Pavement Patching at Various Call-out Locations Throughout District 8
Solicitation number
76V40
Issued by
Illinois

About this file

Summary

This is a Notice to Bidders and contract specification document issued by the Illinois Department of Transportation (IDOT) for Contract No. 76V40, a full-depth pavement patching project at various call-out locations throughout District 8, covering multiple counties including St. Clair, Madison, Monroe, Randolph, Clinton, Bond, Jersey, Greene, Calhoun, and Washington. Electronic bids must be submitted to the iCX-Integrated Contractors Exchange system prior to 12:00 p.m. on September 18, 2026. The project includes patching guidelines and methodologies for multiple pavement types (jointed, continuously reinforced concrete, and bituminous), with minimum patch lengths ranging from 4 to 6 feet depending on pavement classification and previous resurfacing history. The contract runs from execution through June 30, 2029, with the contractor required to be on a five working day response time from notification of required patching work, provided weather conditions permit. The contractor is guaranteed minimum work equal to 70 percent of the awarded contract cost.

The contract includes strict traffic control requirements with peak hour restrictions on specified interstate and state routes, including mandatory maintenance of two lanes open during peak hours and potential liquidated damages of $1,000 per 15-minute interval for traffic flow impediments. Pricing is structured on a unit price basis for various work items including call-outs, pavement removal, replacement materials, saw cuts, reinforcement, and traffic control. The project is funded through District 8 Construction Funds and is subject to federal-aid requirements including EEO compliance, certified payroll reporting (Form SBE 48), monthly labor summaries, and DBE participation reporting. The contract includes supplemental specifications for materials including hot-mix asphalt, Portland cement concrete, and various reinforcement requirements, with work permitted between April 15 and December 1 for HMA patches and only PCC material allowed between December 1 and April 15 unless otherwise approved.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

September 18, 2026 Letting

Notice to Bidders, Specifications and Proposal

Contract No. 76V40 Various Counties Section DIST 8 PATCHING 2027-2 Various Routes District 8 Construction Funds

Prepared by S

Checked by (Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

September 18, 2026 prevailing time at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Section DIST 8 PATCHING 2027-2 Various Routes District 8 Construction Funds

Pavement patching at various call-out locations throughout District 8.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to readvertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

VARIOUS ROUTES

SECTION DIST 8 PATCHING 2027-2

VARIOUS COUNTIES

CONTRACT NO. 76V40

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 Additional State Requirements for Federal-Aid Construction Contracts 2 Subletting of Contracts (Federal-Aid Contracts)

3 X EEO

4 X Specific EEO Responsibilities Nonfederal-Aid Contracts 5 X Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 X Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays i

TABLE OF CONTENTS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

SUBMITTAL OF EEO/LABOR DOCUMENTATION

COMPLETION DATE

CONTRACT GUARANTEE

PROGRESS SCHEDULE AND PROSECUTION OF WORK

PEAK HOUR RESTRICTIONS

PATCHING GUIDELINES W/TABLE FOR METHOD OF PATCHING

SALVAGING EXISTING TIE BARS

WELDED WIRE REINFORCEMENT

SAWCUTS

PATCHING REINFORCEMENT

PAVEMENT REMOVAL FOR PATCHING

PAVEMENT REPLACEMENT, HOT-MIX ASPHALT

PAVEMENT REPLACEMENT, CONCRETE

PAVEMENT REPLACEMENT CONCRETE SPECIAL

CALL-OUT W/WORK ORDER SHEET

DOWEL BAR ASSEMBLY

DRILL AND GROUT DOWEL BARS

EXPANSION JOINT (SPECIAL)

TIE BARS, ¾”

PIPE DRAINS 4” (SPECIAL)

TRAFFIC CONTROL PLAN

TRAFFIC CONTROL AND PROTECTION (SPECIAL)

TEMPORARY SIGNING

BARRICADES

STATUS OF UTILITIES TO BE ADJUSTED

AUTOMATED FLAGGER ASSISTANCE DEVICES (BDE)

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

COMPENSABLE DELAY COSTS (BDE)

CONSTRUCTION AIR QUALITY – DIESEL RETROFIT (BDE)

DISADVANTAGED BUSINESS ENTERPRISE PARTICIPATION (BDE)

ILLINOIS WORKS APPRENTICESHIP INITIATIVE – STATE FUNDED CONTRACTS (BDE)

PAVEMENT MARKING (BDE)

PAVEMENT PATCHING (BDE)

PERFORMANCE GRADED ASPHALT BINDER (BDE)

ii

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)

SHORT TERM AND TEMPORARY PAVEMENT MARKINGS (BDE)

SIGN PANELS AND APPURTENANCES (BDE)

SPEED DISPLAY TRAILER (BDE)

SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)

SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)

SUBMISSION OF BIDDERS LIST INFORMATION (BDE)

SUBMISSION OF PAYROLL RECORDS – STATE CONTRACT (BDE)

SURVEYING SERVICES (BDE)

VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)

WEEKLY DBE TRUCKING REPORTS (BDE)

WORK ZONE TRAFFIC CONTROL DEVICES (BDE)

WORK ZONE WIDTH RESTRICTION (BDE)

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," adopted January 1, 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways," and the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction of Various Routes, Section Dist 8 Patching 2027-2, Various Counties, Contract No.

76V40, and in case of conflict with any part or parts of said Specifications, the said Special Provisions shall take precedence and shall govern.

Various Routes Section Dist 8 Patching 2027-2

LOCATION OF PROJECT

This project is located at various counties throughout District 8.

DESCRIPTION OF PROJECT

This project includes call out full-depth patching .

SUBMITTAL OF EEO/LABOR DOCUMENTATION

Effective: April 2016

This work shall be done in accordance with Check Sheets No. 1, 3, and 5 of the IDOT Supplemental Specifications and Recurring Special Provisions and the “Weekly DBE Trucking Reports (BDE)” special provision, except as here-in modified.

PAYROLL AND STATEMENT OF COMPLIANCE:

Certified payroll (FORM SBE 48 OR AN APPROVED FACSIMILE) and the Statement of Compliance (FORM SBE 348) shall be submitted by two methods:

1. By Mail (United States Postal Service): The ORIGINAL of the certified payroll and the Statement of Compliance for the Prime Contractor and each Subcontractor shall be submitted by mail to the Regional Engineer for District 8.

2. Electronically: Scan both the ORIGINAL of the certified payroll and the Statement of Compliance to the same PDF file, and email to the District at the email address designated by the District EEO Officer.

SBE 48 and SBE 348 forms shall be submitted weekly and will be considered late if received after midnight seven business days after the payroll ending date.

WEEKLY DBE TRUCKING REPORT:

The Weekly DBE Trucking Report (FORM SBE 723) shall be submitted electronically.

Scan the form to a PDF file, and email to the District at the email address designated by the District EEO Officer.

SBE 723 forms shall be submitted weekly and will be considered late if received after midnight ten business days following the reporting period.

MONTHLY LABOR SUMMARY & MONTHLY CONTRACT ACTIVITY REPORTS:

The Monthly Labor Summary Report (MLSR) shall be submitted by one of two methods:

1. For contractors having IDOT contracts valued in the aggregate at $250,000 or less, the report may be typed or clearly handwritten using Form D8 PI0148. Submit the ORIGINAL report by mail to the Regional Engineer for District 8. Contractors also have the option of using the method #2 outlined below.

2. For contractors having IDOT contracts valued in the aggregate at more than $250,000, the report must be submitted in a specific “Fixed Length Comma Delimited ASCII Text File Format”. This file shall be submitted by e-mail using specific file formatting criteria provided by the District EEO Officer. Contractors must submit a sample text file to District 8 for review at least 14 days prior to the start of construction.

The Monthly Contract Activity Report (MCAR) may be typed or clearly handwritten using Form D8 PI0149.

The MLSR and the MCAR shall be submitted concurrently. If the method of transmittal is method #1 above, then both the MLSR and the MCAR shall be mailed together in the same envelope. If the method of transmittal is method #2 above, then the MCAR shall be scanned to a .pdf file and attached to the email containing the MLSR .txt file.

The MLSR and MCAR must be submitted for each consecutive month, for the duration of the project, and will be considered late if received after midnight ten calendar days following the reporting period.

REQUEST FOR APPROVAL OF SUBCONTRACTOR:

The ORIGINAL and one copy of the Request for Approval of Subcontractor (FORM BC 260A) shall be submitted to the District at the IDOT Preconstruction Conference.

SUBSTANCE ABUSE PREVENTION PROGRAM CERTIFICATION:

The ORIGINAL and one copy of the Substance Abuse Prevention Program Certification (FORM BC 261) shall be submitted to the District at the IDOT Preconstruction Conference.

The Contractor is required to follow submittal procedures as provided by the EEO Officer at the preconstruction conference and to follow all revisions to those procedures as issued thereafter.

If a report is rejected, it is the Contractor’s responsibility to make required adjustments and/or corrections and resubmit the report. Reports not submitted and accepted within the established timeframes will be considered late.

Disclosure of this information is necessary to accomplish the statutory purpose as outlined under 23CFR part 230 and 41CFR part 60.4 and the Illinois Human Rights Act. Disclosure of this information is REQUIRED. Failure to comply with this special provision may result in the withholding of payments to the Contractor and/or cancellation, termination, or suspension of the contract in whole or part.

This special provision must be included in each subcontract agreement.

ALL HARD COPY FORMS TO BE SUBMITTED TO:

Region 5 Engineer Illinois Department of Transportation

ATTN: EEO/LABOR OFFICE

1102 Eastport Plaza Drive Collinsville, IL 62234-6198

Compliance with this special provision shall be included in the cost of the contract, and no additional compensation will be allowed for any costs incurred.

COMPLETION DATE

The contract is to run from the date of execution of the contract through June 30, 2029. All work on this contract shall be completed by June 30, 2029.

CONTRACT GUARANTEE

The Contractor will be guaranteed work for a minimum of 70% of the awarded cost of the contract.

PROGRESS SCHEDULE AND PROSECUTION OF WORK

Article 108.02 and the ten calendar days allowed in Article 108.03 of the Standard Specifications for beginning the work is hereby waived. Instead, the Contractor will be on a five working day response time from the time of notification by the Engineer, or their representative, that the patching is required at a specific location, provided weather conditions permit the work to be performed at that time. If weather conditions do not permit work at that time, work shall be performed as soon as conditions permit. Once the work has been started, work will be continuous until completed. The Contractor is not expected to work on weekends or legal holidays.

A written work order will be provided to the Contractor. This will serve either as notification or to confirm a verbal notification and will be provided as soon after verbal notification as practical.

PEAK HOUR RESTRICTIONS

The Contractor shall have two lanes open to traffic during peak hours in the appropriate direction.

The Contractor shall not be permitted to conduct any type of operation that would impede the flow of traffic during peak hours. The Contractor shall be permitted to work through the weekends, except for those holiday weekends specified in Article 107.09.

Peak hours are defined as:

• I-270; 6:00 a.m. to 6:00 p.m. for the westbound traffic and eastbound traffic.

• I-55/70, from the St. Clair County line to the intersection with I-270; 6:00 a.m. to 6:00 p.m.

for the westbound traffic and eastbound traffic.

• I-55 from I-270 to IL 143; 6:00 a.m. to 9:00 a.m. for the southbound traffic and 3:00 p.m.

to 6:00 p.m. for the northbound traffic.

• I-70 from I-270 to IL 4; 6:00 a.m. to 9:00 a.m. for the westbound traffic and 3:00 p.m. to

6:00 p.m. for the eastbound traffic.

• I- 255 from I-270 to Collinsville Rd; 6:00 a.m. to 6:00 p.m.

• I-55, 64, 70 and 55/64 in St. Clair County; 6:00 a.m. to 6:00 p.m.

• 3 lane section of I-255; 6:00 a.m. to 6:00 p.m.

• IL 3 from IL 158 to I-55/64: 6:00 a.m. to 9:00 a.m. for the northbound traffic, and 3 p.m. to

6 p.m. for southbound traffic.

• IL 15 from IL 159 to I-55/64: 6:00 a.m. to 9:00 a.m. for the west \bound traffic and 3:00 p.m. to 6:00 p.m. for the east \bound traffic.

Should the Contractor fail to have all lanes open to traffic during the defined peak hours, the Contractor shall be liable and shall pay to the Department $1000, not as a penalty but as liquidated damages, for every 15 minute interval or portion thereof that the flow of traffic is impeded by the Contractor’s operations. The Department will deduct these liquidated damages from any monies due or to become due to the Contractor from the Department.

PATCHING GUIDELINES W/TABLE FOR METHOD OF PATCHING

Following are the guidelines to be used for different types of pavement to be patched under this contract unless otherwise directed by the Engineer.

All type A, B, and type C (concrete) patches shall be edged the entire perimeter of the patch with an edging tool having a 1/4 inch radius.

Non-Interstate Highways

Non-Jointed Pavement - Previously Resurfaced or Not Previously Resurfaced:

a) The minimum patch length shall be 4 feet.

b) The minimum distance between undowelled patches shall be 15 feet.

c) A full depth undowelled patch in accordance with Section 442 of the Standard

Specifications shall be used with the replacement material at the option of the Contractor unless valid reasons exist for the Engineer to specify one type of material.

d) Patching Code: C, C (Special) or D.

Jointed Pavement - Pavement Not Previously Resurfaced:

a) The minimum patch length shall be 6 feet and full lane width.

b) A full depth dowelled patch in accordance with Section 442 of the Standard Specifications shall be used providing the Engineer determines that the existing adjacent pavement is sound enough to dowel the patch in. Should the Engineer determine that the existing adjacent pavement is not sufficiently sound enough to dowel the patch in or if the existing surrounding pavement has been successfully patched with undowelled patches previously, the Engineer may determine that undowelled patches will be used.

c) The minimum distance between undowelled patches shall be 15 feet, and the minimum distance between doweled patches shall be 20 feet.

d) The Engineer shall specify the replacement material for undowelled patches.

e) Patching Code: B, C, or D.

Jointed Pavement - Pavement Previously Resurfaced:

a) The minimum patch length shall be 6 feet and full lane width. A full depth undowelled patch in accordance with Section 442 of the Standard Specifications shall be used.

However, should the Engineer determine that the existing adjacent pavement is sufficiently sound enough to dowel the patch in or if the existing surrounding pavement has been successfully patched with doweled patches previously, the Engineer may determine that doweled patches will be used.

b) The minimum distance between undowelled patches shall be 15 feet, and the minimum distance between doweled patches shall be 20 feet.

c) The Engineer will specify the replacement material for undowelled patches.

d) Patching Code: B (Special), C (Special) or D.

Interstate Highways

Jointed Pavement - Pavement Not Previously Resurfaced:

a) The minimum patch length shall be 6 feet and full lane width.

b) A full depth doweled patch in accordance with Section 442 of the Standard Specifications shall be used providing the Engineer determines that the existing adjacent pavement is sound enough to dowel the patch in. Should the Engineer determine that the existing adjacent pavement is not sufficiently sound enough to dowel the patch in or if the existing surrounding pavement has been successfully patched with undowelled patches previously, the Engineer may determine that undowelled patches will be used.

c) The minimum distance between undowelled patches shall be 15 feet, and the minimum distance between dowelled patches shall be 20 feet.

d) The Engineer shall specify the replacement material for undowelled patches.

e) Patching Code: B, C, or D.

Jointed Pavement - Pavement Previously Resurfaced:

a) The minimum patch length shall be 6 feet and full lane width. A full depth undowelled patch in accordance with Section 442 of the Standard Specifications shall be used.

However, should the Engineer determine that the existing adjacent pavement is sufficiently sound enough to dowel the patch in or if the existing surrounding pavement has been successfully patched with doweled patches previously, the Engineer may determine that doweled patches will be used.

b) The minimum distance between undowelled patches shall be 15 feet, and the minimum distance between dowelled patches shall be 20 feet.

c) The Engineer will specify the replacement material for undowelled patches.

d) Patching Code: B (Special), C (Special) or D.

Continuously Reinforced Concrete Pavement - Pavement Not Previously Resurfaced:

a) The minimum patch length shall be 4 1/2 feet and half lane width. Half lane width shall not be used unless one edge of the patch is an outside pavement edge.

b) A full depth continuous reinforced concrete patch in accordance with Section 442 of the

Standard Specifications shall be used.

c) Patching Code: A

Continuous Reinforced Concrete Pavement - Pavement Previously Resurfaced:

a) The minimum patch length shall be 4 1/2 feet and full lane width.

b) If the continuous integrity of the existing pavement has been retained, a full depth continuous reinforced concrete patch in accordance with Section 442 of the Standard Specifications shall be used.

c) If structural deterioration of the surrounding pavement has taken place to the extent that the continuous integrity of the pavement cannot be retained, or if the continuous integrity of the surrounding pavement has been previously cut free, a full depth undowelled patch in accordance with Section 442 of the Standard Specifications shall be placed.

d) The minimum distance between undowelled patches shall be 15 feet.

e) The Engineer will specify the replacement material for undowelled patches.

f) Patching Code: A (Special), C (Special) or D.

Patching Requirements

Continuous Reinforced Concrete Patches:

a) The desirable minimum distance between the partial-depth saw cut and the nearest tight transverse crack in the pavement to remain is 18 inches. However, in areas of close crack spacing where the pavement otherwise appears to be sound, this dimension may be reduced to 6 inches. A tight crack should have no surface spalling and no faulting. The alignment of the partial and full-depth saw cuts may be skewed slightly if necessary to maintain this dimension.

b) When patching two adjacent lanes in one operation, the longitudinal joint shall be a sawed, longitudinal joint as detailed on Standard 420001. However, tie bars shall only be included for patches 20 feet or longer.

Dowelled Patches:

a) When patching two adjacent lanes in one operation, the longitudinal joint shall be a sawed longitudinal joint as detailed on Standard 420001. However, tie bars shall be included for patches 20 feet or longer.

b) Patches 40 feet or longer shall have sawed contraction joints, in accordance with Standard 420001, at 40 feet maximum intervals and be in prolongation with joints or cracks in the adjacent lane whenever possible.

c) Centerline joints, transverse joints and saw-cut extension into stabilized shoulders shall be sealed in accordance with Article 442.06(j) of the Standard Specifications.

d) For patches on 11 feet wide lanes, the 18 inch dimension from the centerline to the dowel bars shown on Standard 442101 shall be reduced to 12 inches.

Undowelled Concrete Patches:

a) Longitudinal joints shall be as detailed on Standard 420001 except that the tie bars are not required for patches less than 20 feet in length. Existing tie bars shall be either cut or removed. Marginal bars shall be cut.

b) When patching two adjacent lanes in one operation, tie bars shall be included in the sawed longitudinal joint for patches 20 feet or longer.

c) Centerline joints, transverse joints, and saw-cut extensions into stabilized shoulders shall be sealed in accordance with Article 442.06(j) of the Standard Specifications.

Bituminous Patches: Existing tie bars shall be either cut or removed. Marginal bars shall be cut.

General Requirements:

a) The Contractor shall have the option of sealing joints on doweled or undowelled patches with hot poured joint sealer or with a 1¼ inches wide. Preformed elastomeric joint seal shall be placed in accordance with Article 420.14(b) of the Standard Specifications and as shown on Standard 420001, except for patches on ramps or pavements that are superelevated more than 3% where the hot poured joint sealer may not be used.

b) Saw cut extension into pavement that is to remain in place will not be permitted.

c) After the forms are removed from the patch but prior to opening the patch to traffic, the disturbed stabilized shoulder area shall be restored to the existing line and grade with material designated by the Engineer.

d) The final finish of the patch at the transverse edges shall conform to any existing longitudinal surface variations.

Patching Material: The Engineer will determine the patching code (A, B, C, D, A(Special) B(Special) or C(Special) for each patch and include this information in the written work order. It will not be possible for the Engineer to determine the patching code for continuous reinforced concrete pavement that has been previously resurfaced until the existing pavement has been removed. Also, the Engineer may not be able to determine the patching code on jointed pavement until the existing pavement has been removed.

Table For Method of Patching

Patching Code Type of Patching Construction

Specs.

Payment for

Removal

Payment for Replacement

Type A CRC Concrete Section 442 Case A Pavement Replacement Concrete

Type B Dowelled Concrete Section 442 Case B Pavement Replacement Concrete

Type C Undowelled Concrete Section 442 Case C Pavement Replacement

Concrete

Type D Bituminous Section 442 Case C Pavement Replacement Hot-Mix Asphalt

Type A (Special)

CRC Concrete Previously Resurfaced

Section 442 And Special Provisions Case A Pavement Replacement

Concrete (Special)

Type B (Special)

Doweled Concrete Previously Resurfaced

Section 442 And Special Provisions Case B Pavement Replacement

Concrete (Special)

Type C (Special)

Undowelled Concrete

Section 442 And Special Provisions Case C Pavement Replacement

Concrete (Special)

SALVAGING EXISTING TIE BARS

The existing tie bars between the existing pavement and existing medians, gutters and/or combination curb and gutters that are found suitable for reuse shall be cleaned, straightened and incorporated into the new construction. Any existing tie bars that are found unsuitable to be incorporated into the proposed construction due to excessive rusting or distress shall be removed flush with the face of the existing concrete and disposed of outside the limits of right-of-way in accordance with Article 202.03 of the Standard Specifications.

This work will not be paid for separately but shall be considered included in the various removal pay items and no additional compensation will be allowed.

WELDED WIRE REINFORCEMENT

This work shall consist of furnishing and installing pavement fabric meeting the requirements of Article 1006.10 of the Standard Specifications in dowelled patches that are 12 feet or greater in length.

This work will be paid for at the contract unit price per SQUARE YARD for WELDED WIRE

REINFORCEMENT.

SAWCUTS

This work shall consist of providing saw cuts as described in Section 442 of the Standard Specification and the appropriate highway standard, except that saw cuts will be mandatory for all patches regardless of the class and per the Pavement Removal for Patching special provision.

This work will be measured in feet for the length of the required saw cut.

This work will be paid for at the contract unit price per FOOT for SAWCUTS.

PATCHING REINFORCEMENT

This work shall consist of furnishing and installing reinforcement bars in accordance with Article

442.06 of the Standard Specifications where continuously reinforced patches are required on interstate highways. Five eighths inch diameter bars of the required length will be used. The bar spacing is approximately 6 ½ inches. The exact spacing will be determined during patching operations.

This work will be paid for at the contract unit price per SQUARE YARD for PATCHING

REINFORCEMENT.

PAVEMENT REMOVAL FOR PATCHING

This work shall consist of the removal of various types of pavement for patching as follows:

Case C: For HMA and undowelled concrete patches (including CRC pavement), saw cut or score and remove in accordance with Article 442.05(c) of the Standard Specifications and as directed by the Engineer. The saw cut on previously resurfaced CRC pavement shall extend through existing reinforcement.

Case B: For doweled concrete patches, saw cut and remove in accordance with Article 442.05(b) of the Standard Specifications and as directed by the Engineer.

Case A: For continuously reinforced concrete pavement patches, saw cut and remove in accordance with Article 442.05(a) of the Standard Specifications and as directed by the Engineer.

The depth of the saw cut in CRC pavement with drainage mat underdrains will be determined by the Engineer to prevent damage to the underdrains.

This work will be measured in cubic yards by measuring from the top of pavement to the sub-base for depth (in yards) multiply by the square yards removed.

If additional sub-base or subgrade material is removed due to negligence on the part of the Contractor, its removal and replacement will not be measured for payment. Where unsuitable material is encountered in the subgrade and its removal and replacement is required by the Engineer, the additional quantity for removal and replacement will be measured for payment.

This work will be paid for at the contract unit price per CUBIC YARD for PAVEMENT REMOVAL FOR PATCHING, CASE C; PAVEMENT REMOVAL FOR PATCHING, CASE B; and PAVEMENT

REMOVAL FOR PATCHING, CASE A.

Replacement will be paid for separately. All mandatory saw cuts for removal operations will be paid for separately.

PAVEMENT REPLACEMENT, HOT-MIX ASPHALT

This work shall consist of pavement patch replacement and furnishing and replacing with HMA material in accordance with Section 442 of the Standard Specifications, except that the HMA mixture shall conform to the requirements of Section 406 of the Standard Specifications. The Engineer shall contact the District Bureau of Materials for the type of class 1 mixture required.

HMA patch replacement will be used only between April 15 and December 1 at locations allowed in the Patching Guidelines special provision. Between December 1 and April 15, only PCC material will be allowed unless otherwise approved by the Engineer.

This work will be measured in cubic yards by measuring from the top of pavement to the sub-base for depth (in yards) multiplied by the square yard of the surface area.

This work will be paid for at the contract unit price per CUBIC YARD for PAVEMENT

REPLACEMENT, HOT-MIX ASPHALT.

PAVEMENT REPLACEMENT, CONCRETE

This work shall consist of pavement patch replacement, furnishing and placing PCC material, sealing, and/or sawing of the joints as specified, and restoring any disturbed stabilized shoulder areas in accordance with Section 442 of the Standard Specifications.

This work will be measured in cubic yards by measuring from the top of pavement to the sub-base for depth (in yards) multiplied by the square yards of surface area.

This work will be paid for at the contract unit price per CUBIC YARD for PAVEMENT

REPLACEMENT, CONCRETE.

Reinforcement, dowel bars, tie bars, and expansion and anchor ties will be paid for separately.

PAVEMENT REPLACEMENT CONCRETE SPECIAL

This work shall consist of pavement patch replacement, furnishing and placing PCC material, sealing joints as specified, completing work as indicated on detail shown in the plans, and restoring any disturbed stabilized shoulder areas in accordance with Section 442 of the Standard Specifications.

This work will be measured in cubic yards by measuring from the top of pavement to the sub-base for depth (in yards) multiplied by the square yards of surface area.

This work will be paid for at the contract unit price per CUBIC YARD for PAVEMENT

REPLACEMENT, CONCRETE (SPECIAL).

Reinforcement, dowel bars, tie bars, and expansion and anchor ties will be paid for separately.

CALL-OUT W/WORK ORDER SHEET

This work shall consist of all preparations and operations necessary for the movement of personnel, equipment, supplies, and incidentals for each call-out to various sites as designated by the Engineer with the issuance of a work order sheet. Individual work order sheets may consist of numerous sites located within St. Clair, Madison, Monroe, Randolph, Clinton, Bond, Jersey, Greene, Calhoun, and Washington Counties.

This work will be paid for at the contract unit price per EACH for CALL-OUT as described above, regardless of the number of job sites listed on the individual work order sheet and no additional compensation will be allowed.

WORK ORDER SHEET

WORK ORDER NUMBER: ____________________________________

To: _________________________ DATE & TIME NOTIFICATION:

(Contractor’s Name) (When called or presented, whichever is first)

FROM: ______________________ DATE: _________________

(Dist. Maintenance Area) Engineer or his/her Authorized Representative) TIME: __________________

PLEASE PROCEED TO PATCH ON:

ROUTE: FROM: TO: COUNTY:

Estimated Number of Patches: __________________________

Estimated Cu. Yd. Of Removal of Case: ________ = __________

Estimated Cu. Yd. Of Replacement of: _________ = __________

Estimated Ft. of Saw Cuts: ____________

SPECIAL NOTES:

Use Traffic Control Protection Standard: ___________________

Dowell Bars Required: YES or NO Pavement Fabric: YES or NO Reinforcement Bars: YES or NO

OFFICE INFORMATION:

Work completed on: _____________ at ________________ (Date) (Time)

Engineer

DOWEL BAR ASSEMBLY

This work shall consist of furnishing and placing a dowel bar assembly as shown on Standard 420001 at locations designated by the Engineer. The dowel bar assembly shall be a minimum of 12 feet long.

This work will be paid for at the contract unit price per EACH for DOWEL BAR ASSEMBLY.

DRILL AND GROUT DOWEL BARS

This work shall consist of furnishing and installing dowels in accordance with Article 442.06 of the Standard Specifications where dowelled patches are required on highways with jointed pavements.

This work will be paid for at the contract unit price per EACH for DRILL AND GROUT DOWEL

BARS.

EXPANSION JOINT (SPECIAL)

This work consists of furnishing all labor, equipment, and materials required to install a 3-inch expansion joint near the center of a class A pavement patch at location(s) shown on the plans or as directed by the Engineer.

Materials of the expansion joint shall conform to Article 1051.08 or 1051.09, Article 1106.11, and Article 1050.02.

Work shall be according to Section 442, Article 420.10 (c), Standard 420001, and plan details.

The expansion joint shall be measured for payment in place in feet. The pavement removal and replacement shall be measured for payment in place as specified elsewhere without reduction for expansion joint (special).

This work will be paid for at the contract unit price bid per FOOT for EXPANSION JOINT

(SPECIAL).

TIE BARS, ¾”

When patching two adjacent lanes and when the patches are 20 feet or longer, ¾ inch (#6) tie bars shall be included at 2’ centers under patching codes B, C, B (special) and C (special) and as directed by the Engineer.

This work shall include all labor, equipment, and materials required to complete drilling and installation and will be paid for at the contract unit price per EACH for TIE BARS, ¾”.

PIPE DRAINS 4” (SPECIAL)

This work shall consist of all equipment, labor and materials as required to install pipe drain 4” (special) in accordance with Section 601 of the Standard Specifications and as per the plans.

Pipe elbows and end caps will be required.

Pipe material shall conform to Article 1040.04 of the Standard Specifications.

Pipe trench shall be sawed to the dimensions shown in the plans to the satisfaction of the Engineer.

This work will be paid for at the contract unit price per FOOT for PIPE DRAINS 4” (SPECIAL).

TRAFFIC CONTROL PLAN

Effective: July 12, 1993 Revised: May 12, 1997

Traffic control shall be in accordance with the applicable sections of the “Standard Specifications for Road and Bridge Construction”, the applicable guidelines contained in the “National Manual on Uniform Traffic Control Devices for Streets and Highways”, Illinois Supplement to the National Manual of Uniform Traffic Control Devices, these special provisions, and any special details and highway standards contained herein and in the plans.

Special attention is called to Articles 107.09 and 107.14 of the “Standard Specifications for Road and Bridge Construction and the following highway standards relating to traffic control:

701201 701206 701336 701400 701401 701406 701411 701421 701422 701446 701456 701501 701502 701601 701602 701606 701701 701901

In addition, the following special provision(s) will also govern traffic control for this project:

Peak Hour Restrictions Traffic Control and Protection (SPECIAL) Temporary Signing

Barricades Automated Flagger Assistance Device Speed Display Trailer Vehicle and Equipment Warning Lights Work Zone Traffic Control Devices Work Zone Width Restriction

Traffic: It is the intention of the Department that all roads be kept open to traffic at all times during the construction of this contract. One-lane, two-way traffic will be permitted in the immediate work areas during construction on two-lane pavements and one-lane one-way traffic on divided highways. At all other times, all traffic lanes shall be kept open throughout the project.

At any particular location on a four lane divided highway when the driving lane is closed to traffic, the Contractor shall keep all equipment, materials and vehicles out of the median and off right of way beyond the median unless the passing lane is closed to traffic in the opposite direction. When the passing lane is closed to traffic, the Contractor shall keep all equipment, materials and vehicles off right of way beyond the adjacent driving lane that is open to traffic and off right of way beyond the centerline in the median unless the passing lane in the opposite direction is also closed to traffic.

No overnight closures will be permitted on 2-lane, 2-way traffic roadways.

Infrequently, IDOT personnel working on this project may do layout or inspection outside the limits of traffic control and protection provided during the various Contractor’s operations. To provide adequate traffic control and protection during layout and inspection, the Contractor shall furnish signs, barricades, flagmen and other necessary traffic control items as directed by the Engineer.

This work will be paid for in accordance with Article 109.04.

Any inconveniences or delays caused by the Contractor in complying with these special provisions relating to traffic control will be considered as included in the contract unit prices for the various traffic control and protection items and no additional compensation will be allowed.

TRAFFIC CONTROL AND PROTECTION (SPECIAL)

This work includes furnishing, installing, maintaining, replacing, relocating and removal of work zone traffic control and protection. This work shall be according to Section 701 of the Standard Specifications except as modified by this special provision and the highway standards shown on the plans.

The work zone traffic control and protection for each work location shall be provided as designated by the Engineer. More than one traffic control standard may be indicated for each location. The traffic control highway standards may need to be modified and/or combined to protect all ramps, intersections and entrances near each work location. Traffic control signs may also need to be omitted or added for traffic entering the project site from ramps, intersections and entrances. No additional compensation will be allowed for these modifications.

Full width pavement on ramps shall be open to traffic before night fall. Any damage to the existing shoulders adjacent to the ramp pavement resulting from traffic being directed onto the shoulder around a work area shall be repaired as directed by the Engineer and paid for according to Article

109.04 of the Standard Specifications.

Any additional flaggers not shown on the highway standard shall be paid for according to Article

109.04 of the Standard Specifications.

Method of Measurement: Traffic control and protection required under Standards 701201, 701206, 701336, 701401, 701406, 701411, 701421, 701422, 701446, 701456, 701501, 701502, 701601, 701602, 701606, 701701 will be measured for payment on an each basis only when the traffic control and protection applies to isolated stationary work areas and does not involve or is not a part of other protected areas.

A contiguous lateral movement of the work area causing a change in the location of traffic control devices, but not a longitudinal relocation of the work area, will not be considered a new location or installation.

Basis of Payment:: Traffic control and protection will be paid for at the contract unit price per EACH for TRAFFIC CONTROL AND PROTECTION STANDARD 701401, TRAFFIC CONTROL

AND PROTECTION, STANDARD 701411, TRAFFIC CONTROL AND PROTECTION,

STANDARD 701422, and TRAFFIC CONTROL AND PROTECTION, STANDARD 701446.

Traffic control for Standards 701201, 701206, 701336, 701406, 701421, 701456, 701501, 701502, 701601, 701602, 701606, 701701 will be paid for at the contract unit price per EACH for

TRAFFIC CONTROL AND PROTECTION, (SPECIAL).

The following chart describes how many times each highway standard is anticipated to be used.

This list shall not be considered all inclusive. Traffic control standards required are subject to change based on the location of the work to be done.

STANDARD ESTIMATED NUMBER OF

SETUPS

701201 15 701206 3 701336 3 701406 3 701421 3 701456 11 701501 14 701502 3 701601 3 701602 3 701606 11 701701 3

TEMPORARY SIGNING

The Contractor may be required to provide signage in addition to that required by the traffic control standards and Section 701 of the Standard Specifications. When additional signs are required as determined by the Engineer, they shall include furnishing, erecting, maintaining, and removing said signs.

This work will be paid for at the contract unit price per EACH for TEMPORARY SIGNING.

Additional flaggers required beyond what is included in traffic control standards shall be paid according to Art. 109.04.

BARRICADES

This work shall consist of any additional barricades/barrels when the work area for Standard 701201 exceeds 1,000 feet in each lane of traffic or when Standard 701401 exceeds 2,000 feet.

This work will be paid for at the contract unit price per EACH for BARRICADES. The additional barricades/barrels required for work area lengths exceeding 1,000 feet for two-lane highways and exceeding 2,000 feet for multilane highways will be paid for separately at the contract unit price.

STATUS OF UTILITIES TO BE ADJUSTED

NO UTILITIES TO BE ADJUSTED

The above represents the best information of the Department and is only included for the convenience of the bidder. The applicable provisions of Sections 102 and 103 and Articles 105.07 and 107.20 of the Standard Specifications for Road and Bridge Construction shall apply.

If any utility adjustment or removal has not been completed when required by the Contractor's operation, the Contractor should notify the Engineer in writing. A request for an extension of time will be considered to the extent the Contractor's operations were affected.

AUTOMATED FLAGGER ASSISTANCE DEVICES (BDE)

Effective: January 1, 2008 Revised: April 1, 2023

Description. This work shall consist of furnishing and operating automated flagger assistance devices (AFADs) as part of the work zone traffic control and protection for two-lane highways where two-way traffic is maintained over one lane of pavement in segments where no sideroads or entrances require deployment of additional flaggers. Use of these devices shall be at the option of the Contractor.

Equipment. AFADs shall be the STOP/SLOW or Red/Yellow Lens type mounted on a trailer or moveable cart meeting the requirements of the MUTCD and NCHRP 350 or MASH 2016, Category 4.

General. AFADs shall be placed at each end of the traffic control, where a flagger is shown on the plans. The AFAD shall be setup within five degrees of vertical.

Flagger symbol signs as shown on the plans shall be replaced with “BE PREPARED TO STOP” signs when the AFAD is in operation.

Personal communication devices shall not be used to operate the AFAD.

Flagging Requirements. Flaggers and flagging requirements shall be according to Article 701.13 of the Standard Specifications and the following.

Each AFAD shall be operated by a flagger trained to operate the specific AFAD to be deployed.

A minimum of two flaggers shall be on site at all times during operation. Each flagger shall be positioned outside the lane of traffic and near each AFAD’s location.

Flagging equipment required for traditional flagging shall be available near each AFAD location in the event of AFAD equipment malfunction/failure.

For nighttime flagging, the AFAD and flagger shall be illuminated according to Article 701.13 of the Standard Specifications.

When not in use, AFADs will be considered non-operating equipment and shall be stored according to Article 701.11 of the Standard Specifications.

Basis of Payment. This work will not be paid for separately but shall be considered as included in the cost of the various traffic control items included in the contract.

CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)

Effective: January 1, 2025 Revised: January 1, 2026

Revise the first paragraph of Article 285.05 of the Standard Specifications to read:

“ 285.05 Fabric Formed Concrete Revetment Mat. The grout shall consist of a mixture of cement, fine aggregate, and water so proportioned and mixed as to provide a pumpable slurry.

Fly ash or ground granulated blast furnace (GGBF) slag, and concrete admixtures may be used at the option of the Contractor. The grout shall have an air content of not less than 6.0 percent nor more than 9.0 percent of the volume of the grout. The mix shall obtain a compressive strength of 2500 psi (17,000 kPa) at 28 days according to Article 1020.09.”

Revise Article 302.02 of the Standard Specifications to read:

“ 302.02 Materials. Materials shall be according to the following.

Item Article/Section

(a) Cement

(b) Water

(c) Hydrated Lime .................................................................................................... 1012.01

(d) By-Product, Hydrated Lime ................................................................................ 1012.02

(e) By-Product, Non-Hydrated Lime ........................................................................ 1012.03

(f) Lime Slurry ......................................................................................................... 1012.04

(g) Fly Ash

(h) Soil for Soil Modification (Note 1) ....................................................................... 1009.01

(i) Bituminous Materials (Note 2)

Note 1. This soil requirement only applies when modifying with lime (slurry or dry).

Note 2. The bituminous materials used for curing shall be emulsified asphalt RS-2, CRS- 2, HFE 90, or HFE 150; rapid curing liquid asphalt RC-70; or medium curing liquid asphalt MC-70 or MC-250.”

Revise Article 312.07(c) of the Standard Specifications to read:

“ (c) Cement .................................................................................................................... 1001”

Add Article 312.07(i) of the Standard Specifications to read:

“ (i) Ground Granulated Blast Furnace (GGBF) Slag ...................................................... 1010”

Revise the first paragraph of Article 312.09 of the Standard Specifications to read:

“ 312.09 Proportioning and Mix Design. At least 60 days prior to start of placing CAM II, the Contractor shall submit samples of materials to be used in the work for proportioning and testing.

The mixture shall contain a minimum of 200 lb (120 kg) of cement per cubic yard (cubic meter).

Cement may be replaced with fly ash or ground granulated blast furnace (GGBF) slag according to Article 1020.05(c)(1) or 1020.05(c)(2), respectively, however the minimum cement content in the mixture shall be 170 lbs/cu yd (101 kg/cu m). Blends of coarse and fine aggregates will be permitted, provided the volume of fine aggregate does not exceed the volume of coarse aggregate. The Engineer will determine the proportions of materials for the mixture according to the “Portland Cement Concrete Level III Technician Course” manual. However, the Contractor may substitute their own mix design. Article 1020.05(a) shall apply, and a Level III PCC Technician shall develop the mix design.”

Revise Article 352.02 of the Standard Specifications to read:

“ 352.02 Materials. Materials shall be according to the following.

(a) Cement (Note 1)

(b) Soil for Soil-Cement Base Course ....................................................................... 1009.03

(c) Water

(d) Bituminous Materials (Note 2)

Note 1. Bulk cement may be used for the traveling mixing plant method if the equipment for handling, weighing, and spreading the cement is approved by the Engineer.

Note 2. The bituminous materials used for curing shall be emulsified asphalt RS-2, CRS-2, HFE 90, or HFE 150; rapid curing liquid asphalt RC-70; or medium curing liquid asphalt MC-70 or MC-250.”

Revise Article 404.02 of the Standard Specifications to read:

“ 404.02 Materials. Materials shall be according to the following.

(a) Cement

(b) Water

(c) Fine Aggregate .................................................................................................... 1003.08

(d) Bituminous Material (Tack Coat) .......................................................................... 1032.06

(e) Emulsified Asphalts (Note 1) (Note 2) .................................................................. 1032.06

(f) Fiber Modified Joint Sealer .................................................................................. 1050.05

(g) Additives (Note 3)

Note 1. When used for slurry seal, the emulsified asphalt shall be CQS-1h according to Article 1032.06(b).

Note 2. When used for micro-surfacing, the emulsified asphalt shall be CQS-1hP according to Article 1032.06(e).

Note 3. Additives may be added to the emulsion mix or any of the component materials to provide the control of the quick-traffic properties. They shall be included as part of the mix design and be compatible with the other components of the mix.

Revise the last sentence of the fourth paragraph of Article 404.08 of the Standard Specifications to read:

“When approved by the Engineer, the sealant may be dusted with fine sand, cement, or mineral filler to prevent tracking.”

Revise Note 2 of Article 516.02 of the…