03-Hatch_Specs- 2009-11-03.pdf

PDF 2 MB Posted

Attached to
RECOVERY-Hatch Levee Improvements Federal contract opportunity
Solicitation number
IBM10B0001
Issued by
International Boundary and Water Commission U.S.-Mexico

About this file

IBM10B0001 Hatch Specifications

View the file

Other files for this federal contract opportunity

Other files attached to RECOVERY-Hatch Levee Improvements, newest first.
File Type Posted
Hatch Abstract Spreadsheet 12-22-09 pg 1.xls XLS spreadsheet
Hatch 2 Bidders additional questions.pdf PDF
summary of specs plans revisions.pdf PDF
IBM10B0001 A003.pdf PDF
Hatch 1 Bidder additional questions.pdf PDF
Summary of Questions 1-97.pdf PDF
IBM10B0001 A002.pdf PDF
Hatch Summary of Questions-2009-12-09.pdf PDF
HatchAddenum1-SummaryofPlanRevisions.xls XLS spreadsheet
IBM10B0001 Amendment A001.pdf PDF
Hatch-Specificaions-Addendum Revisions.pdf PDF
Bidder list.xls XLS spreadsheet
hatch_addendum 1.pdf PDF
sf24_f.pdf PDF
IBWC 110.pdf PDF
sf28.pdf PDF
IBWC 117.pdf PDF
IBM10B0001.pdf PDF
wage determination.pdf PDF
IBWC 116.pdf PDF
01-Hatch_Plans_100 _sealed.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FINAL

TECHNICAL SPECIFICATIONS

FOR

Upper Rio Grande Flood Control Project –Rehabilitation Improvements for the Rio Grande Canalization Protective Levee System

Hatch Levee System From Hatch Siphon to Bignell Arroyo

Doña Ana County, New Mexico

Prepared for:

United States Section, International Boundary & Water Commission

Submitted / Prepared by:

Project Manager: Daniel O. Rios

Task Order Manager: James M. Sassin, PE Senior Project Manager: Michael C. Riojas

This document is being submitted for interim review under the authority of James M. Sassin, PE, New Mexico No. 13960. It is not intended for use as bid documents, permits, or construction.

Contract No. IBM05D0001 Task Order No. IBM09T0030

November 3, 2009

11-3-2009 princebr james_sassin_sealsig

UPPER RIO GRANDE FLOOD CONTROL PROJECT

REHABILITATION IMPROVEMENTS FOR THE RIO GRANDE CANALIZATION

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

TABLE OF CONTENTS

USIBWC Contract No.: IBM05D0001 Page - 1

TABLE OF CONTENTS

US INTERNATIONAL BOUNDARY & WATER COMMISSION

GOVERNING SPECIFICATIONS AND PROVISIONS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SPECIFICATION 00 01 01 PROJECT TITLE

SPECIFICATION 00 01 10 TABLE OF CONTENTS

SPECIFICATION 00 01 15 LIST OF CONTRACT DRAWINGS

SPECIFICATION 00 01 20 LIST OF SCHEDULES

SPECIFICATION 00 31 19 EXISTING CONDITION INFORMATION

SPECIFICATION 00 31 21 SURVEY INFORMATION (RIGHT OF WAY)

SPECIFICATION 00 31 24 ENVIRONMENTAL ASSESSMENT INFORMATION

SPECIFICATION 00 31 26 EXISTING HAZARDOUS MATERIAL INFORMATION

SPECIFICATION 00 31 32 GEOTECHNICAL DATA

SPECIFICATION 00 31 43 PERMIT APPLICATION

SPECIFICATION 00 31 50 OTHER PROJECT INFORMATION

DIVISION 01 - GENERAL REQUIREMENTS

SPECIFICATION 01 01 00 IDENTIFICATION OF TECHNICAL SPECIFICATIONS

SPECIFICATION 01 19 00 SCOPE OF WORK

SPECIFICATION 01 27 00 MEASUREMENT AND PAYMENT

SPECIFICATION 01 31 00 PROJECT MANAGEMENT AND COORDINATION

SPECIFICATION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION

SPECIFICATION 01 33 00 SUBMITTALS

SPECIFICATION 01 39 00 SAFETY

SPECIFICATION 01 42 00 REFERENCES

SPECIFICATION 01 46 00 QUALITY CONTROL / QUALITY ASSURANCE

SPECIFICATION 01 56 00 BARRICADES AND SIGNS

SPECIFICATION 01 57 00 TEMPORARY EROSION, SEDIMENTATION AND

ENVIRONMENTAL CONTROLS

SPECIFICATION 01 59 00 TEMPORARY CONTROLS FOR WORK AREAS /

PROJECT-SPECIFIC LOCATIONS

SPECIFICATION 01 69 00 CONTROL OF MATERIALS

SPECIFICATION 01 70 00 MOBILIZATION

SPECIFICATION 01 71 00 FIELD ENGINEERING

SPECIFICATION 01 77 00 CONTRACT CLOSE-OUT

STANDARD DIVISIONS

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

TABLE OF CONTENTS

USIBWC Contract No.: IBM05D0001 Page - 2

DIVISIONS 31 / 34 - SITE GRADING

SPECIFICATION 31 11 00 PREPARING RIGHT OF WAY

SPECIFICATION 31 14 00 REMOVE / STOCKPILE EXISTING MATERIALS

SPECIFICATION 31 81 00 PROOF ROLLING

SPECIFICATION 31 92 00 VEGETATION FOR EROSION CONTROL

SPECIFICATION 34 01 00 CLEAN EXISTING CHANNEL

DIVISION 35 - WATERWAY / MARINE

SPECIFICATION 35 41 00 CONSTRUCTION OF LEVEE

SPECIFICATION 35 42 00 RIPRAP

SPECIFICATION 35 43 00 TOE DRAIN

SPECIFICATION 35 44 00 GABION

DIVISION 50 - ROADWAY CONSTRUCTION

SPECIFICATION 50 20 00 ROADWAY BASE

SPECIFICATION 50 91 00 PROVIDE AND INSTALL NEW TRAFFIC SIGNS

SPECIFICATION 50 94 00 DELINEATOR AND OBJECT MARKER

DIVISION 60 - STRUCTURES

SPECIFICATION 60 10 00 EXCAVATION AND BACKFILL FOR STRUCTURES

SPECIFICATION 60 20 00 CONCRETE STRUCTURES

SPECIFICATION 60 21 00 HYDRAULIC CEMENT CONCRETE

SPECIFICATION 60 40 00 REINFORCING STEEL

SPECIFICATION 60 42 00 METAL FOR STRUCTURES

SPECIFICATION 60 45 00 GALVANIZING

SPECIFICATION 60 46 00 CLEANING AND PAINTING STEEL

SPECIFICATION 60 48 00 STRUCTURAL FIELD WELDING

SPECIFICATION 60 64 00 REINFORCED CONCRETE PIPE

SPECIFICATION 60 66 00 HDWLLS WINGWALLS

SPECIFICATION 60 68 00 SLUICE GATES

SPECIFICATION 60 69 00 SLUICE GATE MAINTENANCE

SPECIFICATION 60 80 00 FLOODGATES

SPECIFICATION 60 96 00 REMOVING EXISTING STRUCTURES

DIVISION 90 - MISCELLANEOUS

SPECIFICATION 90 82 00 GEOTEXTILE FABRIC

SPECIAL DIVISIONS

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

DIVISION 00-

USIBWC Contract No.: IBM05D0001 PROCUREMENT AND CONTRACTING

REQUIREMENTS

US INTERNATIONAL BOUNDARY & WATER COMMISSION

GOVERNING TECHNICAL SPECIFICATIONS AND PROVISIONS

DIVISION 00 – PROCUREMENT AND CONTRACTING

REQUIREMENTS

(INTRODUCTORY / AVAILABLE INFORMATION)

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

DIVISION 00-

USIBWC Contract No.: IBM05D0001 PROCUREMENT AND CONTRACTING

REQUIREMENTS

This Page Intentionally Blank

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

PROJECT TITLE

USIBWC Contract No.: IBM05D0001 Page 00.01.01 - 1

INTRODUCTORY INFORMATION 00.01.01

PROJECT TITLE

The title of this project is as follows:

International Boundary & Water Commission – United States Section Upper Rio Grande Flood Control Project

Rehabilitation Improvements for the Rio Grande Canalization Protection Levee-Hatch Levee System From Hatch Siphon to Bignell Arroyo

Doña Ana County, New Mexico

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

PROJECT TITLE

USIBWC Contract No.: IBM05D0001 Page 00.01.01 - 2

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

TABLE OF CONTENTS

USIBWC Contract No.: IBM05D0001 Page 00.01.10 - 1

INTRODUCTORY INFORMATION 00.01.10

TABLE OF CONTENTS

US INTERNATIONAL BOUNDARY & WATER COMMISSION

GOVERNING SPECIFICATIONS AND PROVISIONS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SPECIFICATION 00 01 01 PROJECT TITLE

SPECIFICATION 00 01 10 TABLE OF CONTENTS

SPECIFICATION 00 01 15 LIST OF CONTRACT DRAWINGS

SPECIFICATION 00 01 20 LIST OF SCHEDULES

SPECIFICATION 00 31 19 EXISTING CONDITION INFORMATION

SPECIFICATION 00 31 21 SURVEY INFORMATION (RIGHT OF WAY)

SPECIFICATION 00 31 24 ENVIRONMENTAL ASSESSMENT INFORMATION

SPECIFICATION 00 31 26 EXISTING HAZARDOUS MATERIAL INFORMATION

SPECIFICATION 00 31 32 GEOTECHNICAL DATA

SPECIFICATION 00 31 43 PERMIT APPLICATION

SPECIFICATION 00 31 50 OTHER PROJECT INFORMATION

DIVISION 01 - GENERAL REQUIREMENTS

SPECIFICATION 01 01 00 IDENTIFICATION OF TECHNICAL SPECIFICATIONS

SPECIFICATION 01 19 00 SCOPE OF WORK

SPECIFICATION 01 27 00 MEASUREMENT AND PAYMENT

SPECIFICATION 01 31 00 PROJECT MANAGEMENT AND COORDINATION

SPECIFICATION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION

SPECIFICATION 01 33 00 SUBMITTALS

SPECIFICATION 01 39 00 SAFETY

SPECIFICATION 01 42 00 REFERENCES

SPECIFICATION 01 46 00 QUALITY CONTROL / QUALITY ASSURANCE

SPECIFICATION 01 56 00 BARRICADES AND SIGNS

SPECIFICATION 01 57 00 TEMPORARY EROSION, SEDIMENTATION AND

ENVIRONMENTAL CONTROLS

SPECIFICATION 01 59 00 TEMPORARY CONTROLS FOR WORK AREAS /

PROJECT-SPECIFIC LOCATIONS

SPECIFICATION 01 69 00 CONTROL OF MATERIALS

SPECIFICATION 01 70 00 MOBILIZATION

SPECIFICATION 01 71 00 FIELD ENGINEERING

SPECIFICATION 01 77 00 CONTRACT CLOSE-OUT

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

TABLE OF CONTENTS

USIBWC Contract No.: IBM05D0001 Page 00.01.10 - 2

DIVISIONS 31 / 34 - SITE GRADING

SPECIFICATION 31 11 00 PREPARING RIGHT OF WAY

SPECIFICATION 31 14 00 REMOVE / STOCKPILE EXISTING MATERIALS

SPECIFICATION 31 81 00 PROOF ROLLING

SPECIFICATION 31 92 00 VEGETATION FOR EROSION CONTROL

SPECIFICATION 34 01 00 CLEAN EXISTING CHANNEL

DIVISION 35 - WATERWAY / MARINE

SPECIFICATION 35 41 00 CONSTRUCTION OF LEVEE

SPECIFICATION 35 42 00 RIPRAP

SPECIFICATION 35 43 00 TOE DRAIN

SPECIFICATION 35 44 00 GABION

DIVISION 50 - ROADWAY CONSTRUCTION

SPECIFICATION 50 20 00 ROADWAY BASE

SPECIFICATION 50 91 00 PROVIDE AND INSTALL NEW TRAFFIC SIGNS

SPECIFICATION 50 94 00 DELINEATOR AND OBJECT MARKER

DIVISION 60 - STRUCTURES

SPECIFICATION 60 10 00 EXCAVATION AND BACKFILL FOR STRUCTURES

SPECIFICATION 60 20 00 CONCRETE STRUCTURES

SPECIFICATION 60 21 00 HYDRAULIC CEMENT CONCRETE

SPECIFICATION 60 40 00 REINFORCING STEEL

SPECIFICATION 60 42 00 METAL FOR STRUCTURES

SPECIFICATION 60 45 00 GALVANIZING

SPECIFICATION 60 46 00 CLEANING AND PAINTING STEEL

SPECIFICATION 60 48 00 STRUCTURAL FIELD WELDING

SPECIFICATION 60 64 00 REINFORCED CONCRETE PIPE

SPECIFICATION 60 66 00 HDWLLS WINGWALLS

SPECIFICATION 60 68 00 SLUICE GATES

SPECIFICATION 60 69 00 SLUICE GATE MAINTENANCE

SPECIFICATION 60 80 00 FLOODGATES

SPECIFICATION 60 96 00 REMOVING EXISTING STRUCTURES

DIVISION 90 - MISCELLANEOUS

SPECIFICATION 90 82 00 GEOTEXTILE FABRIC

SPECIAL DIVISIONS

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

LIST OF CONTRACT DRAWINGS

USIBWC Contract No.: IBM05D0001 Page 00.01.15 - 1

INTRODUCTORY INFORMATION 00.01.15

LIST OF CONTRACT DRAWINGS

The Contract Drawings applicable to this Contract are entitled: “United States Section International Boundary and Water Commission, Upper Rio Grande Flood Control Project, Rehabilitation of the Hatch-Tonuco, Texas, Doña Ana County, New Mexico.” An index of drawings is identified on the title sheet, and includes the following:

INDEX OF SHEETS-HATCH LEVEE SYSTEM

SHEET NO. DESCRIPTION

01.01 TITLE SHEET

02.01-02.04 PROJECT LAYOUT

02.05-02.07 SURVEY CONTROL SHEET LEVEE HW1 / BM DATA

03.01 GENERAL NOTES

04.01 ESTIMATE OF QUANTITIES

05.01-05.02 SUMMARY OF LEVEE

05.03 SUMMARY OF SMALL STRUCTURES

06.01 EXISTING TYPICAL SECTIONS

06.02-06.03 PROPOSED TYPICAL SECTIONS

07.01-07.17 ALIGNMENT DATA SHEETS

08.01-08.66 PLAN & PROFILE – LEVEE

08.67-08.69 PLAN & PROFILE – INTERSECTING ROADS

08.70-08.93 PLAN & PROFILE – ACCESS RAMPS

09.01-09.26 BOG LOGS

10.01-10.177 CROSS SECTIONS

11.01 MISCELLANEOUS SIGN DETAILS

11.02 MISCELLANEOUS LEVEE DETAILS

12.01-12.05 STRUCTURE LAYOUTS

12.06-12.15 CULVERT LAYOUT

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

LIST OF CONTRACT DRAWINGS

USIBWC Contract No.: IBM05D0001 Page 00.01.15 - 2

12.16-12.32 STRUCTURE DETAILS

12.33-12.34 FLOOD GATE DETAILS

13.01-13.02 EROSION CONTROL (SW3P)

14.01 EPIC

15.01 SEQUENCE OF WORK

15.02-15.09 BARRICADES / TRAFFIC CONTROL

15.10-15.12 SIGN STANDARDS

-END OF SPECIFICATION-

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNEL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

LIST OF SCHEDULES

USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 1

INTRODUCTORY INFORMATION 00.01.20

LIST OF SCHEDULES

1. Schedule of Submittals. For this Project, the requirements for submittals are identified on the Contract Drawings and Technical Specifications (Divisions 01, 31, 34, 35, 50, 60, and 90). For this project, a schedule of submittals includes, but may not be limited to the following: (The Contractor shall refer to each Technical Specification for a full description of applicable submittals and submittal requirements.)

SPECIFICATION Submittal 01 32 00 Construction Progress Documentation Progress Schedule 01 39 00 Safety Accident Prevention Plan 01 46 00 Quality Control / Quality Assurance Contractor Quality Control Plan, Certifications for Testing Personnel

01 56 00 Barricades and Signs Traffic Control, Barricade and Signing Plans

Written Certification of Temporary Barriers

01 57 00 Temporary Erosion, Sedimentation, And Environmental Controls

FEM Qualifications

SW3P

Construction Plan 01 59 00 Temporary Controls For Work Areas / Project-Specific

Locations Staging Area Plan Layout

SW3P

Hazardous Materials Tests

Hazardous Waste Manifests 01 69 00 Control of Materials Materials Source Identification and Certifications 01 70 71 Field Engineering Survey Plan and Submittals 01 71 70 Mobilization 01 77 00 Contract Close-Out As-Built Plans, Reports, Drawings

Final Inspection / Testing Records 31 11 00 Preparing Right of Way 31 14 00 Remove / Stockpile Existing Materials 31 81 00 Proof Rolling 31 92 00 Vegetation for Erosion Control Seeding Plan/ Seeds of Designated

Plants 34 01 00 Clean Existing Channel

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNEL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

LIST OF SCHEDULES

USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 2

SPECIFICATION Submittal 35 41 00 Construction Of Levee Plan of Operations, Testing Facilities, Testing Results for Classification of Fill Material, Nuclear-Density Operator

Certification, Test Results for Construction, Designs and Details for Contractor Repairs, Dewatering Controls, Excavation or Fill Support Details

Moisture Content Adjustment Plan

35 42 00 Rip Rap Geotextile Membrane Shop Drawing, Data, Product Warranty

& Certification Submittal 35 43 00 Toe Drain Manufacturer’s Literature, Samples, & Written Material Specs

Sequence of Toe Drain Installation 35 44 00 Gabion Mattress and Block Alternative Wire Fasteners

Supplier’s Certification 50 20 00 Roadway Base Test Results for Material 50 91 00 Provide and Install New Traffic Signs Manufacturer’s Certification 50 94 00 Delineator and Object Marker Assemblies Manufacturer’s Certification 60 64 00 Reinforced Concrete Pipe Manufacturer’s Compliance

Certificate for Jointing Materials 60 66 00 Headwalls and Wingwalls 60 68 00 Sluice Gates Gate and Lift Mechanism Shop

Drawings & Submittals Design Calculations

Manufacturer’s Qualifications 60 69 00 Sluice Gate Maintenance 60 80 00 Floodgate Shop Drawings, Data, Product

Warranty & Certification 60 96 00 Removing Existing Structures

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNEL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

LIST OF SCHEDULES

USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 3

2. Schedule of Assemblies, Materials, and Estimated Quantities. For this Project, the schedules of assemblies, material specifications and associated estimated quantities are identified on the Contract Drawings and Technical Specifications (Divisions 01, 31, 34, 35, 50, 60, and 90). Estimated quantities for each Bid Item are shown on Plan Sheet No. 4.01; and estimated quantities are also summarized by plan sheet on Plan Sheet Nos. 5.01-5.03.

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNEL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

LIST OF SCHEDULES

USIBWC Contract No.: IBM05D0001 Page 00.01.20 - 4

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

EXISTING CONDITION INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.19 - 1

AVAILABLE INFORMATION 00.31.19

EXISTING CONDITION INFORMATION

The existing condition of the levee has been evaluated by the Government, and is included in a report entitled “Condition Assessment of U.S. International Boundary & Water Commission, Texas and New Mexico Levees” by the US Army Corps of Engineers (USACE) dated June 2004, and the “Flood Simulation Study of Rio Grande Levees Near Las Cruces, New Mexico, Using Seismic and Electrical Geophysical Methods” dated May 2007.The applicable sections of this report are available to the Contractor for the purposes of understanding the existing condition of the levee within the project limits of this Contract. Additionally, geotechnical investigations were performed during the final design of the project, and the associated geotechnical data and reports are identified in 00.31.32 Geotechnical Data herein.

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

EXISTING CONDITION INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.19 - 2

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

SURVEY INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.21 - 1

AVAILABLE INFORMATION 00.31.21

SURVEY INFORMATION

For these Contract Drawings, surveying and data collection was performed as follows:

(1) Light Detection and Ranging (LIDAR) was obtained from the Government and used for preliminary information.

(2) Control was performed in April / May 2009 by Frank X. Spencer & Associates., who developed and provided the following (at .01-foot accuracy):

(a) Control. The surveyor established points at cross-roads to establish horizontal and vertical control; control sheets were developed for each control point set, signed and sealed by a New Mexico Registered Professional Land Surveyor (RPLS). The control sheet includes a drawing of the control point with a 3-point tie to existing physical features, description of the control point, X,Y & Z coordinates and the coordinate system. Plan Sheet No. 2.08- 2.09, within the Contract Drawings includes the control information data for all the control points set for the project, signed and sealed by the RPLS.

(b) Benchmarks. The surveyor established bench marks along project limits; vertical benchmarks were set at 1000-foot intervals at the right of way (ROW) line of the levee reach. A tabulation of the benchmarks is shown on the Plan Sheets within the Contract Drawings.

(3) Ultimately, an aerial survey (at 0.1-foot accuracy) was performed in April / May 2009 by Martinez Corporation who developed and provided the following, which was used as the basis of design:

(a) Field Control for Photogrammetry. The surveyor set panels for aerial photogrammetry along the levee reach for a low-level flight (1500 feet). Panels were set along the flight path at 800-foot intervals and wing panels were set at cross-roads or 2400-foot intervals.

The surveyor performed a global positioning (GPS) survey to establish x-y-z coordinates of the panel points.

(b) Aerial Photogrammetry. The aerial photogrammetry was developed as follows:

1. Black and white photography at a 1-inch = 250-foot photo scale (1500 feet above ground level (AGL))

2. Data Processing. The aerial photography was scanned at 12 microns to produce 0.25-foot pixel resolution; aerial triangulation process was performed to orient individual stereo pairs.

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

SURVEY INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.21 - 2

3. Planimetric and Topographic Data Compilation. Planimetric and topographic data was compiled (suitable for 1-inch = 50-foot map scale showing 1-foot contours.

4. Digital Orthophotos. A digital elevation model (DEM) or digital terrain model (DTM) was created for the project area to support the orthophoto rectification; rectified mosaic digital images to hold 0.25-foot ground pixel resolutions suitable for a 1-inch = 50-foot map scale.

(4) Supplemental ground surveys were performed by SLI Engineering Inc., and Frank X. Spencer & Associates. Data as follows:

(a) Voids. A topographic survey was performed by the surveyors to fill-in the voids of the aerial planimetrics; additionally, the surveyor performed topographic survey on existing structures, including bridges, inlets, culverts and irrigation structures.

(b) ROW Verification. The surveyors recovered and staked ROW points from available ROW maps supplied by the Government. This ROW information is shown on the plan / profile sheets of the Contract Drawings.

(c) Utility Survey. The surveyors coordinated with utility notification companies to get utilities marked in the field; the surveyor performed field location of underground utilities as marked by utility companies along the levee reach and intersecting streets. These locations are shown on the plan / profile sheets of the Contract Drawings. NOTE: IT IS THE

CONTRACTOR’S RESPONSIBILITY TO VERIFY LOCATIONS OF ALL EXISTING

UTILITIES (SHOWN AND NOT SHOWN ON THE CONTRACT DRAWINGS) PRIOR

TO CONSTRUCTION.

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

ENVIRONMENTAL DOCUMENT INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.24 - 1

AVAILABLE INFORMATION 00.31.24

ENVIRONMENTAL DOCUMENT INFORMATION

The Project’s environmental documents can be obtained from the United States International Boundary and Water Commission (USIBWC) and are available for the Contractor to review upon request.

1. Establishing and Acquisition Authorities. Various authorities include:

• Fish and Wildlife Act of 1956 [16 U.S.C. 742f (a) (4)], [16 U.S.C. 742f(b)(1)]

• An Act Authorizing the Transfer of Certain Real Property for Wildlife, or other purposes [16

U.S.C. 667b]

• Refuge Recreation Act, as amended [16 U.S.C. 460k-1], [16 U.S.C. 460k-2]

• Migratory Bird Treaty Act [16 U.S.C. 703]

• National Wildlife Refuge System Improvement Act of 1997

Abatement and Mitigation of Excessive or Unnecessary Noise. Minimize noise throughout all phases of the Contract. Exercise particular and special efforts to avoid the creation of unnecessary noise impact on adjacent noise sensitive receptors in the placement of non-mobile equipment such as air compressors, generators, pumps, etc. Place mobile and stationary equipment to cause the least disruption of normal adjacent activities.

All equipment associated with the work must be equipped with components to suppress excessive noise and these components must be maintained in their original operating condition considering normal depreciation. Noise attenuation devices installed by the manufacturer such as mufflers, engine covers, insulation, etc. must not be removed nor rendered ineffectual nor be permitted to remain off the equipment while the equipment is in use.

Preservation of Cultural and Natural Resources and the Environment. If the Contractor initiates changes to the Contract and IBWC approves the changes, the Contractor is responsible for obtaining clearances and coordinating with the appropriate regulatory agencies.

A. Cultural Resources. Cease all work immediately if a site, building, or location of historical, archeological, educational, or scientific interest is discovered within the right of way. The site, building, or location will be investigated and evaluated by IBWC.

B. New Mexico Environmental Department for the Pollutant Discharge Elimination System Permits and Storm Water Pollution Prevention Plans (SWP3). The contractor will file the Notice of Intent (NOI) and the Notice of Termination (NOT) for work shown on the plans in the right of way.

Adhere to all requirements of the SWP3.

C. Work in Waters of the United States. For work in the right of way, IBWC will obtain any required Section 404 permits from the U.S. Army Corps of Engineers before work begins. Adhere to all agreements, mitigation plans, and standard best management practices required by the permit.

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

ENVIRONMENTAL DOCUMENT INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.24 - 2

When Contractor-initiated changes in the construction method changes the impacts to waters of the U.S., obtain new or revised Section 404 permits.

D. Project-Specific Locations. For all project-specific locations (PSLs) on or off the right of way (material sources, waste sites, parking areas, storage areas, field offices, staging areas, haul roads, etc.), signing the Contract certifies compliance with all applicable laws, rules, and regulations pertaining to the preservation of cultural resources, natural resources, and the environment as issued by the following or other agencies:

• Occupational Safety and Health Administration,

• New Mexico Environmental Department,

• New Mexico Department of Transportation,

• New Mexico Commission of Public Records (Historical),

• New Mexico Energy, Minerals, and Natural Resources Department,

• New Mexico States Parks Department,

• New Mexico Department of Fish and Game,

• New Mexico-NCRS Natural Conservation Resources Service,

• U.S. Army Corps of Engineers,

• U.S. Department of Energy

• U.S. Department of Transportation,

• U.S. Environmental Protection Agency,

• U.S. Federal Emergency Management Agency, and

• U.S. Fish and Wildlife Service.

All subcontractors must also comply with applicable environmental laws, rules, regulations, and requirements in the Contract. Maintain documentation of certification activities including environmental consultant reports, Contractor documentation on certification decisions and contacts, and correspondence with the resource agencies. Provide documentation upon request.

Obtain written approval from the Engineer for all PSLs in the right of way not specifically addressed in the plans. Prepare an SWP3 for all Contractor facilities, such as asphalt or concrete plants located within IBWC right of way. Comply with all permit requirements for portable facilities, such as concrete batch plants, rock crushers, asphalt plants, etc. Address all environmental issues, such as Section 404 permits, wetland delineation, endangered species consultation requirements, or archeological and historic site impacts. Obtain all permits and clearances in advance.

2. Other considerations. The Contractor is required to adhere to the following:

(a) Ensure that all Environmental Permits, Issues, and Commitments (EPIC), which are included within the PS&E are followed and implemental to ensure potential impacts are avoided.

- END OF SPECIFICATION -

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

EXISTING HAZARDOUS MATERIAL INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.26 - 1

AVAILABLE INFORMATION 00.31.26

EXISTING HAZARDOUS MATERIAL INFORMATION

There is no available information regarding hazardous materials within / adjacent to the Project limits and/or right of way.

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

EXISTING HAZARDOUS MATERIAL INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.26 - 2

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

GEOTECHNICAL DATA

USIBWC Contract No.: IBM05D0001 Page 00.31.32 - 1

AVAILABLE INFORMATION 00.31.32

GEOTECHNICAL DATA

Geotechnical investigations were performed by Raba-Kistner Consultants, Inc.

The Contractor may request a copy of the report from the Government for their review and use.

The data and report are not intended as a representation or warranty of continuity of conditions between soil borings nor of groundwater levels at dates and times other than date and time when measured. The Government will not be responsible for interpretations or conclusions drawn there from by the Contractor. Data are solely made available for the convenience of Contractor. Additional test borings and other exploratory operations may be made by Contractor subsequent to award of the Contract at no additional cost to the Government.

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

GEOTECHNICAL DATA

USIBWC Contract No.: IBM05D0001 Page 00.31.32 - 2

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

PERMIT APPLICATION

USIBWC Contract No.: IBM05D0001 Page 00.31.43 - 1

AVAILABLE INFORMATION 00.31.43

PERMIT APPLICATION

No information is available regarding required permit applications. The Contractor will be required to research the need for any required permits. For the Work under this Contract, the Contractor shall be responsible for coordinating and obtaining all permits required by Federal, state, and local entities.

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

PERMIT APPLICATION

USIBWC Contract No.: IBM05D0001 Page 00.31.43 - 2

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

OTHER PROJECT INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 1

AVAILABLE INFORMATION 00.31.50

OTHER PROJECT INFORMATION

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

OTHER PROJECT INFORMATION

USIBWC Contract No.: IBM05D0001 Page 00.31.50 - 2

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

DIVISION 01-

USIBWC Contract No.: IBM05D0001 GENERAL REQUIREMENTS

US INTERNATIONAL BOUNDARY & WATER COMMISSION

GOVERNING TECHNICAL SPECIFICATIONS AND PROVISIONS

DIVISION 01 – GENERAL REQUIREMENTS

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

DIVISION 01-

USIBWC Contract No.: IBM05D0001 GENERAL REQUIREMENTS

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

IDENTIFICATION OF TECHNICAL SPECIFICATIONS

USIBWC Contract No.: IBM05D0001 Page 01.01.00 - 1

SPECIFICATION 01.01.00

IDENTIFICATION OF TECHNICAL SPECIFICATIONS

This specification provides for the identification and introduction to the technical specifications and related information, and includes the following:

1.1 Governing Technical Specifications

1.2 Related Documents & Provisions

1.3 Provisions for Measurement and Payment

1.4 Specification / Bid Item Format and Conventions

PART 1 - GENERAL

1.1 GOVERNING TECHNICAL SPECIFICATIONS

A. All technical specifications applicable to this Contract are identified as follows:

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SPECIFICATION 00 01 01 PROJECT TITLE

SPECIFICATION 00 01 10 TABLE OF CONTENTS

SPECIFICATION 00 01 15 LIST OF CONTRACT DRAWINGS

SPECIFICATION 00 01 20 LIST OF SCHEDULES

SPECIFICATION 00 31 19 EXISTING CONDITION INFORMATION

SPECIFICATION 00 31 21 SURVEY INFORMATION (RIGHT OF WAY)

SPECIFICATION 00 31 24 ENVIRONMENTAL ASSESSMENT INFORMATION

SPECIFICATION 00 31 26 EXISTING HAZARDOUS MATERIAL INFORMATION

SPECIFICATION 00 31 32 GEOTECHNICAL DATA

SPECIFICATION 00 31 43 PERMIT APPLICATION

SPECIFICATION 00 31 50 OTHER PROJECT INFORMATION

DIVISION 01 - GENERAL REQUIREMENTS

SPECIFICATION 01 01 00 IDENTIFICATION OF TECHNICAL SPECIFICATIONS

SPECIFICATION 01 19 00 SCOPE OF WORK

SPECIFICATION 01 27 00 MEASUREMENT AND PAYMENT

SPECIFICATION 01 31 00 PROJECT MANAGEMENT AND COORDINATION

SPECIFICATION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION

SPECIFICATION 01 33 00 SUBMITTALS

SPECIFICATION 01 39 00 SAFETY

SPECIFICATION 01 42 00 REFERENCES

SPECIFICATION 01 46 00 QUALITY CONTROL / QUALITY ASSURANCE

SPECIFICATION 01 56 00 BARRICADES AND SIGNS

SPECIFICATION 01 57 00 TEMPORARY EROSION, SEDIMENTATION AND

ENVIRONMENTAL CONTROLS

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

IDENTIFICATION OF TECHNICAL SPECIFICATIONS

USIBWC Contract No.: IBM05D0001 Page 01.01.00 - 2

SPECIFICATION 01 59 00 TEMPORARY CONTROLS FOR WORK AREAS /

PROJECT-SPECIFIC LOCATIONS

SPECIFICATION 01 69 00 CONTROL OF MATERIALS

SPECIFICATION 01 70 00 MOBILIZATION

SPECIFICATION 01 71 00 FIELD ENGINEERING

SPECIFICATION 01 77 00 CONTRACT CLOSE-OUT

DIVISIONS 31 / 34 - SITE GRADING

SPECIFICATION 31 11 00 PREPARING RIGHT OF WAY

SPECIFICATION 31 14 00 REMOVE / STOCKPILE EXISTING MATERIALS

SPECIFICATION 31 81 00 PROOF ROLLING

SPECIFICATION 31 92 00 VEGETATION FOR EROSION CONTROL

SPECIFICATION 34 01 00 CLEAN EXISTING CHANNEL

DIVISION 35 - WATERWAY / MARINE

SPECIFICATION 35 41 00 CONSTRUCTION OF LEVEE

SPECIFICATION 35 42 00 RIPRAP

SPECIFICATION 35 43 00 TOE DRAIN

SPECIFICATION 35 41 20 GABION

DIVISION 50 - ROADWAY CONSTRUCTION

SPECIFICATION 50 20 00 ROADWAY BASE

SPECIFICATION 50 91 00 PROVIDE AND INSTALL NEW TRAFFIC SIGNS

SPECIFICATION 50 94 00 DELINEATOR AND OBJECT MARKER

DIVISION 60 - STRUCTURES

SPECIFICATION 60 10 00 EXCAVATION AND BACKFILL FOR STRUCTURES

SPECIFICATION 60 20 00 CONCRETE STRUCTURES

SPECIFICATION 60 21 00 HYDRAULIC CEMENT CONCRETE

SPECIFICATION 60 40 00 REINFORCING STEEL

SPECIFICATION 60 42 00 METAL FOR STRUCTURES

SPECIFICATION 60 45 00 GALVANIZING

SPECIFICATION 60 46 00 CLEANING AND PAINTING STEEL

SPECIFICATION 60 48 00 STRUCTURAL FIELD WELDING

SPECIFICATION 60 64 00 REINFORCED CONCRETE PIPE

SPECIFICATION 60 66 00 HDWLLS WINGWALLS

SPECIFICATION 60 68 00 SLUICE GATE

SPECIFICATION 60 69 00 SLUICE GATE MAINTENANCE

SPECIFICATION 60 80 00 FLOODGATES

SPECIFICATION 60 96 00 REMOVING EXISTING STRUCTURES

DIVISION 90 - MISCELLANEOUS

SPECIFICATION 90 82 00 GEOTEXTILE FILTER FABRIC

B. In any case where these technical specifications conflict with the Federal Acquisition Regulations

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

IDENTIFICATION OF TECHNICAL SPECIFICATIONS

USIBWC Contract No.: IBM05D0001 Page 01.01.00 - 3

(FAR), FAR requirements will take precedence. In any case where FAR requirements are more strict or impose a higher standard than these technical specifications, FAR requirements will take precedence.

1.2 RELATED DOCUMENTS & PROVISIONS

Other related documents describing the requirements for the Work to be performed include the construction drawings entitled “UPPER RIO GRANDE FLOOD CONTROL PROJECT –

REHABILITATION IMPROVEMENTS FOR THE RIO GRANDE CANALIZATION

PROTECTION LEVEE SYSTEM, HATCH LEVEE SYSTEM, FROM HATCH SIPHON TO

BIGNELL ARROYO, DONA ANA COUNTY, NEW MEXICO”, the technical specifications, and the associated provisions included in the Contract.

1.3 PROVISIONS FOR MEASUREMENT AND PAYMENT

For Work performed by the Contractor under this Contract, the identified technical specifications (as shown in paragraph 1.1 herein) are those under which payment is to be made to the Contractor.

Measurement and payment of work shall be in accordance with SPECIFICATION 01 27 00 of this Contract.

1.4 SPECIFICATION / BID ITEM FORMAT AND CONVENTIONS

A. Specification Format. The technical specifications are organized into Divisions, and identified in

Level 2 title format, using the Construction Specifications Institute’s (CSI) "MasterFormat – 2004 Edition" numbering system. For this Contract, the Divisions are grouped in two categories: (1) Standard Divisions, which are Divisions identified and defined by CSI, and (2) Special Divisions, which are Divisions that have been developed using industry standards, for some unique items of Work under this Contract.

B. Bid Item Format. Bid Items under this Contract have been derived from the governing specifications identified in paragraph 1.1 herein. Bid Items are numbered in Level 3 title format, using CSI’s “MasterFormat – 2004 Edition" numbering system. All Bid Items are identified in Section B of the Contract Provisions.

PART 2 – MATERIALS & EQUIPMENT (Not Applicable To This Specification)

PART 3 – CONSTRUCTION (Not Applicable To This Specification)

PART 4 – MEASUREMENT AND PAYMENT (Not Applicable To This Specification)

- END OF SPECIFICATION –

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

IDENTIFICATION OF TECHNICAL SPECIFICATIONS

USIBWC Contract No.: IBM05D0001 Page 01.01.00 - 4

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

SCOPE OF WORK

USIBWC Contract No.: IBM05D0001 Page 01.19.00 - 1

SPECIFICATION 01.19.00

SCOPE OF WORK

This specification includes descriptions and requirements for the following:

1.1 Related Documents

1.2 Work Covered by the Contract Documents

1.3 Sequence of Work / Time for Completion of Work

1.4 Work Under Other Contracts

1.5 Materials and Equipment

1.6 Use of Right-of-Way

1.7 Occupancy of Right-of-Way

1.8 Work Restrictions

2.0 Materials and Equipment (Not Applicable to this Specification)

3.0 Construction Methods (Not Applicable to this Specification)

4.0 Measurement and Payment (Not Applicable to this Specification)

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

The following may not include all related documents, contract clauses, & technical specifications, and does not relieve the Contractor of the responsibility of performing work associated with this specification in accordance with all terms of the Contract herein.

A. Related documents: As described in paragraph 1.2 of SPECIFICATION 01 01 00.

B. Contract: Section I “Specifications and Drawings for Construction”

C. Technical Specifications: All

1.2 WORK COVERED BY THE CONTRACT DOCUMENTS

A. Project Identification. The Project to be constructed under this Contract is identified as follows:

(1) Name of Project - “UPPER RIO GRANDE FLOOD CONTROL PROJECT, REHABILITATION OF HATCH-TANUCO LEVEE SYSTEM” and,

(2) Location of Project –Doña Ana, New Mexico.

B. General Description of Work. The Work consists of the rehabilitation of the Hatch-Tanuco Levee System, for a total reach of 14.34 miles. The majority of the proposed improvements include reconstruction of the existing earthen levee system. Major construction efforts include:

(1) Proposed Raising Existing Levee, PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

SCOPE OF WORK

USIBWC Contract No.: IBM05D0001 Page 01.19.00 - 2

(2) Proposed New Levee,

(3) Proposed Installing a Clay Cap to the Existing Levee,

(4) Proposed Floodgates, and floodwalls where shown on the plans,

(5) Various appurtenances to the levee (sluice gates, pipe crossings, connecting roadways, etc.)

are to be rehabilitated also, to accommodate the new height of the levee.

(6) New or Refurbished Road Signs.

1.3 SEQUENCE OF WORK / TIME FOR COMPLETION OF WORK

A. The Work is to be performed in sequence as shown on the plans.

B. The Work under this Contract shall be completed within the contract calendar days.

1.4 WORK UNDER OTHER CONTRACTS

No work is anticipated to be performed at the Project site, under separate contract with other contractors, during the Contractor’s performance under this Contract.

1.5 MATERIALS AND EQUIPMENT

A. Materials Ordered in Advance. The Government has not negotiated any purchase orders in advance for suppliers of materials and equipment to be incorporated into the Work.

B. Other Government-Furnished Materials. The Government will not provide any materials for the Work.

C. Materials and Equipment to be Furnished by the Contractor.

(1) The Contractor shall provide all materials and equipment required to execute the Project.

(2) All materials provided by the Contractor for the Project shall be new or recycled, high grade, free from defects, meeting the specifications herein. Quality of the Work shall be in accordance with the specifications herein. The testing company will ensure that materials, equipment, and Work quality strictly adhere to the requirements of the Contract documents.

(3) Materials, equipment, and work quality not conforming to the requirements of these specifications shall be considered defective and will be subject to rejection. Defective Work material, whether in place or not, or equipment shall be removed immediately from the site by the Contractor, at its expense, when so directed by the CO.

(4) If the Contractor fails to replace any defective or damaged work, materials or equipment

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

SCOPE OF WORK

USIBWC Contract No.: IBM05D0001 Page 01.19.00 - 3 after receiving notice, the CO may cause such work or materials to be replaced by other forces. The replacement expense shall be deducted from the amount to be paid to the Contractor. Defective equipment will not be allowed in the performance of any work.

1.6 USE OF RIGHT-OF-WAY

The Contractor shall limit use of the right-of-way to that which is indicated in the construction drawings, so as to allow for the USIBWC’s use and occupancy. Contractor operations shall be confined to the Project site and other areas permitted and identified by the construction drawings.

Portions of the site beyond areas on which the work is to be performed are not to be disturbed. Roads serving the facility, and identified as such, shall be clear and available to the USIBWC as indicated in the construction drawings.

1.7 OCCUPANCY OF RIGHT-OF-WAY

A. Partial Government Occupancy. The Government may need to occupy the right-of-way during the entire construction period, with the exception of areas under construction. The Contractor shall cooperate with the Government during construction operations to minimize conflicts and facilitate Government access. The Contractor needs to maintain existing access to the facility, unless otherwise indicated in the construction drawings. The Contractor shall provide not less than seventy-two (72) hours notice to the Government of construction activities that will affect any Government activities.

B. Government Occupancy of Completed Areas of Construction. The Government reserves the right to occupy and to place and install equipment in completed areas of the facility, before Substantial Completion, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the total Work.

1.8 WORK RESTRICTIONS

A. On-Site Work Hours. The Contractor’s attention is directed to the Contract Provisions.

B. Irrigation Pipe. Irrigation structures are owned by others. The work to be performed on irrigation structures shall be performed in accordance with the irrigation owner’s restrictions.

C. Cutting the Levee for Structure Improvements. In some instances, the work may require cutting the levee. This Work may not be performed during hurricane season or periods of known heavy rains or flooding.

PART 2 – MATERIALS & EQUIPMENT (Not Applicable To This Specification)

PART 3 – CONSTRUCTION METHODS (Not Applicable To This Specification)

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

SCOPE OF WORK

USIBWC Contract No.: IBM05D0001 Page 01.19.00 - 4

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

MEASUREMENT AND PAYMENT

USIBWC Contract No.: IBM05D0001 Page 01.27.00 - 1

SPECIFICATION 01.27.00

MEASUREMENT AND PAYMENT

This specification identifies administrative and procedural requirements for measurement of the work and payment to the Contractor for Work performed, and includes the following:

1.1 Related Documents

1.2 Measurement of Quantities

1.3 Scope of Payment

1.4 Measurement and Payment for Changes in Work

1.5 List of Bid Items

2.0 Materials and Equipment (Not Applicable to this Specification)

3.0 Construction Methods (Not Applicable to this Specification)

4.0 Measurement and Payment (Not Applicable to this Specification)

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

The following may not include all related documents, contract clauses, & technical specifications, and does not relieve the Contractor of the responsibility of performing work associated with this specification in accordance with all terms of the Contract herein.

A. Related documents: As described in paragraph 1.2 of SPECIFICATION 01 01 00.

B. Contract: Section I, “Specifications and Drawings for Construction”

C. Technical Specifications: All

1.2 MEASUREMENT OF QUANTITIES

The Government will measure all completed work using US standard measures. The method of measurement for each Bid Item is identified under the applicable technical specifications and the unit of measure is identified in the Summary of Quantities in the plans sheets in the contract documents.

1.3 SCOPE OF PAYMENT

Payment to the Contractor shall be at the Unit Price for each Bid Item, and shall, in general, be considered full compensation for all materials, equipment, labor, tools, supplies, and incidentals necessary to complete the Bid Items and the Work under the Contract. The method of payment for each Bid Item is further identified under the applicable technical specifications and the Unit Price set forth in the Bid Schedule of the Contract Documents. Payment of the Unit Price for each Bid Item will be payment in full for this Contract. All costs and expenses for which no specific Unit Price is set forth in the Bid Schedule shall be considered subsidiary, and included in the Unit Prices that are applicable and specifically set forth in the Bid Schedule, and no additional payment will be made therefore.

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

MEASUREMENT AND PAYMENT

USIBWC Contract No.: IBM05D0001 Page 01.27.00 - 2

1.4 MEASUREMENT AND PAYMENT FOR CHANGES IN WORK

Measurement and payment to the Contractor for extra work directed and incorporated by Construction Change Directive, performed by the Contractor, and compliance-confirmed by the Government or COR, will be made in accordance with the provisions of the Contract.

1.5 LIST OF BID ITEMS

The items to be bid by the Contractor for the performance of Work under this Contract are located under SECTION B of the Contract.

PART 2 – MATERIALS & EQUIPMENT (Not Applicable To This Specification)

PART 3 – CONSTRUCTION METHODS (Not Applicable To This Specification)

PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

PROJECT MANAGEMENT AND COORDINATION

USIBWC Contract No.: IBM05D0001 Page 01.31.00 - 1

SPECIFICATION 01.31.00

PROJECT MANAGEMENT AND COORDINATION

This specification identifies administrative provisions for coordinating construction operations while the Work is being performed by the Contractor, and includes the following:

1.1 Related Documents

1.2 Coordination

1.3 Project Meetings

1.4 Requests for Information

2.0 Materials and Equipment (Not Applicable to this Specification)

3.0 Construction Methods (Not Applicable to this Specification)

4.0 Measurement and Payment

PART 1 – GENERAL

1.1 RELATED DOCUMENTS

The following may not include all related documents, contract clauses, & technical specifications, and does not relieve the Contractor of the responsibility of performing work associated with this specification in accordance with all terms of the Contract herein.

A. Related documents: As described in paragraph 1.2 of SPECIFICATION 01 01 00.

B. Contract: Section I, “Specifications and Drawings for Construction”

C. Technical Specifications: 01 19 00 Scope of Work 01 27 00 Measurement and Payment 01 32 00 Construction Progress Documentation 01 33 00 Submittals 01 57 00 Temporary Erosion, Sedimentation, and Environmental

Controls Written Health and Safety Plan Divisions 31, 33, 34, 35, 50, 60 and 90

1.2 COORDINATION

In general, construction operations shall be coordinated to ensure efficient and orderly installation of each part of the work. In addition to a Project Superintendent, the Contractor shall provide other administrative and supervisory personnel as required for proper coordination and administration of the work. The Contractor’s Project Superintendent shall be available to the Government during business hours, as well as emergency contact. Other coordination responsibilities and activities required to be provided by the Contractor includes the following:

A. The Contractor shall be responsible for ascertaining the nature and extent of any simultaneous, PROTECTIVE LEVEE – HATCH LEVEE SYSTEM

FROM HATCH SIPHON TO BIGNELL ARROYO

Contract No. IBM05D0001 Order No. IBM09T0030

PROJECT MANAGEMENT AND COORDINATION

USIBWC Contract No.: IBM05D0001 Page 01.31.00 - 2 collateral, and essential work by others. The Government, its workers and contractors, and others, shall have the right to operate within or adjacent to the Construction site to perform such work.

B. In accordance with the provisions and time frames stated in SPECIFICATION 01 32 00, the Contractor shall submit to the COR a proposed Schedule of Work. This Schedule of Work shall be in the form as described in SPECIFICATION 01 32 00, and shall reflect all coordination efforts of the Work under this Contract.

1.3 PROJECT MEETINGS

All meetings, unless otherwise directed shall be scheduled and conducted at the locations requested (Most meeting will take place at the US-IBWC American Dam Field Office in El Paso, Texas). The COR shall inform participants and others involved, and individuals whose presence is required, of date and time and location of each meeting. The COR shall prepare the meeting agenda, and distribute to all invited attendees. The “Government’s Construction Management Contractor” shall record significant discussions and agreements achieved, and distribute the meeting minutes to everyone concerned, within seven (7) calendar days of the meeting. The following meetings are anticipated, and the Contractor shall identify them in the Schedule of Work:

A. Preconstruction Conference. A preconstruction conference shall be scheduled by the CO prior to the start of construction, but no later than fifteen (15) calendar days after Government receipt of acceptable payment and performance bonds and proof of insurance. The preconstruction conference will be held at the American Dam Field office in El Paso, Texas (located at 2616 W.

Paisano Drive, El, Paso, Texas) unless otherwise specified on the letting/bidding documentation.

The purpose of the meeting is to introduce project personnel and review responsibilities and procedures. The Contractor shall provide a copy of his Draft Schedule of Work as specified under SPECIFICATION 01 32 00, Construction Progress and Documentation.

(1) Attendees - Authorized representatives of the Government (including the COR), the Engineer, the Contractor’s Superintendent, major subcontractors, suppliers; and other concerned parties shall attend the conference. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.

(2) Agenda – Discussion of items of significance that could affect the Work and project, including the following: introduction / designation of key personnel and their duties; review of the Draft Schedule of Work, phasing, critical work sequencing and long-lead items; review of procedures for handling and processing field decisions, Change Orders, RFIs, testing and inspection, applications for payment, and submittals; preparation of record documents; use of right-of-way; work restrictions; USIBWC and others occupancy requirements; responsibilities for temporary facilities and controls; construction waste management and recycling; field office, parking, Work, and storage areas; equipment and materials deliveries and priorities;

safety and first aid; security; maintenance of project site; and…