Hatch 1 Bidder additional questions.pdf
PDF 9 KB Posted
- Attached to
- RECOVERY-Hatch Levee Improvements Federal contract opportunity
- Solicitation number
- IBM10B0001
About this file
2nd set of 3 questions
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Hatch Abstract Spreadsheet 12-22-09 pg 1.xls | XLS spreadsheet | |
| Hatch 2 Bidders additional questions.pdf | ||
| summary of specs plans revisions.pdf | ||
| IBM10B0001 A003.pdf | ||
| Summary of Questions 1-97.pdf | ||
| IBM10B0001 A002.pdf | ||
| Hatch Summary of Questions-2009-12-09.pdf | ||
| HatchAddenum1-SummaryofPlanRevisions.xls | XLS spreadsheet | |
| IBM10B0001 Amendment A001.pdf | ||
| Hatch-Specificaions-Addendum Revisions.pdf | ||
| hatch_addendum 1.pdf | ||
| Bidder list.xls | XLS spreadsheet | |
| sf24_f.pdf | ||
| IBWC 110.pdf | ||
| sf28.pdf | ||
| IBWC 117.pdf | ||
| IBM10B0001.pdf | ||
| wage determination.pdf | ||
| IBWC 116.pdf | ||
| 01-Hatch_Plans_100 _sealed.pdf | ||
| 03-Hatch_Specs- 2009-11-03.pdf |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BIDDER QUESTIONS SUMMARY
Project: Rehabilitation of Improvements for the Rio Grande Canalization Protective Levee System
River Segment Upper Rio Grande By:
Task Order: IBM09T0030 S&B Infrastructure, Ltd.
Client: IBWC Combined Bidders Questions Hatch, Canutillo & Mesilla Date: 12/11/2009
Ite m
N o.
B id
P kg
Date Contractor Contractor Comment Agree (Y/N) S&B Response Comments Respon der
All three Hatch, Canutillo , Mesilla
12/10/09 Skanska USA Civil West RMD
This message is sent regarding the Specification 60 69 00, Sluice Gate Maintenance, in the above-referenced projects. We have the following concerns:It seems that the existing gates on these projects are from different manufacturers. We will require a list of the manufacturer of each gate to know who to contact. Coordinating with suppliers is the responsibility of the Contractor
All three Hatch, Canutillo , Mesilla
12/10/09 Skanska USA Civil West RMD
It is difficult at this time to determine the condition and the scope of the maintenance required at each individual gate. We request that the specification describe exactly what the Government wants done to each gate to be able to have the manufacturers give us a price for the work.
It is unclear about whether this is in refernce to vehicular gates or hydro gates. In each case, the Contractor is responsible for contructing the gates to the final specification and verifying the condition of the gates prior to construction.
All three Hatch, Canutillo , Mesilla
12/10/09 Skanska USA Civil West RMD
In lieu of the above information, we believe it would be better if this work be handled as an allowance. Please let us know if this is something the Government would consider. IBWC is responsible for this decision