Vendor_Submitted_Questions.pdf
PDF 78 KB Posted
- Attached to
- Telecommunications Switch System Federal contract opportunity
- Solicitation number
- M00146-16-T-9014
- Issued by
- United States Marine Corps
About this file
Attachment 04
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| M00146-16-T-9014_0004.docx | DOCX document | |
| M00146-16-T-9014_0002.docx | DOCX document | |
| M00146-16-T-9014_0001.docx | DOCX document | |
| Vendor_Submitted_Questions.pdf | ||
| M00146-16-T-9014.docx | DOCX document | |
| Attachment_01_Westbrooke_Telecom_Room_Locations.pdf | ||
| 16-9014_JA_Switch_Redacted.pdf | ||
| Attachment_02_MCAS_Cherry_Point_Signed_CO_Letter_12.01.15.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
M00146-16-T-9014 Attachment 04
GOVERNMENT RESPONSES TO VENDOR SUBMITTED QUESTIONS 10.19.2016
1. When accounting for equipment lead times (approximately 4 - 6 weeks), upcoming end-of-year holidays, and the logistics effort required to ensure quality training, information assurance (IA) and project execution, would the
Government consider extending the period of performance?
Government Response: According to the required Project Master Schedule located in Paragraph 7.2.1 of the product description, the Government requires all installation and testing to be complete no later than 1 February 2017. As required by Addenda to 52.212-1 3) a) (ii), vendor’s shall provide milestones for completion in accordance with the required schedule (1 February 2017). The Government has considered the timeline for execution, and is not able to waiver from the required schedule. It is critical to the mission of the FRC East that this project be completed no later than 1 February 2017.
Questions 2 through 6 are all in reference to paragraph 5.18 of the specification: “The contractor shall extended fiber connectivity from the DMARC location room 149 to the telecommunications room 128 for the telephone/data equipment. The fiber connectivity shall be installed utilizing contractor provided wire management systems and ran above the ceiling.”
2. Multimode or Single-mode?
Government Response: Single-mode.
3. How many fiber strands?
Government Response: 12 strand fiber.
4. Type of fiber connectors desired? (SC,ST?)
Government Response: SC.
5. Purpose of fiber? Extend PRI/T-1’s? Without electronics or media converters of some type we will not be able to extend PRI/T-1’s. Is this for carrier use?
Government Response: The purpose of the fiber is to extend the T1’s from the entrance facility to the telecommunications room where the telephone switch will be located.
6. Is there a plan to have a copper feed from room 149 to room 128?
Government Response: At this time the Government’s position is that there is not a need for a copper feed between the two rooms.
7. Addenda to FAR 52.212-1, Page 8, subpara 5.4 & 5.5 of Gov’t Solicitation – what are the technical support requirements for the UPS? i.e. how hours or minutes of support time is required for the systems?
Government Response: The UPS shall have an up time of at least one (1) hour.
8. How much backup time is required for the UPS design?
Government Response: The backup time for the UPS design shall be at least one (1) hour.
File details come from the government source that posted it. Updated .