USC-9_Pre-Sol_Mtg_Summary.pdf

PDF 21 KB Posted

Attached to
Universal Service Contract (USC)-9 Federal contract opportunity
Solicitation number
HTC71119RW001
Issued by
Department of Defense United States Transportation Command

About this file

This document summarizes a pre-solicitation conference for the Universal Service Contract (USC)-9. The conference provided updates on performance measures, claims timelines, periods of performance, and small business subcontracting requirements for the new contract. Estimated transit times were analyzed using over 600,000 lanes of historical shipment data and will be used to set more accurate required delivery dates. The carrier composite score calculation and performance evaluation criteria were adjusted to better reward performance on specific lanes. The claims timeline was changed to three years for both government and carriers. The base period of performance is one year with four one-year unpriced options and potential industry days. Additional meetings are needed to address invoicing issues. The proposal deadline was moved to January to allow more time for carrier submissions. The government will consider supporting documentation for increases to government-set accessorial rates.

USC-9 Pre-Solicitation Conference Meeting Minute Summary

View the file

Other files for this federal contract opportunity

Other files attached to Universal Service Contract (USC)-9, newest first.
File Type Posted
USC-9_Other_Than_Full_and_Open_JA_Redacted.pdf PDF
USC-9_Other_Than_Full_and_Open_FINAL_JA_(Signed).pdf PDF
USC-9_RFP_Q&As_(3).pdf PDF
USC-9_RFP_Q&As_(1).pdf PDF
12_RFP_USC-9_PWS_Att_6_Inv_and_Pay.pdf PDF
18_RFP_USC-9_PWS_Att_12_Trade_zones.pdf PDF
14_RFP_USC-9_PWS_Att_8_DLA_PV.pdf PDF
17_RFP_USC-9_PWS_Att_11_Definitions.pdf PDF
04_RFP_USC-9_Exhibit_2_Additional_USC-9_Info.pdf PDF
08_RFP_USC-9_PWS_Att_2_Operational_Reports.pdf PDF
11_RFP_USC-9_PWS_Att_5_Route_Info.pdf PDF
21_RFP_USC-9_Exhibit_4_Ordering_Procedure.pdf PDF
01_RFP_USC-9_1449_and_Clauses.pdf PDF
23_RFP_DD-254_USC-9.pdf PDF
20_RFP_USC-9_PWS_Att_14_SHARP.pdf PDF
USC-9_Synopsis.pdf PDF
02_USC-9_Exhibit_3_PWS.pdf PDF
14_USC-9_PWS_Att_11_Definitions.pdf PDF
16_USC-9_Exhibit_4_Ordering_Procedures.pdf PDF
03_USC-9_Exigency_Annex.pdf PDF
04_USC-9_PWS_Att_1_EDI.pdf PDF
09_USC-9_PWS_Att_6_Inv_and_Pay.pdf PDF
USC-9_PWS_Att_8_DLA_PV_(Clean_Version).pdf PDF
USC-9_PWS_Att_8_DLA_PV_(Tracked_Changes).pdf PDF
USC-9_Draft_RFP_Comment_Matrix.xlsx XLSX spreadsheet
02_USC-9_Exhibit_3_PWSDRAFT.pdf PDF
04_USC-9_PWS_Att_1_EDIDRAFT.pdf PDF
08_USC-9_PWS_Att_5_Route_InfoDRAFT.pdf PDF
00_a_USC-9_1449_and_Clauses_Draft.pdf PDF
00_b_USC-9_Exhibit_1_Instructions_and_Eval_CriteriaDRAFT.pdf PDF
15_USC-9_PWS_Att_12_Trade_zonesDRAFT.pdf PDF
05_USC-9_PWS_Att_2_Operational_ReportsDRAFT.pdf PDF
09_USC-9_PWS_Att_6_Inv_and_PayDRAFT.pdf PDF
13_USC-9_PWS_Att_10_YubikeyDRAFT.pdf PDF
00_d_USC-9_Att_2_to_Exhibit_1,_Domestic_Shipyard_ReportDRAFT.pdf PDF
USC-9_Draft_PWS_Feedback_Matrix_(FBO).pdf PDF
00__USC-9_Exhibit_2_Additional_Clauses_DRAFT.pdf PDF
5__USC-9_PWS_Att_5_Route_Info_DRAFT.pdf PDF
1__USC-9_PWS_Att_1_EDI_DRAFT.pdf PDF
3__USC-9_PWS_Att_3_Rate_Rules_DRAFT.pdf PDF
13__USC-9-_Exigency_Annex_DRAFT.pdf PDF
4__USC-9_PWS_Att_4_City_Groups_DRAFT.pdf PDF
6__USC-9_PWS_Att_6_Inv_and_Pay_DRAFT.pdf PDF
9__USC-9_PWS_Att_9_NIST.SP.800-171-POAM_DRAFT.pdf PDF
10__USC-9_PWS_Att_10_Yubikey_DRAFT.pdf PDF
11__USC-9_PWS_Att_11_Definitions_DRAFT.pdf PDF
8__USC-9_PWS_Att_8_DLA_Prime_Vendor_DRAFT.pdf PDF
0__Exhibit_3_PWS_USC9_DRAFT.pdf PDF
12__USC-9_PWS_Att_12_Trade_zones_DRAFT.pdf PDF
7__USC-9_PWS_Att_7_EPAs_DRAFT.pdf PDF
Show all 50

Universal Service Contract (USC)-9 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBJECT: USC-9 Pre-Solicitation Conference Date: 13 September 2018

Summary of Items discussed:

Topic: RDD Construction

- Historical EDI data analyzed from a 5 year period. More than 600k lanes of data were analyzed.

The output of the analysis is an excel data table, providing estimate times for end-to-end moves and for major checkpoints along the way. These times were then averaged across all shipments on the same route. Standard deviation was also calculated for the averages. This table is the basis for revising the current Customer Advisory to reflect updated travel times.

- This will be used as a planning tool for the Government when setting RDDs. It’s not a guarantee or entitlement for setting RDDs. Carriers will still have the ability to counter an RDD if they can’t meet it.

- The Government will review updated data sets when needed; next review after 6 months to determine if the transit times have changed.

- The goal of analyzing this data and setting updated transit times was to avoid unrealistic RDDs.

Topic: Performance Measures and Composite Score

- The BVN calculation for the composite score will change to 90% lane score and 10% world score. The goal of this change is to reward better performance on specific lanes. Shippers are concerned with performance on the lane they use and carriers don’t want a difficult lane to affect their high volume lanes.

- Within the EDI factor, the weight for submission and timeliness is changing to 50/50, from 80/20.

With more emphais on timeliness, the timeline to submit EDI is changing to 48 hours.

- Industry had a concern with timeliness credit when a TCN needs to be corrected due to Government fault. The Government is looking into how to address this issue in the system.

- Industry wanted the Government to look at weighting price and performance differently in the BVN calcuation. However, the Government analyzed the data and determined that this would not change the outcome and felt that the current calculation demonstrates the Government’s desire to have price and performance equal in importance.

- One-Time-Only evaluations will include BVN. The Government will look to include a requirement for vessel sharing agreements, when applicable.

Topic: D-RAP

- D-RAPS should be submitted as delays occur for visibility of delays and invoicing purposes.

They will be processed by the Ordering Officers. For missed RDD credit, requests are to be submitted through CPP for COR review.

Topic: Claims Timeline

- Moving to a 3 year claims timeline for both Government and Carriers. Timeline is the only change we are making; all other processes will remain as they are today.

- Industry was concerned with the events that qualify to start the 3 year timeline. The Government response is that case law governs this and it’s unnecessary to put additional language in the contract.

Topic: Period of Performance

- Moving to a one-year base plus four one-year unpriced options with potential industry days as needed.

Topic: Small Business

- Subcontracting plan will be required in the solicitation. Difference from last time- FAR 19.704 requires you to address 15 elements (MUST ADDRESS)

Topic: Invoicing and Payment

- Discussion of invoicing issues. Additional meetings will be necessary to further investigate the problems relating to TIPP/BRT/invoices.

Topic: Milestones

- Due to waived OSD Peer Reviews, TCAQ is giving the carriers additional time to submit proposals in CARE. Deadline moved from November to January. More updates regarding the outcome/status of the VOLPE study will be given as they become available.

Topic: Government-Set Accessorials

- If carriers are able to provide documentation to support an increase in these rates, the Government will look at the data and consider an increase

Topic: Container Pools

- Potentially developing a customer advisory with a listing of the container pool locations

Topic: Shipment Liability

- Carriers interested in language mirroring the Multimodal language by incorporating a liability cap. The Government will look into this further.

Topic: Government Terminal Working Hours

- Carriers request removal of the language as it is not currently enforced. Government is looking at this.

Topic: Enhanced In Transit Visibility Pings

- Government looking at giving partial credit for 48 pings

Topic: Origin Services

- Notification for inability to spot a container went from 1 business day to 2 business days

Topic: Stow Plans

- Contract language removed

Topic: Origin Cutoff

- Clarified difference between origin cutoff and port cutoff. Carriers set the port cutoff.

Topic: Trucking Tables

- Updated for clarity

Topic: Supercargoes

- Potential notice or advisory regarding documentation requirements

Topic: Prime Vendor

- Leadership is engaged and working on a solution with DLA.