This document is a guidance document issued by the State of Illinois outlining procurement procedures for state agencies using JPMorgan Chase (JPMC) service contracts that have been awarded to multiple vendors. The guidelines establish a hierarchical vendor selection process for Illinois state agencies when engaging JPMC service contractors, with designated primary, secondary, tertiary, and quaternary vendors available to provide services.
The procedures require state agencies to first contact the primary vendor and request an estimate of hours and materials required for the work. Agencies may transition to secondary or subsequent vendors only under specific circumstances: if the primary vendor declines the work, cannot meet time constraints, or fails to acknowledge a request for estimate within the contractually specified timeframe. Vendors must provide labor hour quotes broken down by basic/journeyman and foreman rates per contract pricing, along with a detailed materials listing. State agencies retain the right to verify vendor quotes against industry standards and request copies of material invoices to ensure no markup. Hourly rate differences between vendors are explicitly prohibited as a reason for vendor substitution. All communications with vendors, including declined work and unresponded requests, must be documented and attached to requisitions when moving to alternative vendors. If all JPMC contract vendors are exhausted, agencies may conduct independent solicitations but must still attach all required documentation to the new requisition.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P-90252 Executed Contract_Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JPMC Service Contracts - Use by State Agencies When JPMC service contracts are done as multiple awards, per 44 Il Admin 1.2036(b), one vendor shall be designated as the primary recipient of orders. The other awardees (Secondary, Tertiary, etc.) may receive orders in the event the Primary Vendor is unable to meet the terms of the contract. The following guidelines shall be followed by State Agencies when using these contracts:
1. Contact the Primary Vendor for the service and have them submit an estimate of the hours and materials required for the work.
2. If the Primary Vendor cannot meet the terms of the contract for any of the following reasons, the Agency may move to the Secondary Vendor.
A) Vendor declines the work, or B) Vendor cannot meet the time constraints of the work required (I.E. year-end date), or C) Outside of Emergency Requests - Vendor does not acknowledge the request for an estimate within the time frame outlined in the contract or the time frame outlined by the agency in the request for quote, whichever is longer.
The same process will be used down the line to Tertiary and Quaternary.
3. All communications with awarded vendors, including emails sent and not answered, emails stating they are declining the work, etc. shall be attached to the Requisition (REQ) when moving to the next awarded vendor.
For Example: A) If both the Primary and Secondary Vendor decline the work, any email correspondence with this information to and from both vendors must be attached to the REQ to have the Tertiary Vendor complete the work.
4. Vendor should supply the quote with labor hour broken out by basic/journeyman and foreman hours as per contract pricing.
5. Vendor should provide a listing of materials that will be required for the repair. Per the contract, Agencies have a right to request a copy of the Vendor’s material pricing (invoices/quotes) for verification of no mark-up.
6. Per the contract, Agencies have the right to verify quotes if the hours quoted or required materials appear to be extremely high compared to industry standard.
7. Hourly rates are NOT a reason to move from Primary to Secondary and so on down the line.
8. If all JPMC Vendors have been exhausted through the above means, then the agency may do their own solicitation; however, they must still attach all required items above to the new REQ.
File details come from the government source that posted it. Updated .