J01b Drawings - Boiler Replacement.pdf
PDF 6 MB Posted
- Attached to
- Whiteriver Boiler Replacement & Steam System Conversion Federal contract opportunity
- Solicitation number
- 75H701-23-R-00033
About this file
This document is a solicitation notice for a construction project to replace two existing steam boilers with condensing boilers and convert supported steam systems at the Whiteriver Indian Hospital in Whiteriver, Arizona. The scope of work includes furnishing all labor, materials, equipment, tools, insurance, and supervision for mechanical, plumbing, and electrical work. The construction magnitude is estimated between $500,000 to $1,000,000. The period of performance is 180 calendar days from notice to proceed. A site visit will be scheduled and details provided in the solicitation. The Indian Health Service intends to award a single firm fixed price contract through a request for proposal with lowest price technically acceptable evaluation criteria. Offerors must register in the System for Award Management database to be considered.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1050 E. Southern Ave, Suite #D, Tempe, Arizona 85282, (480) 751-9542designgroup
Architecture, Engineering, and Sustainable Design
AESUS
KEY PLAN NTS NORTH
Drawing Title: Project Title:
Date
Location
Checked
Building Number:
Project Number:
Drawing Number:
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
WR BOILER REPLACEMENT & STEAM
SYSTEM CONVERSION DESIGN
Location:
Final Submittal
NOV. 3, 2022
PH19WR02H6
WHITE RIVER INDIAN HEALTH SERVICE
200 W HOSPITAL DR. WHITERIVER, AZ 85941
AESUS
BOILER PLANT
AREA OF WORK
AESUS
G-100
COVER SHEET
DX
A3-301
X
XX
X
DETAIL FLAG NUMBER
DOOR NUMBER
AE-501
BUILDING SECTION CUT
OTHER SECTION CUT
SHEET WHERE APPEARS (TYPICAL)
AE-301
AA
SHEET WHERE APPEARS
ELEVATION NUMBER
SHEET WHERE APPEARS
x x x x
EXISTING COLUMN CENTER LINEA
X
WINDOW TAG
AE-301
AA
AE-301
AA
ELEVATION NUMBER
AE-710
4 2
DASHED LINE
AROUND
AREA DETAILED
PLAN OR DETAIL NUMBERX
EQ-X
CPT1
W-X
E
EA EACH
E EAST
EWC ELECTRIC WATER COOLER
ELEC ELECTRIC (AL)
EL ELEVATION
ELEV ELEVATOR
EMER EMERGENCY
ENGR ENGINEER
EQ EQUAL
EQUIP EQUIPMENT
EXIST EXISTING
ETR EXISTING TO REMAIN
EXP EXPANSION
EXP BT EXPANSION BOLT
EJ EXPANSION JOINT
EXP EXPOSED
EXT EXTERIOR
EIFS EXTERIOR INSULATION AND
FINISH SYSTEM
F
FWC FABRIC WALL COVERING
FT FEET, FOOT
FGL FIBERGLASS
FIN FINISH
FIN GR FINISH GRADE
FDV FIRE DEPARTMENT VALVE
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER
CABINET
FHC FIRE HOSE CABINET
FP FIREPROOF
FIXT FIXTURE
FLASH FLASHING
FLEX FLEXIBLE
FLR FLOOR
FD FLOOR DRAIN
FLUOR FLUORESCENT
FTG FOOTING
FDTN FOUNDATION
FRMG FRAMING
FURN FURNACE, FURNITURE
G
GA GAGE
GALV GALVANIZED
GC GENERAL CONTRACTOR
GEN GENERATOR
GL GLASS
GL BLK GLASS BLOCK
GB GRAB BAR
GR GRADE
GRAN GRANITE
GFCI GROUND FAULT CIRCUIT INTERRUPTER
GUT GUTTER
GYP BD GYPSUM BOARD
H
HNDRL HANDRAIL
HDW HARDWARE
HDWD HARDWOOD
HD HEAD
HVAC HEATING, VENTILATING, AIR CONDITIONING
HT HEIGHT
HPT HIGH POINT
HC HOLLOW CORE
HM HOLLOW METAL
HORIZ HORIZONTAL
HB HOSE BIBB
HOSP HOSPITAL
HR HOUR
I
IN INCH
INFO INFORMATION
ID INSIDE DIAMETER
INSUL INSULATED,INSULATION
INT INTERIOR
J
JAN JANITOR
JT JOINT
K
KPL KICKPLATE
KIT KITCHEN
KB KNEE BRACE
L
LAB LABORATORY
LAM LAMINATE
LC LAUNDRY CHUTE
LV LAVATORY
LT LIGHT
LD LINEAR DIFFUSER
L CL LINEN CLOSET
LL LIVE LOAD
LLV LONG LEG VERTICAL
LPT LOW POINT
M
MACH MACHINE
MH MANHOLE
MFD MANUFACTURED
MFR MANUFACTURER
MRB MARBLE BASE
MRF MARBLE FLOOR
MKR BD MARKER BOARD
MO MASONRY OPENING
MATL MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MED MEDICAL
MC MEDICINE CABINET
MEMB MEMBRANE
MTL METAL
MIN MINIMUM, MINUTE
MISC MISCELLANEOUS
MOD MODIFIED
MLDG MOLDING
N
NAT FIN NATURAL FINISH
NOM NOMINAL
N NORTH
NA NOT APPLICABLE
NIC NOT IN CONTRACT
NTS NOT TO SCALE
NO NUMBER
O
OFF OFFICE
OC ON CENTER
OPNG OPENING
OPP OPPOSITE
OPH OPPOSITE HAND
ORCH ORCHESTRA
ORN ORNAMENTAL
OD OUTSIDE DIAMETER
OH OVERHANG, OVERHEAD
OF/CI OWNER FURNISHED/
CONTRACTOR INSTALLED
O OXYGEN
P
P PAINT
PR PAIR
PNL PANEL
PTD PAPER TOWEL DISPENSER
PTN PARTITION
PERF PERFORATED
PC PIECE
PLAM PLASTIC LAMINATE
PLAS PLASTIC, PLASTER
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
PCC PRECAST CONCRETE
PREFAB PREFABRICATE
PREFIN PREFINISH
PROD PRODUCTION
Q
QTY QUANTITY
QT QUARRY TILE
A
AFF ABOVE FINISHED FLOOR
ACST ACOUSTIC (AL)
ACT ACOUSTICAL CEILING TILE
APC ACOUSTICAL PANEL CEILING
AWP ACOUSTICAL WALL PANEL
AWT ACOUSTICAL WALL
ADJ ADJUSTABLE
A/C AIR CONDITIONING
AHU AIR HANDLING UNIT
ALT ALTERNATE
ALUM ALUMINUM
AB ANCHOR BOLT
AL ANGLE
APPROX APPROXIMATE
ARCH ARCHITECT (URAL)
ASPH ASPHALT
ASSY ASSEMBLY
AUTO AUTOMATIC
AWN AWNING
B
BALC BALCONY
BSMT BASEMENT
BM BEAM, BENCHMARK
BR BEDROOM
BLKG BLOCKING
BD BOARD
BOT BOTTOM
BRKT BRACKET
BRK BRICK
B CL BROOM CLOSET
BLDG BUILDING
BLT IN BUILT-IN
BUR BUILT-UP ROOFING
C
CAB CABINET
CPT CARPET
CSMT CASEMENT
CI CAST IRON
CB CATCH BASIN
CLG CEILING
CEM CEMENT
CL CENTER LINE
CER CERAMIC
CT CERAMIC TILE
CO CLEANOUT, CASED OPENING
CLR CLEAR, COLOR
CLO CLOSET
COL COLUMN
CMPST COMPOSITE
CONC CONCRETE
CMU CONCRETE MASONRY UNIT
CONSTR CONSTRUCTION
CONT CONTINUOUS
CONTR CONTRACTOR
COTR CONTRACTING OFFICER
CJ CONTROL JOINT
COP COPING
CU COPPER
CG CORNER GUARD
CORR CORRIDOR
CNTR COUNTER
CSK COUNTER SUNK
D
DMPF DAMPPROOFING
DL DEAD LOAD
DEMO DEMOLITION
DET DETAIL
DIA DIAMETER
DIFF DIFFUSER
DIM DIMENSION
DR DOOR, DRAIN
DH DOUBLE HUNG
DN DOWN
DS DOWNSPOUT
DWR DRAWER
DWG DRAWING
DF DRINKING FOUNTAIN
DUPL DUPLICATE
R
R RADIUS, RISER
RWD REDWOOD
REF REFERENCE, REFRIGERATOR
REINF REINFORCE
REQD REQUIRED
RB RESILIENT BASE
RF RESILIENT FLOORING
RA RETURN AIR
REV REVISION
RD ROOF DRAIN
RM ROOM
RO ROUGH OPENING
RS ROUGH SAWN
S
SCHED SCHEDULE
SECT SECTION
SHTHG SHEATHING
SHT SHEET
SHV SHELVING
SIM SIMILAR
S SOUTH
SP FIN SPECIAL FINISH
SPEC SPECIFICATION
SQ SQUARE
SF SQUARE FEET
SST STAINLESS STEEL
STD STANDARD
STL STEEL
STL JST STEEL JOIST
STOR STORAGE
STRUCT STRUCTURAL
S4S SURFACED FOUR SIDES
SUSP SUSPEND
SW SWITCH
SYMM SYMMETRICAL
T
TK BD TACKBOARD
TEL TELEPHONE
TV TELEVISION
TMPD TEMPERED
TEMP TEMPORARY
TER TERRAZZO
THK THICKNESS
TPD TOILET PAPER DISPENSER
T&G TONGUE AND GROOVE
TOS TOP OF SLAB, STEEL
T TREAD
TYP TYPICAL
U
UC UNDERCUT
UNFIN UNFINISH
UNO UNLESS NOTED OTHERWISE
V
VAC VACUUM
VR VAPOR RETARDER
VNR VENEER
VP VENEER PLASTER
VIF VERIFY IN FIELD
VERT VERTICAL
VEST VESTIBULE
VCT VINYL COMPOSITION TILE
VWC VINYL WALL COVERING
W
W CAB WALL CABINETS
WC WALL COVERING, WATER CLOSET
WP WATERPROOFING, WEATHER
PROOF, WORKING POINT
WT WEIGHT
WWF WELDED WIRE FABRIC
W WEST
WF WIDE FLANGE
WDW WINDOW
W/ WITH
W/O WITHOUT
WD WOOD
WDP WOOD PANELING
INDIAN HEALTH SERVICE
KEYED NOTE
WALL TYPE
X
X WINDOW TREATMENT TYPE
EQUIPMENT
INTERIOR FINISH TYPE
FURNITURE, FIXTURE, EQUIPMENT
CONTRACT LIMIT LINE
COLUMN CENTER LINE
NEW WALL
DEMOLITION
EXISTING WALL
NORTH
Project No: PH19WR02H6
DESIGN TEAM
ABBREVIATIONS OWNER
CODE REFERENCES
FOR THE PURPOSE OF THIS TASK WE WILL BE USING THE LATEST VERSION OF THE
NFPA AND IBC CODES.
A. BUILDING: 2021 INTERNATIONAL BUILDING CODE
B. ENERGY: 2021 INTERNATIONAL ENERGY CONSERVATION CODE
C. PLUMBING: 2021 INTERNATIONAL PLUMBING CODE
D. MECHANICAL: 2021 INTERNATIONAL MECHANICAL CODE
E. ELECTRICAL: 2020 INTERNATIONAL ELECTRICAL CODE, NFPA 70
F. FIRE: 2021 INTERNATIONAL FIRE CODE
G. NFPA 99, HEALTH CARE FACILITIES CODE
H. NFPA 110, STANDARD FOR EMERGENCY AND STANDBY POWER SYSTEMS
I. ASHRAE, THE COMMISSIONING PROCESS, GUIDELINE 0
J. ASHRAE, COMMISSIONING PROCESS FOR BUILDING AND SYSTEMS, STANDARD 202
K. ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL LOW RISE
RESIDENTIAL BUILDINGS 10 CFR PART 435
L. 2019 IHS ARCHITECT/ENGINEER DESIGN GUIDE.
M. CONSULT THE WHITE MOUNTAIN APACHE TRIPE AND LOCAL UTILITIES FOR ANY
LOCAL JURISDICTIONAL CODES AND STANDARDS THAT MUST BE FOLLOWED
PROJECT DESCRIPTION
FACILITY MAP
SYMBOL LEGEND
BUILDING INFORMATION
BUILDINGS INVOLVED IN PROJECT INCLUDE THE FOLLOWING:
THE WHITERIVER BOILER PLANT.
NO LIFE SAFET WILL BE AFFECTED BY THIS PROJECT OR THE
CONSTRUCTION OPERATION.
GENERAL NOTES
VICINITY MAP
THE SCOPE OF WORK SHALL REPLACE THE TWO EXISTING STEAM BOILERS WITH
CONDENSING BOILERS INCLUDING CONVERTING THE EXISTING STEAM TO WATER
HEAT EXCHANGER FOR HEATING HOT WATER AND TWO STEAM TO HOT WATER
EXCHANGERS FOR DOMESTIC HOT WATER. THE NEW CONDENSING BOILERS AND
SUPPORTING CONVERTED SYSTEMS SHALL BE INTEGRATED IN THE BUILDING
AUTOMATION SYSTEM.
THIS WORK SHALL INCLUDE BUT NOT BE LIMITED TO ARCHITECTURAL, MECHANICAL,
PLUMBING, & ELECTRICAL.
DESCRIPTIONSYMBOL
IHS BOILER REPLACEMENT PROJECT
WHITERIVER INDIAN HOSPITAL
INDIAN HEALTH SERVICE
Architect & Structual
MPE Engineers
1050 E. Southern Ave. Suite 5, Tempe, Arizona 85282
AESUS Design Group
1050 E. Southern Ave. Suite 5, Tempe, Arizona 85282
AESUS Design Group
Orlando Gonzales (ogonzales@aesusdesign.com)
480-454-2861
David Combs (dcombs@aesusdesign.com)
480-454-2861
NORTH
PROJECT AREA
PROJECT SITE
IHS Whiteriver Indian Hospital
A. ANY CHANGES MUST BE APPROVED BY OWNER BEFORE DOING ANY
ADDITIONAL WORK. WORK SCHEDULE TO BE PERFORMED DURING
REGULAR DAY SHIFT HOURS (8AM-4:30PM) ANY WORK OUTSIDE OF
REGULAR SCHEDULE REQUIRES APPROVAL FROM OWNER.
B. COORDINATE STAGING AREA WITH OWNER, AND FIND INTERIOR
COVERED STORAGE ON SITE FOR MATERIALS THAT MUST BE
PROTECTED FROM ELEMENTS - COORDINATE WITH OWNER.
C. WORK PERFORMED FOR THIS PROJECT MAY INTERRUPT SERVICE TO
ADJACENT AREAS AT TIMES BUT WILL NOT INTERRUPT OVERALL
FACILITY OPERATION. SEE ELECTRICAL FOR POWER INTERRUPTION
AND OUTAGE REQUIREMENTS.
D. CONTRACTOR TO VERIFY ALL DETAILS AGAINST EXISTING
CONDITIONS PRIOR TO PURCHASE OF EQUIPMENT AND PRIOR TO
CONSTRUCTION. CONTRACTOR IS RESPONSIBLE FOR BRINGING ANY
DISCREPANCIES IN PLANS AND EXISTING SITE CONDITIONS TO
IMMEDIATE ATTENTION OF THE OWNER
E. CONTRACTOR SHALL PERFORM ALL WORK AND PROVIDE ALL
MATERIALS IN ACCORDANCE WITH CONSTRUCTION SPECIFICATIONS.
G. NOT ALL KEYNOTES ARE ON ALL SHEETS.
200 West Hospital Drive, Whiteriver, AZ 85941
ISSUED SHEETS
Sheet Number Sheet Name
GENERAL
G-100 COVER SHEET
ARCHITECTURE
AS-100 LEVEL 01 OVERALL PHASING PLAN
AD-100 LEVEL 01 DEMOLITION
AE-100 LEVEL 01 FLOOR PLAN
MECHANICAL
M-001 MECHANICAL ABBREVIATIONS
MD-201 MECHANICAL DEMOLITION PLAN
M-201 MECHANICAL PLAN
M-501 MECHANICAL DETAILS
M-502 MECHANICAL DETAILS
M-801 MECHANICAL CONTROL DIAGRAMS
ELECTRICAL
E-001 SYMBOLS AND ABBREVIATIONS
ED-101 ELECTRICAL DEMOLITION PLAN
EP-101 ELECTRICAL POWER PLAN
EP-601 ELECTRICAL ONE-LINE DIAGRAM
David Combs Snapshot
A. ANY CHANGES MUST BE APPROVED BY OWNER BEFORE DOING ANY
ADDITIONAL WORK. WORK SCHEDULE TO BE PERFORMED DURING
REGULAR DAY SHIFT HOURS (8AM-4:30PM) ANY WORK OUTSIDE OF
REGULAR SCHEDULE REQUIRES APPROVAL FROM OWNER.
B. COORDINATE STAGING AREA WITH OWNER, AND FIND INTERIOR
COVERED STORAGE ON SITE FOR MATERIALS THAT MUST BE
PROTECTED FROM ELEMENTS - COORDINATE WITH OWNER.
C. WORK PERFORMED FOR THIS PROJECT MAY INTERRUPT SERVICE
TO ADJACENT AREAS AT TIMES BUT WILL NOT INTERRUPT OVERALL
FACILITY OPERATION. SEE ELECTRICAL FOR POWER INTERRUPTION
AND OUTAGE REQUIREMENTS.
D. CONTRACTOR TO VERIFY ALL DETAILS AGAINST EXISTING
CONDITIONS PRIOR TO PURCHASE OF EQUIPMENT AND PRIOR TO
CONSTRUCTION. CONTRACTOR IS RESPONSIBLE FOR BRINGING
ANY DISCREPANCIES IN PLANS AND EXISTING SITE CONDITIONS TO
IMMEDIATE ATTENTION OF THE OWNER.
E. CONTRACTOR SHALL PERFORM ALL WORK AND PROVIDE ALL
MATERIALS IN ACCORDANCE WITH CONSTRUCTION
SPECIFICATIONS.
GENERAL NOTES
A. THE CONTRACTORS SHALL COORDINATE EQUIPMENT AND
MATERIAL TRAFFIC AND STORAGE WITH OWNER.
B. ALL UTILITY WORK SHALL BE COORDINATED WITH MECHANICAL,
PLUMBING ELECTRICAL, AND FIRE PROTECTION.
C. ALL ASPECTS OF CONTRACTOR STAGING AND CONSTRUCTION
PHASING SHALL BE APPROVED BY OWNER.
D. ALL HOSPITAL ACCESS POINTS, AND ALL BUILDING EXITS, MUST
REMAIN ACCESSIBLE, CLEAR AND UNOBSTRUCTED THROUGHOUT
ALL PHASES OF DEMOLITION AND CONSTRUCTION. SHORT-TERM
CLOSURE MAY BE ACCEPTABLE AS COORDINATED WITH OWNER.
E. THE CONTRACTOR SHALL COORDINATE ALL ROOF TOP WORK AND
ROOF REPAIRS WITH THE OWNER.
GENERAL PHASING NOTES
FLOOR PLAN LEGEND
INCLUDED IN SCOPE OF WORK
14 15 16 17 18
AREA OF WORK
EXISTING WALL
EXISTING DOOR
EXISTING DOOR
EXISTING WALL
EXISTING WALL
EXISTING COLUMN
A
B
C
1050 E. Southern Ave, Suite #D, Tempe, Arizona 85282, (480) 751-9542designgroup
Architecture, Engineering, and Sustainable Design
AESUS
KEY PLAN NTS NORTH
Drawing Title: Project Title:
Date
Location
Checked
Building Number:
Project Number:
Drawing Number:
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
WR BOILER REPLACEMENT & STEAM
SYSTEM CONVERSION DESIGN
Location:
Final Submittal
NOV. 3, 2022
PH19WR02H6
WHITE RIVER INDIAN HEALTH SERVICE
200 W HOSPITAL DR. WHITERIVER, AZ 85941
AESUS
BOILER PLANT
AREA OF WORK
AESUS
AS-100
LEVEL 01 OVERALL PHASING PLAN
1/4" = 1'-0"1
LEVEL 01 - FLOOR PLAN OVERALL SCOPE
OPEN PIT
14 15 16 17 18
6 1
8 8
11 10
A
B
C
DEMOLITION SYMBOL LEGEND
GENERAL DEMOLITION NOTES
KEYED DEMOLITION NOTES
ITEMS SHOWN DASHED TO BE
DEMOLISHED
HATCH INDICATES AREA TO BE COVERED
BY KEYED NOTES LOCATED WITHIN
01 02
A. EXISTING CONSTRUCTION TO BE REMOVED IS INDICATED ON
THE DRAWINGS: COORDINATE DEMOLITION WITH
ARCHITECTURAL DRAWINGS AND REQUIREMENTS SHOWN ON
ALL MECHANICAL PLUMBING AND ELECTRICAL, AND
STRUCTURAL DRAWINGS
B. EXISTING CONDITIONS SHOWN ARE FROM AVAILBLE RECORD
DRAWINGS AND VISUAL FIELD SURVEYS. THE CONTRACTOR
SHALL VERIFY ACTUAL EXISTING CONDITIONS AND NOTIFY THE
OWNER OF ANY DISCREPENCIES.
C. CONDUCT DEMOLITION TO MINIMIZE INTERFERENCE WITH
ADJACENT BUILDING AREAS
D. AREA OF WORK CONTAINS BUILDING INFRASTRUCTURE WHICH
MAY BE CRITICAL TO THE ONGOING OPERATIONS OF THE
HOSPITAL. ATTENTION SHALL BE BROUGHT TO THE OWNER
PRIOR TO ANY DEMOLITION OR SHUT-DOWNS. REFER TO
SPECIFICATIONS FOR MAJOR AND MINOR SHUTDOWN
PROCEDURES.
E. PROTECT EXISTING MATIERALS AND EQUIPMENT WHICH ARE
NOT TO BE DEMOLISHED. CONTRACTOR TO PROTECT FROM
DAMAGE ALL EXISTING FLOORS, WALLS, CEILINGS, ETC.
CONTRACTOR IS RESPONSIBLE FOR REPAIR AND
REPLACEMENT OF ALL DAMAGED FLOORING, WALLS, CEILINGS,
ETC. IF AREAS NEED TO BE REPAIRED, FINISHES ARE TO
MATCH EXISTING.
F. MAINTAIN PROTECTED EGRESS AND ACCESS TO THE WORK.
ALSO MAINTAIN REQUIRED EGRESS AROUND TEMPORARY
PARTITIONS.
G. REMOVE ANY UNUSED OR ABANDONED MATERIALS IN WALLS
AND ABOVE CEILINGS.
H. THE CONTRACTOR SHALL NOTIFY THE OWNER IN ADVANCE OF
ANY SCHEDULED DEMO WORK IN THE AREA TO ALLOW THE
OWNER TO REMOVE PERSONAL BELONGINGS AND DESIGNATE
ALL MEDICAL EQUIPMENT, FURNITURE, AND OTHER ITEMS TO
BE SALVAGED AND STORED BY THE CONTRACTOR. ALL ITEMS
NOT DESIGNATED AS "SALVAGED" BY THE OWNER AFTER THIS
TIME SHALL BE DISPOSED OF BY THE CONTRACTOR. REFER TO
SPECIFICATION FOR NOTIFICATION REQUIREMENTS.
I. OWNER SHALL REMOVE ALL EQUIPMENT AND WALL-MOUNTED
FURNITURE, AND ALL WALL MOUNTED SINGAGE AND ARTWORK
TO BE SALVAGED PRIOR TO COMMENCEMENT OF DEMOLITION.
J. SCOPE OF WORK TO BE REMOVED IS SHOWN WITH DASHED
LINES. COORDINATE EXTENT OF DEMOLITION OF EXISTING
ITEMS TO BE PARTIALLY DEMOLISHED WITH THE FLOOR PLAN
AND REFLECTED CEILING PLAN.
K. REMOVE AND SALVAGE ANY DOORS, DOOR CLOSERS, AND
MAGNETS, PNEUMATIC DAMPER OPERATORS, AND HEATING
COIL ACTUATORS AND VLAVES. SALVAGED ITEMS ARE TO BE
STORED BY CONTRACTOR IF THEY ARE TO BE RE-USED IN
PROJECT. REPORT ANY OTHER ITEMS TO OWNER FOR
HANDLING.
L. CONTRACTOR SHALL REMOVE EXISTING INSULATION OR PIPE
JACKETING WHERE IT DOES NOT COMPLY WITH FIRE
STOPPING REQUIREMENTS AT PIPING PENETRATIONS AND
OTHER CONDITIONS WHERE FIRE STOPPING IS REQUIRED.
REFER TO, AND COMPLY WITH, I.B.C. SECTION 712.
M. REMOVE ANY REMAINING CASEWORK AND EQUIPMENT NOT
INDICATED ON PLANS IN SPACES, REQUIRING DEMOLITION IN
ITS ENTIRETY.
N. REMOVE AND DISPOSE OF ALL DEMOLISHED MATERIALS OFF-
SITE WHICH ARE NOT SCHEDULED TO REMAIN, BE RELOCATED,
OR BECOME THE PROPERTY OF THE OWNER.
O. DO NOT PROCEED WITH DEMOLITION WORK BEFORE THE
INSTALLATION OF CONSTRUCTION TUNNEL AND BARRICADES.
RELOCATE CONSTRUCTION BARRICADES AS NECESSARY FOR
CONSTRUCTION WORK AND/OR AS DIRECTED BY OWNER AT
NO ADDITIONAL COST TO OWNER.
P. CONTRACTOR TO SUBMIT BARRICADE LOCATIONS DRAWINGS
TO OWNER FOR REVIEW AND APPROVAL PRIOR TO THE
INSTALLATION.
Q. PROVIDE CONSTRUCTION BARRICADE IN ALL OCCUPIED AREAS
AS REQUIRED AND/OR AS DIRECTED BY OWNER AT NO
ADDITIONAL COST TO OWNER.
R. PROVIDE TEMPORARY EXIT SIGNS AND ILLUMINATION LEVELS
PER THE IBC AND OWNER GUIDELINES. ALL EGRESS PATHS
SHALL REMAIN CLEAR AT ALL TIMES.
S. ALL CONSTRUCTION BARRICADES FIRE-RATING SHALL
MAINTAIN FIRE RATING CONTINUITY OF THE SURROUNDING
WALLS. FIRE-RATING OF CONSTRUCTION ACCESS DOORS
SHALL BE APPROPRIATE FOR THE FIRE-RATED WALL TYPES.
PAINT ALL TUNNELS AND BARRICADES ON THE SIDE VISIBLE TO
THE PUBLIC.
T. CONTRACTOR TO VERIFY EXISTING CONDITIONS AT ALL
COLUMNS AND CHASES PRIOR TO DEMOLITION
U. REMOVE CONSTRUCTION TUNNEL AND BARRICADE AT
COMPLETION OF EACH PHASE AND EACH PROJECT'S
CONSTRUCTION WORK, U.O.N.
V. DO NOT PENETRATE THE FLOOR SLAB WITHOUT
COORDINATING WITH STRUCTURAL REQUIREMENTS.
1050 E. Southern Ave, Suite #D, Tempe, Arizona 85282, (480) 751-9542designgroup
Architecture, Engineering, and Sustainable Design
AESUS
KEY PLAN NTS NORTH
Drawing Title: Project Title:
Date
Location
Checked
Building Number:
Project Number:
Drawing Number:
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
WR BOILER REPLACEMENT & STEAM
SYSTEM CONVERSION DESIGN
Location:
Final Submittal
NOV. 3, 2022
PH19WR02H6
WHITE RIVER INDIAN HEALTH SERVICE
200 W HOSPITAL DR. WHITERIVER, AZ 85941
AESUS
BOILER PLANT
AREA OF WORK
AESUS
AD-100
LEVEL 01 DEMOLITION
1/4" = 1'-0"1
LEVEL 01 - DEMO
KEYNOTES
1 EXISTING CONCRETE EQUIPMENT PAD TO REMAIN. PATCH AND REPAIR AS
REQUIRED PER THIS CONTRACT.
2 REMOVE EXISTING MECHANICAL EQUIPMENT, SEE MECHANICAL.
5 DEMOLISH EXISTING LADDER AND ALL ASSOCIATED COMPONENTS.
6 DEMOLISH EXISTING CONCRETE EQUIPMENT PAD, PATCH AND REPAIR SLAB.
7 EXISTING PIPE TRENCH TO REMAIN. REPLACE DIAMOND PLATE PANELS, TYP.
8 REMOVE AND RETAIN LOUVER FOR BOILER REPLACEMENT.
10 EXISTING WALLS TO REMAIN, TYPICAL.
11 EXISTING DOORS TO REMAIN, TYPICAL.
12 EXISTING COLUMNS TO REMAIN, TYPICAL.
4"
MIN
TEMPERATURE APPROPRIATE
SEALANT-TOOL TO FACILITATE
WATER RUN OFF
1" SS DRAW BAND
PREFABRICATED
COVER / ROOF BOOT
NOTE: ALL ROOF PENETRATIONS
SHALL BE FIRE SEALED TO
MATCH EXISTING RATING. GC TO
REUSE EXISTING GUY-WIRES,
TYP.
WELDED SEAM
EXISTING ROOF DECK
AND STRUCTURE TO
REMAIN
EXISTING ROOF TO
REMAIN, TYP.
REMOVE, PATCH,
AND REPAIR
EXISTING ROOF AS
REQ'D FOR PIPE
PENETRATION, SEE
MECHANICAL. TYP.
1. THE ARCHITECTURAL DRAWINGS SHOW PRINCIPAL AREAS AND
LIMITS OF CONSTRUCTION WHERE WORK MUST BE
ACCOMPLISHED UNDER THIS CONTRACT. WORK MUST BE
ACCOMPLISHED IN AREAS NOT SHOWN ON ARCHITECTURAL
DRAWINGS DUE TO CHANGES AFFECTING ELECTRICAL,
MECHANICAL, PLUMBING AND TECHNOLOGY ALONG WITH
OTHER SYSTEMS. THIS WORK SHALL BE PART OF THIS
CONTRACT, AND ALL TRADES SHALL INSPECT THESE AREAS,
ASCERTAIN WORK REQUIRED AND DO THE WORK IN
ACCORDANCE OF CONTRACT REQUIREMENTS AT NO
ADDITIONAL COST. SEE MECHANICAL, ELECTRICAL, PLUMBING
AND TECHNOLOGY PLANS FOR ADDITIONAL WORK.
2. CONTRACTORS SHALL VISIT THE SITE DURING BIDDING TO
BECOME FAMILIAR WITH THE EXISTING CONDITIONS. THE
GENERAL CONTRACTOR SHALL LOCATE, INSPECT AND FIELD
VERIFYALL EXISTING CONDITIONS, DIMENSIONS AND
ELEVATIONS PRIOR TO DEMOLITION AND CONSTRUCTION.
NOTIFY ARCHITECT IMMEDIATELY OF ANY DISCREPANCIES
3. DO NOT SCALE DRAWINGS. NOTIFY ARCHITECT IMMEDIATELY
OF ANY DISCREPANCIES.
4. WHEREVER OPENINGS ARE CUT THROUGH FIRE RATED
PARTITIONS, IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR FOR WHOM THE HOLE
IS CUT TO PATCH AND REPAIR ANY OPENING TO MAINTAIN THE
INTEGRITY OF THE FIRE RATING.
5. GENERAL CONTRACTOR TO CHECK MECHANICAL DRAWINGS
FOR EXISTING PIPES AND DUCTSFURRED IN WALLS. VERIFY
SIZE AND LOCATION WITH MECHANICAL CONTRACTOR PRIOR
TO PROCEEDING WITH REMODELING.
6. FIREPROOFING SHALL BE UNPIERCED. ANY SUBCONTRACTOR
PENETRATING THE FIREPROOFING SHALL BE REQUIRED TO
REPLACE FIREPROOFING TO THE ORIGINAL CONDITION AND
FIRE RATING, AT THE SUBCONTRACTORS EXPENSE.
7. EQUIPMENT UNIT DIMENSIONS ARE FOR PRODUCT
DESCRIPTION ONLY, VERIFY SIZE WITH MANUFACTURER.
8. ALL DIMENSIONS PERTAINING TO MECHANICAL OR ELECTRICAL
SERVICES OR EQUIPMENT SHALL BE VERIFIED WITH THE
RESPECTIVE TRADE.
9. ALL CONTRACTORS THAT PENETRATE AND/OR DISTURB ANY
AREAS AT EXISTING CONDITIONS SHALL PATCH AREA TO
MATCH EXISTING ADJACENT AREA OR SURFACE AND PREPARE
FOR SCHEDULED FINISH APPLICATION. COORDINATE WORK
WITH GENERAL CONTRACTOR PRIOR TO PROCEEDING.
10. VERIFY HEIGHTS AND LOCATIONS OF ACCESS PANELS (AP)
AND COORDINATE TYPES WITH TRADES WHICH REQUIRE
THEM.
11. PROVIDE LINTELS AND FRAMING FOR GRILLES, LOUVERS, AND
ROOF VENTS AS REQUIRED BY MECHANICAL CONTRACTOR,
VERIFY SIZE AND LOCATION.
12. STRUCTURAL, MECHANICAL, AND ELECTRICAL ABBREVIATIONS
AND SYMBOLS MAY DIFFER FROM ARCHITECTURAL. SEE
RESPECTIVE SECTIONS AND/OR DRAWINGS FOR DEFINITIONS.
13. AT MECHANICAL AND ELECTRICAL EQUIPMENT ROOMS,
PROVIDE 3/4" FRT PLYWOOD BACKING BEHIND ALL SURFACE
MOUNTED FIXTURES AND EQUIPMENT, UNLESS NOTED
OTHERWISE.
14. CONTRACTOR SHALL EVALUATE INTEGRITY OF ALL PARTITIONS
INDICATED BY SYMBOLS ON THE LIFE SAFETY PLAN(S) WITHIN
THE PROJECT SCOPE AND UPGRADE AS REQUIRED. ALL FIRE
RESISTIVE RATED WALLS SHALL BE CONSTRUCTED OF
MATERIALS / ASSEMBLIES MEETING THE RATING INDICATED,
TERMINATE AT THE DECK ABOVE WITH A TESTED HEAD OF
WALL ASSEMBLY AND ALL PENETRATIONS SHALL BE SEALED
WITH A TESTED ASSEMBLY. ALL SMOKE PARTITIONS SHALL BE
CONSTRUCTED OF MATERIALS THAT RESIST THE PASSAGE OF
SMOKE, TERMINATE AT THE DECK ABOVE WITH A JOINT
SEALED WITH FIRE CAULK AND ALL PENETRATIONS SHALL BE
SEALED WITH FIRE CAULK.
GENERAL NOTES
OPEN PIT
14 15 16 17 18
1 1
1 1
A
B
C
13 13
1050 E. Southern Ave, Suite #D, Tempe, Arizona 85282, (480) 751-9542designgroup
Architecture, Engineering, and Sustainable Design
AESUS
KEY PLAN NTS NORTH
Drawing Title: Project Title:
Date
Location
Checked
Building Number:
Project Number:
Drawing Number:
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
WR BOILER REPLACEMENT & STEAM
SYSTEM CONVERSION DESIGN
Location:
Final Submittal
NOV. 3, 2022
PH19WR02H6
WHITE RIVER INDIAN HEALTH SERVICE
200 W HOSPITAL DR. WHITERIVER, AZ 85941
AESUS
BOILER PLANT
AREA OF WORK
AESUS
AE-100
LEVEL 01 FLOOR PLAN
1/4" = 1'-0"1
LEVEL 01 - FLOOR PLAN
KEYNOTES
1 EXISTING CONCRETE EQUIPMENT PAD TO REMAIN. PATCH AND REPAIR AS
REQUIRED PER THIS CONTRACT.
4 NEW MECHANICAL EQUIPMENT, SEE MECHANICAL.
7 EXISTING PIPE TRENCH TO REMAIN. REPLACE DIAMOND PLATE PANELS, TYP.
9 REINSTALL LOUVER IN ORIGINAL LOCATION AFTER NEW BOILERS ARE IN PLACE.
PROVIDE NEW FLASHING AND SEALANTS AS REQUIRED, TYPICAL.
10 EXISTING WALLS TO REMAIN, TYPICAL.
11 EXISTING DOORS TO REMAIN, TYPICAL.
12 EXISTING COLUMNS TO REMAIN, TYPICAL.
13 EXISTING FLUE TO BE REPLACED, SEE MECHANICAL AND DETAIL 2/AE-100 FOR
FLASHING AND ROOF REPAIR.
1 1/2" = 1'-0"2
VENT PIPE PENETRATION
SYMBOL
ALL SYMBOLS SHOWN MAY NOT APPEAR IN ALL DRAWINGS. SYMBOLS ARE SHOWN SCHEMATIC AND MAY NOT BE TO SCALE.
MECHANICAL SYMBOLS LEGEND
DESCRIPTION
X-X, Xø
DIFFUSER TAG
(X-X = DIFFUSER TYPE, Xø = NECK SIZE, ### = CFM VALUE)
VAV BOX - HW
VAV BOX - EH
VAV UNIT - PARALLEL POWERED
SUPPLY DIFFUSER
RETURN GRILLE
EXHAUST GRILLE
SUPPLY SLOT DIFFUSER
RETURN SLOT GRILLE
SUPPLY, RETURN, OR EXHAUST SIDEWALL DIFFUSER/GRILLE
FLEXIBLE ROUND DUCT
FLEXIBLE RECTANGULAR DUCT
SUPPLY RECTANGULAR DUCT GOING DOWN
SUPPLY RECTANGULAR DUCT GOING DOWN
SUPPLY RECTANGULAR DUCT GOING DOWN
SUPPLY RECTANGULAR DUCT GOING UP
RETURN RECTANGULAR DUCT GOING UP
EXHAUST RECTANGULAR DUCT GOING UP
SUPPLY ROUND DUCT GOING DOWN
RETURN ROUND DUCT GOING DOWN
SUPPLY ROUND DUCT GOING DOWN
SUPPLY ROUND DUCT GOING UP
RETURN ROUND DUCT GOING UP
SUPPLY ROUND DUCT GOING UP
PIPE GOING DOWN
PIPE TEE GOING DOWN
PIPE GOING UP
PIPE TEE GOING UP
AIR VALVE FOR SUPPLY, RETURN, AND EXHAUST
M
SD
FSD
MANUAL DAMPER
SMOKE DAMPER
FD FIRE DAMPER
FIRE AND SMOKE DAMPER
MOTORIZED DAMPER
AM AIR FLOW MEASURING DAMPER
HUMIDIFIER GRIDH
REHEAT COIL
THERMOSTAT
HUMIDISTAT
CO2 SENSOR
PRESSURE MONITOR
PRESSURE SENSOR
T
H
CO2
BALANCING VALVE
R
BALL VALVE
BUTTERFLY VALVE
CHECK VALVE
GATE VALVE
GLOBE VALVE
PRESSURE REGULATING VALVE
STEAM TRAP - INVERTED VALVE
DUCT SMOKE DETECTOR
1050 E. Southern Ave, Suite #D, Tempe, Arizona 85282, (480) 751-9542designgroup
Architecture, Engineering, and Sustainable Design
AESUS
KEY PLAN NTS NORTH
Drawing Title: Project Title:
Date
Location
Checked
Building Number:
Project Number:
Drawing Number:
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
WR BOILER REPLACEMENT & STEAM
SYSTEM CONVERSION DESIGN
Location:
NOV. 3, 2022
PH19WR02H6
WHITE RIVER INDIAN HEALTH SERVICES
200 W HOSPITAL DR. WHITERIVER, AZ 85941
AESUS
BOILER PLANT
AREA OF WORK
AESUS
M-001
MECHANICAL ABBREVIATIONS
GENERAL NOTES
A. ALL MECHANICAL, ELECTRICAL, AND PLUMBING WORK SHALL COMPLY WITH ALL
APPLICABLE STATE AND LOCAL BUILDING CODES. REFER TO SPECIFICATIONS FOR
MATERIALS AND METHODS FOR MECHANICAL CONSTRUCTION.
B. CONTRACTOR SHALL OBTAIN ALL NECESSARY PERMITS, PAY ALL FEES, AND COMPLY
WITH ALL NATIONAL, STATE, AND MUNICIPAL LAWS, CODES, AND ORDINANCES
RELATING TO BUILDING AND PUBLIC SAFETY.
C. CONTRACTOR SHALL FURNISH ALL MATERIALS, EQUIPMENT, AND LABOR REQUIRED
FOR A COMPLETE WORKING AND COORDINATED SYSTEM.
D. REFER TO ARCHITECTURAL DRAWINGS FOR LOCATIONS OF WALLS WHICH EXTEND TO
STRUCTURE. EACH HVAC DUCT OR PIPE PENETRATION THROUGH THESE WALLS SHALL
BE INSTALLED AS DETAILED. WHERE FLEXIBLE DUCT WOULD PENETRATE A WALL
WHICH EXTENDS TO STRUCTURE, PROVIDE INSULATED RIGID DUCT EXTENDING 12
INCHES ON EITHER SIDE OF THE PARTITION.
E. COORDINATE THE EXACT LOCATION OF MECHANICAL EQUIPMENT WITH THE
LOCATIONS OF LIGHT FIXTURES, PIPING, CONDUIT AND OTHER CONSTRUCTION, TO
ALLOW FOR PROPER ACCESS TO SERVICE EQUIPMENT.
F. COORDINATE THE LOCATION OF DUCTWORK AND PIPING WITH OTHER TRADES AND
PROVIDE OFFSETS IN DUCTWORK AND PIPING AS REQUIRED.
G. IT IS THE INTENT OF THESE DOCUMENTS TO ALLOW ALL CEILING CONSTRUCTION AND
HEIGHTS TO BE AS SHOWN ON THE ARCHITECTURAL DRAWINGS. COORDINATE THE
LOCATION OF DUCTWORK AND PIPING AND PROVIDE OFFSETS IN DUCTWORK AND
PIPING AS REQUIRED TO MEET THIS INTENT.
H. CONDUIT, PIPING, AND DUCTWORK SHALL BE INDEPENDENTLY SUPPORTED, AND EACH
SUPPORT SHALL BE INDEPENDENT OF PARTITION AND CEILING SYSTEMS SUPPORTS.
I. REFER TO RISER DIAGRAMS AND FLOW DIAGRAMS FOR PIPE SIZES NOT SHOWN ON
THE PLANS.
J. INSTALL ALL FLOOR MOUNTED EQUIPMENT ON PADS AS SPECIFIED. PAD BY GENERAL
CONTRACTOR. COORDINATE REQUIREMENTS WITH GENERAL CONTRACTOR.
K. PROTECT EQUIPMENT FROM DAMAGE DURING HANDLING AND INSTALLATION UNTIL
COMPLETION OF CONSTRUCTION.
L. REMOVE ALL EXCESS MATERIAL AND DEBRIS AND CLEAN ALL EQUIPMENT UPON
COMPLETION OF WORK. TOUCH UP WITH PAINT WHERE REQUIRED.
M. CONTRACTOR SHALL VISIT JOBSITE AND VERIFY SIZE AND LOCATION OF ALL EXISTING
ITEMS AND CONDITIONS.
N. ALL CONNECTIONS BETWEEN PIPES OF DISSIMILAR MATERIALS SHALL BE MADE WITH
DIELECTRIC UNIONS.
O. ALL EXISTING FACILITIES SHALL BE PROTECTED DURING THE CONSTRUCTION
ACTIVITIES. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO RELOCATE
AND STORE ITEMS WHICH ARE SUBJECT TO DAMAGE.
P. ARCHITECT SHALL HAVE FINAL APPROVAL OF ALL GRILLE, DIFFUSER, AND
THERMOSTAT LOCATIONS.
Q. COORDINATE ALL AIR DEVICE LOCATIONS AND MOUNTING FRAME STYLES WITH
LIGHTING PLANS AND ARCHITECTURAL REFLECTED CEILING PLANS. PROVIDE 6'-0"
FROM CENTER TO CENTER FROM SUPPLY TO EXHAUST/RETURN GRILLES FOR PROPER
AIRFLOW.
R. COORDINATE ALL WALL MOUNTED DEVICE LOCATIONS WITH ARCHITECTURAL INTERIOR
ELEVATIONS.
S. REFER TO ARCHITECTURAL LIFE SAFETY PLANS FOR COORDINATION OF FIRE, SMOKE,
AND COMBINATION FIRE/SMOKE DAMPERS. THE DESIGN INTENT IS TO PROVIDE THE
INDICATED DAMPERS IN ACCORDANCE WITH REQUIREMENTS OF THE INTERNATIONAL
BUILDING CODE. THE CONTRACTOR SHALL PROVIDE ANY ADDITIONAL LIFE SAFETY
DAMPERS, INCLUDING FIRE ALARM CONTROL WIRING AND MONITORING REQUIRED BY
THE IBC AND LOCAL ORDINANCES AND CODE INTERPRETATIONS.
T. ALL DUCT RUN-OUTS TO VAV TERMINAL BOXES SHALL BE 2" LARGER THAN INLET SIZE
IF BOX IS MORE THAN 15 FT. FROM MAIN SUPPLY DUCT.
U. ANY DEVIATIONS FROM SCHEDULED EQUIPMENT RESULTING IN ADDITIONAL COST DUE
TO THE LACK OF COORDINATION WITH DIMENSIONS AND WEIGHTS WILL BE THE
RESPONSIBILITY OF THE CONTRACTOR.
V. ALL FIRE/SMOKE COMBINATION DAMPERS AND/OR FIRE DAMPERS SHALL BE INSTALLED
IN ACCORDANCE WITH THE MANUFACTURER'S INSTALLATION DETAILS THAT WERE
TESTED AT U.L. LABORATORIES AND U.L. LISTED.
W. EXCEPT AS REQUIRED BY SECTIONS 602.1.1 THROUGH 602.1.5 OF THE IMC, MATERIALS
WITHIN PLENUMS SHALL BE NON-COMBUSTIBLE OR SHALL HAVE A FLAME SPREAD
INDEX OF NOT MORE THAN 25 AND SMOKE DEVELOPED INDEX OF NOT MORE THAN 50
WHEN TESTED IN ACCORDANCE WITH ASTM E 84.
EXCEPTIONS:
1. RIGID AND FLEXIBLE DUCTS AND CONNECTORS SHALL CONFORM TO SECTION
603 ON THE 2012 IMC.
2. DUCT COVERINGS, LININGS, TAPE AND CONNECTORS SHALL CONFORM TO
SECTIONS 603 AND 604 OF THE IMC.
3. THE SECTION SHALL NOT APPLY TO MATERIALS EXPOSED WITHIN PLENUMS IN
ONE AND TWO STORY FAMILY
DWELLINGS.
4. THIS SHALL NOT APPLY TO SMOKE DETECTORS.
5. COMBUSTIBLE MATERIALS ENCLOSED IN NON-COMBUSTIBLE RACEWAYS OR
ENCLOSURES, APPROVED GYPSUM
BOARD ASSEMBLIES OR ENCLOSED IN MATERIALS LISTED AND LABELED FOR
SUCH APPLICATIONS.
X. WIRING:
COMBUSTIBLE ELECTRICAL OR ELECTRONIC WIRING METHODS AND MATERIALS,
OPTICAL FIBER CABLE, AND OPTICAL FIBER RACEWAYS EXPOSED WITHIN A PLENUM SHALL
HAVE A PEAK OPTICAL DENSITY NOT GREATER THAN .50, AN AVERAGE OPTICAL DENSITY
NOT GREATER THAN 0.15 AND A FLAME SPREAD NOT GREATER THAN 5 FEET WHEN TESTED
IN ACCORDANCE WITH NFPA 262. ONLY TYPE OFNP (PLENUM RATED NON-CONDUCTIVE
FIBER CABLE) SHALL BE INSTALLED IN PLENUM-RATED RACEWAYS. WIRING, CABLE, AND
RACEWAYS ADDRESSED IN THIS SECTION SHALL BE LISTED AND LABELED AS PLENUM
RATED AND SHALL BE INSTALLED IN ACCORDANCE WITH ICC ELECTRICAL CODE.
Y. PROVIDE VOLUME AND BALANCING DAMPERS AS REQUIRED BY IMC 603.17 FOR EACH
BRANCH OR DIFFUSER. REFERENCE CONSTRUCTION DOCUMENT SPECIFICATION SECTIONS
233300 & 230593. PROVIDE LINKAGE VOLUME DAMPERS TO
DAMPERS LOCATED ABOVE HARD-LID CEILINGS SIMILAR TO YOUNG REGULATOR
MODEL 927C OR EQUIVALENT SOLID
LINKAGE DAMPER.
Z. ALL DUCT DETECTORS TO COMPLY WITH 2018 IMC 606.4.1 WHICH REQUIRES VISUAL LED
MONITORING AS WELL AS CENTRAL FIRE ALARM & BMS MONITORING OF ALL DUCT
DETECTORS. VISUAL MONITORS WILL BE INSTALLED WHERE AVAILABLE. WHERE NOT
AVAILABLE, A VISUAL AND AUDIBLE ALARM WILL BE PROVIDED THROUGH THE BMS AND FIRE
ALARM SYSTEM TO A CONSTANTLY ATTENDED LOCATION.
AA. VENTILATION SYSTEMS SHALL BE BALANCED USING A NATIONALLY ACCEPTED AIR
BALANCING TEST METHOD. SUCH BALANCING SHALL VERIFY THAT THE VENTILATION
SYSSTEM IS CAPABLE OF SUPPLYING AND EXHAUSTING THE AIRFLOW RATES REQUIRED BY
SECTIONS 403.3 AND 403.3.1.2. A FINAL REPORT SHALL BE PROVIDED TO THE ENGINEER OF
RECORD AND THE MECHANICAL INSPECTOR.
NOTES:
1. PROVIDE BLOWDOWN VALVE AT BOTTOM CONNECTION.
AIR SEPARATOR SCHEDULE
MARK LOCATION SERVES TYPE
AIR SEPERATOR
BUILT-IN
STRAINER
DIRT
SEPERATOR
WEIGHT
(LBS)
BASIS OF DESIGN
REMARKS
SIZE
(IN)
FLOW
(GPM)
WPD
(FT) MANUFACTURER MODEL
AS-1 MECH RM HHW INLINE 6 400 5 NO NO 170 Taco AC06-125 NOTE 1
NOTES:
1. PROVIDE RELIEF VALVE AND EXTEND TO NEAREST FLOOR SINK.
EXPANSION TANK SCHEDULE
MARK LOCATION SYSTEM TYPE
INITIAL PRESSURE
IN TANK (PSIG)
MAX OPERATING
PRESSURE
(PSIG)
FILL PRESSURE AT TANK MIN
BLADDER
VOLUME
(GAL)
PIPE SIZE
TO TANK
(IN)
WEIGHT
(LBS)
BASIS OF DESIGN
REMARKS
RELIEF
VALVE
(PSIG)
AT TANK
(PSIG) MANUFACTURER MODEL
ET-1 MECH RM HHW BLADDER 35 125 100 45 57 1 250 TACO CA215-125 NOTE 1
NOTES:
1. PROVIDE AL29-4C OR 316L STAINLESS STEEL VENTING (14" ROUND) UP THROUGH ROOF. EXTEND TO 4' ABOVE ROOF AND PROVIDE ROOF CAP. PROVIDE CONDENSATE NEUTRALIZATION TRAP KIT. PROVIDE INTERFACE FOR BACNET CONTROL SYSTEM. PROVIDE LEAD/LAG CONTROLLER MODULE.
HOT WATER HEATING BOILER SCHEDULE
MARK LOCATION SERVES SYSTEM TYPE
FLUID HEATING
FUEL OIL
(GPH)
EFFICIENCY
WEIGHT
(LBS)
ELECTRICAL BASIS OF DESIGN
REMARKS
FLOW
(GPM)
EWT
(°F)
LWT
(°F)
WPD
(FT)
OUTPUT
GENERATED
(MBH)
MAX HEAT INPUT
(MBH) VOLT PHASE HERTZ
CIRCUIT
MANUFACTURER MODELFLA MCA MOCP
B-1 MECH RM CAMPUS HHW CONDENSING,
FUEL-OIL
400 120 °F 140 °F 5 3680 4000 150 92 9000 460 3 60 8 9 -- 1: FULTON
2: RIELLO
1: VANTAGE,
4000DF
2: RTC4000
#2 FUEL OIL ONLY,
NOTE 1
B-1 MECH RM CAMPUS HHW CONDENSING,
FUEL-OIL
400 120 °F 140 °F 5 3680 4000 150 92 9000 460 3 60 8 9 -- 1: FULTON
2: RIELLO
1: VANTAGE,
4000DF
2: RTC4000
#2 FUEL OIL ONLY,
NOTE 1
NOTES:
1. HX COMPLETE ON SKID WITH AUTOMATIC CONTROLS (MODULATING THERMOSTATIC VALVE, Y-STRAINER, TEMPERATURE GAUGE, ISOLATION VALVES). PROVIDE UNIT ELECTRONIC TEMPERATURE MONITOR PACKAGE AND AUTOMATIC
BOILER MODULATING VALVE PACKAGE (BACNET PROTOCOL).
PLUMBING LIQUID TO LIQUID HEAT EXCHANGER SCHEDULE
MARK LOCATION SERVES SYSTEM TYPE
HOT SIDE COLD SIDE
WEIGHT
(LBS)
BASIS OF DESIGN
REMARKS
FLOW
(GPM)
EWT
(°F)
WPD
(FT)
FLOW
(GPM)
EWT
(°F)
LWT
(°F)
WPD
(FT) MANUFACTURER MODEL
HX-2 MECH RM DOMESTIC HW DOMESTIC HW INSTANTANEOUS,
BRAZED PLATE
75 140 3.2 40 40 130 6 PVI Industries, LLC EZ75DW NOTE 1, 316L DOUBLE WALL.
REQUIRES DEDICATED 120V/15A
CIRCUIT.
HX-1 MECH RM DOMESTIC HW DOMESTIC HW INSTANTANEOUS,
BRAZED PLATE
75 140 3.2 40 40 130 6 PVI Industries, LLC EZ75DW NOTE 1, 316L DOUBLE WALL.
REQUIRES DEDICATED 120V/15A
CIRCUIT.
NOTES:
1. STAINLESS STEEL SHAFT, VARIABLE SPEED CAPABLE MOTOR.
2. PUMP BODY SHALL BE STAINLESS STEEL, LEAD-FREE, RATED FOR DOMESTIC HOT WATER RECIRCULATION SERVICE.
PUMP SCHEUDLE
MARK LOCATION SERVES SYSTEM TYPE
FLUID
EFFICIENCY
WEIGHT
(LBS)
ELECTRICAL BASIS OF DESIGN
REMARKS
FLOW
(GPM)
HEAD
(FT)
TEMPERTURE
(°F) SP GR VOLT PHASE HERTZ
MOTOR
MANUFACTURER MODELHP RPM
SPEED
CONTROL
P-1 MECH RM BOILERS PRIMARY HHW END SUCTION, BASE
MOUNT, CENTRIF
400 75 140 °F 1 75 560 460 3 60 15 1750 VFD ARMSTRONG 4030 5x4 NOTE 1
P-2 MECH RM BOILERS PRIMARY HHW END SUCTION, BASE
MOUNT, CENTRIF
400 75 140 °F 1 75 560 460 3 60 15 1750 VFD ARMSTRONG 4030 5x4 NOTE 1
RP-1 MECH RM DOMESTIC HOT
WATER
HWR INLINE 90 20 110 °F 1 -- 50 460 3 60 3/4 -- CONST TACO IL1233, STAINLESS STEEL NOTE 2
NOTES:
1. PROVIDE UNIT WITH FINGER-PROOF GUARD AND THERMOSTAT.
UNIT HEATER SCHEDULE
MARK LOCATION SERVES TYPE
AIR
FLOW
(CFM)
HEATING
WEIGHT
(LBS)
ELECTRICAL BASIS OF DESIGN
REMARKSTYPE
CAPACITY
(MBH)
EWT
(°F)
FLOW
(GPM) VOLT PHASE HERTZ
MOTO
R
MANUFACTURER MODELHP
UH-1 MECH RM MECH RM HHW 650 WATER 70 140 °F 6 200 120 1 60 1/5 MODINE HC 121 NOTE 1
UH-2 MECH RM MECH RM HHW 650 WATER 70 140 °F 6 200 120 1 60 1/5 MODINE HC 121 NOTE 1
R
GENERAL NOTES
A. REFER TO SHEET M-001 FOR ADDITIONAL GENERAL NOTES.
B. ALONG WITH PIPE DEMOLITION, REMOVE ALL ASSOCIATED HANGERS AND STRUCTURAL
ELEMENTS NOT OTHERWISE RE-USED FOR NEW WORK.16 17 18
A
M-201
MD-201
REMOVE
(E)3-WAY
REMOVE
(E)DIVERTING
VALVE
EXISTING
CHEMICAL
FEEDS TO
REMAIN
(E)3/4"LPR
(E)1"LPS
REMOVE
PRESSURE
REDUCING
STATION AND
BYPASS
(E)6"LPS
(E)3"LPR
(E)8"HPS
(E)6"HHW
(E)6"HHW
(E)1"HPR
(E)4"LPS
(E)3"HPS
(E )4
"L P
S
(E )2
"L P
R
(E)LPR
REMOVE
BLOWDOWN
TANK
(E)6"HWS
DN
(E)6"HWR
(E)2"HW
(E )2
"H W
R
(E)2"CW
(E)6"HWR
HHW
DN
(E)1"CW
DN
REMOVE BLOWDOWN PIPING AND
FEEDWATER PIPING LOCATED IN PIT. FUEL
OIL PIPING TO REMAIN.
REMOVE
(E)RECIRC
PUMP
REMOVE ALL PNEUMATIC LINES
THROUGHOUT AND CAP AT MAIN AIR LINE.
DEMOLISH
(E)FUEL PUMPS
REPLACE DAY
TANK
M-501
M-501
M-501
Level 1 0' - 0"
Level 2 15' - 9"
16 17 18
REMOVE
RELIEF VENTS
UP THROUGH
ROOF. PATCH
ROOF. TYP.
REMOVE
DEAERATOR
VENT. PATCH
ROOF.
1 1
REMOVE EXISTING BOILER VENT
UP THROUGH ROOF (12"/14").
PREPARE FOR INSTALLATION OF
NEW 12" DOUBLE-WALL VENT.
TYP.
M-501
M-501
M-501
1050 E. Southern Ave, Suite #D, Tempe, Arizona 85282, (480) 751-9542designgroup
Architecture, Engineering, and Sustainable Design
AESUS
KEY PLAN NTS NORTH
Drawing Title: Project Title:
Date
Location
Checked
Building Number:
Project Number:
Drawing Number:
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
WR BOILER REPLACEMENT & STEAM
SYSTEM CONVERSION DESIGN
Location:
NOV. 3, 2022
PH19WR02H6
WHITE RIVER INDIAN HEALTH SERVICES
200 W HOSPITAL DR. WHITERIVER, AZ 85941
AESUS
BOILER PLANT
AREA OF WORK
AESUS
MD-201
MECHANICAL DEMOLITION PLAN
3/8" = 1'-0"
MECHANICAL LEVEL 1 DEMOLITION PLAN - PIPING
3/8" = 1'-0"
MECHANICAL DEMOLITION SECTION VIEW
LEGEND NOTES
1 REMOVE EXISTING BOILER AND ASSOCIATED COMPONENTS. EXISTING CONCRETE PAD IS
TO BE RE-USED FOR NEW BOILER, REFER TO ARCHITECTURAL. TEMPORARILY REMOVE
LOUVERS FOR REMOVAL OF BOILER AND INSTALLATION OF NEW. REINSTALL LOUVER WHEN
COMPLETE.
2 REMOVE EXISTING DEAERATOR AND ASSOCIATED COMPONENTS.
3 REMOVE EXISTING STEAM AND STEAM CONDENSATE COMPONENTS THROUGHOUT THE
MECHANICAL ROOM. PER THE OWNER, THE EXISTING FLASH TANK AND CONDENSATE PUMP
IN PIT AREA MAY REMAIN.
4 REMOVE PUMPED CONDENSATE PIPING FROM DEAERATOR BACK TO PIT. REMOVE HIGH
PRESSURE STEAM FROM DEARATOR BACK TO MAIN. CAP AND ABANDON EXISTING.
5 REMOVE EXISTING PIPING BACK TO PIT. CAP AND ABANDON PIPING AT PIT/TRENCH AREA.
R
GENERAL NOTES
A. REFER TO SHEET M-001 FOR ADDITIONAL GENERAL NOTES.
16 17 18
UH-2
UH-1
ET-1
M-201
MD-201
VFD VFD
CAP
EXISTING
CHEMICAL
FEEDS TO
REMAIN
1" H
W S
1" H
W R
3/4"HWS
3/4"HWR 3/4"HWR
3/4"HWS
(E )2
"H W
(E )2
"H W
R
1"IW
2"CW
2" H
W
DN
DN
DN
DN
6"HWR
(E)6"HHW
6"HHW
AS-1
CONDENSATE
NEUTRALIZATION
KIT (TYP)
ROUTE SAFETY
VALVE
DISCHARGE TO
DRAIN
4 4
6"HHW
P-1
6"HWR
6"HWS
3" H
W S
3"HWR
(E)1/2"FOS
(E)1/2"FOR
CHECK VALVE
RP-1
7 7
NEW DAY
TANK, SEE
DETAIL
NEW FUEL
PUMPS, SEE
DETAIL
HX-1 HX-2
2"HW2"CW
Level 1 0' - 0"
Level 2 15' - 9"
16 17 18
HX-2
ET-1
UH-1UH-2
AS-1
B-1 5
VFDVFD
M-501
M-501
M-501
RP-1
ISO VALVE
(TYP)
1050 E. Southern Ave, Suite #D, Tempe, Arizona 85282, (480) 751-9542designgroup
Architecture, Engineering, and Sustainable Design
AESUS
KEY PLAN NTS NORTH
Drawing Title: Project Title:
Date
Location
Checked
Building Number:
Project Number:
Drawing Number:
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
WR BOILER REPLACEMENT & STEAM
SYSTEM CONVERSION DESIGN
Location:
NOV. 3, 2022
PH19WR02H6
WHITE RIVER INDIAN HEALTH SERVICES
200 W HOSPITAL DR. WHITERIVER, AZ 85941
AESUS
BOILER PLANT
AREA OF WORK
AESUS
M-201
MECHANICAL PLAN
3/8" = 1'-0"
MECHANICAL LEVEL 1 PLAN - PIPING
3/8" = 1'-0"
MECHANICAL SECTION VIEW
LEGEND NOTES
1 PROVIDE BLIND FLANGE AND BUTTERFLY VALVE (FUTURE CONNECTION FOR EXANSION OR
TEMPORARY SERVICE).
2 CONNECT MAKE-UP WATER AND PROVIDE AUTOMATIC AIR VENT AT TOP OF AIR
SEPARATOR. PROVIDE BALL VALVE WITH HOSE CONNECTION AT BOTTOM CONNECTION OF
AIR SEPARATOR.
3 PROVIDE HOT WATER UNIT HEATER TO REPLACE EXISTING STEAM UNIT HEATERS.
4 ROUTE SAFETY VALVE DISCHARGE FULL SIZE TO FLOOR SINK (GRAVITY FLOW). ROUTE
CONDENSATE TO FLOOR SINK AND INSTALL CONDENSATE NEUTRALIZATION TRAP.
5 INSTALL NEW BOILERS ON EXISTING CONCRETE PAD. REINSTALL EXISTING LOUVERS,
WHERE REMOVED FOR TRANSPORT OF EQUIPMENT INTO MECHANICAL ROOM.
6 MINIMUM FLOW SENSOR. REFER TO CONTROL DIAGRAM.
7 EXTEND NEW FUEL OIL PIPING FROM EXISTING PIT TO NEW BOILER. CUT HOLES IN METAL
LIDS AS NEEDED.
8 INSTALL NEW STAINLESS STEEL VENT UP THROUGH ROOF (AL29-4C). EXTEND UP THROUGH
ROOF TO 6' ABOVE ROOF AND PROVIDE NEW ROOF CAP. REFER TO ARCH FOR FLASHING
DETAILS.
CONTROL VALVE BY
MANUFACTURER OF
DOMESTIC WATER HEATER
DOMESTIC WATER HEATER
FLOOR
NOTES:
1. VERTICAL COIL TYPE DOMESTIC WATER HEATER IS SHOWN. IF HORIZONTAL TUBE BUNDLE TYPE IS
FURNISHED, PIPING SHALL BE SIMILAR.
2. SEE PLAN DRAWINGS FOR PIPING CONNECTIONS.
3. PIPING TO UPPER HEATER HEAD SHOULD BE PROVIDED WITH UNION OR FLANGES, LOCATED OUTSIDE THE
OUTER DIAMETER OF HEAD TO FACILITATE REMOVAL OF HEAD AND SHELL.
D H
W
DCW
DHWR
TEMPERATURE & PRESSURE
RELIEF VALVE BY
MANUFACTURER OF DOMESTIC
WATER HEATER ROUTE TO
NEAREST FLOOR DRAIN
THERMOMETER
HWR
HWS
TYPICAL MANUAL AIR VENT
ELEVATION
THREADED
PIPING
TYPICAL WATER
PIPING
REDUCER, IF
REQUIRED
3/4" [20mm] BALL
VALVE
ADAPTER TO 3/4" [20mm] HOSE
THREAD-PROVIDE HOSE CAP NUT
NOTES:
1. DRAIN ALL LOW POINTS AS INDICATED ABOVE.
2. WHERE SCALE POCKETS ARE SHOWN ON PIPE RISER DIAGRAMS
AND/OR PLANS LOCATE DRAIN AT BOTTOM OF SCALE
POCKET.
AIR
VENT
1/2" [15mm]
BALL VALVE
1/4" [8mm]
COPPER TUBING
1/2" [15mm] x 4" [100mm]
NIPPLE
CIRCULATING WATER
PIPING
ELEVATION
NOTES:
1. VENT ALL HIGH POINTS INDICATED ABOVE.
2. IF AUTOMATIC AIR VENTS ARE USED, PIPE DISCHARGE TO
DRAIN.
MV
OR
AV
1" M
A X
SIDE VIEW TRAPEZE HANGER FOR UP TO
453KG [1000 LB.] UNIFORM LOAD
ADJUSTABLE CLEVIS HANGER TYPE 1 -
SEE SPECIFICATIONS
ADJUSTABLE CLEVIS HANGER TYPE 43 -
SEE SPECIFICATIONS
MAXIMUM PIPE/TUBING SUPPORT SPACING
NOTE: FOR TRAPEZE HANGER TAKE SPACING OF SMALLEST SIZE ON TRAPEZE.
NOM. SIZE
PIPE
TUBING
mm [IN] mm
[FT]
mm
[FT]
THRU 20
[THRU 3/4
[7]
[5]
[1]
[7]
[6]
[1 1/4
[7]
[7]
[1 1/2
[9]
[8]
[2]
[10]
[8]
[2 1/2
[11]
[9]
[3]
[12]
[10]
[4]
[14]
[12]
[5]
[16]
[13]
[6]
[17]
[14]
[8]
[19]
[16]
[10]
[22]
[12]
[23]
[14]
[25]
[16]
[27]
[18]
[28]
[20]
[30]
[24]
[32]
PROVIDE INSULATION SHIELD
& INSERT FOR ALL PIPING
(200mm [8"] MIN.)
BAND
43mm [1-5/8"] 12 GAUGE CHANNEL OR 50x50x6.4mm
[2"X2"X1/4"] ANGLE
15mm [1/2"] DIA.
HANGER RODS WITH
900mm [36"] MAX.
SPACING ON EACH
CHANNEL
WELD
SADDLE
INSULATION SHIELD
AT HANGER
PROVIDE HIGH COMPRESSIVE
STRENGTH INSULATION (9 PSF
MIN. DENSITY) UNDER INSULATION
SHIELD
INSULATION (VAPOR
BARRIER TYPE IS
REQUIRED FOR LOW
TEMPERATURE PIPE)
HANGER ROD
NOTE:
SEE SPECIFER FOR DETAILED HANGER REQUIREMENTS
STEEL EXPANSION SHIELD FOR
EXISTING CONSTRUCTION AND
INSERTS FOR NEW CONSTRICTION
THIS TYPE SHALL BE USED ONLY IN
SLABS OR BEAMS OF 4" MIN DEPTH
3/8" MIN DIA EXPANSION
BOLTS FOR EXISTING CONSTRUCTION
AND INSERTS FOR NEW CONSTRUCTION
CONCRETE
FLOOR SLAB
CLIP
ANGLE
NUTS &
WASHERS
3/8" MIN DIA HANGER
RODS
FOR PIPES UNDER 2" IN SIZE USE 1 1/2"x1 1/2"x1/4" ANGLE.
ALL PIPES 2" & LARGER USE 3"x3"x1/4" ANGLE
TURNBUCKLE
3/8" MIN DIA HANGER
RODS
3/8" MIN DIA INSERTS NEW
CONSTRUCTION ONLY.
UNIT
HEATER
HOT
WATER
SUPPLY
HOT
WATER
RETURN
MV
AUTOMATIC FLOW
CONTROL VALVE
NOTE: UNIT MOUNTED
THERMOSTAT SHALL
MAINTAIN SPACE
TEMPERATURE BY
CYCLING
NOTES:
1. PAINT ALL STEEL WITH HEAT RESISTANT PAINT.
2. PROVIDE BOTTOM CLEAN-OUT AND DRAIN CONNECTION.
3. SEE ARCHITECTURAL PLANS AND SPECIFICATIONS FOR ROOFING AND FLASHINGS.
ROOF
2" MINIMUM CLEARANCE
TO COMBUSTIBLES AND
THROUGH ROOF
STACK CAP
STORM COLLAR
6 GAUGE CANT, BASE, AND
ADJUSTABLE FLASHING
BOTTOM OF FLASHING
OVER ROOF
FLUE UP (REFER
TO SPECIFICATIONS)
6'-0" MIN
NEW GUY
WIRES TO
EXISTING
ATTACHMENT
POINT
A
RE-USE
EXISTING
CONCRETE
PAD
FLEXIBLE
CONNECTOR
NEW CHECK
VALVE
A
CONDENSATE
NEUTRALIZATION
KIT (TYP)
SAFETY VALVE,
75 PSI
MOTORIZED/MANUAL
CONTROL
VALVE
6"HHW
6"HHW
CAT IV VENT
UP THRU ROOF
TRAP AT BOTTOM
OF VENT,
CONNECT TO
NEUTRALIZATION
KIT.
CONNECT FUEL
OIL SUPPLY &
RETURN
1050 E. Southern Ave, Suite #D, Tempe, Arizona 85282, (480) 751-9542designgroup
Architecture, Engineering, and Sustainable Design
AESUS
KEY PLAN NTS NORTH
Drawing Title: Project Title:
Date
Location
Checked
Building Number:
Project Number:
Drawing Number:
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
WR BOILER REPLACEMENT & STEAM
SYSTEM CONVERSION DESIGN
Location:
NOV. 3, 2022
PH19WR02H6
WHITE RIVER INDIAN HEALTH SERVICES
200 W HOSPITAL DR. WHITERIVER, AZ 85941
AESUS
BOILER PLANT
AREA OF WORK
AESUS
M-501
MECHANICAL DETAILS
NTS
CONNECTIONS TO DOMESTIC WATER HEATER
NTS
HYDRONIC PIPING VENT AND DRAINS
NTS
PIPE HANGERS
NTS
SECURING HANGER RODS IN CONCRETE
NTS
UNIT HEATERS (HOT WATER) - PIPING CONNECTIONS
NTS
FLUE THROUGH ROOF DETAIL
3/8" = 1'-0"
PUMP NEW WORK DETAIL
3/8" = 1'-0"
PUMP DEMOLITION DETAIL
3/8" = 1'-0"
BOILER DETAIL
SS
FUEL SUPPLY
SOLENOID FILL
VALVE
TO ACTIVATE FUEL
OIL RETURN PUMPS
HIGH FUEL LEVEL SENSOR
EMER. FUEL OIL LEVEL
DAY TANK (REFER TO
DIV 23
SPECIFICATIONS)
LOW FUEL LEVEL SENSOR
NORMAL SHUT-OFF LEVEL
LOW FUEL LEVEL
FIN. FLOOR
HIGH FUEL OIL LEVEL
100 GAL
CONTROL SEQUENCE
A. UPON A SIGNAL FROM THE LOW FUEL OIL SENSOR THE FILL SOLENOID VALVE IS
ENERGIZED TO THE "OPEN" POSITION AND FUEL OIL SUPPLY PUMP IS ACTIVATED.
UPON LOSS OF THE SIGNAL AT THE NORMAL SHUT OFF POINT THE FILL VALVE IS DE-
ENERGIZED TO THE "CLOSED" POSITION AND FUEL OIL SUPPLY PUMP IS
DEACTIVATED.
B. A SIGNAL FROM THE HIGH FUEL OIL SENSOR CLOSES THE FILL SOLENOID SHUT-OFF
VALVE, ACTIVATES AN ALARM AT THE FUEL OIL MASTER CONTROL PANEL AND FUEL
OIL RETURN PUMP #1 IS ACTIVATED UNTIL THE NORMAL SHUT-OFF LEVEL IS
REACHED.
C. A SIGNAL FROM THE EMERGENCY FUEL OIL LEVEL SENSOR CLOSES THE FILL
SOLENOID SHUT-OFF VALVE (AGAIN), ACTIVATES ANOTHER ALARM AT THE FUEL OIL
MASTER CONTROL PANEL AND FUEL OIL RETURN PUMP #2 IS ACTIVATED UNTIL THE
NORMAL SHUT-OFF LEVEL IS REACHED.
D. FORP #1 & #2 RETURN PUMPS SHALL ALTERNATE DUTY.
E. WHEN ONE PUMP CANNOT SATISFY THE DEMAND WITHIN ONE MINUTE THE SECOND
PUMP SHALL ALSO ENERGIZE TO MEET DEMAND.
F. MASTER CONTROL PANEL SHALL BE PROVIDED IN THE PLANT.
G. LEAK DETECTION CONTROL PANEL SHALL BE LOCATED IN PLANT.
2" MAIN TANK
VENT THROUGH
ROOF
3" EMERGENCY
TANK VENT
THROUGH ROOF
BOILER
BRAIDED STAINLESS STEEL FLEX COUPLING; MFG.
TITEFLEX TO BOILER FUEL OIL TRAIN.
MANUFACTURER'S TRAIN TO INCLUDE FUEL PUMP,
ISOLATION VALVE, PRESSURE GAUGES, SOLENOID
VALVES, AND HIGH/LOW SWITCHES.
BOILER
1/2"FOR
1/2"FOS
F O
R
F O
S
FUEL RETURN
PUMPS
1"
150 GAL. DIESEL FUEL STORAGE DAY
TANK WITH FACTORY MOUNTED AND
PRE-WIRED RETURN PUMP. EQUAL TO
TRAMONT 2000 ECM.
FUEL-OIL CIRCULATION PUMPS, 120 GPH
@ MIN 15 PSI. EQUAL TO PREFERRED-
MFG 104-D (1/2 HP). PUMP SET COMES
COMPLETE WITH FUEL FILTER, STAINER,
AND CONTROLLER.
FLOODED LOOP. INSTALL PER
MANUFACTUER'S
INSTRUCTIONS.
SOLENOID
VALVES AND
BASKET
STRAINER
PUMPED
RETURN BACK
TO TANK
1/2" FOS & FOR TO
GENERATORS
1"FOR
1"
1/2"FOR
1/2"FOS
1050 E. Southern Ave, Suite #D, Tempe, Arizona 85282, (480) 751-9542designgroup
Architecture, Engineering, and Sustainable Design
AESUS
KEY PLAN NTS NORTH
Drawing Title: Project Title:
Date
Location
Checked
Building Number:
Project Number:
Drawing Number:
Drawn
Revisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
WR BOILER REPLACEMENT & STEAM
SYSTEM CONVERSION DESIGN
Location:
NOV. 3, 2022
PH19WR02H6
WHITE RIVER INDIAN HEALTH SERVICES
200 W HOSPITAL DR. WHITERIVER, AZ 85941
AESUS
BOILER PLANT
AREA OF WORK
AESUS
M-502
MECHANICAL DETAILS
NOT TO SCALE
TYPICAL DAY TANK FUEL OIL SUPPLY SENSOR SCHEMATIC
NOT TO SCALE
FUEL OIL PIPING SCHEMATIC
Phase 1
Phase 2
Phase 3
Phase 4
Phase 5
Phase 6
PHASING NOTES
REFER TO GENERAL PHASING NOTES ON
ARCHITECTURAL SHEET AS-100. THE FOLLOWING
PHASING AND TIMELINES ARE FOR REFERENCE ONLY
AND REPRESENTS DISCUSSIONS WITH THE OWNER. THE
CONTRACTOR SHALL DEVELOP DETAILED PHASING
PLANS AND COORDINATE EACH INTERRUPTION OF
SERVICE WITH OWNER.
1. HEATING HOT WATER PUMPS MAY BE ISOLATED,
DEMOLISHED, AND REPLACED INDIVIDUALLY.
AT COORDINATED PERIOD WITH FACILITIES,
INTERRUPT SERVICE OF BOILERS AND REPLACE
DAY TANK AND FUEL PUMPS. DURING OUTAGE,
PREPARE NEW FUEL OIL BRANCH PIPING TO NEW
WATER BOILERS AS DETAILED IN PHASE 2 AND
PHASE 6 TO EXPEDITE TRANSITION. INTERRUPTION
TO BE LIMITED TO 48 HOURS.
EXISTING BOILERS ARE REDUNDANT.
DECOMMISSION EAST BOILER AND PREPARE FOR
DEMOLITION. DEMOLISH EXISTING STEAM BOILER.
DISCONNECT EXISTING LOUVER FOR REMOVAL OF
BOILER.
AT COORDINATED PERIOD WITH FACILITIES,
INTERRUPT SERVICE OF DOMESTIC HOT WATER
AND HEATING HOT WATER. DEMOLISH EXISTING
HOT WATER HEAT EXCHANGER. PRIOR TO
DEMOLITION, PREPARE NEW RUNOUTS DETAILED IN
PHASE 2 TO EXPEDITE TRANSITION. INTERRUPTION
TO BE LIMITED TO 48 HOURS.
2. INSTALL NEW EAST HOT WATER BOILER AND
ASSOCIATED COMPONENTS. REINSTALL EXISTING
LOUVER.
INSTALL NEW WATER HEATER. STARTUP NEW
DOMESTIC HOT WATER SYSTEM.
3. AT COORDINATED PERIOD WITH FACILITIES,
INTERRUPT SERVICE OF HEATING HOT WATER.
DEMOLISH EXISTING HEATING HOT WATER PIPING.
PRIOR TO DEMOLITION, PREPARE PORTIONS OF
NEW PIPING DETAILED IN PHASE 4 TO EXPEDITE
TRANSITION (WHERE POSSIBLE). INTERRUPTION TO
BE LIMITED TO 96 HOURS.
4. INSTALL NEW HEATING HOT WATER PIPING AND
ASSOCIATED COMPONENTS. WHERE EXISTING
STEAM PIPING CONFLICTS, ISOLATE AND
DEMOLISH.
STARTUP NEW HEATING HOT WATER SYSTEM.
5. DECOMMISSION REMAINING STEAM BOILER AND
DEMOLISH. DISCONNECT EXISTING LOUVER FOR
REMOVAL OF BOILER.
DEMOLISH REMAINING STEAM PIPING
THROUGHOUT MECHANICAL ROOM.
6. INSTALL NEW WEST HOT WATER BOILER AND
ASSOCIATED COMPONENTS. REINSTALL EXISTING
LOUVER.
INSTALL NEW HOT WATER UNIT HEATERS AND
REMAINING HEATING HOT WATER PIPING.
STARTUP NEW BOILER SYSTEM AND CONFIGURE
BOILERS FOR LEAD/LAG SERVICE.
SEQUENCE OF OPERATION
Note:
The basis-of-design includes an electronic control package which includes a modulation hot water valve which maintains the leaving domestic hot water temperature at desired temperature.
Additional items are monitored as described below:
Domestic Hot Water Temperature Monitoring:
The following temperatures shall be monitored:
• Leaving domestic hot water supply.
Alarms shall be provided as follows::
• Domestic hot water exceeds 140 deg for a period of 30 min (adj.)
• Domestic hot water falls below 110 deg (adj.) for a period of 2 hours (adj.)
WH
AI - Domestic Hot Water Supply Temp
T
HWS
HWR
SEQUENCE OF OPERATION
Boiler System - Run Conditions:
The boiler system shall be enabled to run whenever outside air temperature is less than 65°F (adj.). To prevent short cycling, each boiler shall run for and be off for minimum adjustable times (both user definable), unless shutdown on safeties or outside air conditions. Each boiler shall run subject to its own internal safeties and controls.
The boiler system shall also run for freeze protection whenever the outside air temperature is less than 38°F (adj.).
Hot Water Pump Lead/Lag Operation:
The two hot water pumps shall operate in a lead/lag fashion.
• The lead pump shall run first.
• On failure of the lead pump, the lag pump shall run and the lead pump shall turn off.
• On decreasing hot water differential pressure, the lag pump shall stage on and run in unison with the lead pump to maintain hot water differential pressure setpoint.
The designated lead pump shall rotate upon one of the following conditions (user selectable):
• manually through a software switch
• if pump runtime (adj.) is exceeded
• daily
• weekly
• monthly
Alarms shall be provided as follows:
• Hot Water Pump 1
• Failure: Commanded on, but the status is off.
• Running in Hand: Commanded off, but the status is on.
• Runtime Exceeded: Status runtime exceeds a user definable limit.
• VFD Fault.
• Hot Water Pump 2
• Failure: Commanded on, but the status is off.
• Running in Hand: Commanded off, but the status is on.
• Runtime Exceeded: Status runtime exceeds a user definable limit.
• VFD Fault.
Hot Water Differential Pressure Control:
The controller shall measure hot water differential pressure and modulate the hot water pump VFDs in sequence to maintain its hot water differential pressure setpoint.
The following setpoints are recommended values. All setpoints shall be field adjusted during the commissioning period to meet the requirements of actual field conditions.
The controller shall modulate hot water pump speeds to maintain a hot water differential pressure of 25 PSI (adj.). The VFDs minimum speed shall not drop below 20% (adj.).
On dropping hot water differential pressure, the VFDs shall stage on and run to maintain setpoint as follows:
• The controller shall modulate the lead VFD to maintain setpoint.
• If the lead VFD speed is greater than a setpoint of 90% (adj.), the lag VFD shall stage on.
• The lag VFD shall ramp up to match the lead VFD speed and then run in unison with the lead VFD to maintain setpoint.
On rising hot water differential pressure, the VFDs shall stage off as follows:
• If the VFDs speeds drops back to 60% (adj.) below setpoint, the lag VFD shall stage off.
• The lead VFD shall continue to run to maintain setpoint.
Alarms shall be provided as follows:
• High Hot Water Differential Pressure: If 25% (adj.) greater than setpoint.
• Low Hot Water Differential Pressure: If 25% (adj.) less than setpoint.
Boiler Lead/Standby Operation:
The two boilers shall operate in a lead/standby fashion when called to run and flow is proven.
• The lead boiler shall run first.
• On failure of the lead boiler, the standby boiler shall run and the lead boiler shall turn off.
The designated lead boiler shall rotate upon one of the following conditions: (user selectable):
• manually through a software switch
• if boiler runtime (adj.) is exceeded
• daily
• weekly
• monthly
Alarms shall be provided as follows:
• Boiler 1
• Failure: Commanded on but the status is off.
• Running in Hand: Commanded off but the status is on.
• Runtime Exceeded: Status runtime exceeds a user definable limit.
• Boiler 2
• Failure: Commanded on but the status is off.
• Running in Hand: Commanded off but the status is on.
• Runtime Exceeded: Status runtime exceeds a user definable limit.
• Lead Boiler Failure: The lead boiler is in failure and the standby boiler is on.
Hot Water Supply Temperature Setpoint:
The boiler shall maintain a hot water supply temperature setpoint as determined by its own internal controls (provided by others).
Primary Hot Water Temperature Monitoring:
The following temperatures shall be monitored:
• Primary hot water supply.
• Primary hot water return.
Alarms shall be provided as follows:
• High Primary Hot Water Supply Temp: If greater than 200°F (adj.).
• Low Primary…