HVAC Line Replacements Scope~1.docx
DOCX document 15 KB Posted
- Contract number
- 26-444DHS-MENTH-P-97218
- Issued by
- Illinois
About this file
This is a Scope of Work document outlining HVAC line replacement services for a government facility. The document does not specify particular states, agencies, consortiums, or companies involved, presenting instead a general statement of work for facility improvements.
The scope encompasses the replacement and insulation of HVAC dual purpose heating and cooling water lines across three facility locations: the Infirmary (approximately 60 linear feet of supply and return lines serving two fan coils with two isolation valves), the Doctor's Office (approximately 40 linear feet of supply and return lines serving two fan coils with two isolation valves), and Staff Development (approximately 20 linear feet of supply and return lines serving one fan coil). The work requires coordination with the facility schedule and necessitates a scheduled shutdown during mild weather. Priority shall be given to isolation valve installation to restore HVAC operations as quickly as possible. The document does not specify pricing, contract amounts, option periods, renewals, or set-asides.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Standard Terms and Conditions v.23.2~52.pdf | ||
| RMU150~45.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace HVAC Dual Purpose Heating/Cooling Water Lines
1. Infirmary Replace and insulate ¾” supply and return lines to (x2) Fan coils (approx. 60’) Install one isolation valve near the main supply and return (x2)
2. Doctor office Replace and insulate ¾” supply and return lines to (x2) Fan coils (approx. 40’) Install one isolation valve near the main supply and return (x2)
3. Staff development Replace and insulate ¾” supply and return lines to fan coil (approx. 20’)
Project shall be coordinated with facility schedule
Project initiation requires a scheduled shutdown on a mild weather day
Isolation valve installation shall be priority so HVAC operation can resume asap
File details come from the government source that posted it. Updated .