_IFB No. 403 - Addendum 2.pdf
PDF 7 MB Posted
- Solicitation number
- 34597
- Issued by
- Charlottesville City, Virginia
About this file
This document is an Addendum for IFB No. 403 - Red Hill Water Treatment Plant Upgrades, issued by the Rivanna Sewer & Water Authority in Albemarle County, Virginia. The Addendum provides changes to the project specifications, including the addition of a hydropneumatic tank inspection report and requirements related to the tank's coating work. It also includes changes to the drawings and requirements for acknowledging receipt of the Addendum. The project involves building construction, process piping, electrical, and mechanical work for the upgrades to the Red Hill Water Treatment Plant.
The Addendum outlines the inspection report for the 10,000-gallon hydropneumatic tank, which was found to be in generally good condition with some minor coating deterioration. The report provides recommendations for maintenance, cleaning, and recoating the tank in the future. The Addendum also specifies that the Owner will coordinate and pay for a coatings inspection to determine the extent of coatings work required, and the Contractor will be responsible for temporary bypassing and cleaning of the tank prior to the inspection.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IFB No. 403 - Red HIll WTP Upgrades - Bid Specs.pdf | ||
| _Addendum 1.pdf | ||
| IFB No. 403 - Red Hill WTP Upgrades - Bid Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum
RIVAN 168434 00 00 12 - 1
DOCUMENT 00 00 12
ADDENDUM NO. 2
December 15, 2023
Red Hill Water Treatment Plant - Upgrades
IFB No. 403 Rivanna Sewer & Water Authority
Albemarle County, Virginia
SEH No. RIVAN 168434
From: Short Elliott Hendrickson Inc.
615 9th Street North Virginia, MN 55792-3761 218.741.4284
To: Document Holders
DOCUMENT HOLDERS on the above-named project are hereby notified that this document shall be appended to, take precedence over and become part of the original bidding documents dated September 28, 2023, and previous addenda dated November 21, 2023, for this work. Bids submitted for the construction of this work shall conform to this document.
This addendum consists of 2 pages and attached Document 01 11 00b Dixon Engineering Inspection Report (30 pages).
Changes to Specifications:
1. Section 01 11 00 Summary of Work, ADD the following immediately after Article 1.24:
1.25 HYDROPNEUMATIC TANK INSPECTION REPORT
A. The hydropneumatic tank inspection used by the Engineer in the preparation of the Bidding Documents are attached to this document.
B. This report is provided as a reference document ONLY and not to be considered for use in development of pricing for the Work.
C. Owner will coordinate and pay for a coatings inspection of the existing hydropneumatic tank at the Red Hill WTP. Contractor is responsible for temporary bypassing and cleaning of the tank prior to inspection and any coatings work. The results of the coatings inspection will be used to determine the extent of the coatings to be applied to the hydropneumatic tank.
2. Section 01 11 00b Inspection Report, ADD new attachment as stated below:
Report dated September 1, 2017, consisting of 30 pages, prepared by Dixon Engineering, Inc., titled:
Preliminary Maintenance Inspection 10,000 Gallon Hydropneumatic Tank (Red Hill)
3. Section 01 12 16 Work Sequence, Article 3.01.K, DELETE subparagraph 1 and REPLACE with the following:
1. Owner will coordinate and pay for an inspection of the existing hydropneumatic tank.
4. Section 09 97 20 Coatings Systems for Industrial Facilities, Article 1.01, ADD the following immediately after subparagraph A:
B Hydropneumatic tank coatings work
1. Owner will coordinate and pay for a coatings inspection of the existing hydropneumatic tank at the Red Hill WTP. The results of the coatings inspection will be used to determine the extent of
Addendum
00 00 12 - 2 RIVAN 168434
the coatings to be applied to the hydropneumatic tank. The most recent inspection report is included following Section 01 11 00.
2. Contractor shall be permitted to use accelerators, as recommended by the coatings Manufacturer and approved by Owner/Engineer, to decrease the required cure time and minimize the duration the temporary hydropneumatic tank is required to be onsite.
3. Basis of Payment:
a. All exterior surface preparation coating work for the hydropneumatic tank, coatings system H2, shall be included in the Part A lump sum bid amount.
b. The interior surface preparation and coatings work for the hydropneumatic tank, coatings system H1, shall be included in the Part B Hydropnematic Tank – Select Interior Coatings as a unit price bid item. Assumptions have been made by the Engineer on quantity of spot-repair coatings work extents based upon the most recent inspection and good judgement.
The final locations and extents of the interior coatings work will be determined as part of the hydropneumatic tank inspection process.
5. Section 09 97 20 Coatings Systems for Industrial Facilities, Article 3.09, Coatings Schedule, System Number H2, ADD the following immediately after the Notes text.
Coatings manufacturer shall provide approval of tie coat. Contractor shall perform a 24” x 24” minimum test patch of first coat to verify adhesion of coatings to existing.
Changes to Drawings:
6. Drawing No. P101 Building Plan, Keynote 33, Change “09 97 21” to “09 97 20”.
Note: Receipt of this Addendum No. 2, dated December 15, 2023 shall be acknowledged on Page 00 41 00-2 of the submitted Bid Form. Failure to do so may subject Bidder to disqualification.
END OF ADDENDUM
Dixon
Engineering, Inc.
Preliminary Maintenance Inspection
10,000 Gallon Hydropnuematic Tank
(Red Hill)
Albemarle County Service Authority
Charlottesville, Virginia
Inspection Performed: July 18, 2017 Report Prepared: September 1, 2017
Reviewed by Ira M. Gabin, P.E.: September 6, 2017
Dixon Engineering Inc.
815 W. Liberty St. , Suite 1, Medina, OH 44256
Phone (330) 983-0062
Fax (330) 725-0512 http://www.dixonengineering.net ohio@dixonengineering.net
CONCLUSIONS:
1. The exterior coating outside the building is a urethane system that is in good condition overall. The coating is slightly faded and there are no significant coating failures.
2. The exterior coating inside the building is a urethane system that is in good condition overall. The coating has good gloss retention and there are no significant coating failures.
3. The wet interior coating is a multi coat epoxy system that is in good condition overall.
Below the high water line, the coating has minor delamination on the bottom and sidewall. Above the high water line, the coating is deteriorating in the form of rust bleedthrough in a few areas on the roof and endcaps.
RECOMMENDATIONS:
1. Schedule regular cleanings and inspections of the tank by an independent third party as recommended by AWWA, or once every five years.
2. Complete the recommended work pending the revised condition assessment after the next 5-year inspection. The coating work is the greatest cost and largest part of the recommendations. The repairs and upgrades should be completed during the next major tank rehabilitation process when coating work is completed.
3. Budget for exterior overcoating in seven years, or when aesthetics dictate. At that time, the coating would be entering the typical recoat window for modern urethane systems.
The estimated cost is $10,000.
4. Coat the foundation to help prevent deterioration. Cost would be incidental to exterior coating.
5. Recaulk between the tank and building on the exterior. Cost would be incidental to exterior coating or could be done by in-house personnel.
COST SUMMARY:
Exterior Overcoat $10,000 Engineering and Contingencies $6,000 Total $16,000
Note: Better prices will be obtained if work is combined with another larger coating project.
INSPECTION:
On July 18, 2017, Dixon Engineering, Inc., performed a preliminary maintenance inspection on the 10,000 gallon hydropneumatic water storage tank (Red Hill) owned by the Albemarle County Service Authority, in North Gordon, Virginia. Purposes of the inspection were to evaluate the interior and exterior coating’s performance and life expectancy; assess the condition of metal surfaces and appurtenances; review safety and health aspects; and make budgetary recommendations for continued maintenance of the tank. All recommendations, with budgeting estimates for repairs are incorporated in this report. The inspection was performed by Kyle Lay, Staff Technician. The inspector was assisted by Larry Houck, Staff Technician. Scheduling and arrangements for the inspection were completed through Jeremy Lynn. A source of water for cleaning was provided by the County. Following the inspection, chlorine was added to disinfect the tank per AWWA Standard C652-11 method No. 3.
The tank was built in 2009 by RECO USA. The tank is installed horizontally with a diameter of 8 feet and a length of 28 feet. The exterior and wet interior coatings are original.
CONDITIONS and RECOMMENDATIONS:
EXTERIOR COATING CONDITIONS:
An exterior coating sample was taken and tested; the coating is a urethane system. The bottom, sidewall, and roof coating is in good condition with no significant coating failures.
The interior coating system is the same as the coating outside of the building. The end cap coating is in good condition with no significant coating failures.
EXTERIOR COATING RECOMMENDATIONS:
Take no immediate action on the exterior coating. Budget for overcoating in 7 years. At that time, the coating will be entering the typical recoat window for modern urethane systems. Perform a maintenance inspection in five years to update the recoating times and costs. Current adhesion showed the existing coating would support an additional recoat. The estimated cost to recoat with a urethane system is $10,000.
WET INTERIOR COATING CONDITIONS:
The bottom and sidewall coating is in good condition with deterioration in the form of delaminated topcoat and cracking.
The roof and end cap coating is in good condition with deterioration in the form of rust bleedthrough in a few areas. Minor failures are also present on weld seams and penetrations.
The bottom was covered with approximately ½ inch of sediment that was flushed from the interior.
The equator area was covered with moderate mineral staining which does not affect the integrity of the coating system.
Overall adhesion of the coating is good. Adhesion was tested using a low pressure power washer. With poor adhesion, it would be possible to notice the coating fluctuate and loose coating could be completely removed during cleaning. This is a crude form of testing, yet the least destructive. A destructive test involves cutting the coating to the substrate; the test area is then susceptible to corrosion.
WET INTERIOR COATING RECOMMENDATIONS:
The existing coating system has not deteriorated to the point where replacement is warranted. Reinspect in five years to update conditions and recommendations.
Long term budget to repaint in 10 years. The estimated cost is $25,000.
PIPING CONDITIONS:
There is piping located inside the control building that enters into the tank. The piping is in good condition. The piping is not coated and the pipes have minor surface rust.
PIPING RECOMMENDATIONS:
When the interior is repainted, abrasive blast clean the piping to a commercial (SSPC- SP6) condition and apply an epoxy system. The estimated cost is $3,000.
SITE CONDITIONS:
The size of the tank site is small and is fenced. There are woods surrounding the tank site.
There is adequate room for the staging of contractor’s equipment outside the fenced area.
FOUNDATION CONDITIONS:
The exposed saddle foundations are in good condition and showed no signs of deterioration. The exposed foundation is not coated.
FOUNDATION RECOMMENDATIONS:
Pressure wash and coat the exposed concrete with an epoxy coating system to help prevent deterioration. The cost would be incidental to exterior coating.
CAULK CONDITIONS:
The caulk between the tank and building is in good condition with approximately three total lineal feet missing on the top side.
CAULK RECOMMENDATIONS:
Repair the caulk by removing all dried and cracked caulk and fill missing areas with new caulking. Cost would be incidental to exterior coating or could be done by in-house personnel.
MANWAY CONDITIONS:
There is a 24 inch diameter bolted manway located in the end cap outside of the building that is in good condition. There were no signs of leakage.
PENETRATIONS AND CONTROL CONDITIONS:
The end cap has penetrations for the fill pipe, air lines, sight glasses, and pressure relief valve. There are seven total penetrations in the tank. The penetrations are in good condition.
An 8 inch fill line enters the east end cap inside of the building and stubs just inside of the tank. The pipe is in good condition.
An 8 inch draw line enters the east end cap inside of the building and routes across the bottom to within 5 feet of the west end cap. The pipe is in good condition.
There is a 2 inch drain line in the bottom of the tank. The drain line is in good condition.
WET INTERIOR METAL CONDITIONS:
The steel structure is in good condition above the high water line and in good condition below it. No significant steel loss was absent at the coating failures.
STEEL TANK INSPECTION REPORT
HYDROPNEUMATIC TANK
DATE: July 18, 2017
OWNER: Albemarle County Service
CLIENT CODE: 46-02-66-02
TANK NAME: Red Hill LOCATION: Street: 2885 Monacan Trail Rd.
City: North Garden State: Virginia
TANK SIZE: Capacity: 10,000 gallons Diameter: 8 feet (measured) Length: 28 feet (measured)
CONSTRUCTION: Welded Tank inside building: Part in part out Tank underground: No Amount of tank exposed: Entire tank
DATE CONSTRUCTED: 2009
MANUFACTURER: RECO USA
CONTRACT NUMBER: U-13596
MAX PRESSURE: 125 psi (from nameplate) at 250 oF; 125 psi (from nameplate) at -20oF
COATING
HISTORY EXTERIOR WET INTERIOR
DATE LAST
COATED 2009 2009
CONTRACTOR Reco Reco
COATING
SYSTEM
Presumed urethane Presumed epoxy
SURFACE
PREPARATION SSPC-SP6 SSPC-SP10
COATING
MANUFACTURER Unknown Unknown
HEAVY METAL
COATING SAMPLES No No
HEAVY METAL
BEARING No No
PERSONNEL: Inspector Kyle Lay, Ground person Larry Houck TYPE OF INSPECTION: Preliminary Maintenance METHOD OF INSPECTION: Dry DATE LAST INSPECTED: Unknown
SITE CONDITIONS
Fenced: Yes Control building: Yes Neighborhood: Woods Site drainage: Away from tank Indications of underground leakage: No Shrub, tree, etc. encroachment: No Site Comments: Propane tank approximately 12 feet south; fence approximately 6 feet west
EXPOSED PIPING:
Door condition: Good Locked: Yes
Describe coating: Not coated Condition of metal: Good
FOUNDATION
Foundation exposed: Yes Height exposed: 14-24 inches Type of foundation: Saddles Foundation construction: Metal on concrete Undermining of foundation: No Exposed foundation condition: Good Damage or deterioration: No Foundation coated: No Type of baseplate gap filler: None Indications of foundation settlement: No Foundation comments: Gasket present between tank and saddle but not between saddle and concrete
EXTERIOR COATING
Tank bottom (1/3):
Topcoat condition: Good Primer condition: Good Describe coating: No significant coating deterioration
Mildew growth: Yes Dry film thickness: 5-8 mils Coating adhesion: Wet Metal condition: Good
Inside building tank bottom(1/3):
Topcoat condition: Good Primer condition: Good Describe coating: No significant coating deterioration Mildew growth: No Dry film thickness: 6-9 mils Coating adhesion: Not taken
Tank Sidewall (1/3):
Primer condition: Good Describe coating: No significant coating deterioration Mildew growth: Yes Dry film thickness: 7-10 mils
Inside building tank sidewall (1/3):
Primer condition: Good Describe coating: No significant coating deterioration Mildew growth: No Dry film thickness: 7-10 mils
Tank Roof Top (1/3):
Primer condition: Good Describe coating: No significant coating deterioration Mildew growth: Yes Dry film thickness: 7-10 mils
Roof comments: Caulking pulling away on top ⅓ between tank and building
Inside building tank roof top (1/3):
Primer condition: Good Describe coating: No significant coating deterioration Mildew growth: No Dry film thickness: 7-10 mils
End caps:
Primer condition: Good Describe coating: No significant coating deterioration Mildew growth: No Dry film thickness: 7-9 mils
Inside the building end caps:
Primer condition: Good Describe coating: No significant coating deterioration Mildew growth: No Dry film thickness: 7-9 mils Coating adhesion: Not taken Metal condition: Good End cap comments: Two 8 inch fill/draw; two sight glass; one plug in center; one pressure relief; one pressure gauge
EXTERIOR APPURTENANCES
Anchor bolts:
Number of bolts: 4 per saddle; 12 total Diameter: 1 inch
Anchor bolt chairs: No Coating condition: Good
Anchor bolt comments: Anchor bolts are stacked up in pairs
EXTERIOR APPURTENANCES
Wet interior access:
Location: In end cap Coating condition: Good Dimensions: 24 inch diameter
Comments: West end cap with bolted style hatch
WET INTERIOR COATING
Tank bottom (1/3):
Topcoat condition: Good Primer coating condition: Good Describe coating: Delaminating Mineral deposits: Light Metal condition: Good Active pitting: No Previous pitting: No Depth of sediment: ¼-½ inches Bottom comments: 25-50 spots of topcoat delamination
Sidewall (1/3):
Primer coating condition: Good Describe coating: Rust undrcutting Mineral deposits: Light Metal condition: Good Active pitting: No Previous pitting: No Sidewall comments: Weld seam nearest building (not end cap) has moderate rust undercutting around 40%; another 30% of connection has hairline cracking in the coating; the metal appears to be solid in those locations
Roof Top (1/3):
Primer coating condition: Good Describe coating: Rust bleedthrough Mineral deposits: Light
Active pitting: No
WET INTERIOR COATING
Previous pitting: No Roof comments: Bleedthrough around the roof penetration
End caps:
Primer coating condition: Good Describe coating: Rust undercutting and rust bleedthrough Mineral deposits: Light Metal condition: Good Active pitting: No Previous pitting: No End caps comments: Some hairline coating cracks between sidewall and endcap connection with minor rust undercutting
WET INTERIOR APPURTENANCES
Baffle Wall:
N/A
Draw Line:
Diameter: 8 inches Coating condition: Good Metal condition: Good Comments: Routes across floor and discharges approximately 5 feet 6 inches from western end cap
Fill Line:
Diameter: 8 inches Comments: Stubs at end cap
Troughs:
N/A
Drain Line:
Size: 2 inches Metal condition: Good Comments: Stubs out floor on western end of tank with ball valve to open and close
WET INTERIOR APPURTENANCES
Tank penetrations (other than those noted above):
Number: Three on roof; one bolted 1 ½ inch diameter with large cap and two 2 inch plugged Function: Future use Coating condition: Good
Field Inspection Report is prepared from the contractor’s viewpoint. It contains information the contractor needs to prepare his bid for any repair or recoating. The engineer uses it to prepare the engineering report. Cost estimates are more accurate if the contractor’s problems can be anticipated. While prepared from the contractor’s viewpoint, the only intended beneficiary is the owner. These reports are completed with diligence, but the accuracy is not guaranteed. The contractor is still advised to visit the site.
10,000 gallon hydropneumatic tank (Red Hill ) owned by
Albemarle County Service Authority, Virginia
1) Coating on bottom of the tank is in good condition.
2) Same.
3) Same.
4) The sidewall coating is in good condition.
5) Same.
6) Same.
7) The coating on roof is in good condition.
8) Same.
9) Original lifting lugs remain.
10) Concrete foundation and steel saddles are in good condition.
11) Same.
12) Same.
13) The coating on the exterior end cap is in good condition.
14) Interior end cap coating is in good condition.
15) Manway to wet interior on exterior endcap.
16) Caulking between the building and the tank is missing on the top.
17) Piping inside of building is not coated and has some minor surface rust.
18) Drain line discharges to a concrete splash pad.
19) View of the wet interior.
20) Bottom of tank was covered with sediment.
21) Interior of tank was power washed and cleaned.
22) The sidewall coating is in good condition with mineral staining at the equator.
23) Same.
24) Minor topcoat delamination on the sidewall.
25) The roof coating is in good condition overall with coating failures on roof couplings.
26) Minor rust bleedthrough on the roof.
27) Minor rusting at the roof weld seam.
28) The roof coating is in good condition with minor cracking of coating at the weld seams.
29) Same.
30) Same.
31) Draw line routed across the floor.
32) Fill line stubs just inside of the tank.
33) Drain in the bottom of the tank.
34) Coating on endcap is in good condition with minor rust bleedthrough.
35) View of rust bleedthrough and couplings in the end cap.
| Section 01 11 00b - 2017_Inspection_Report_with_temp_tank_photos.pdf |
| 2017 Tank inspection Report |
| Ablemarle Co. (Red Hill) Cover Page.pdf |
| Albemarle Cnty. 10MG Hydro Red Hill Report |
| Ablemarle Co. (Red Hill) FIR |
| photo album |
| 1-TemporaryTank |
| 2-TemporaryTankConnections_Exterior |
| 3-TemporaryTankConnections_Interior |
File details come from the government source that posted it. Updated .