ILDOT 61M29-024.pdf

PDF 14 MB Posted

Attached to
Route FAU 3561 (Willow Road) Project
Solicitation number
61M29
Issued by
Cook County, Illinois

About this file

Summary

This is a Notice to Bidders and Special Provisions document for Illinois Department of Transportation (IDOT) Contract No. 61M29 in Cook County, Village of Winnetka, involving full-depth pavement reconstruction on FAU 3561 (Willow Road) and Hibbard Road. The project, designated Section 08-00103-00-FP and Project W0QM-228, spans 4,602.35 feet (0.87 miles) and includes jointed Portland cement concrete (PCC) pavement over aggregate subgrade improvement, new curb and gutter, sidewalk sections, drainage improvements, traffic signal improvements, and lighting enhancements. Electronic bids must be submitted to the iCX (Integrated Contractors Exchange) system no later than 12:00 p.m. on September 18, 2026, with bids to be publicly opened from the iCX SecureVault on the same date. The contract will be awarded to the lowest responsive and responsible bidder. Working hours are restricted to 7:00 a.m. to 7:00 p.m. Monday through Friday and 7:00 a.m. to 5:00 p.m. Saturday (by Village request only), with no work permitted on Sundays or holidays without Village of Winnetka approval.

The project involves substantial utility coordination with multiple agencies including MCI/Verizon, North Shore Gas, AT&T, Comcast, and the Metropolitan Water Reclamation District, with identified conflicts requiring resolution across five construction stages totaling approximately 131 days of utility work. Key materials include Hot-Mix Asphalt (HMA) with performance-graded binder, Portland cement concrete, various drainage structures, traffic signals, and water/sanitary sewer infrastructure. The contract is funded through District 1 Construction Funds and may include Federal-aid funding, requiring compliance with state and federal certifications. Contractors must provide comprehensive quality control documentation, maintain an Engineer's Field Office Type A (Special) with specified equipment and staffing, and establish a project progress schedule accounting for utility relocation durations. Estimated costs for temporary access, traffic control, and field office operations are bid items to be priced separately by the contractor.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting September 18, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 61M29 COOK County Section 08-00103-00-FP (Winnetka) Route FAU 3561 (Willow Road) Project W0QM-228 () District 1 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system

(iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

September 18, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 61M29 COOK County Section 08-00103-00-FP (Winnetka) Project W0QM-228 () Route FAU 3561 (Willow Road) District 1 Construction Funds

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

CONTRACT 61M29

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 Additional State Requirements for Federal-Aid Construction Contracts 2 Subletting of Contracts (Federal-Aid Contracts)

3 EEO

4 Specific EEO Responsibilities Non Federal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos HMA Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS

Table of Contents

CHECK SHEET # PAGE NO.

LRS 1 Reserved LRS 2 Furnished Excavation LRS 3 Work Zone Traffic Control Surveillance LRS 4 Flaggers in Work Zones LRS 5 Contract Claims LRS 6 Bidding Requirements and Conditions for Contract Proposals LRS 7 Bidding Requirements and Conditions for Material Proposals LRS 8 Reserved LRS 9 Bituminous Surface Treatments LRS 10 Reserved LRS 11 Employment Practices LRS 12 Wages of Employees on Public Works LRS 13 Selection of Labor LRS 14 Paving Brick and Concrete Paver Pavements and Sidewalks LRS 15 Partial Payments LRS 16 Protests on Local Lettings LRS 17 Substance Abuse Prevention Program LRS 18 Multigrade Cold Mix Asphalt LRS 19 Reflective Crack Control Treatment

FAU 3561 (Willow Road) Section 08-00103-00-FP

Project W0QM(228) Cook County

Contract 61M29 i

TABLE OF CONTENTS

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

DEFINITION OF TERMS

WORKING HOURS

MAINTENANCE OF ROADWAYS (D1)

STATUS OF UTILITIES (D-1)

PUBLIC CONVENIENCE AND SAFETY (D1)

EARTH EXCAVATION

AGGREGATE SURFACE COURSE FOR TEMPORARY ACCESS (D1)

HOT-MIX ASPHALT BINDER AND SURFACE COURSE (D1)

WINTERIZED TEMPORARY ACCESS (D1)

STORM SEWER ADJACENT TO OR CROSSING WATER MAIN (D1)

ADJUSTMENTS AND RECONSTRUCTIONS (D1)

ENGINEER’S FIELD OFFICE TYPE A (SPECIAL) (D1)

TRAFFIC CONTROL AND PROTECTION (ARTERIALS) (D1)

TRAFFIC CONTROL PLAN (D1)

FRICTION AGGREGATE (D1)

ROCKFILL

SLIPFORM PAVING (D1)

MINERALIZED CARBON DIOXIDE CONCRETE (D-1)

HOT-MIX ASPHALT – MIXTURE DESIGN VERIFICATION AND PRODUCTION (D1)

COMBINATION LIGHTING CONTROLLER

GENERAL ELECTRICAL REQUIREMENTS

TEMPORARY LUMINAIRE, LED, ROADWAY

WIRE AND CABLE

TEMPORARY INFORMATION SIGNING

RAISED REFLECTIVE PAVEMENT MARKER, REFLECTOR REMOVAL

RAISED REFLECTIVE PAVEMENT MARKER, REFLECTOR REPLACEMENT

MAST ARM SIGN PANELS

TRAFFIC SIGNAL GENERAL REQUIREMENTS

RE-OPTIMIZE TRAFFIC SIGNAL SYSTEM

SERVICE INSTALLATION (TRAFFIC SIGNALS)

UNDERGROUND RACEWAYS

HANDHOLES

Project W0QM(228) Cook County ii

TRAFFIC SIGNAL PAINTING

FULL-ACTUATED CONTROLLER AND CABINET

UNINTERRUPTABLE POWER SUPPLY, SPECIAL

ELECTRIC CABLE

EMERGENCY VEHICLE PRIORITY SYSTEM LINE SENSOR CABLE, NO. 20 3/C

TRAFFIC SIGNAL POST

MAST ARM ASSEMBLY AND POLE

CONCRETE FOUNDATIONS

LIGHT EMITTING DIODE (LED) SIGNAL HEAD AND OPTICALLY PROGRAMMED LED

SIGNAL HEAD

LED SIGNAL FACE, LENS COVER

LIGHT EMITTING DIODE (LED) PEDESTRIAN SIGNAL HEAD

TRAFFIC SIGNAL BACKPLATE

VIDEO VEHICLE DETECTION SYSTEM

RELOCATE EXISTING EMERGENCY VEHICLE PRIORITY SYSTEM, DETECTOR UNIT

RELOCATE EXISTING EMERGENCY VEHICLE PRIORITY SYSTEM, PHASING UNIT

ACCESSIBLE PEDESTRIAN SIGNALS

TEMPORARY TRAFFIC SIGNAL INSTALLATION

TEMPORARY TRAFFIC SIGNAL TIMING

REMOVE EXISTING TRAFFIC SIGNAL EQUIPMENT

MEMBRANE WATERPROOFING SYSTEM FOR BURIED STRUCTURES

COMBINATION CONCRETE CURB AND GUTTER, TYPE B6.12 (SPECIAL)

COMBINATION CONCRETE CURB AND GUTTER, TYPE B (SPECIAL)

CONNECTION TO EXISTING WATER MAIN

CONTRACTOR COOPERATION

BUTTERFLY VALVE WITH VAULT

CUT AND CAP EXISTING WATER MAIN

DETECTABLE WARNINGS

DRAINAGE STRUCTURE TO BE REMOVED

PROTECTION OF EXISTING TREES

SUPPLEMENTAL WATERING

DUST CONTROL WATERING

EXPLORATORY EXCAVATION

EXPLORATORY EXCAVATION FOR WATER MAIN IMPROVEMENTS

FIRE HYDRANTS TO BE REMOVED

FIRE HYDRANT WITH AUXILIARY VALVE AND VALVE BOX

FRAMES AND GRATES, TYPE 11V

Project W0QM(228) Cook County iii

FRAMES AND LIDS TO BE ADJUSTED / INLETS TO BE ADJUSTED

FRAMES AND LIDS TO BE ADJUSTED WITH NEW FRAME AND LID

INLETS TO BE ADJUSTED WITH NEW FRAME AND LID

GATE VALVE WITH VAULT

HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH

HIGH-EARLY-STRENGTH PORTLAND CEMENT CONCRETE PAVEMENT (JOINTED)

DRAINAGE STRUCTURES NO. 1

INLET RISER STRUCTURES (OPEN BOTTOM)

JUNCTION CHAMBER

LIDS, TYPE 1, CLOSED LID

LUMINAIRE, TYPE A (SPECIAL)

MANHOLES, CATCH BASINS, AND INLETS

MANHOLES, SANITARY, 4’-DIAMETER, TYPE 1 FRAME, CLOSED LID

PLUG EXISTING CULVERTS

PORTLAND CEMENT CONCRETE DRIVEWAY PAVEMENT

PORTLAND CEMENT CONCRETE SIDEWALK 5 INCH (SPECIAL)

PRIVATE DECORATIVE MATERIAL

PREPARATION OF BASE

ROAD CLOSURES AND LOCAL ACCESS

RECESSED REFLECTIVE PAVEMENT MARKERS

REMOVE AND RELOCATE SIGN PANEL AND SIGN PANEL ASSEMBLY

SANITARY MANHOLES TO BE ADJUSTED

SANITARY MANHOLES TO BE ADJUSTED WITH NEW TYPE 1 FRAME, CLOSED LID

SANITARY SEWER

SANITARY SEWER SERVICE, 6” PVC, COMPLETE

SEWER TELEVISING

SIDEWALK CURB

SLEEPER SLAB

STABILIZED CONSTRUCTION ENTRANCE

STORM SEWER CONNECTION

STORM SEWER REMOVAL AND INSTALLATION

TEMPORARY FENCE

TEMPORARY CHAIN LINK FENCE, 6’

WOOD FENCE TO BE REMOVED AND RE-ERECTED

TEMPORARY LIGHTING CONTROLLER

TEMPORARY RAMP (SPECIAL)

Project W0QM(228) Cook County iv

TEMPORARY SURFACE OVER TRENCH FOR UTILITY IMPROVEMENTS

TEMPORARY TRAFFIC SIGNAL TIMING (SPECIAL) FOR COOK COUNTY DEPARTMENT OF

TRANSPORTATION AND HIGHWAYS (CCDOTH) TRAFFIC SIGNALS

TRAFFIC SIGNAL WORK GENERAL FOR COOK COUNTY DEPARTMENT OF

TRANSPORTATION AND HIGHWAYS (CCDOTH) TRAFFIC SIGNALS

MULCH PLACEMENT FOR EXISTING WOODY PLANTS

REMOVE AND RELOCATE EXISTING RECTANGULAR RAPID FLASHING BEACON

ASSEMBLY

TRENCH BACKFILL

TRENCHLESS CONSTRUCTION

TRIAXIAL GEOGRID REINFORCEMENT, TYPE I

VALVE VAULTS TO BE ABANDONED

VALVE VAULTS TO BE ADJUSTED

VALVE VAULTS TO BE REMOVED

WATER MAIN

WATER MAIN LINE STOP

WATERMAIN CASING PIPE

WATER SERVICE LINE

LEAD WATER SERVICE REPLACEMENT

REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (PROJECT SPECIFIC)

WORK ZONES

FAILURE TO COMPLETE PLANT CARE AND ESTABLISHMENT WORK ON TIME

TEMPORARY SIDEWALK

AVAILABLE REPORTS (D1 LR)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING

LR 107-4 SPECIAL PROVISION FOR INSURANCE

LR 1030-2 LOCAL QUALITY ASSURANCE/ QUALITY MANAGEMENT QC/QA

BDE 2342 STORM WATER POLLUTION PREVENTION PLAN

BDE 2342A CONTRACTOR CERTIFICATION STATEMENT

IEPA PERMIT

COOK COUNTY DEPARTMENT OF TRANSPORTATION AND HIGHWAYS DRAFT

PERMIT

MWRD PERMIT

IDNR-OWR PERMIT

LPC 663 STATE ROW

LPC 663 LOCAL ROW

BDE SPECIAL PROVISIONS

The following special provisions indicated by an “X” are applicable to this contract. An * indicates a new or revised special provision for the letting.

File Name Pg. Special Provision Title Effective Revised 80099 Accessible Pedestrian Signals (APS) April 1, 2003 Jan. 1, 2022 _ 80274 241 Aggregate Subgrade Improvement April 1, 2012 April 1, 2022 80192 Automated Flagger Assistance Device Jan. 1, 2008 April 1, 2023 80173 Bituminous Materials Cost Adjustments Nov. 2, 2006 Aug. 1, 2017 80426 Bituminous Surface Treatment with Fog Seal Jan. 1, 2020 April 1, 2026 80475 Bridge Deck Concrete Overlays Jan. 1, 2026 80241 Bridge Demolition Debris July 1, 2009

5053I Building Removal Sept. 1, 1990 Aug. 1, 2022 5026I Building Removal with Asbestos Abatement Sept. 1, 1990 Aug. 1, 2022

80460 244 Cement, Finely Divided Minerals, Admixtures, Concrete, and Mortar Jan. 1, 2025 Jan. 1, 2026 80384 261 Compensable Delay Costs June 2, 2017 April 1, 2019 80198 Completion Date (via calendar days) April 1, 2008 80199 Completion Date (via calendar days) Plus Working Days April 1, 2008 80461 Concrete Barrier Jan. 1, 2025 80453 Concrete Sealer Nov. 1, 2023 80261 265 Construction Air Quality – Diesel Retrofit June 1, 2010 Jan. 1, 2025 80476 Deck Slab Repair Jan. 1, 2026 80029 267 Disadvantaged Business Enterprise Participation Sept. 1, 2000 Jan. 2, 2025 80467 Erosion Control Blanket Aug. 1, 2025 80229 Fuel Cost Adjustment April 1, 2009 Aug. 1, 2017 80452 Full Lane Sealant Waterproofing System Nov. 1, 2023 80433 Green Preformed Thermoplastic Pavement Markings Jan. 1, 2021 Jan. 1, 2022 80471 Guardrail Nov. 1, 2025 80472 High Friction Surface Treatment Nov. 1, 2025 80456 Hot-Mix Asphalt Jan. 1, 2024 April 1, 2026 80446 Hot-Mix Asphalt – Longitudinal Joint Sealant Nov. 1, 2022 Aug. 1, 2023 80438 Illinois Works Apprenticeship Initiative – State Funded Contracts June 2, 2021 April 2, 2024 80483 271 Inlet Filters April 1, 2026

* 80477 273 Longitudinal Tining Jan. 1, 2026 July 1, 2026 80450 Mechanically Stabilized Earth Retaining Walls Aug. 1, 2023 Aug. 1, 2025 80478 Modified Longitudinal Construction Joint Jan. 1, 2026 80464 275 Pavement Marking April 1, 2025 Nov. 1, 2025 80468 Pavement Patching Aug. 1, 2025 80441 276 Performance Graded Asphalt Binder Jan 1, 2023 April 1, 2026 80459 Preformed Plastic Pavement Marking June 2, 2024 3426I Railroad Protective Liability Insurance Dec. 1, 1986 Jan. 1, 2022 80473 282 Raised Reflective Pavement Markers Nov. 1, 2025 80455 283 Removal and Disposal of Regulated Substances Jan. 1, 2024 April 1, 2026 80474 Residential Driveway Temporary Signal Nov. 1, 2025

* 80445 Seeding Nov. 1, 2022 July 1, 2026 80457 285 Short Term and Temporary Pavement Markings April 1, 2024 April 2, 2024 80462 289 Sign Panels and Appurtenances Jan. 1, 2025 Jan. 1, 2026 80479 Sinusoidal Rumble Strips Jan. 1, 2026 80469 Slope Wall Aug. 1, 2025 80448 291 Source of Supply and Quality Requirements Jan. 2, 2023 Jan. 1, 2026 80340 Speed Display Trailer April 2, 2014 Jan. 1, 2022 80127 Steel Cost Adjustment April 2, 2004 Nov. 1, 2025 80480 Structural Repair of Concrete Jan. 1, 2026 80397 293 Subcontractor and DBE Payment Reporting April 2, 2018 80391 294 Subcontractor Mobilization Payments Nov. 2, 2017 April 1, 2019 80463 295 Submission of Bidders List Information Jan. 2, 2025 Mar. 2, 2025

File Name Pg. Special Provision Title Effective Revised 80482 296 Submission of Payroll Records – Federal Aid Contract April 1, 2026 80437 Submission of Payroll Records – State Contract April 1, 2021 April 1, 2026 80435 298 Surface Testing of Pavements – IRI Jan. 1, 2021 Jan. 1, 2023 80465 304 Surveying Services April 1, 2025 80481 305 Temporary Concrete Barrier Jan. 1, 2026 80466 Temporary Rumble Strips April 1, 2025

* 80484 Tolerance in Thickness for Continuously Reinforced PCC Pavement July 1, 2026 80470 Traffic Signal Backplate Aug. 1, 2025 20338 306 Training Special Provisions Oct. 15, 1975 Sept. 2, 2021 80429 Ultra-Thin Bonded Wearing Course April 1, 2020 Jan. 1, 2022 80439 309 Vehicle and Equipment Warning Lights Nov. 1, 2021 Nov. 1, 2022 80458 Waterproofing Membrane System Aug. 1, 2024 80302 310 Weekly DBE Trucking Reports June 2, 2012 Jan. 2, 2025 80454 Wood Sign Support Nov. 1, 2023 80427 311 Work Zone Traffic Control Devices Mar. 2, 2020 Jan. 1, 2026

* 80485 314 Work Zone Width Restriction July 1, 2026 80071 315 Working Days Jan. 1, 2002

Project W0QM(228) Cook County

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," adopted January 1 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways," and the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction of Contract 61M29, Project W0QM(228) Section 08-00103-00-FP, FAU 3561 (Willow Road), Cook County and in case of conflict with any part or parts of said Specifications, the said Special Provisions shall take precedence and shall govern.

Project W0QM(228)

LOCATION OF PROJECT

This project beings at a point on the reference centerline of FAU 3561 (Willow Road) just to the east of Forestway Drive and extends to the east along Willow Road to the intersection of Provident Avenue. The project also includes work on Hibbard Road along both approaches with the intersection of Willow Road. The gross and net length of this project is 4,602.35 feet (0.87 miles).

The project takes place in the Village of Winnetka, Illinois.

DESCRIPTION OF PROJECT

Improvements on this project include full depth pavement reconstruction consisting of jointed PCC pavement over an aggregate subgrade improvement. The project also includes new curb and gutter, sections of new sidewalk, drainage improvements, traffic signal improvements, lighting improvements, as well as additional roadway items and work necessary to complete the improvement as shown in the drawings and as described herein.

Project W0QM(228)

DEFINITION OF TERMS

Add the following to Article 101.01

SSWSC Standard Specifications for Water and Sewer Construction in Illinois, 8th Edition, 2020, and as amended from time to time.

Add the following articles:

101.56 OWNER. The Village of Winnetka, acting through its legally constituted officials, officers, or employees.

WORKING HOURS

The Contractor shall perform all work in the Municipality in accordance with Section 15.32.140 of the Village of Winnetka Construction Hours Ordinance, which states the following permitted construction hours:

7 A.M. to 7:00 P.M., Monday through Friday 7 A.M. to 5:00 P.M., Saturday (by request to the Village only)

No work will be permitted on Sundays or holidays or at other times outside the above working hours without permission of the Village of Winnetka.

MAINTENANCE OF ROADWAYS (D1)

Effective: September 30, 1985 Revised: November 1, 1996

Beginning on the date that work begins on this project, the Contractor shall assume responsibility for normal maintenance of all existing roadways within the limits of the improvement. This normal maintenance shall include all repair work deemed necessary by the Engineer, but shall not include snow removal operations. Traffic control and protection for maintenance of roadways will be provided by the Contractor as required by the Engineer.

If items of work have not been provided in the contract, or otherwise specified for payment, such items, including the accompanying traffic control and protection required by the Engineer, will be paid for in accordance with Article 109.04 of the Standard Specifications.

STATUS OF UTILITIES (D-1)

Effective: June 1, 2016 Revised: April 1, 2025

Utility companies and/or municipal owners located within the construction limits of this project have provided the following information regarding their facilities and the proposed improvements. The tables below contain a description of specific conflicts to be resolved and/or facilities which will require some action on the part of the Department’s contractor to proceed with work. Each table entry includes an identification of the action necessary and, if applicable, the estimated duration required for the resolution.

Project W0QM(228)

UTILITIES TO BE ADJUSTED

Conflicts noted below have been identified by following the suggested staging plan included in the contract.

The company has been notified of all conflicts and will be required to obtain the necessary permits to complete their work; in some instances, resolution will be a function of the construction staging. The responsible agency must relocate or complete new installations as noted below; this work has been deemed necessary to be complete for the Department’s contractor to then work in the stage under which the item has been listed.

Pre-Stage

NO UTILITIES IN CONFLICT

Stage 1 and 5

STAGE / LOCATION TYPE DESCRIPTION

RESPONSIBLE

AGENCY

DURATION

OF TIME

Sta. 31+75 Relocation Verizon handhole in proposed sidewalk. Verizon to relocate.

MCI/Verizon 10 days

Sta. 35+22 to Sta.

35+42

Relocation

MCI/Verizon conduit in conflict with storm sewer and high-capacity inlet MCI/Verizon 2 days

Sta. 38+15 to Sta.

38+34

MCI/Verizon conduit in conflict with storm sewer and high-capacity inlet MCI/Verizon 2 days

Sta. 38+40 to Sta.

39+10

Gas main in conflict with storm catch basin and storm sewer

North Shore Gas

2 days

Sta. 44+10 to Sta.

44+84

MCI/Verizon 2” HDPE facility in conflict with precast concrete box culvert and proposed 6-inch water main. Verizon to relocate.

MCI/Verizon 10 days

Sta. 48+65 Retirement

North Shore Gas facility crossing Willow Road near 48+65 to be abandoned in place. Contractor to coordinate removal as necessary during installation of box culvert.

North Shore Gas

0 days

Sta. 48+00 to Sta.

52+40

Gas main installation in south parkway

North Shore Gas

10 days

Sta. 49+55 Retirement

North Shore Gas facility crossing Willow Road near 49+55 to be abandoned in place. Contractor to coordinate removal as necessary during installation of box culvert.

North Shore Gas

0 days

Sta. 50+78 Retirement

North Shore Gas facility crossing Willow Road near 50+78 to be abandoned in place. Contractor to coordinate removal as necessary during installation of box culvert.

North Shore Gas

0 days

Sta. 51+40 to Sta.

64+50

Relocation Gas main in conflict with storm manhole and storm sewer and installation in north parkway

North Shore Gas

15 days

Sta. 52+28 Retirement North Shore Gas facility crossing Willow Road near Sta. 52+28 to be abandoned in place. Contractor

North Shore Gas

0 days

Project W0QM(228) to coordinate removal as necessary during installation of box culvert.

Sta. 53+64 Retirement

North Shore Gas facility crossing Willow Road near Sta. 53+64 to be abandoned in place. Contractor to coordinate removal as necessary during installation of box culvert.

North Shore Gas

0 days

Sta. 56+00 to Sta.

57+60

Relocation Gas main in conflict with water main North Shore

Gas 4 days

Sta. 56+00 to Sta.

67+00

Relocation MCI/Verizon replacement of existing conduit and conductor in south parkway

MCI/Verizon 20 days

Sta. 56+26 Retirement

North Shore Gas facility crossing Willow Road near 56+26 to be abandoned in place. Contractor to coordinate removal as necessary during installation of box culvert.

North Shore Gas

0 days

Sta. 63+16 Retirement

North Shore Gas facility crossing Willow Road near 63+16 to be abandoned in place. Contractor to coordinate removal as necessary during installation of box culvert.

North Shore Gas

0 days

Sta. 63+32 Retirement

North Shore Gas facility crossing Willow Road near 63+32 to be abandoned in place. Contractor to coordinate removal as necessary during installation of box culvert.

North Shore Gas

0 days

Sta. 63+62 Retirement

North Shore Gas facility crossing Provident Avenue near Sta.

63+62, 22’ LT to be abandoned in place. Contractor to coordinate removal as necessary during installation of box culvert.

North Shore Gas

0 days

Sta. 63+60 to Sta.

64+60

Relocation Gas main in conflict with water main North Shore

Gas 4 days

Stage 2

NO UTILITIES IN CONFLICT

Stage 3

STAGE / LOCATION TYPE DESCRIPTION

RESPONSIBLE

AGENCY

DURATION OF TIME

Sta. 22+10 to Sta.

29+50

Relocation Buried concrete-encased duct package to be relocated

AT&T Distribution 25 days

Sta. 30+35 Curb and

Gutter Adjustment

Bump curb and gutter around existing AT&T manhole Village of Winnetka 1 day

Project W0QM(228)

Stage 4

NO UTILITIES IN CONFLICT

Pre-Stage: 0 Days Total Installation Stage 1/5: 79 Days Total Installation Stage 2: 0 Days Total Installation Stage 3: 26 Days Total Installation Stage 4: 0 Days Total Installation

The following contact information is what was used during the preparation of the plans provided by the Agency/Company responsible for resolution of the conflict.

Agency/Company Responsible to

Resolve Conflict

Name of contact Phone E-mail address

AT&T-Distribution Chris Cass 708-972-8993 cc4361@att.com North Shore Gas Jay Hammer 847-263-4678 jay.hammer@northshoregasdelivery.com

MCI/Verizon Eve Campbell 312-612-5216 ecampbell@telecom-eng.com Comcast Daniel O-Shea 847-561-4220 Daniel_oshea@comcast.com

Metropolitan Water Reclamation District

Paul Sobanski 708.588.4080 WMOJobStart@mwrd.org

Village of Winnetka Water & Electric

24/7 Emergency Line 847.501.2531 nnarhi@winnetka.org

UTILITIES TO BE WATCHED AND PROTECTED

The areas of concern noted below have been identified by following the suggested staging plan included for the contract. The information provided is not a comprehensive list of all remaining utilities, but those which during coordination were identified as ones which might require the Department’s contractor to take into consideration when making the determination of the means and methods that would be required to construct the proposed improvement. In some instances, the contractor will be responsible to notify the owner in advance of the work to take place so necessary staffing on the owner’s part can be secured.

Pre-Stage

STAGE / LOCATION TYPE DESCRIPTION OWNER

Sta. 19+80 Watch and

Protect Existing buried cable is perpendicular to proposed water main installation.

AT&T-TCG

Sta. 30+20 Watch and

Protect Existing buried cable is perpendicular to proposed water main installation.

Comcast

Stage 1 and 5

Sta. 31+50 Watch and

Protect Existing buried cable is perpendicular to proposed 16-inch water main installation.

Comcast

Sta. 34+60 Watch and

Protect Existing conduit is perpendicular to proposed 8-inch water main installation MCI/Verizon

Project W0QM(228)

Sta. 36+25 Watch and

Protect Existing conduit is perpendicular to proposed water service installation

MCI/Verizon

Sta. 36+88 Watch and

Protect Existing conduit is perpendicular to proposed water service installation

MCI/Verizon

Sta. 37+98 Watch and

Protect Existing conduit is perpendicular to proposed 8-inch water main installation MCI/Verizon

Sta. 39+30 Watch and

Protect Existing conduit is perpendicular to proposed storm sewer installation

MCI/Verizon

Sta. 40+20 Watch and

Protect Existing conduit is perpendicular to proposed storm sewer installation

MCI/Verizon

Sta. 45+90 Watch and

Protect Existing buried cable is perpendicular to proposed box culvert installation.

AT&T-Distribution

Sta. 48+15 Watch and

Protect Existing conduit is perpendicular to proposed fire hydrant installation

MCI/Verizon

Sta. 48+22 Watch and

Protect Existing conduit is perpendicular to proposed electrical conduit for light pole MCI/Verizon

Sta. 48+45 Watch and

Protect

Existing conduit is perpendicular to proposed 8-inch water main and valve vault installation MCI/Verizon

Sta. 49+05 Watch and

Protect Proposed gas main is perpendicular to proposed 1.5-inch water service North Shore Gas

Sta. 49+60 Watch and

Protect Proposed gas main is perpendicular to proposed 1.5-inch water service North Shore Gas

Sta. 50+69 Watch and

Protect Proposed gas main is perpendicular to proposed 1.5-inch water service North Shore Gas

Sta. 50+69 Watch and

Protect Existing conduit is perpendicular to proposed water service installation

MCI/Verizon

Sta. 51+63 Watch and

Protect Existing conduit is perpendicular to proposed fire hydrant installation

MCI/Verizon

Sta. 51+65 Watch and

Protect Proposed gas main is perpendicular to proposed 1.5-inch water service North Shore Gas

Sta. 51+82 Watch and

Protect

Existing conduit is approximately perpendicular to proposed electrical conduit for light pole MCI/Verizon

Sta. 52+06 Watch and

Protect Existing conduit is perpendicular to proposed 8-inch water main installation MCI/Verizon

Sta. 52+06 Watch and

Protect Proposed gas main is perpendicular to proposed 8-inch water main North Shore Gas

Sta. 52+13 Watch and

Protect Proposed gas main is perpendicular to proposed 1.5-inch water service North Shore Gas

Sta. 53+57 Watch and

Protect Existing conduit is perpendicular to proposed water service installation

MCI/Verizon

Sta. 55+36 Watch and

Protect Existing conduit is perpendicular to proposed water service installation

MCI/Verizon

Sta. 56+07 Watch and

Protect Existing conduit is perpendicular to proposed 10-inch water main installation MCI/Verizon

Sta. 56+25 Watch and

Protect Existing buried cable is perpendicular to proposed box culvert installation.

AT&T-Distribution

Sta. 56+29 Watch and

Protect

Existing conduit is approximately perpendicular to proposed electrical conduit for light pole MCI/Verizon

Sta. 57+50 to Sta.

57+90

Watch and Protect

Existing buried cable is parallel to proposed storm sewer installation.

Comcast

Project W0QM(228)

Sta. 57+96 Watch and

Protect Proposed gas main is perpendicular to proposed 1.5-inch water service North Shore Gas

Sta. 58+25 Watch and

Protect

Existing buried cable is perpendicular to proposed sanitary service lateral installation.

Comcast

Sta. 58+50 Watch and

Protect

Existing buried cable is perpendicular to proposed sanitary service lateral installation.

Comcast

Sta. 58+75 Watch and

Protect Existing buried cable is perpendicular to proposed water service line installation.

Comcast

Sta. 58+79 Watch and

Protect

Existing gas main is being retired in place and is perpendicular to proposed 1.5-inch water service.

North Shore Gas

Sta. 59+10 Watch and

Protect

Existing buried cable is perpendicular to proposed sanitary service lateral and water service line installation.

Comcast

Sta. 59+19 Watch and

Protect

Existing gas main is being retired in place and is perpendicular to proposed 1.5-inch water service.

North Shore Gas

Sta. 59+70 Watch and

Protect

Existing buried cable is perpendicular to proposed sanitary service lateral and water service line installation.

Comcast

Sta. 59+78 Watch and

Protect

Existing gas main is being retired in place and is perpendicular to proposed 1.5-inch water service.

North Shore Gas

Sta. 60+25 Watch and

Protect

Existing buried cable is perpendicular to proposed sanitary service lateral and water service line installation.

Comcast

Sta. 60+36 Watch and

Protect

Existing gas main is being retired in place and is perpendicular to proposed 1.5-inch water service.

North Shore Gas

Sta. 60+50 Watch and

Protect

Existing buried cable is perpendicular to proposed sanitary service lateral and water service line installation.

Comcast

Sta. 60+70 Watch and

Protect

Existing gas main is being retired in place and is perpendicular to proposed 1.5-inch water service.

North Shore Gas

Sta. 60+75 Watch and

Protect

Existing buried cable is perpendicular to proposed sanitary service lateral and water service line installation.

Comcast

Sta. 61+25 Watch and

Protect

Existing gas main is being retired in place and is perpendicular to proposed 1.5-inch water service.

North Shore Gas

Sta. 61+30 Watch and

Protect

Existing buried cable is perpendicular to proposed sanitary service lateral and water service line installation.

Comcast

Sta. 62+40 Watch and

Protect

Existing buried cable is perpendicular to proposed sanitary service lateral and water service line installation.

Comcast

Sta. 63+60 Watch and

Protect Existing conduit is perpendicular to proposed 8-inch water main installation MCI/Verizon

Sta. 63+75 Watch and

Protect Existing buried cable is perpendicular to proposed water main installation.

AT&T-Distribution

Project W0QM(228)

Sta. 63+85 Watch and

Protect Existing conduit is perpendicular to proposed 16-inch water main installation MCI/Verizon

Sta. 63+86 Watch and

Protect Proposed gas main is perpendicular to proposed 16-inch water main.

North Shore Gas

Sta. 63+90 Watch and

Protect Existing buried cable is perpendicular to proposed water main installation.

Comcast

Sta. 64+00 Watch and

Protect Existing buried cable is perpendicular to proposed water main installation.

Comcast

Sta. 64+05 Watch and

Protect Proposed gas main is perpendicular to proposed 8-inch water main.

North Shore Gas

Stage 2

NO FACILITIES REQUIRE EXTRA CONSIDERATION

Stage 3

Sta. 20+00 Watch and

Protect AT&T’s contractor to support and protect existing 2’x2’ duct package.

AT&T-Distribution

Stage 4

Sta. 200+98 Watch and

Protect

Existing buried 2” HDPE perpendicular to proposed storm sewer installation

AT&T-TCG

The following contact information is what was used during the preparation of the plans as provided by the owner of the facility.

Agency/Company Responsible to

Resolve Conflict

Name of contact Phone E-mail address

AT&T-Distribution Chris Cass 708-972-8993 cc4361@att.com AT&T-TCG Jason Sterenberg 708-240-9085 Jsterenberg@networkconnex.com Comcast Thomas Munar Thomas_Munar@comcast.com

North Shore Gas Jay Hammer 847-263-4678 jay.hammer@northshoregasdelivery.com Verizon Eve Campbell 312-612-5216 ecampbell@telecom-eng.com

The above represents the best information available to the Department and is included for the convenience of the bidder. The days required for conflict resolution should be considered in the bid as this information has also been factored into the timeline identified for the project when setting the completion date. The applicable portions of the Standard Specifications for Road and Bridge Construction shall apply.

Estimated duration of time provided above for the first conflicts identified will begin on the date of the executed contract regardless of the status of the utility relocations. The responsible agencies will be working toward resolving subsequent conflicts in conjunction with contractor activities in the number of days noted.

Project W0QM(228)

The estimated relocation duration must be part of the progress schedule submitted by the contractor. A utility kickoff meeting will be scheduled between the Department, the Department’s contractor, and the utility companies when necessary.

The contractor is responsible for contacting JULIE (or DIGGER within the City of Chicago) prior to any excavation work. Please note that IDOT electrical facilities are not part of the one-call locating services, such as JULIE or DIGGER.

If the contract requires the services of an electrical contractor, it is the contractor’s responsibility, at their own expense, to locate existing IDOT electrical facilities before commencing work. For contracts that do not require an electrical contractor, the contractor may request one free locate of IDOT electrical facilities by contacting the Department’s Electrical Maintenance Contractor. Additional locate requests will be at the contractor’s expense.

The Department’s Electrical Maintenance Contractor must be notified at least 72 hours in advance of the work by calling 773-287-7600 or emailing dispatch@meade100.com to arrange for the locating of underground electrical facilities.

Please note, the marking of underground facilities does not absolve the contractor of their responsibility to repair or replace any facilities damaged during construction at their expense.

PUBLIC CONVENIENCE AND SAFETY (D1)

Effective: May 1, 2012 Revised: July 15, 2012

Add the following to the end of the fourth paragraph of Article 107.09:

“If the holiday is on a Saturday or Sunday, and is legally observed on a Friday or Monday, the length of Holiday Period for Monday or Friday shall apply.”

Add the following sentence after the Holiday Period table in the fourth paragraph of Article 107.09:

“The Length of Holiday Period for Thanksgiving shall be from 5:00 AM the Wednesday prior to 11:59 PM the Sunday After”

Delete the fifth paragraph of Article 107.09 of the Standard Specifications:

“On weekends, excluding holidays, roadways with Average Daily Traffic of 25,000 or greater, all lanes shall be open to traffic from 3:00 P.M. Friday to midnight Sunday except where structure construction or major rehabilitation makes it impractical.”

Project W0QM(228)

EARTH EXCAVATION

202.03 Removal and Disposal of Surplus, Unsuitable, and Organic Materials: Add the following;

The Contractor may seek approval from the Village of Winnetka to dispose of surplus materials related to this contract at the Village’s landfill located at Willow Road. Surplus materials that will be accepted at the landfill include clean, inorganic clay meeting the recommendations of the Engineer. The clean inorganic clay must have a pH value between 6.25 and 9.0, inclusive. The Contractor shall perform the pH testing and provide the results to the Village at no additional cost.

The following materials will not be accepted by the Village at the landfill;

Concrete Restricted-use miscellaneous materials according to Article 1009.04.

Organic material and topsoil.

Sand.

Materials with pH values below 6.25 and above 9.0.

Regulated substances according to Section 669.

All materials, equipment, testing, dust control, and labor needed to dump surplus materials at the landfill will not be paid for separately and shall be included in the cost of EARTH EXCAVATION, REMOVAL AND DISPOSAL OF UNSUITABLE MATERIALS, and STRUCTURE EXCAVATION.

202.04 Classification: Add the following;

Stripping of existing topsoil will be paid for as EARTH EXCAVATION.

All posts, railroad ties, and decorative timber in conflict with the proposed improvements shall be removed and relocated as determined by the Engineer at the time of construction. Every effort shall be made by the Contractor when removing these items to preserve them from harm. Items not relocated shall be properly disposed of by the Contractor. This work shall be included in the cost of EARTH EXCAVATION.

AGGREGATE SURFACE COURSE FOR TEMPORARY ACCESS (D1)

Effective: April 1, 2001 Revised: January 2, 2007

Revise Article 402.10 of the Standard Specifications to read:

“402.10 For Temporary Access. The contractor shall construct and maintain aggregate surface course for temporary access to private CURBs, commercial entrances and roads according to Article 402.07 and as directed by the Engineer.

The aggregate surface course shall be constructed to the dimensions and grades specified below, except as modified by the plans or as directed by the Engineer.

Project W0QM(228)

(a) Private Entrance. The minimum width shall be 12 ft (3.6 m). The minimum compacted thickness shall be 6 in. (150 mm). The maximum grade shall be eight percent, except as required to match the existing grade.

(b) Commercial Entrance. The minimum width shall be 24 ft (7.2 m). The minimum compacted thickness shall be 9 in. (230 mm). The maximum grade shall be six percent, except as required to match the existing grade.

(c) Road. The minimum width shall be 24 ft (7.2 m). The minimum compacted thickness shall be 9 in. (230 mm). The grade and elevation shall be the same as the removed pavement, except as required to meet the grade of any new pavement constructed.

Maintaining the temporary access shall include relocating and/or regrading the aggregate surface coarse for any operation that may disturb or remove the temporary access. The same type and gradation of material used to construct the temporary access shall be used to maintain it.

When use of the temporary access is discontinued, the aggregate shall be removed and utilized in the permanent construction or disposed of according to Article 202.03.”

Add the following to Article 402.12 of the Standard Specifications:

“Aggregate surface course for temporary access will be measured for payment as each for every private entrance, commercial entrance or road constructed for the purpose of temporary access. If a residential drive, commercial entrance, or road is to be constructed under multiple stages, the aggregate needed to construct the second or subsequent stages will not be measured for payment but shall be included in the cost per each of the type specified.”

Revise the second paragraph of Article 402.13 of the Standard Specifications to read:

“Aggregate surface course for temporary access will be paid for at the contract unit price per each for TEMPORARY ACCESS (PRIVATE ENTRANCE), TEMPORARY ACCESS (COMMERCIAL ENTRANCE) or TEMPORARY ACCESS (ROAD).

Partial payment of the each amount bid for temporary access, of the type specified, will be paid according to the following schedule:

(a) Upon construction of the temporary access, sixty percent of the contract unit price per each, of the type constructed, will be paid.

(b) Subject to the approval of the Engineer for the adequate maintenance and removal of the temporary access, the remaining forty percent of the pay item will be paid upon the permanent removal of the temporary access.”

Project W0QM(228)

HOT-MIX ASPHALT BINDER AND SURFACE COURSE (D1)

Effective: November 1, 2019 Revised: April 1, 2026

Add the following to the end of Article 406.06(c) of the Standard Specifications:

“ The amount of HMA binder course placed shall be limited to that which can be surfaced during the same construction season.”

Revise the fifteenth through eighteenth paragraphs of Article 406.14 of the Standard Specifications to read:

“ The mixture used in constructing acceptable HMA test strips will be paid for at the contract unit price. Unacceptable HMA test strips shall be removed and replaced at no additional cost to the Department.”

Revise Article 1004.03(c) to read:

“(c) Gradation. The coarse aggregate gradations shall be as listed in the following table.

Use Size/Application Gradation No.

Class A-1, A-2, & A-3 3/8 in. (10 mm) Seal CA 16 or CA 20 Class A-1 1/2 in. (13 mm) Seal CA 15 Class A-2 & A-3 Cover Coat CA 14

HMA High ESAL

IL-19.0;

Stabilized Subbase IL-19.0

CA 11 1/

SMA 12.5 2/ CA 134/, CA 14, or CA 16 SMA 9.5 2/ CA 133/4/ or CA 163/

IL-9.5 CA 16, CM 134/

IL-9.5FG CA 16

HMA Low ESAL

IL-19.0L CA 11 1/

IL-9.5L CA 16

1/ CA 16 or CA 13 may be blended with the CA 11.

2/ The coarse aggregates used shall be capable of being combined with the fine aggregates and mineral filler to meet the approved mix design and the mix requirements noted herein.

3/ The specified coarse aggregate gradations may be blended.

4/ CA 13 shall be 100 percent passing the 1/2 in. (12.5mm) sieve.”

Revise Article 1004.03(e) of the Standard Specifications to read:

Project W0QM(228)

“(e) Absorption. For SMA the coarse aggregate shall also have water absorption ≤ 2.0 percent.”

Revise the “High ESAL” portion of the table in Article 1030.01 to read:

“High ESAL Binder Courses

IL-19.0, IL-9.5, IL-9.5FG, IL-4.75,

SMA 12.5, SMA 9.5

Stabilized Subbase IL-19.0

Surface Courses

IL-9.5, IL-9.5FG,

SMA 12.5, SMA 9.5”

Revise Note 2. and add Note 6 to Article 1030.02 of the Standard Specifications to read:

“Item Article/Section

(g)Performance Graded Asphalt Binder (Note 6) 1032

(h) Fibers (Note 2)

Note 2. A stabilizing additive such as cellulose or mineral fiber shall be added to the SMA mixture according to Illinois Modified AASHTO M 325. The stabilizing additive shall meet the Fiber Quality Requirements listed in Illinois Modified AASHTO M 325. Prior to approval and use of fibers, the Contractor shall submit a notarized certification by the producer of these materials stating they meet these requirements. Reclaimed Asphalt Shingles (RAS) may be used in Stone Matrix Asphalt (SMA) mixtures designed with an SBA polymer modifier as a fiber additive if the mix design with RAS included meets AASHTO T305 requirements. The RAS shall be from a certified source that produces either Type I or Type 2. Material shall meet requirements noted herein and the actual dosage rate will be determined by the Engineer.

Note 6. The asphalt binder shall be an SBS PG 76-28 when the SMA is used on a full-depth asphalt pavement and SBS PG 76-22 when used as an overlay, except where modified herein. The asphalt binder shall be a SBS PG 76-22 for IL-4.75, except where modified herein..”

Project W0QM(228)

Revise table in Article 1030.05(a) of the Standard Specifications to read:

“MIXTURE COMPOSITION (% PASSING) 1/

Sieve Size

IL-19.0 mm SMA 12.5 SMA 9.5 IL-9.5mm IL-9.5FG IL-4.75 mm min max min max min max min max min max min max

1 1/2 in (37.5 mm)

1 in.

(25 mm) 100

3/4 in.

(19 mm) 90 100 100

1/2 in.

(12.5 mm) 75 89 80 100 100 100 100 100

3/8 in.

(9.5 mm) 65 90 100 90 100 90 100 100

#4 (4.75 mm) 40 60 20 30 36 50 34 69 60 756/ 90 100

#8 (2.36 mm) 20 42 16 24 4/ 16 324/ 34 5/ 52 2/ 45 606/ 70 90

#16 (1.18 mm) 15 30 10 32 25 40 50 65

#30 (600 m) 12 16 12 18 15 30

#50 (300 m) 6 15 4 15 8 15 15 30

#100 (150 m) 4 9 3 10 6 10 10 18

#200 (75 m) 3.0 6.0 7.0 9.0 3/ 7.5 9.5 3/ 4.0 6.0 4.0 6.5 7.0 9.0 3/

#635 (20 m)

≤ 3.0 ≤ 3.0

Ratio Dust/Asphalt Binder

1.0 1.5 1.5 1.0

1.0 1.0

1/ Based on percent of total aggregate weight.

2/ The mixture composition shall not exceed 44 percent passing the #8 (2.36 mm) sieve for surface courses with Ndesign = 90.

3/ Additional minus No. 200 (0.075 mm) material required by the mix design shall be mineral filler, unless otherwise approved by the Engineer.

4/ When establishing the Adjusted Job Mix Formula (AJMF) the percent passing the

#8 (2.36 mm) sieve shall not be adjusted above the percentage stated on the table.

5/ When establishing the Adjusted Job Mix Formula (AJMF) the percent passing the

#8 (2.36 mm) sieve shall not be adjusted below 34 percent.

6/ When the mixture is used as a binder, the maximum shall be increased by 0.5 percent passing.”

Project W0QM(228)

Revise Article 1030.05(b) of the Standard Specifications to read:

(b) Volumetric Requirements. The target value for the air voids of the HMA shall be 4.0 percent, for IL-4.75 and SMA mixtures it shall be 3.5 percent and for Stabilized Subbase it shall be

3.0 percent at the design number of gyrations. The voids in the mineral aggregate (VMA) and voids filled with asphalt binder (VFA) of the HMA design shall be based on the nominal maximum size of the aggregate in the mix and shall conform to the following requirements.

Voids in the Mineral Aggregate (VMA), % Minimum for Ndesign

Mix Design 30 50 70 80 90

IL-19.0 13.5 13.5 13.5

IL-9.5 15.0 15.0

IL-9.5FG 15.0 15.0

IL-4.751/ 18.5

SMA-12.51/2/5/ 17.03//16.04/

SMA-9.51/2/5/ 17.03//16.04/

IL-19.0L 13.5

IL-9.5L 15.0

1/ Maximum draindown shall be 0.3 percent according to Illinois Modified

AASHTO T 305.

2/ The draindown shall be determined at the JMF asphalt binder content at the mixing temperature plus 30°F.

3/ Applies when specific gravity of coarse aggregate is ≥ 2.760.

4/ Applies when specific gravity of coarse aggregate is < 2.760.

5/ For surface course, the coarse aggregate can be crushed steel slag, crystalline crushed stone or crushed sandstone. For binder course, coarse aggregate shall be crushed stone (dolomite), crushed gravel, crystalline crushed stone, or crushed sandstone”

Revise the last paragraph of Article 1102.01 (a) (5) of the Standard Specifications to read:

“IL-4.75 and Stone Matrix Asphalt (SMA) mixtures which contain aggregate having absorptions greater than or equal to 2.0 percent, or which contain steal slag sand, shall have minimum surge bin storage plus haul time of 1.5 hours.”

Revise the first and second paragraphs of Articles 1030.06(c)(2) of the Standard Specifications to read:

Project W0QM(228)

“(2) Personnel. The Contractor shall provide a QC Manager who shall have overall responsibility and authority for quality control. This individual shall maintain active certification as a Hot-Mix Asphalt Level II technician.

In addition to the QC Manager, the Contractor shall provide sufficient personnel to perform the required visual inspections, sampling, testing, and documentation in a timely manner. Mix designs shall be developed by personnel with an active certification as a Hot-Mix Asphalt Level III technician. Technicians performing mix design testing and plant sampling/testing shall maintain active certification as a Hot-Mix Asphalt Level I technician. The Contractor may provide a technician trainee who has successfully completed the Department’s “Hot-Mix Asphalt Trainee Course” to assist in the activities completed by a Hot-Mix Asphalt Level I technician for a period of one year after the course completion date. The Contractor may also provide a Gradation Technician who has successfully completed the Department's "Gradation Technician Course" to run gradation tests only under the supervision of a Hot-Mix Asphalt Level II Technician. The Contractor shall provide a Hot-Mix Asphalt Density Tester who has successfully completed the Department's "Nuclear Density Testing” course to run all nuclear density tests on the job site.”

Add Article 1030.06(d)(3) to the Standard Specifications to read:

“(3) The Contractor shall take possession of any Department unused backup or dispute resolution HMA mixture samples or density specimens upon notification by the Engineer.

The Contractor shall collect the HMA mixture samples or density specimens from the location designated by the Engineer and may add these materials to RAP stockpiles according to Section 1031.”

Revise the second paragraph of Articles 1030.07(a)(11) and 1030.08(a)(9) of the Standard Specifications to read:

“When establishing the target density, the HMA maximum theoretical specific gravity (Gmm) will be based on the running average of four available Department test results for that project. If less than four Gmm test results are available, an average of all available Department test results for that project will be used. The initial Gmm will be the last available Department test result from a QMP project. If there is no available Department test result from a QMP project, the Department mix design verification test result will be used as the initial Gmm.”

Revise the Quality Control Limits table in Article 1030.09(c) to read:

CONTROL LIMITS

Parameter

IL-19.0, IL-9.5,

IL-9.5FG, IL-19.0L,

IL-9.5L

SMA-12.5,

SMA-9.5

IL-4.75

Individual Test

Moving Avg. of 4

Individual Test

Moving Avg. of 4

Individual Test

Moving Avg. of 4

% Passing: 1/ 1/2 in. (12.5 mm) ± 6 % ± 4 % ± 6 % ± 4 %

Project W0QM(228)

3/8 in. (9.5mm) ± 4 % ± 3 % # 4 (4.75 mm) ± 5 % ± 4 % ± 5 % ± 4 % # 8 (2.36 mm) ± 5 % ± 3 % ± 4 % ± 2 % # 16 (1.18 mm) ± 4 % ± 2 % ± 4 % ± 3 % # 30 (600 µm) ± 4 % ± 2.5 % ± 4 % ± 2.5 % Total Dust Content # 200 (75 µm) ± 1.5 % ± 1.0 % ± 1.5 % ± 1.0 %

Asphalt Binder Content

± 0.3 % ± 0.2 % ± 0.2 % ± 0.1 % ± 0.3 % ± 0.2 %

Air Voids 2/ ± 1.2 % ± 1.0 % ± 1.2 % ± 1.0 % ± 1.2 % ± 1.0 %

Field VMA 3/ -0.7 % -0.5 % -0.7 % -0.5 % -0.7 % -0.5 %

1/ Based on washed ignition oven or solvent extraction gradation.

2/ The air voids target shall be 3.2 to 4.8 percent.

3/ Allowable limit below minimum design VMA requirement.

Revise Article 1030.09(g)(1) of the Supplemental Specifications with the following:

“(1) The…