Question_and_Answer_A002_IBM15-22.pdf

PDF 20 KB Posted

Attached to
Structure Assessments Within the Lower Rio Grande Flood Control Project Federal contract opportunity
Solicitation number
IBM15-22
Issued by
International Boundary and Water Commission U.S.-Mexico

About this file

Q A Amendment A002 IBM15-22

View the file

Other files for this federal contract opportunity

Other files attached to Structure Assessments Within the Lower Rio Grande Flood Control Project, newest first.
File Type Posted
Question_and_Answer_A004_IBM15-22.pdf PDF
Question_and_Answer_A003_IBM15-22.pdf PDF
Question_and_Answer_A001.pdf PDF
Structures_by_Patrol-2015.xlsx XLSX spreadsheet
WD_05-2519_(Rev.-19).pdf PDF
Compensation_and_Liability_Insurance_--_IBWC.docx DOCX document
LRGFCP_Structure_Inspection_PWS_08-31-2015.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question and Answer Amendment A002

Solicitation Number IBM15-22 Structure Assessments within the

Lower Rio Grande Flood Control Project

Q) If during the course of the inspections the contractor comes upon a structure that is covered with silt and a full detailed inspection is not feasible due to the silt build-up – who is responsible for removal of the silt build-up to allow for the required detailed inspection, i.e. the Contractor or the IBWC? If it is determined that the Contractor is responsible for silt build-up removal, how does the IBWC propose for contractor to determine what percentage of the 485 structures may have silt build-up that may require removal for the inspection process to be carried out. This is important due to the period of performance requirement which is currently 180 days from date of contract award in addition, cost will become a factor.

A) The structures are not completely covered with silt. There are about 15 structures that have mud at the bottom that need to be cleaned so that the gate can be properly inspected. The contractor should be responsible for the silt build-up removal.