Text of this file

Award-Term Evaluation Period Ends

Performance Evaluation Board (PEB) Convenes and Evaluates Contractor Performance

Other DHS Evaluation Data

Contractor Self-Assessment

Other Government Performance Information

PEB Determines Performance Ratings

PEB Chairperson Prepares Evaluation Ratings/ Documents

Preliminary Findings Briefing (PFB)

Preliminary Findings Briefing (PFB)

PEB Chairperson Provides Executive Agent (EA) with PFB for review/approval

EA reviews PFB submission

If not acceptable, EA sends PFB back to PEB Chairperson To correct until acceptable

If acceptable, EA will forward the PFB approval to PEB Chairperson for action

Government, led by EA, provides PFB to NBACC FFRDC Contractor

Contractor Decides to provide reclama

Contractor submits reclama to Government for consideration

Contractor elects not to submit reclama.

PEB finalizes PFB comments into Preliminary Report and submits to EA For review

PEB will evaluate reclama and generate PR for EA Review

EA reviews PR

Government will provide Contractor with Final PR for Evaluation Period

Preliminary Report (PR)

EA reviews PR

If acceptable, the EA will provide the PEB Chairperson with his written approval.

If not acceptable, the EA will send back to PEB Chairperson for corrections until acceptable

If acceptable, the EA will provide the PEB Chairperson with his written approval

If not acceptable, the EA will send back to PEB Chairperson until acceptable

Evaluation Process for the Semi-Annual Evaluation of Contractor Performance

Exhibit 1 to Attachment 5 to Award-Term Plan for NBACC FFRDC Management and Operations Project

Evaluation Process for the Annual Evaluation of Contractor Performance

Award-Term Evaluation Period Ends

Performance Evaluation Board (PEB) Convenes and Evaluates Contractor Performance

Contractor Self-Assessment

Other DHS Evaluation Data

Other Government Performance Information

PEB

Determines Ratings/Scores

PEB Chairperson Prepares Evaluation Ratings and Documents

Preliminary Findings Briefing (PFB)

Draft Final Performance Report (DFPR)

PEB Chairperson provides Executive Agent with PFB/DFPR for review/approval.

EA reviews

PFB/DFPR

If not acceptable, EA sends PFB/DFPR back to PEB Chairperson to correct until acceptable

If acceptable, EA will forward PFB/DFPR approval to PEB Chairperson for action.

Government, led by EA will provide PFB to NBACC FFRDC Contractor

Contractor Decides to Reclama

Contractor Elects to not submit reclama

Contractor elects to submit reclama

PEB Finalizes DFPR and submits to EA for review/approval.

EA reviews DFPR

Contractor submits Reclama to Government for consideration

PEB will evaluate reclama and will update the DFPR as required

EA Reviews DFPR

If acceptable, the EA will forward it onto the Term Determining Official for review

If not acceptable, the EA will send DFPR back to the PEB Chairperson until acceptable

If not acceptable, the EA will send back to PEB Chairperson until acceptable

FDO reviews

DFPR

If acceptable, the EA will forward it onto the Fee Determining Official

If TDO does not concur, he/she will provide comments and send back to EA until acceptable

If acceptable, TDO will approve the DFPR and provide written approval and comments to EA

EA prepares Final Performance Report and NBACC Debriefing based on the TDO comments

NBACC FPR Debriefing

Final Performance Report

EA provides CO with original signed copy of the written TDO determination

EA chairs a meeting with Contractor to conduct NBACC FPR Debriefing

CO issues contract modification for award-term

Exhibit 1 to Attachment 6 to Award-Term Plan for NBACC FFRDC Management and Operations Project

Other files for this federal contract opportunity

Other files attached to NBACC FFRDC, newest first.
File Type Posted
Final_RFP_Q A_Set_2.docx DOCX document
A9_SF30.pdf PDF
Final_RFP_Q A_Set_1_v5.docx DOCX document
A8_SF30.pdf PDF
Revised_Final_RFP_Executive_Summary_v1.docx DOCX document
A7_SF30.pdf PDF
Revised_Final_RFP_A14_PPQ.docx DOCX document
Amendment_000007_v1.docx DOCX document
Revised_Section_M_v1.docx DOCX document
Amendment_000006_v1.docx DOCX document
Updated_A6_Draft_SA_v2.docx DOCX document
Amendment_000005_v2.docx DOCX document
Updated_A3_AT_Plan_v1.docx DOCX document
Award_Term_Evaluation_Process_for_NBACC_v1.vsd VSD drawing
Revised_Final_RFP_A1_CDRL_Package_v2.xlsx XLSX spreadsheet
A4_Cover_Page_SF_30.pdf PDF
Updated_Final_RFP_Section_H_v1.docx DOCX document
Updated_Final_RFP_Section_C_v1.docx DOCX document
Updated_Final_RFP_Section_D_v1.docx DOCX document
Revised_Final_RFP_A13_v1.docx DOCX document
Updated_Attachment_16_for_Final_NBACC_RFP.txt TXT text file
Amendment_000002_SF_30_Cover.pdf PDF
Amendment_000002.docx DOCX document
Updated_Final_RFP_Section_L.docx DOCX document
A1_Cover_Page_SF_30.pdf PDF
Amendment_000001.docx DOCX document
Final_RFP_Section_G.docx DOCX document
Award_Fee_Evaluation_Process_for_NBACC.vsd VSD drawing
Final_RFP_A3_AT_Plan.docx DOCX document
Final_RFP_Section_B.docx DOCX document
Final_RFP_Section_K.docx DOCX document
Final_RFP_A9_GFI_List.docx DOCX document
Final_RFP_Section_I.docx DOCX document
Final_RFP_A10_Draft_DD254.pdf PDF
Final_RFP_A4_Cost_Charts.xlsx XLSX spreadsheet
Final_A6_Draft_SA.docx DOCX document
Final_RFP_A20_BQSF.docx DOCX document
Final_RFP_Section_H.docx DOCX document
Final_RFP_Section_L.docx DOCX document
Attachment_1_to_CDRL_Package.docx DOCX document
Section_A_Cover_Page.docx DOCX document
Final_RFP_Section_A.pdf PDF
Final_RFP_A7_NBACC_Photo.docx DOCX document
Final_RFP_A21_Table_T1.xlsx XLSX spreadsheet
Final_RFP_A16_SCA_WD.pdf PDF
Final_RFP_Section_E.docx DOCX document
Final_RFP_A15_WEE.docx DOCX document
Final_RFP_A13_Contract_Directives_List.docx DOCX document
Final_RFP_Executive_Summary.docx DOCX document
Final_RFP_A11_OSHA_Form_300A.xls XLS spreadsheet
Show all 50

NBACC FFRDC has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .