Question_and_Answer_A001.pdf

PDF 21 KB Posted

Attached to
Structure Assessments Within the Lower Rio Grande Flood Control Project Federal contract opportunity
Solicitation number
IBM15-22
Issued by
International Boundary and Water Commission U.S.-Mexico

About this file

Amendment A001 is posted to answer Questions.

View the file

Other files for this federal contract opportunity

Other files attached to Structure Assessments Within the Lower Rio Grande Flood Control Project, newest first.
File Type Posted
Question_and_Answer_A004_IBM15-22.pdf PDF
Question_and_Answer_A003_IBM15-22.pdf PDF
Question_and_Answer_A002_IBM15-22.pdf PDF
LRGFCP_Structure_Inspection_PWS_08-31-2015.docx DOCX document
Structures_by_Patrol-2015.xlsx XLSX spreadsheet
WD_05-2519_(Rev.-19).pdf PDF
Compensation_and_Liability_Insurance_--_IBWC.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question and Answer Amendment A001

Solicitation Number IBM15-22 Structure Assessments within the

Lower Rio Grande Flood Control Project

Q) Thank you for posting the solicitation for the U.S. IBWC’s Structure Assessments within the Lower Rio Grande Flood Control Project (Solicitation Number: IBM15-22).

Our firm has a question regarding response to the solicitation: What is the required format and documentation required for response?

We have utilized both SF 1442 and SF 330 forms for past responses and would like to confirm requirements for this solicitation.

A) The response may be submitted on the Company’s letterhead and the format is outlined in the synopsis under CLIN Structure.

The synopsis and Performance Work Statement outlines the requirements that need to be submitted.

There is no need to submit an SF 1442 or SF 330.

Q) We are interested in submitting our response to the above solicitation and we were wondering what format you all looking at the response. Like SF330 part 1 and 2, technical proposal, and price proposal and etc. Please let me know.

A) There is no need to submit an SF 330. You may submit your response on the Company’s letterhead.