentative's responsibility to account for his/her units qualifications and readiness for training. |
| Question 28 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Trainee Readiness | 3.7.4 | paragraph 3 states "Upon creating the roster, the contractor shall shred the training screening form(s) immediately." Request this be modified to authorize shredding at the conclusion of the pool training, since there might be information on the form that would be critical in the event of a medical emergency (i.e. current meds). This would be in-line with current best practices. | PWS Section 3.7.4 has been updated with, following the conclusion of practical device training. |
| Question 29 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Practical Device Utilization | 3.7.5 | paragraph 2 states "In the event a unit shows no more than 1 hour late, and the arrival does not conflict with an already scheduled training event…the contractor will accommodate" Who makes the determination that it will not conflict with an already scheduled training event (for example, if a Monday and Tuesday class were each an hour late, that 2 hours could make it impossible to conduct training scheduled on Friday without exceeding 40 hours)? | PWS has been updated. |
| Question 30 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Practical Device Utilization | 3.7.5 | paragraph 2 states "In the event a unit shows no more than 1 hour late, and the arrival does not conflict with an already scheduled training event…the contractor will accommodate..." Will the government authorize overtime pay at California in the event this occurs, since state law dictates that anything over 8 hours in a scheduled work day is overtime. | No, please see 19 and 29 above. |
| Question 31 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Completion | 3.7.7 | states "…the contractor shall provide both the….COR (CDRL F001) with the trainee roster…" Do these need to be submitted on the actual day of the training, the end of the week, each month, etc.? | Delivery of CDRL is in accordance with CDRL F001 Block 10. |
| Question 32 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Trainer Maintenance Certification | 3.9.5 | states "Each load test shall be witnessed and documented by the base certified crane and lifting inspector." Who will be the designated government representative at each base responsible for ensuring the inspector's presence during the load tests? (B) If the test has been coordinated in advance, will the government reimburse the contractor for travel and expenses for inspector no-shows? | The designated Government Representatives will be identified at the PAC for each training location. |
Testing occurs onsite, no travel is necessary.
| Question 33 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Modular Facility Maintenance | 3.9.6 | states "Maintenance activities shall include the following:" Is the list of activities all-inclusive? | Please see updated PWS. |
| Question 34 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Consumables | 3.10.4 | states "The contractor shall submit the purchase request and costs to the COR for approval to purchase prior to incurring any costs." Attachment 9 provides listings of GFP and a separate folder specifically named "Consumables," however, all items identified on in both files (RGFP Data Input Spreadsheet & Consumables _RGFP V4_2) are listed as non-reimbursable. Section 3.10.4 also refers to Section B where all X018 CLINs are identified as COST line items. Can the Government please clarify how the cost of consumables is to be handled? | Updated GFP has been provided with Amendment 03 |
| Question 35 | | |
| Document/Section | Paragraph | Question/Issue/Concern |
| PWS, SEBD Bottles | 3.10.4.1 | states "...SEBD bottles will be requalified every five years." Is the government referring to normal cylinder hydrostatic testing. (B) If not, what requalification is the government referring to? If so, the OEM "recommends following the DOT regulation as these cylinders fall under the Note 1 exemption for |
diameter and length. This recommendation is in accordance with the Department Of Transportation (DOT) Title 49 CFR Ch-1 (10-1-01) Section 173.34, Qualification, maintenance and use of cylinders, Table “Retest and Inspection of Cylinders1”, Note 1. Any cylinder not exceeding two inches outside diameter and less than two feet in length is excepted from hydrostatic retest." See Response # 5
| Question 36 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Warranty Items | 3.10.5 | states "Any equipment under warranty shall be maintained IAW OEM operations and maintenance manuals" Is any GFP currently under warranty? | No GFP is currently under warranty |
| Question 37 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Appendix A | All | Is there a requirement for wall training to be conducted simultaneously with MAET or SVET training? | Not required, however, it can be conducted simultaneously for training efficiency. |
| Question 38 | | |
| Document/Section | Paragraph | Question/Issue/Concern |
| PWS, Appendix A | Item 1.d).i) | states "One (1) instructor shall be provided on the pool deck at all times during the exercise to coordinate in-water evolutions and operate the lift system." It is a violation of OSHA regulation 1926.1417(d) |
| which states "The operator must not engage in any practice or activity that diverts his/her attention while actually engaged in operating the equipment, such as the use of cellular phones (other than when used for signal communications)" for hoist operators to have other duties. Will a second instructor, non-hoist operator, be required to stay on the pool deck to coordinate activities? | PWS, Appendix A has been updated. | | |
| Question 39 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Appendix B | Table | Under Government Approved Certifying Organizations for Rescue Diver/Rescue Scuba Diver, the only two organizations listed are Professional Association of Dive Instructors (PADI) and National Association of Underwater Instructors (NAUI). Both PADI and NAUI themselves recognize other SCUBA organizations, specifically those that are recognized by the World Recreational SCUBA Training Council. Request that the list of government approved organizations be expanded to include "PADI, NAUI and any other organization recognized by the US Council of the World Recreational SCUBA Training Council." | The Government will not update the table in Appendix B. Please see the note in Appendix B. In addition, the Government has updated section L to allow for submission of demonstration of equivalent certification that does not go against the page count of the technical proposal. |
| Question 40 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| QASP, 3.9 Maintenance | 13 | "The contractor shall ensure that the load tests are conducted…or as required by the base if less than (2) years…" Does any base currently require load testing more frequently than a two year interval? | No |
| Question 41 | | |
| Document/Section | Paragraph | Question/Issue/Concern |
| Safety Assessment Report | 4 | There are several errors in the SAR. For example: |
- On page 4, the picture of the control panel shown is NOT the control panel on the XGH. The lift can't be controlled (raise/lower/traverse) from the XGH control panel. It's controlled via a remote or a pendant hard wired to the control panel, but the panel does not give the full capability that the remote does.
- On page 4, the RRS has no independent air compressor. It uses a large 2400 psi air cylinder for an air source.
- Page 8 recommends 85°F water temperature. Camp Lejeune is the only facility where that is possible.
- Pages 18-19 state that EMTs are on site. Does the Government require an EMT on site to begin training? There seems to be no reference in the PWS to an EMT requirement.
The SAR is a critical document. PWS paragraph 3.9.3 states that no training system shall be operated outside the conditions identified within the UET Safety Assessment Report (SAR) (Attachment 5). Would the Government please clarify the discrepancies between the SAR and the PWS to allow the contractor to accurately staff and price the effort. An updated SAR has been provided with Amendment 03
| Question 42 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| Safety Assessment Report | 10 | The SAR states static load testing is conducted on an annual basis. The nxt sentence says load testing is conducted every four years as per OSHA (this is repeated again on pg. 15). The OEM Manual requires 1 wire rope change every other year, which means load testing is only done every other year. Please clarify the requirement for static load testing | An updated SAR has been provided with Amendment 03 |
| Question 43 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| UET Training Screening Form | 2 | The form has a block for "Training Screener" signature. Please define who the training screener is (unit representative, contractor personnel, etc.). | Training Unit Government Representative , Attachment has been updated |
| Question 44 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| UET Training Screening Form | 2 | The form has a block for "Commanding Officer" signature. Please confirm that each individual form must be signed by that individual's actual Commanding Officer. | Revised to reflect Unit Representative and Commanding Officer was removed, Attachment has been updated |
| Question 45 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| CDRL B001 | | Block 16 Para 4 says Transition Plan will be due 6 months after Post Award Conference. Para 11 in Block 16 states it will required at the Post Award Conference. Please clarify the Transition Plan initial submission requirement. | CDRL B001 has been updated |
| Question 46 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| Past Performance Questionnaire | | states "MCTOG RFP No. M67854-17-R-7800 and Required Response Date: No later than 2:00 p.m, 15 March 2017." Would the government please confirm this information and provide an updated questionnaire, if appropriate? | This date was an error, an updated Past Performance Questionnaire has been provided with the Amended solicitation |
| Question 47 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| GFP | | Can the Government please clarify the differences between listings for each site? We would anticipate that while quantities may differ from site to site, the components provided should be identical. | There is no clarification necessary. The GFP provided may vary between sites. |
| Question 48 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| CDRL B003 | | Block 16 Para 2 states first submission shall be two (2) days prior to the Post Award Conference. Since no meetings will have been held yet, what is to be submitted 2 days prior to the PAC? | CDRL B003 has been updated |
| Question 49 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| Solicitation/Section L | L.5.1, Section 1, Recent and Relevant Past Performance, 1st full paragraph / page 83 of 91 | Question: Will the Government allow and evaluate past performance from a subcontractor who may perform less than 25% of the Total Evaluated Price? | No |
| Question 50 | | |
| Document/Section | Paragraph | Question/Issue/Concern |
| Solicitation/Section L | L.5.2, 1st and 2nd paragraphs / page 84 of 91 | Question: If an Offeror has not received every annual CPARS report for a given performance (in your example, one out of two), should the Offeror still submit the CPARS reports received, even if they don’t comprise a full set, in addition to processing a questionnaire? |
The first sentence of the 2nd paragraph indicates that the questionnaire is only required “without a completed annual report” [emphasis added].
You may submit the CPARS for the years you have and supplement with a PPQ for the years that are missing,
| Question 51 | | |
| Document/Section | Paragraph | Question/Issue/Concern |
| Attachments CD / Various sections | Various paragraphs / N/A | Due to corruption of a number of files on the Government-provided “Attachments” CD, potential bidders might still be in need of: OEM Manuals for the MAET, SWET, SVET, XGH, Crane and XGH controller; and OEM manuals for the MAET/SVET modules and the Model 10000/12000 XGH lifting system. |
Additionally, new potential bidders may be without the Emergency Action Plans (EAP)s for each UET site and MAET/SVET and XGH User and Maintenance manuals in the Safety Assessment Report, Attachment 5, either as a result of file corruption or just a lack of provision.
Updated OEM manuals were provided under Amendment 02 and 03
An updated SAR has been provided with Amendment 03
| Question 52 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| Solicitation / Section L | L.1.h. / page 81 of 91 | Once the Government provides new copies (Attachments CD) of previously corrupted and missing materials, would the Government consider a two-week extension of the proposal deadline to accommodate review and proposal impact? | The Government has extended the solicitation due date to 17 April 2017 |
| Question 53 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS/Section 5.1 and Attachment J.2v1 (QASP)/Section 7 Performance Requirements Summary | List following only paragraph/Pages 37-8; and Performance Requirements Summary Table/Pages 13 of 20 | Between the referenced documents (PWS and QASP), there are two instances where different titles are applied to the same CDRL. | |
1) In the QASP table, the two 3.4 entries on the bottom of page 10 (Transition Out Plan and Transition Plan) are matched with “Deliverables: B001 Transition Plan.” But in the CDRL list of 5.1 in the PWS, B001 is associated with “Contractor’s Progress, Status, and Management Report,” while there is no CDRL associated with “Transition Plan” in the PWS.
2) In the QASP table, the 3.5 entry near the bottom of page 11 (Mobilization Plan) is matched with, among others, “B003 Mobilization Plan,” while the PWS 5.1 CDRL list associates B003 with “Report Record of Meeting Minutes.” There is no CDRL associated with “Mobilization Plan” in the PWS.
Would the Government consider adjusting or adding the necessary CDRL titles for clarity?
| QASP has been updated to provide for correct CDRL titles. | | | |
| Question 54 | | | |
| Document/Section | Paragraph | Question/Issue/Concern | |
| PWS, Normal Operating Window | 3.6.2 | states "The normal operating window for all practical training devices for each site is forty (40) hours in a (7) day week..." Please confirm this operating window includes normal maintenance activities, such as pre/post operational checks? | Hours to complete the Academic Training and pre/post operational checks are not included in the Normal Operating Window. |