HVAC Line Replacements Scope~1.docx

DOCX document 15 KB Posted

Attached to
Open Market Small Purchase IL|26-444DHS-MENTH-P-97218
Contract number
26-444DHS-MENTH-P-97218
Issued by
Illinois

About this file

This is a Scope of Work document outlining HVAC line replacement services for a government facility. The document does not specify particular states, agencies, consortiums, or companies involved, presenting instead a general statement of work for facility improvements.

The scope encompasses the replacement and insulation of HVAC dual purpose heating and cooling water lines across three facility locations: the Infirmary (approximately 60 linear feet of supply and return lines serving two fan coils with two isolation valves), the Doctor's Office (approximately 40 linear feet of supply and return lines serving two fan coils with two isolation valves), and Staff Development (approximately 20 linear feet of supply and return lines serving one fan coil). The work requires coordination with the facility schedule and necessitates a scheduled shutdown during mild weather. Priority shall be given to isolation valve installation to restore HVAC operations as quickly as possible. The document does not specify pricing, contract amounts, option periods, renewals, or set-asides.

View the file

Other files

File Type Posted
Standard Terms and Conditions v.23.2~52.pdf PDF
RMU150~45.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace HVAC Dual Purpose Heating/Cooling Water Lines

1. Infirmary Replace and insulate ¾” supply and return lines to (x2) Fan coils (approx. 60’) Install one isolation valve near the main supply and return (x2)

2. Doctor office Replace and insulate ¾” supply and return lines to (x2) Fan coils (approx. 40’) Install one isolation valve near the main supply and return (x2)

3. Staff development Replace and insulate ¾” supply and return lines to fan coil (approx. 20’)

Project shall be coordinated with facility schedule

Project initiation requires a scheduled shutdown on a mild weather day

Isolation valve installation shall be priority so HVAC operation can resume asap