_Addendum 1.pdf
PDF 6 MB Posted
- Solicitation number
- 34597
- Issued by
- Charlottesville City, Virginia
About this file
This document is an Addendum to an Invitation for Bids (IFB) issued by the Rivanna Water and Sewer Authority for the Red Hill Water Treatment Plant - Upgrades project in Albemarle County, Virginia. The project includes building construction, process piping, electrical, and mechanical work. Key details include:
The Bid opening date has been changed to December 21, 2023 at 10:00 a.m. The addendum includes revisions to specifications, drawings, and other contract documents. Specification changes include updates to Section 32 31 13 Chain Link Fences and Gates, Section 40 23 30 Valves and Accessories, and Section 43 23 00 Centrifugal Pumps. Drawing revisions are provided for the Site Plan, Civil Details, Foundation Plan, Power Plan, Domestic Water/Gas/Sanitary Floor Plans, Plumbing Details/Schedules, and Plumbing Riser Diagrams. A pre-bid meeting was held on October 26, 2023 and the sign-in sheet and pre-bid presentation are attached.
The contract will be awarded to the lowest responsive and responsible bidder. No specific pricing terms, set asides, or incumbent contractor details are provided. Funding for the project is from the Rivanna Water and Sewer Authority, though the specific funding source and amount are not disclosed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum
RIVAN 168434 00 00 11 - 1
DOCUMENT 00 00 11
ADDENDUM NO. 1
November 21, 2023
Red Hill Water Treatment Plant - Upgrades
IFB No. 403 Rivanna Sewer & Water Authority
Albemarle County, Virginia
SEH No. RIVAN 168434
From: Short Elliott Hendrickson Inc.
615 9th Street North Virginia, MN 55792-3761 218.741.4284
To: Document Holders
DOCUMENT HOLDERS on the above-named project are hereby notified that this document shall be appended to, take precedence over and become part of the original bidding documents dated September 28, 2023, for this work. Bids submitted for the construction of this work shall conform to this document.
This addendum consists of 3 pages and attached Pre-Bid PowerPoint Presentation (12 pages), Pre-bid Sing-in Sheet (1 page), Construction Form RA-1 Invitation for Bids (1 page), Section 32 31 13 - Chain Link Fences and Gates, Section 40 23 30 Valves and Accessories, and 43 23 00 Centrifugal Pumps, Drawings C03 Site Plan, C04 Civil Details, S110 Foundation Plan, E201 Power Plan, M201 - Domestic Water, Gas, and Sanitary Floor Plans, M401 - Plumbing Details and Schedules, M501 - Plumbing Riser Diagrams, P070 Removals Plan, P101 Building Plan, and P501 Chemical Feed Systems.
Note: Bid opening has been changed to December 21, 2023 at 10:00 a.m.
Pre-Bid Conference
1. A pre-bid meeting was held on October 26, 2023. The sign-in sheet for the conference is attached. The comments or questions from the conference, where applicable are addressed in this addendum.
2. A photo presentation was shared during the pre-bid conference. This photo presentation is attached.
Changes to Bidding Requirements:
3. Construction Form RA-1 Invitation for Bids, DELETE in its entirety and REPLACE with attached new Form
RA-1.
Bid opening has been changed to December 21, 2023 at 10:00 a.m.
Changes to Specifications:
4. Section 32 31 13 Chain Link Fences and Gates, ADD new section in its entirety.
5. Section 40 23 10 Process Water and Waste Piping, 2.09, DELETE in its entirety.
6. Section 40 23 30 Valves and Accessories, replace in its entirety with the attached Revised Section 40 23 30 Valves and Accessories.
7. Section 40 90 00 Control System Functional Descriptions, 1.03.A, ADD the following lines to the end of the table:
FS-WT-1 – Waste Storage Tank High Level Add Alarm on SCADA PT-GAC-1 – GAC Filter Differential High Alarm Add Alarm on SCADA
00 00 11 - 2 RIVAN 168434
8. Section 46 61 21 Granular Activated Carbon Pressure Filters, 2.01.B, DELETE the table in its entirety and replace with the following:
Criteria Observatory WTP Design Flow per GAC Contactor 23 gallons per minute Number of GAC Contactors 1 Design Empty Bed Contact Time (EBCT) at Design Flowrate 21 minutes Total Vessel Volume 105ft^3 Total GAC Capacity 73ft^3 Total vessel height 96-3/8” Side shell height 60” Pressure Vessel Diameter 56” Maximum Pressure Drop across Vessel System including face piping at the design flowrate 8 psi
Minimum Water Temperature 33 degrees F Maximum Water Temperature 83 degrees F
9. Section 43 23 00 Process Valves and Accessories, replace in its entirety with the attached Revised Section 43 23 00 Process Valves and Accessories.
10. Section 46 61 21 Granular Activated Carbon Pressure Filters, 2.02.O:FLOW METERS
O. Flow Meters 1: GAC Effluent Flow Meter
a. Quantity: 1
b. Size: 4”
c. Manufacturer: Krohne Optiflux 2100
d. Connection Type: Flanged
e. Provide wall mounted transmitter and connect to plant PLC
f. Electrical Equipment Tag No.: FM-RW/FE-RW
2. GAC Backwash Supply Flow Meter
a. Quantity: 1
b. Size: 4”
c. Manufacturer: Krohne Optiflux 2100
d. Connection Type: Flanged
e. Provide wall mounted transmitter and connect to plant PLC
f. Electrical Equipment Tag No.: FM-BW/FE-BW
Changes to Drawings:
11. Drawing C03 Site Plan, DELETE in its entirety and REPLACE with attached new Drawing No. C03.
12. Drawing C04 Civil Details, DELETE in its entirety and REPLACE with attached new Drawing No. C04.
13. Drawing C05 Civil Details, Detail 1/C05, DELETE 24’-0”.
14. Drawing S110 Foundation Plan, DELETE in its entirety and REPLACE with attached new Drawing No. S110.
15. Drawing E201 Power Plan, DELETE in its entirety and REPLACE with attached new Drawing No. E201 Power Plan
16. Drawing M101 Mechanical HVAC and Roof Plans, Detail 2/M101, Add the following item to the Notes list:
5. Detail applies to generator pad, propane tank pad, and HP-1.
17. Drawing M201 - Domestic Water, Gas, and Sanitary Floor Plans, DELETE in its entirety and REPLACE with attached new Drawing No. M201 - Domestic Water, Gas, and Sanitary Floor Plans.
18. Drawing M401 - Plumbing Details and Schedules, DELETE in its entirety and REPLACE with attached new Drawing No. M401 - Plumbing Details and Schedules.
RIVAN 168434 00 00 11 - 3
19. Drawing M501 - Plumbing Riser Diagrams, DELETE in its entirety and REPLACE with attached new Drawing No. M501 - Plumbing Riser Diagrams.
20. Drawing P070 Removals Plan, DELETE in its entirety and REPLACE with attached new Drawing No. P070.
21. Drawing P101 Building Plan, DELETE in its entirety and REPLACE with attached new Drawing No. P101.
22. Drawing P501 Chemical Feed Systems, DELETE in its entirety and REPLACE with attached new Drawing No. P501.
Note: Receipt of this Addendum No. 1, dated November 21, 2023 shall be acknowledged on Page 00 41 00-2 of the submitted Bid Form. Failure to do so may subject Bidder to disqualification.
END OF ADDENDUM
IFB No. 403
Pre Bid Meeting Photo Presentation
Rivanna Water & Sewer Authority
Red Hill Water Treatment Plant Upgrades
Project Location
Building a Better World for All of Us®
Project Location:
2885 Monacan Trail Road
Project Location
Project Location:
110 Lambs Ln
Charlottesville, VA 22901
Project Location:
Red Hill WTP
Exterior – North Side
Exterior – South Side
Exterior – West Side
Exterior – North and East Sides
Exterior – Ex. Gate
Interior – North Wall
Interior – East Wall
Interior – South Wall
Interior – West Wall
PREBID CONFERENCE SIGN-IN
Albemarle County, VA
Rivanna Water & Sewer Authority IFB No. 403
SEH Project No. 168434 10:00 AM October 26, 2023
No. Name Affiliation 1 Brad Weiss SEH 2 Santino Granato RWSA 3 Scott Schiller RWSA 4 John Thornton MEB 5 Blake Begley Morgan Contracting 6 Matt Harrison Sherwood Logan 7 Jason Tucker Rudy L Hawkins Electrical
Form RA-1: Invitation for Bid – Updated per Addendum No. 1
INVITATION FOR BIDS
(Construction Form RA-1)
Rivanna Water and Sewer Authority Rivanna Solid Waste Authority Charlottesville, VA
Charlottesville, Virginia
IFB NO: 403
Due Date for Bids: December 21, 2023 at 10:00AM
Short Elliot Hendrickson Inc.
400 Locust Avenue, Suite 2 Charlottesville, VA 22902
DATE: September 28, 2023
Added Per Addendum No. 1 Chain Link Fences and Gates
RIVAN 168434 32 31 13 - 1
SECTION 32 31 13
CHAIN LINK FENCES AND GATES
PART 1 GENERAL
1.01 SUMMARY
A. Furnish and install steel fencing, posts, gates, etc., where shown on the Drawings and in compliance with these Specifications.
B. Fencing shall be of the chain link type topped with barbed wire.
C. Related Sections:
1. Section 03 30 00 - Cast-in-Place Concrete
2. Section 31 22 10 - Site Grading
1.02 MATERIALS AND CONSTRUCTION
A. Fencing shall be of the chain link type topped with barbed wire.
B. The fabric shall clear the final grade by 3 inches, and shall be topped with three strands of barbed wire.
C. The barbed wire shall be angled outward at the top.
D. All components which are to be galvanized shall be hot dipped galvanized, coating to be 1.8 ounces per square foot of surface.
E. Alternate coatings which employ a zinc coating of less than 1.8 ounces per square foot are not acceptable.
F. Fencing shall be PVC coated: Black.
G. Fence posts, rails and all fixtures and appurtenances shall be black.
H. Swing gate.
I. Fence accessories.
1.03 REFERENCES
A. Without limiting the generality of the other requirements of the Specifications, all work herein shall conform to the applicable requirements of the following documents. All referenced Specifications, codes, and standards refer to the most current issue available at the time of Bid.
B. ASTM:
1. A121 - Metallic Coated Carbon Steel Barbed Wire
2. A123 - Hot Dip Galvanized Coatings on Iron and Steel Products
3. A153 - Hot Dip Zinc Coating on Iron and Steel Hardware
4. A181 - Carbon Steel Forgings for Piping
5. A390 - Hot Dip Galvanized Steel Poultry Fence Fabric
6. A491 - Aluminum-Coated Steel Chain Link Fence Fabric
7. A780 - Repair of Damaged and Uncoated Areas of Hot Dip Galvanized Coatings
8. A817 - Metallic Coated Steel Wire for Chain Link Fence Fabric
9. A824 - Metallic Coated Steel Tension Wire for Chain Link Fence
10. C33 - Concrete Aggregates
Chain Link Fences and Gates Added per Addendum No. 1
32 31 13 - 2 RIVAN 168434
11. C150 - Portland Cement
12. F567 - Installation of Chain Link Fence
13. F626 - Fence Fittings
14. F668 - PVC Coated Steel Chain Link Fence Fabric
15. F900 - Industrial Swing Gates
16. F1043 - Strength and Protective Coatings on Chain Link Fence Framework
17. F1083 - Pipe, Steel, Hot-Dipped Galvanized Welded for Fence Structures
18. F1184 - Industrial and Commercial Horizontal Slide Gates
1.04 SUBMITTALS
A. Product Data: Submit manufacturer’s technical data, finishes, dimensions of individual components and profiles, and installation instructions for fencing, fabric, gates, and accessories.
B. Shop Drawings:
1. Show locations of fences, roller gates and swing gates, posts, rails, tension wires, details of extended posts, extension arms, gate swing, hardware, and accessories.
2. Indicate materials, dimensions, sizes, weights, and finishes of components.
3. Include plans, gate elevations, sections, details of post anchorage, attachment, bracing, and other required installation and operational clearances.
C. Samples: 6-inch length of fabric wire for verification and selection of PVC color.
D. Product Certificates: For each type of chain-link fence and gate, signed by product manufacturer.
E. Testing: Strength test results for framing per ASTM F1043.
1.05 QUALITY ASSURANCE
A. Provide chain link fences, gates as complete units by single source including necessary erection accessories, fittings, and fastenings.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering galvanize steel fencing and fabric which may be incorporated in Work include:
1. Allied Tube and Conduit Corporation
2. American Fence Corporation
3. Ameristar Fence Products
4. Anchor Fence, Inc.
5. Cyclone Fence/United States Steel Corporation
6. Merchants Metals, Inc. www.merchantsmetals.com
7. Tymetal www.tymetal.com
8. Manufacturer of comparable products submitted in compliance with Section 01 25 13.
2.02 CHAIN LINK FABRIC
A. Fabric shall be 6 gauge aluminum coated core wire galvanized conforming to ASTM A641.
B. Fabric shall be woven after PVC coating of black color.
C. Top selvage shall have a twisted, barbed finish.
D. Bottom selvage shall have upturned, or returned, finish.
E. Minimum weight of coating shall be 0.40 ounce per square foot of wire surface.
http://www.merchantsmetals.com/ http://www.tymetal.com/
RIVAN 168434 32 31 13 - 3
F. The coated wire shall have a minimum tensile strength of 80,000 lbs. per square inch.
G. Install fabric at ground level.
H. Fence shall be stretched tight and securely fastened to posts at points spaced no greater than 12 inches apart maximum.
2.03 FRAMING AND ACCESSORIES
A. Dimensions: Pipe, roll-formed, H-sections are outside dimensions, exclusive of coatings.
B. Steel Framework:
1. Hot-dipped galvanized steel, ASTM F1083, not less than 1.8 ounce zinc per square foot of surface.
2. All framework shall be PVC coated with minimum 0.40 ounce per sq.ft of member.
C. Fittings and Accessories: Galvanized, ASTM F626.
D. Posts
1. Posts and rails shall be galvanized standard weight pipe conforming to the requirements of ASTM F1083.
a. Line Posts: Line posts shall be Schedule 40, 2-3/8 inch O.D. galvanized pipe with minimum bending strength of 201 pounds under a 6-foot cantilever load. Line posts shall be spaced at a maximum 10-foot O.C.
b. Terminal Posts: All end, corner, intermediate, and pull posts and gate leaves 6'-0" wide and less shall be 2-7/8 inch O.D. galvanized Schedule 40 pipe with minimum bending strength of 381 pounds on 6-foot cantilever load. Gate posts for gate leaves shall be Schedule 40 pipe complying with ASTM F1083 of diameters as follows:
Gate Leaf Width Pipe O.D. Weight per Ft.
0’ to 6’ 2-7/8” 5.79 lbs Over 6’ to 13’ 4” 9.1 lbs
Over 13’ to 18’ 6-5/8” 18.97 lbs Over 18’ 8-5/8” 24.7 lbs
E. Tension Wire:
1. Top and bottom tension wire shall be No. 7 gauge aluminum coated steel wire. Fabric shall be securely tied to tension wire at intervals not to exceed 24-inches.
F. Post tops and barbed wire support:
1. Gate, end, corner and line post tops shall be malleable iron or pressed steel and shall be hot dipped galvanized conforming to ASTM A153.
2. Extension arms for supporting the three (3) strands of barbed wire for line posts shall be of pressed steel with malleable iron base, or solid aluminum alloy castings.
3. Angles for line post extension arms shall be approximately 45 degrees from the vertical and the top slot for barbed wire shall be a minimum of 12 inches above the fabric and a minimum of 10 inches from the fence line.
G. End, Corner, Pull Posts: Minimum sizes and weights as follows:
1. Up to 6 feet fabric height, 2.375-inch outside diameter steel pipe, 3.65 pounds per lineal foot, or
3.5 inch by 3.5 inch roll-formed sections, 4.85 pounds per lineal foot.
2. Over 6 feet fabric height, 2.875-inch outside diameter steel pipe, 5.79 pounds per lineal foot, or
3.5 inch by 3.5 inch roll-formed sections, 4.85 pounds per lineal foot.
H. Barbed Wire:
1. Barbed wire shall consist of three strands of 12-1/2 gauge aluminum coated steel wire with 4-point barbs of 14 gauge aluminum wire spaced 5 inches apart, conforming to ASTM A585.
32 31 13 - 4 RIVAN 168434
2. Additional strands of barbed wire shall be added beneath the chain link fabric at all ditch crossings to maintain the security of the fence installation.
I. Braces and Top Rails:
1. Braces and top rails (where shown on the Drawings) shall be 1.66-inch O.D., Schedule 40 galvanized pipe with minimum vertical bending strength of 202 pounds on 10-foot span.
2. Top rails shall be continuous and shall pass through the post tops. The coupling used to join the top rail lengths shall allow for expansion. Brace rails shall be provided at all terminal posts, located between the top and grade lines and extend from the terminal post to the first adjacent post. Braces shall be securely fastened at both ends. Brace ends for receiving brace rails shall be malleable iron or castings of 356.0 (formerly SG70A) alloy, or equivalent of ASTM B26 or B108.
3. Truss and stretcher bands shall be 1/8-inch x 7/8-inch pressed steel, supplied with carriage bolts and nuts. Bolts shall be 5/16-inch by 1¼ inch. Truss rods shall be 3/8-inch nominal diameter.
J. Fabric Ties:
1. Wire ties shall be preformed 0.148-inch diameter (9 gauge) aluminum. Flat band type ties shall be 1100-H18 or 3003-H14, .064-inch thick by 1/2-inch wide.
2. Hog rings for attaching tension wire to fabric shall be 0.105-inch diameter, Alloy 1100-H14.
K. Gates:
1. Gate frames shall be made of 2-inch O.D. ASTM F1083 pipe, 2.72 lbs. per foot hot dipped galvanized. Fabric shall match fence. Gate frames shall be welded or assembled with riveted corner castings. Gate frames shall be equipped with 3/8-inch diameter adjustable truss bars.
Hinges shall be ball and socket.
2. Gate shall be equipped with positive latching device with provision for padlocking. Personnel gates shall be minimum 36-inch clear opening.
3. Sliding gates
a. Sliding gates shall be cantilever type of the same height as adjacent fence.
b. Gate shall be furnished as a complete system inclusive of opener, card reader pedestal, and exit loop.
c. Gate operators shall be heavy duty rated for high frequency installation.
d. Shall be powered from Panelboard PP-1 as shown on Sheet 01E501.
e. Design intent is that gate shall open/close as follows:
1) Card reader/security panel shall open gate when card is presented at pedestal reader
2) Exit loop detector shall open the gate automatically as a vehicle approaches
3) The gate shall close automatically after an adjustable 0-3 minute time delay. Field verify location of loop detector with Owner/Engineer in the field.
4. Card Reader Pedestal
a. Contractor shall furnish and install conduit and pedestal for card reader installation
b. Card reader installation and wiring shall be by the Owner.
L. Concrete:
1. All concrete shall be 3000 psi in conformance with Section 03 30 00.
PART 3 EXECUTION
3.01 PREPARATION
A. Examine areas and conditions, with installer present, for compliance with requirements for a verified survey of property lines and legal boundaries, Site clearing, earthwork, pavement work, and other conditions affecting performance.
1. Do not begin installation before final grading is completed, unless otherwise permitted by
Engineer.
2. Proceed with installation only after unsatisfactory conditions have been corrected.
RIVAN 168434 32 31 13 - 5
3.02 INSTALLATION
A. General:
1. Install chain-link fencing to comply with ASTM F567 and more stringent requirements specified.
2. Install fencing on established boundary lines inside property line.
B. Excavation:
1. Drill or hand excavate (using post hole digger) holes for posts to diameters and spacings indicated, in firm, undisturbed or compacted soil.
2. If not indicated on Drawings, excavate holes for each post to minimum diameter recommended by fence manufacturer, but at least 4 times largest cross-section of post.
3. Unless otherwise indicated, excavate hole depths approximately 3 inches lower than post bottom, with bottom of posts set at least 36 inches below finish grade surface.
C. Setting Posts:
1. Center and align posts in holes 3 inches above bottom of excavation.
2. Place concrete around posts, vibrate or tamp for consolidation.
3. Check for vertical and top alignment, hold in position during placement and finishing operations.
4. Unless otherwise indicated, extend concrete footings 2 inches above grade, trowel to crown to shed water.
D. Top Rails:
1. Run rail continuously through post caps, bending to radius for curved runs.
2. Provide expansion couplings as recommended by fencing manufacturer.
E. Brace Assemblies: Install braces so posts are plumb when diagonal rod is under proper tension.
F. Fabric:
1. Leave approximately 3 inches between finish grade and bottom selvage, unless otherwise indicated.
2. Pull fabric taut and tie to posts, rails, tension wires.
3. Install on security side of fence, anchor to framework so that fabric remains in tension after pulling force released.
4. Cantilevered gate fabric: Install using hook bolts inserted through pre-drilled holes in the frame, 15 inches on center and all 4 sides of the gate. Attach fabric with tension bar laced through last link of the fabric.
G. Tension Bars: Thread through or clamp to fabric 4 inches on center, secure to posts with metal bands spaced 15 inches on center.
H. Barbed Wire: Pull wire taut, install securely to extension arms, secure to end post or terminal arms in accordance with manufacturer’s instructions.
I. Tie Wires:
1. Use U-shaped wire, conforming to diameter of pipe to which attached, clasping pipe and fabric firmly with ends twisted at least 2 full turns.
2. Bend ends of wire to minimize hazard to persons or clothing.
3. Tie fabric to line posts, with wire ties spaced 12 inches on center.
4. Tie fabric to rails and braces, with wire ties spaced 24 inches on center.
5. Tie fabric to tension wires, with hog rings spaced 24 inches on center.
J. Fasteners:
1. Install nuts for tension bands and hardware bolts on side of fence opposite fabric side.
2. Peen ends of bolts or score threads to prevent removal of nuts.
K. Gates:
1. Install plumb, level, secure for full opening without interference.
2. Install ground-set items in concrete for anchorage.
3. Adjust hardware for smooth operation, lubricate where necessary.
32 31 13 - 6 RIVAN 168434
3.03 POST FOUNDATIONS
A. Post holes shall be in true alignment and of sufficient size to provide a permanent foundation of concrete. Holes shall be well centered on the posts. A minimum diameter of 12 inches shall be required for all posts.
B. Post foundations shall be carefully rodded or tamped into place. The top of concrete shall extend 2 inches above ground line and shall be neatly troweled and leveled up from edges to the posts so as to have a pitch outward in all directions.
C. No materials shall be installed on the posts, nor shall any load be applied to the posts within 3 days after the individual post foundation is completed.
3.04 RESETTING OF EXISTING FENCE
A. Where shown on the Drawings that resetting of existing fence is required, the fence, after resetting, shall be in a condition that is equal to or better than before the fence was removed.
B. The Contractor shall replace any of the fence components which have been unnecessarily damaged by him.
3.05 PADLOCK AND KEYS
A. Padlocks and keys shall be provided by Owner..
3.06 ADJUSTING
A. Adjust gate to operate smoothly, easily, and quietly, free of binding, warp, excessive deflection, distortion, nonalignment, misplacement, disruption, or malfunction, throughout entire operational range.
B. Confirm latches and locks engage accurately and securely without forcing or binding.
C. Lubricate hardware.
3.07 CLEANING
A. Site:
1. Do not allow accumulation of scraps, debris arising from Work of this Section.
2. Maintain premises in neat, orderly condition.
B. System:
1. Immediately after erection, clean field welds, bolted connections, and abraded areas.
2. Refinish exposed or abraded areas with same material used for shop finishing to comply with
SSPC-PA 1 for touching up shop-finished surfaces.
3. Comply with ASTM A780 for repair of damaged hot dip galvanized coating.
3.08 TEMPORARY FENCING
A. The Contractor shall furnish and install all temporary fencing and appurtenances as shown on the Drawings or as required during construction to adequately secure the site prior to installation of the permanent fence.
3.09 DEMONSTRATION
A. Maintenance Instructions: Manufacturer’s representative to schedule and attend meeting with Owner’s representative to explain:
1. Maintenance and care instructions.
RIVAN 168434 32 31 13 - 7
2. Recommended maintenance program.
3. Warranty requirements.
END OF SECTION
Revised Per Addendum 1 Process Valves and Accessories
RIVAN 168434 40 23 30 - 1
SECTION 40 23 30
PROCESS VALVES AND ACCESSORIES
1.01 SUMMARY
A. Section Includes:
1. Furnish and install all valves, complete with all assemblies and accessories, as specified herein at locations shown on the Drawings including all fittings, appurtenances and transition elements required for a complete and operable installation.
2. Relocation of the filter function valve actuators from the upper filter operating floor to be directly mounted on the corresponding filter function valve located in the lower level pipe gallery. This work includes removal of all floorstands, extension shafts and shaft supports. Six (6) valves total.
3. Except where noted otherwise, all valves shall conform to pertinent sections of the latest revision of AWWA C500 Specifications.
4. All quantities of valves provided within each valve type specified below, shall be supplied from the same manufacturer.
B. General Products Specified Herein
1. Air/Vacuum Valves
2. Gate Valves
3. Ball Valves
4. Solenoid Valves
5. Static Mixers
6. Miscellaneous process piping items.
C. Related Sections:
1. Supplementary Conditions of the Contract, General Conditions of the Contract and Division 1 Sections apply to the Work of this Section.
2. Site and Infrastructure Subgroup.
3. Section 09 97 20 - Coating Systems for Industrial Facilities.
4. Division 22.
5. Division 26.
6. Division 40.
1.02 REFERENCES
A. AWWA:
1. C508 - Swing-Check Valves for Waterworks Service, 2-Inch Through 24 Inch
2. C509/C515 - Resilient-Seated Gate Valves
3. C512 - Air Release, Air/Vacuum, and Combination Air Valves for Waterworks Service
1.03 SUBMITTALS
A. Comply with Section 01 33 00.
B. Submit Product Data which includes the following for each item furnished:
1. Manufacturer and model.
2. Component materials.
3. Dimensions.
C. Provide Operation and Maintenance manuals in accordance with Section 01 78 23.
Process Valves and Accessories Revised Per Addendum 1
40 23 30 - 2 RIVAN 168434
1.04 QUALITY ASSURANCE
A. The materials used in this work shall be new and conform to the requirements of this Section.
B. Refer to Section 09 97 20 for requirements for surface preparation, priming and finish coatings.
2.01 MATERIAL
A. Size, joint type and body material of the valves shall correspond to the size, joint type and material of the adjacent piping, unless otherwise stated on the Contract Drawings and specifications.
2.02 AUTOMATIC HYDROPNEUMATIC TANK PRESSURE RELEASE VALVES
A. Approved Manufacturers:
1. Watts
2. Or approved equal
B. Provide pressure release valves where called for in the plans.
C. Conditions of Service:
1. Application: Air
2. Connection Size: 3/4” – Field verify existing
3. Maximum pressure: 300 PSI
4. Factory set pressure 125 PSI
5. Material: Brass
6. Operation: Automatic
7. Approved for use on ASME certified tank
D. All valves shall be furnished and installed with inlet shutoff ball valves unless specifically called out different in the plans.
E. Route discharge to exterior of building. 1-inch copper pipe routed through exterior wall above CMU.
Seal penetration weathertight. Install 20-mesh stainless steel screen on end of discharge pipe..
2.03 AUTOMATIC HYDROPNEUMATIC TANK PRESSURE RELEASE VALVES WITH PULL RING
1. Milton
2. Watts
3. Or approved equal
B. Provide pressure release valves where called for in the plans.
2. Connection Size: 1/2” – Field verify existing
3. Maximum pressure: 300 PSI
4. Factory set pressure 110 PSI
5. Material: Brass
6. Operation: Automatic. Pull ring for manual testing
7. Approved for use on ASME certified tank
D. All valves shall be furnished and installed with inlet shutoff ball valves unless specifically called out different in the plans.
RIVAN 168434 40 23 30 - 3
E. Route discharge to exterior of building. 0.75-inch copper pipe routed through exterior wall above CMU. Seal penetration weathertight. Install 20-mesh stainless steel screen on end of discharge pipe.
2.04 HYDROPNEUMATIC TANK VACUUM BREAKER VALVE
1. Warren Controls
2. Or approved equal
B. Provide vacuum relief valve where called for in the plans.
2. Connection Size: 4” Flange– Field verify existing
3. Material: stainless steel body and seat
4. Maximum pressure: 150PSI
5. Operation: Automatic
6. Approved for use on ASME certified tank
2.05 BALL VALVES
A. Lead free bronze ball valves:
1. Two piece body
2. Stainless steel ball
3. Teflon seats and stuffing box ring
4. Blow-out proof stem
5. Level handle with balancing stops.
6. FPT threaded ends for connection with threaded steel process pipe.
2.06 0STATIC MIXERS
A. Contractor shall furnish and install a static mixer in the process piping upstream of the hydroneumatic tank.
B. Approved Manufacturers:
1. Koflo
2. Equal Pre-approved by Engineer
C. Quantity: 1
D. Size: 2-inch Diameter
E. Design
1. Water flow range: 10 gpm to 50 gpm
2. No. of mixing elements: 6
3. Material: 316 SS
4. End Connection: Threaded male NPT
F. Miscellaneous
1. Contractor shall furnish and install unions on both ends of the static mixer to facilitate installation/removal of the static mixer
2. Contractor shall furnish a piece of threaded steel pipe of the same length as the static mixer to be installed in the process pipe in the event the static mixer is removed.
Process Valves and Accessories Revised Per Addendum 1
40 23 30 - 4 RIVAN 168434
PART 3 EXECUTION
3.01 EXAMINATION
A. Inspect all material and equipment as it is received to determine damage and/or missing parts. Repair or replace damaged items in accordance with manufacturers’ instructions.
B. Determine locations and dimensions of existing structures, piping, and equipment associated with or potentially interfering with the proper fabrication and installation of proposed work.
C. Coordinate final length and location of required pipe connections to all process equipment to meet the recommendations and requirements of the equipment manufacturer subject to approval of the Engineer.
D. No work shall be installed that directly connects to equipment until such time as complete Shop
Drawings of said equipment have been reviewed by the Engineer.
E. Determine and be responsible for the proper locations and character of all hangers, chases, sleeves and other openings in the construction required for all process piping work.
F. Refer to other drawings for exact locations of partitions, walls, doors, equipment, etc.
3.02 INSTALLATION AND TESTING
A. General:
1. All valves and accessories shall be installed as shown on the Drawings, as described herein, and in accordance with manufacturer's recommendations.
2. Install all items in accordance with manufacturer’s recommendations.
3. Install items only where indicated on the Drawings.
4. Installation at other location only with prior approved by the Engineer.
5. All screwed or soldered piping shall have unions installed on both sides of all valves and at all connection points to all equipment.
6. Install vertical piping runs plumb and horizontal runs parallel with structure wall unless otherwise noted on the Drawings.
B. Air Release Valves and Air and Vacuum Valves:
1. Gate valves or ball valves shall be installed below each air release valve.
2. Gate valves or ball valves shall be installed below each air and vacuum valve.
3. The air and vacuum valves shall have downward positioned return pipes that terminate directly over and 12 inches above the floor drain, unless noted otherwise within the Contract Documents.
Each outlet shall be covered with a 24 mesh stainless steel screen.
4. The air release valves shall be fitted with drain piping that directs vented water to, and down, the nearest wall or structural column to the nearest floor drain. The outlet shall be covered with a 24 mesh stainless steel screen and terminated 2 pipe diameters above the floor trench drain.
C. After installation, operate each valve to ensure proper function.
3.03 CONNECTIONS WITH EXISTING PIPING
A. Where connection between new and existing work is made, use suitable and proper fittings to suit conditions encountered.
B. Provide suitable equipment and facilities to dewater, drain, and dispose of liquid removed without damage to adjacent property.
C. Where connection involves potable water systems, provide disinfection methods as prescribed in these Specifications.
RIVAN 168434 40 23 30 - 5
3.04 PAINTING
A. The exterior of all valves, operators and accessories, unless otherwise specified, shall be painted as specified under Section 09 97 20.
B. Valves shall be painted to match the color of the adjacent piping.
3.05 START-UP TRAINING
A. Provide the services of a factory-trained technician for a minimum of two 1-hour operator training sessions for each type of valve or device provided in this section.
B. Schedule training at Owner’s convenience after the systems are operational.
This Page Left Blank Intentionally
Revised Per Addendum 1 Centrifugal Pumps
RIVAN 144134 43 23 00 - 1
SECTION 43 23 00
CENTRIFUGAL PUMPS
1.01 DESCRIPTION
A. Furnish, install, and test centrifugal pumping units and accessories as indicated on the Drawings and as specified herein.
B. One (1) centrifugal pumps will be installed throughout the facility.
1. One (1) end suction pump to recirculate water through the hydropneumatic tank.
C. Related Sections
1. Section 26 00 00 - Electrical General Provisions
2. Section 40 90 00 - Instrumentation and Control for Process Systems
1.02 DEFINITIONS
A. AFBMA: Anti-friction Bearing Manufacturers Association
B. AISI: American Iron and Steel Institute
C. ASTM: American Society for Testing and Materials
D. FM: Factory Mutual
E. HI: Hydraulic Institute Standards
F. NEC: National Electrical Code
G. NEMA: National Electrical Manufacturers Association
H. NFPA: National Fire Protection Association
1.03 SUBMITTALS
A. Shop Drawings in accordance with Section 01 33 00 and include the following:
1. Name of manufacturer
2. Size and model number
3. Performance curves
4. Certified performance curves
5. Detailed specifications and dimensions
6. Motor specifications
7. Installation guide
8. Printed warranty
B. Operating and Maintenance Data in accordance with Section 01 78 23.
C. Certified Installation Inspection and Start-up Services
1.04 WARRANTY
A. The pump manufacturer shall warrant the pumps, motors, and guide removal systems to the Owner against defects in materials and workmanship for a period of five years or 10,000 hours of operation under normal use and service.
Centrifugal Pumps Revised Per Addendum 1
43 23 00 - 2 RIVAN 144134
B. The pump manufacturer's warranty shall be in printed form and previously published as the manufacturer's standard warranty for all similar units manufactured. A copy of the warranty shall be provided to the Owner at system start-up.
1.05 SYSTEM START-UP
A. The pump manufacturer shall furnish the services of a qualified factory trained field service engineer for two 8-hour work days at the site to inspect the installation and instruct the Owner's personnel on the operation and maintenance of the pumping units.
2.01 MANUFACTURER/MODEL:
A. Approved Manufacturers
1. EBARA
2. Gould
3. Little Giant
4. Or Engineer pre-approved equal.
2.02 BASIS OF DESIGN
A. The basis of design is Goulds Model 1BF40312.
2.03 COMPONENTS
A. End Suction Pump:
1. Pump casing shall be cast iron with smooth water passages and fitted with a steel replaceable wearing ring. Maximum casing working pressure shall be 100 psig.
2. Shall be provided with a face type mechanical seal with Ni-Resist stationary seat, carbon washer, Buna rubber flexible members, 18-8 stainless steel spring and metal parts. Seal shall be mounted over 416 stainless steel shaft sleeve.
3. Pump Shaft:
a. Carbon steel of a size and design to limit shaft deflection at the stuffing box to no more than
0.002 inches.
b. Connections to drives shall be connected through a flexible coupling.
4. Impeller:
a. Shall be one piece iron casting
b. Suitable for use in chlorinated potable water
5. Furnish all necessary fittings for connecting to suction and discharge piping.
6. Pump manufacturer shall furnish necessary anchor bolts, nuts, washers, gaskets, and templates required for setting the pump. Anchor bolts shall be 304 stainless steel. Contractor shall place all anchors in accordance with certified prints supplied by pump supplier.
B. Electrical Requirements:
Motors End Suction Pump Rating 120V, 1ph, 60 Hz
Minimum Horsepower 1/3 Speed, rpm 3500
PART 3 EXECUTION
3.01 DELIVERY OF EQUIPMENT
A. Delivery of equipment shall be coordinated with the requirements of the Contractor.
Revised Per Addendum 1 Centrifugal Pumps
RIVAN 144134 43 23 00 - 3
3.02 INSTALLATION
A. Install equipment in accordance with manufacturer’s recommendations and as shown on Drawings.
B. Equipment manufacturer to furnish necessary anchor bolts, nuts, washers, gaskets and anchor bolt templates.
C. Install all anchors in accordance with certified prints supplied by equipment manufacturer.
3.03 SYSTEM AND EQUIPMENT STARTUP
A. Conform to the requirements of Section 01 75 00.
B. The manufacturer or single source supplier of equipment included in each section shall inspect the completed installation; make all necessary adjustments, corrections, or modifications prior to start-up.
See Section 44 44 00.
C. Provide written certification that check-out services have been completed and 1 week notice prior to start-up and demonstration.
D. Place various items of equipment into operation, along with related piping and control systems, at times acceptable to Owner. After satisfactory start-up of these systems and their related equipment, they will remain in continuous or intermittent operation as required by the Owner.
E. All equipment and accessories shall be adjusted and calibrated prior to any start-up and any equipment placed into temporary operation prior to Final Completion of the total Project shall be readjusted and/or recalibrated as necessary.
F. Contractor shall supervise, control, and be responsible for operation and maintenance of new equipment and/or systems during start up.
G. No system start-ups will be held on holidays, Fridays, or the day before a holiday.
3.04 DEMONSTRATION AND TRAINING
A. Provide factory trained serviceman to instruct the Owner's personnel in the proper operation and maintenance of the equipment and certify to the Engineer that system is installed and operating properly, refer to Sections 01 75 00 and 40 05 00.
B. Following completion of successful equipment start-up, the Contractor shall arrange for a factory representative and installer of each operating piece of equipment and other work requiring regular or continuing maintenance, to meet at Site with Owner’s personnel to provide necessary basic instruction in proper operation and maintenance of entire work. Where installers are not experienced in required procedures, include instruction by manufacturer’s representatives.
C. For each piece of operating equipment, the factory representative and installer shall provide two separate training sessions to the Owner’s operations and maintenance staff. The two training sessions shall be separated in time by at least 1 week (7 days) and shall be arranged to meet the schedules of the Owner’s operations and maintenance staff.
D. Each training session shall be inclusive of a minimum 4 hours on-site instructional time. All travel time and costs necessary to perform each training session shall be considered as additional and incidental to four hours of on-site instructional training time.
E. The training session time shall be separate and distinct from the time spent on equipment start-up.
F. Contractor shall coordinate the schedule for each training session a minimum of 2 weeks (14 days) ahead of schedule.
Centrifugal Pumps Revised Per Addendum 1
43 23 00 - 4 RIVAN 144134
G. All final copies of the Operation & Maintenance manuals for each piece of operating equipment shall be delivered to the Engineer a minimum of 1 week (7 days) prior to scheduling the initial training session.
H. At a minimum, each training session shall include the following:
1. Utilize operation and maintenance manuals as basis for instructions.
2. Review contents of manual with Owners’ personnel in detail to explain all aspects of operation and maintenance.
3. Include a detailed review of the following items:
a. Maintenance manuals.
b. Record documents.
c. Spare parts and materials.
d. Tools.
e. Lubricants.
f. Fuels.
g. Identification systems.
h. Control sequences.
i. Hazards.
j. Cleaning.
k. Warranties.
l. Maintenance agreements and similar continuing commitments.
4. Manufacturer’s representative shall demonstrate the following procedures to Owner’s personnel prior to date of final inspection:
a. Startup.
b. Shutdown.
c. Emergency operations.
d. Noise and vibration adjustments.
e. Safety procedures.
f. Economy and efficiency adjustments.
g. Effective energy utilization.
h. Troubleshooting.
i. Maintenance.
I. Prepare and insert additional data in operations and maintenance manuals if need for additional data becomes apparent during instructions.
35' REAR SETBACK
' S
ID
E
SE
TB
AC
K
75' FRONT SETBACK
PAVED DRIVE
PAVED DRIVE
GRAVEL AREA
CHAIN LINK FENCE
PAVED DRIVE
ONE STORY
CMU BUILDING
FFE = 651.90'
CONCRETE
STOOP
SHED
BENCHMARK:
X ON CONCRETE PAD
ELEV. = 660.37'
WELL W/
CONCRETE
PAD
NEW CHAIN LINK GATE W/ ELECTRIC ACTUATOR
U S
R T.
(N .B
.L
VA
R
IA
BL
E W
ID
TH
R
/W BENCHMARK:
IPF
ELEV. = 6647.18'
PROCESS ROOM
SODIUM HYPOCHLORITE
ROOM
FLUORIDE ROOM
18'
NEW CMU BUILDING
(SEE STRUCTURAL
SHEETS)
NEW 8' L x 4' W GENERATOR PAD W/
RELOCATED GENERATOR & NEW FUEL LINE
RELOCATED CHAIN LINK FENCE
(SEE DETAIL ON SHEET C04)
XC
XC
XC
CO
CO
CO
CO
G
CO
CO
CO
XC
REROUTED WATER SUPPLY &
ELECTRICAL LINES FROM WELL
12'
NEW BUILDING
FFE = 652.50'
NEW DITCH LINE
NEW 4,000 GALLON
UNDERGROUND WASTE
STORAGE TANK
REROUTE 6" DRAIN LINE FROM
BUILDING FLOOR DRAIN
REQ'D:
(1) 6" 45° BEND
(1) CLEANOUT
NEW 6" FLOOR DRAIN
TO UNDERGROUND
WASTE STORAGE TANK
@ MIN. 1% SLOPE
NEW CLEANOUT (TYP)
(SEE DETAIL ON SHEET C04)
EXISTING 6" FLOOR DRAIN
(TO BE ABANDONED)
RELOCATED PROPANE STORAGE
TANK W/ NEW CONCRETE PAD
10' 5'
BOLLARD (TYP)
(SEE DETAIL ON SHEET C04)
SILT FENCE
(TYP)
SILT FENCE
(TYP)
CHAIIN LINK ELECTRIC ACTUATOR
XC
NEW GATE TRAVEL PATH
(APPROXIMATE)
CUT & CAP 6" DRAIN LINE
(CAP BOTH ENDS OF PIPE).
REPAIR PAVED DRIVE IN KIND.
NEW 8" BACKWASH
WASTE LINE FROM
GAC UNIT
CONTRACTOR
STAGING AREA
TEMPORARY HYDROPNEUMATIC TANK
WITH INFLUENT/EFFLUENT HOSES.
CONTRACTOR TO USED EXISTING
PENETRATIOND IN NE CORNER OF
WTP & CONNECT TO INTERNAL PIPING.
CONCRETE STOOP - MATCH
PAVEMENT ELEVATIONS
(SEE STRUCTURAL SHEETS)
EXISTING WELL DISCHARGE LINE IS 4" SCH 80
PVC. CUT EX. WATER WATER MAIN AND
INSTALL SCH 80 PVC 45° BEND FITTING TO
ALIGN WITH NEW FLOOR PENETRATION.
TRANSITION TO DIP 5' FROM WTP. PROVIDE
AWWA C906 DIP MH ADAPTER.
NOTE:
CONTRACTOR TO EXCAVATE AND PROVIDE TEMPORARY CONNECTION FROM EXISTING 4" SCH 80 PVC WELL DISCHARGE PIPING AND WTP INTERNAL PIPING. TEMPORARY CONNECTION SHALL REMAIN IN PLACE WHILE NEW WELL DISCHARGE PIPING AND WTP INTERNAL PIPING IS INSTALLED SUCH THE WTP
HAS A CONTINUOUS WATER SUPPLY FROM THE WELL. TEMPORARY THRUST BLOCKING SHALL BE
PROVIDED AT TEMPORARY CONNECTION TO THE SATISFACTION OF OWNER/ENGINEER TO PREVENT
MOVEMENT OF TEMPORARY PIPING.
NEW 4' WIDE PERSONNAL GATE IN
EXISTING FENCE. INSTALL NEW POST
AND MODIFY MESH TO ACCOMMODATE
INSTALLATION.GATE CARD READER PEDESTAL.
CONTRACTOR TO POUR 24" X 24" X 12"
CONCRETE PAD, INSTALL CONDUIT
AND INSTALL PEDESTAL.
(COORDINATE WITH ELECTRICAL)
CARD READER AND WIRING BY
OTHERS.
BURIED GATE EXIT LOOP
1.5" CONDUIT FROM FLOW
SWITCH TO PLC
(COORDINATE WITH ELECTRICAL)
1" BURIED CONDUIT FROM GATE
CARD READER TO SECURITY PANEL
LPG GENERAL NOTES:
1. LPG PIPING AND VALVES INCLUDING PROPANE PIPING SHALL COMPLY WITH REQUIREMENTS OF NFPA 58 AND THE INTERNATIONAL FUEL GAS CODE FOR PG DISTRIBUTION SYSTEM, INCLUDING MATERIALS, INSTALLATION AND TESTING.
2. MINIMUM OPERATING PRESSURE FOR LPG PIPING AND VALVE: 125 PSIG.
3. BELOW GRADE LPG PIPING SHALL BE 0.75-INCH POLYETHYLENE PIPE AND TUBING, ASTM D2513, SDR 11
WITH BUTT-FUSION FITTINGS AND JOINTS. JOIN PIPING IN ACCORDANCE WITH ASTM D2657. PIPE BURY
DEPTH SHALL BE MINIMUM 36" BELOW GRADE. INSTALL WARNING TAPE OVER PIPE.
4. ABOVE GRADE LPG PIPING SHALL BE 0.75-INCH ASTM A53/A53M, BLACK STEEL, SCHEDULE 40, TYPE E OR S, BRADE B. COAT PIPE AND FITTINGS WITH PROTECTIVE COATING FOR STEEL PIPE.
5. REUSE EXISTING PRESSURE REGULATOR IN GENERATOR ENCLOSURE.
NEW 0.75" LIQUIFIED PETROLEUM
GAS (LPG) PIPING. SEE LPG
GENERAL NOTES ON THIS SHEET.
1" BURIED CONDUIT TO GATE OPENER
(COORDINATE WITH ELECTRICAL)
SEH Project Checked By Drawn By
Project Status Issue Date
This drawing is an instrument of service and shall remain the property of Short Elliott Hendrickson, Inc.
(SEH). This drawing, concepts and ideas contained herein shall not be used, reproduced, revised, or retained without the express written approval of SEH.
Submission or distribution of this drawing to meet official or regulatory requirements or for purposes in connection with the project is not be construed as publication in derogation of any of the rights of SEH.
Project Owner
Sh or t E llio tt H en dr ick so n, Inc
Al l R igh ts
Re se rve d
CO
PY
RI
GH
T
REVISION SCHEDULE
REV. # DESCRIPTION DATE
SA
VE
: 1 0/1
7/2
2 1 2:0
9:4 7 P
M sw illi by
PL
OT
: 1 1/2
0/2
3 4 :15
:28 P
M X:
\P T\
R\
RI
VA
N\
\5-fin al-ds gn
\51 -d ra wi ng s\1
0- Ci vil \ca d\d wg
\sh ee t\R
IV
AN
_S P.
dw g
9/28/2023BID DOCS
168434
9/28/2023
RIVANNA WATER & SEWER AUTHORITY
695 MOORES CREEK LANE
CHARLOTTESVILLE, VA 22902
RE
D
HI
LL
W
AT
ER
T
RE
AT
ME
NT
P
LA
NT
U
PG
RA
DE
S
RI
VA
NN
A W
AT
ER
A
ND
S
EW
ER
A
UT
HO
RI
TY
AL
BE
MA
RL
E
CO
UN
TY
VI
RG
IN
IA
IF
B
No . 4 feetscale
10 2010
C03
TWW
WSW
SITE PLAN
11/20/20231 ADDENDUM 1
SEH Project Checked By Drawn By
Project Status Issue Date
This drawing is an instrument of service and shall remain the property of Short Elliott Hendrickson, Inc.
(SEH). This drawing, concepts and ideas contained herein shall not be used, reproduced, revised, or retained without the express written approval of SEH.
Submission or distribution of this drawing to meet official or regulatory requirements or for purposes in connection with the project is not be construed as publication in derogation of any of the rights of SEH.
Project Owner
Sh or t E llio tt H en dr ick so n, Inc
Al l R igh ts
Re se rve d
CO
PY
RI
GH
T
REVISION SCHEDULE
REV. # DESCRIPTION DATE
SA
VE
: 1 0/1
7/2
2 1 2:0
9:4 7 P
M sw illi by
PL
OT
: 1 1/2
1/2
3 4 :13
:25 P
M X:
\P T\
R\
RI
VA
N\
\5-fin al-ds gn
\51 -d ra wi ng s\1
0- Ci vil \ca d\d wg
\sh ee t\R
IV
AN
_D T.
dw g
9/28/2023BID DOCS
168434
9/28/2023
RIVANNA WATER & SEWER AUTHORITY
695 MOORES CREEK LANE
CHARLOTTESVILLE, VA 22902
RE
D
HI
LL
W
AT
ER
T
RE
AT
ME
NT
P
LA
NT
U
PG
RA
DE
S
RI
VA
NN
A W
AT
ER
A
ND
S
EW
ER
A
UT
HO
RI
TY
AL
BE
MA
RL
E
CO
UN
TY
VI
RG
IN
IA
IF
B
No . 4
C04
TWW
WSW
CIVIL DETAILS
SA
VE
: 1 2/1
1/2
2 5 :16
:38 P
M sw illi by
PL
OT
: 1 1/2
1/2
3 4 :13
:26 P
M X:
\P T\
R\
RI
VA
N\
\5-fin al-ds gn
\51 -d ra wi ng s\1
0- Ci vil \ca d\d wg
\sh ee t\R
IV
AN
_D T.
dw g
FINISHED GROUND
LINE
COMPACTED
SUBGRADE
NOTES:
4' MIN
12" MIN
TYP
1/2" DIA
CRUSHED
ROCK
PIPE
GEOTEXTILE TYPE 4
MNDOT 3733
SUITABLE
MATERIAL
" M
IN
PI
PE
Z O
N E
C04
PIPE BEDDING & TRENCH BACKFILL
NO SCALE
FI
N
AL
BA
C
KF
IL
L
3/8" CROWN
8" DIA SCHEDULE 80 STEEL
PIPE BOLLARD EMBED IN
CONCRETE AND FILL WITH
CONCRETE. APPLY PAINT
PER SECTION 09 97 20.
1/2" EXPANSION JOINT
PAVEMENT SURFACE
AS INDICATED
12" 12"
4'-0"
4'-0"
1'-0" SQUARE
COAT AS SPECIFIED
STANDARD MACHINE SLICED
PREASSEMBLED
DIRECTION OF
RUNOFF FLOW
DIRECTION OF
RUNOFF FLOW
DIRECTION OF
RUNOFF FLOW
6" MIN.
4" MIN.
6" MIN.
6" MIN.
2' M
IN
PO
ST
EM
BE
D M
EN
T
5 FT. MIN. LENGTH POST
AT 6 FT. MAX. SPACING
GEOTEXTILE FABRIC, 36'' WIDE
FABRIC ANCHORAGE TRENCH.
BACKFILL WITH TAMPED
NATURAL SOIL
" M
IN
" M
IN
PO
ST
EM
BE
D M
EN
T
5 FT. MIN. LENGTH POST
AT 6 FT. MAX. SPACING
STAPLES
GEOTEXTILE FABRIC, 36'' WIDE
FABRIC ANCHORAGE
TRENCH. BACKFILL
WITH TAMPED
NATURAL SOIL
5 FT. MIN. LENGTH POST
AT 6 FT. MAX. SPACING
GEOTEXTILE FABRIC, 36'' WIDE
T-
PO
ST
2' M
IN
PO
ST
EM
BE
D M
EN
T
" M
IN
C04
BOLLARD DETAIL
NO SCALE
1. CONTRACTOR SHALL CONSTRUCT TRENCH AND PROVIDE PROTECTIVE
MEASURES AS REQUIRED TO COMPLY WITH OSHA REGULATIONS.
C04
SILT FENCE
NO SCALE
45° WYE
NOTE:
ALL PIPE SHALL BE
SDR35 W/GASKETED JOINTS
24"PVC SERVICE
4" RESIDENTIAL
6" COMMERCIAL
6"
6"
CLEANOUT CASTING
PVC PIPE
4" RESIDENTIAL
6" COMMERCIAL
45°
LONG SWEEP ELBOW
CONNECT TO
EXISTING OR
PLUG / CAP
IN LINE CLEANOUT
C04
SANITARY SEWER SERVICE CLEANOUT
NO SCALE
C04
JOINT RESTRAINT
NO SCALE
TIE TO FIRST FLANGE ABOVE FLOOR WITH
RESTRAINT PLATES
(2) "A" ASTM A307 TIE RODS COATED WITH
BITUMASTIC PAINT TO PREVENT CORROSION
AND ADHESION TO CONCRETE
1/2" EXPANSION MATERIAL AROUND PIPE
"D" RISER CLAMP (TWO HEAVY COATS OF
BITUMASTIC PAINT WHEN IN CONTACT WITH
CONCRETE)
(2) "B" ASTM A307 BENT RODS, 4" HOOKS
(16" MINIMUM EMBEDMENT) COAT RODS WITH
BITUMASTIC PAINT
BURIED MECHANICAL JOINT BEND (TEE SIMILAR)
MECHANICAL JOINT RESTRAINT (EBBA IRON
MEGA-LUG OR EQUIVALENT)(TYPICAL OF 2)
VERIFY PIPE SIZE AND DEPTH
(2) "A" ASTM A307 TIHE RODS TO FIRST JOINT
2 BOLT RISER CLAMP OR STAR BOLTS
"C" x "C" x "C" CONCRETE THRUST BLOCK
"A" 1 1/8"
3/4" 3/4" 3/4" 3/4" 5/8"
"B" 1" 1"
3/4" 3/4" 3/4" 5/8"
"C" 4'-0" 3'-8" 3'-0" 2'-5"
1'-10" 1'-8"
"D"
2 BOLT
4-BOLT
4-BOLT
4-BOLT
4-BOLT
4-BOLT
16" PIPE
12" PIPE
10" PIPE
8" PIPE
6" PIPE
4" PIPE
C04
4,000 GALLON PRECAST WASTE TANK
SCALE: NOT TO SCALE
7' -6
21A OR DVOT NO. 10 SCREENING
(ROCK DUST) LEVELING LAYER
(VERIFY SOIL CONDITIONS WITH
GEOTECH ENGINEER WHEN
EXCAVATED)
6" WELDED STEEL
VENT PIPE
MANHOLE BOOT OR SIMILAR TO
PROVIDE FEXIBLE WATERTIGHT
CONNECTION (TYP.)
8" BWW
6" FLOOR DRAINS
FLOAT SWITCH CONDUIT
FLOAT SWITCH,
MOUNTED TO
TANK SIDE WALL
16" ROUND
ACCESS/CLEANOUT
HATCH
6" WELDED STEEL
VENT PIPE
14'-0"
6" FLOOR DRAINS
6' -0
"FINISHED GRADE
16" ROUND HATCH COVER W/
GRADE RINGS (TYP.)
PRECAST WALLS AND TOP SLAB
(SIZED BY PRECAST MANUFACTURER)
6"
11/20/20231 ADDENDUM 1
PLAN
SECTION
A
B
D
C
WF2-0
WF2-0
WF2-0
WF1-4
S110
S110
Sim
5" SOG W/ #4
BARS @ 18"
O.C. EW
CENTERED
EXISTING BUILDING
8" 8"
8"
S110
Sim
TOP OF FOOTING
650' - 0"
B C
8" CONCRETE FOUNDATION WALL
#5's @12" o.c. EW
6"
EXISTING WALL
EXISTING FOUNDATION
#5 BAR DRILL AND EPOXY 6"
EMBEDMENT @ 24" O.C.
MATCH DOWELS SIZE AND
SPACING TO VERTICAL
REINFORCEMENT
SEE PLAN FOR FOUNDATION
SIZE AND REINFORCEMENT
F.F.E. EXISTING
651.90'
BOND BREAKER
INTERIOR NON-BEARING PARTITION WALL. SEE
GENERAL NOTES FOR VERTICAL REINFORCEMENT
SEE FLOOR PLAN FOR SLAB THICKNESS "T" AND
SLAB REINF
NOTE:
UNO, PROVIDE CONT THICKENED SLAB FOOTING
AT ALL PARTITION WALLS 8" OR GREATER.
D
T 10"
3D
3" CLR
(3) #5 CONT, UNO
FOOTING SCHEDULE
MARK WIDTH THICKNESS REINFORCEMENT
WF1-4
WF2-0
1'-4"
2'-0"
1'-0"
1'-0"
(2) #5 REBAR CONT, BOT
(2) #5 REBAR CONT, BOT
LINTEL SCHEDULE
MARK SIZE REINFORCEMENT
L1 8" DEEP CMU LINTEL (1 COURSE) (2) CONT. #5 REBAR BOTTOM
GENERAL NOTES:
1. 8" CMU REINFORCED WITH #5'S @ 48" O.C. TYPICAL AND AT EACH CORNER
2. UNDERCUT FOOTINGS 6FT BELOW EXISTING GRADE. BACKFILL BELOW
FOOTING (MATCHING FOOTING WIDTH) WITH LEAN CONCRETE OR
FLOWABLE FILL. EXISTING SOIL IS SUITABLE FOR SLAB SUPPORT.
BACKFILL VOID SPACE WITH STRUCTURAL FILL. PROTECT EXISITNG WTP
FOOTINGS DURING EXCAVATION AND SOIL CORRECTION.
3. TOP OF MASONRY WALLS AND PARTITION WALLS TO HAVE 8" DEEP BOND
BEAM WITH 2 - #5 BOTTOM BARS TYPICAL
INSPECTIONS & TESTS SCHEDULE
METAL CONSTRUCTION
1. WELDING
2. DETAILS: BRACING, LOCATIONS, ETC.
3. BOLTING
4. OPEN-WEB STEEL JOISTS & JOIST GIRDERS:
A. INSTALLATION OF OPEN-WEB JOISTS & JOIST GIRDERS END
CONNECTIONS WELD OR BOLT
B. INSTALLATION OF STANDARD BRIDGING & BRIDGING THAT DIFFERS
FROM SJI SPECS
5. STEEL DECK INCLUDING WELDING OR MECHANICAL FASTENING
6. COMPOSITE CONSTRUCTION INCLUDING HEADED STUD ANCHORS
7. COLD FORMED TRUSSES SPANNING 60FT OR GREATER
CONCRETE CONSTRUCTION
1. INSPECT REINFORCEMENT
2. REINFORCING BAR WELD
3. INSPECT ANCHORS CAST IN CONCRETE
4. INSPECT ANCHORS POST-INSTALLED IN CONCRETE
5. VERIFY USE OF REQUIRED DESIGN MIX
6. PRIOR TO CONCRETE PLACEMENT, FABRICATE SPECIMENS FOR
STRENGTH TESTS, PERFORM SLUMP AND AIR CONTENT TESTS, AND
DETERMINE THE TEMPERATURE OF THE CONCRETE
7. INSPECT CONCRETE AND SHOTCRETE PLACEMENT FOR PROPER
APPLICATION TECHNIQUES
8. VERIFY MAINTENANCE OF SPECIFIED CURING TEMPERATURE AND
TECHNIQUES
9. INSPECT PRESTRESSED CONCRETE MEMBERS
10. INSPECT ERECTION OF PRECAST CONCRETE MEMBERS
11. VERIFY IN-SITU CONCRETE STRENGTH PRIOR TO POST-TENSIONING
CONCRETE AND PRIOR TO REMOVAL OF SHORES AND FORMS FROM
BEAMS AND STRUCTURAL SLABS
12…