HTC711-15-R-R016
ATTACHMENT 7
QATAR Stevedoring and Related Terminal Services (S&RTS) AMENDMENT 01 – Summary of Changes
AMENDMENT SUMMARY: The purpose of this amendment is to revise the Performance Work Statement (PWS), Pricing Schedule (Schedule), and Provision 52.212-1 resulting from questions submitted in response to this solicitation. The following is a summary of the changes:
52.212-1
− 52.212.1(b)(4)(A)(6)(b): Changed documentary evidence from “proof of a valid port license” to “authorization to operate within the Port of Mesaieed as a registered agent”.
− 52.212.1(b)(4)(A)(6)(c): Changed documentary evidence from “proof of a valid Customs Broker License” to “capability to perform customs clearance through a licensed customs broker or clearing agency”.
PWS
− Performance Requirement Summary (PRS) #22: Corrected PWS reference from ¶
6.2.2.11 to ¶ 6.2.11.
− PRS #22: Removed covered storage from this objective as it does not apply in Qatar.
− ¶ 3.0: Removed “due 30 days after contract award”, relating to the written safety plan to align with the written safety plan being an evaluation factor.
− ¶ 3.6.1: Added compensation for inspecting cargo to be at the applicable Schedule 1 commodity rate.
− ¶ 3.7.4: Added ¶ 3.7.4.5, stating that compensation for Secondary Containment will be as an out-of-pocket expense under Schedule 8.
− ¶ 6.2.2.4: Clarified compensation for lashing and securing cargo on vessel is included within commodity rate in Schedule 1A.
− ¶ 6.2.2.7: Clarified compensation for staging will be under Schedules 2 & 4, where applicable.
− ¶ 6.2.8: Added Compensation for Inland Transportation shall be at the rates in Schedule
9, unless otherwise noted. Inserted ¶ 6.2.8.3, stating that compensation for unloading equipment at inland destination shall be at Schedule 4 rates.
− ¶ 6.2.13: Clarified compensation for in-stow inspections is included in commodity rate in Schedules 1A and B.
− ¶ 6.4.1.1: Added compensation for exclusive staging area shall be at the rates in Schedule 6.
− ¶ 6.4.1.2: Added “high speed” as the type of internet connection required.
− ¶ 6.4.2.1.4: Added “smart” and “email and internet capabilities” to description of cell phone. Clarified compensation for unit is under Schedule 6 and service is under Schedule 8.
− ¶ 6.4.2.1.5: Added paragraph for Fax machine, with basic functionality description.
− ¶ 6.6.2: Changed “obtain clearance of vessel” to “obtain cargo clearance”.
− Removed or corrected inconsistent use of unit of measure “Measurement Ton”, “M/T” and “MT”.
Pricing Schedule
− Schedule 6: Added line item 8 for Exclusive Use Hardstand Staging Area and line item 9 for Dunnage and Lashing Materials.
− Schedule 6: Added mobilization/demobilization to the description of line item 2 to highlight that rate should include that cost.
− Schedule 6: Changed unit of measure for line items 3 – 7 from “each” to “each per month”.
− Schedule 5: Removed “including reefers” from description of line items 1 – 17. Inserted line items 18 – 21 specifically for reefer containers storage.
− Schedule 4: Added “MOB/DEMOB” to the note to clarify equipment rates should include that cost.