CGC_SAGINAW_VENDOR_QUESTIONS_-_AMEND_0004.docx
DOCX document 18 KB Posted
- Attached to
- CGC SAGINAW Drydock Repairs
- Solicitation number
- HSCG85-16-Q-P45019
About this file
CGC SAGINAW VENDOR QUESTONS AMENDMENT 0004
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CGC_SAGINAW_AMEND_0004.docx | DOCX document | |
| CGC_SAGINAW_AMEND_0003.docx | DOCX document | |
| CGC_SAGINAW_VENDOR_QUESTIONS_-_AMEND_0003.docx | DOCX document | |
| CGC_SAGINAW_AMEND_0002.docx | DOCX document | |
| CGC_SAGINAW_VENDER_QUESTIONS.docx | DOCX document | |
| CGC_SAGINAW_Attachment_2_-_SCHEDULE_OF_SUPPLIES_For_Amend_-_2.docx | DOCX document | |
| CGC_SAGINAW_SPEC_REV-2.pdf | ||
| AMEND_0001_SAGINAW.docx | DOCX document | |
| SAGINAW_FY16_DD_-_SOLICITATION_AMENDMENT.docx | DOCX document | |
| CGC_SAGINAW_Attachment_3_-_GOVERNMENT_PROPERTY_REPORT.docx | DOCX document | |
| SAGINAW_(WLIC_160B)_DD_SPEC.pdf | ||
| CGC_SAGINAW_Attachement_5_-_PAST_PERFORMANCE_INFORMATION_FORM.docx | DOCX document | |
| CGC_SAGINAW_Attachement_4_-_Request_for_Clarification.docx | DOCX document | |
| SAGINAW_FY16_DD_-__SOLICITATION.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question 13: LBP Abate; LBP Encapsulate Work Item 47 & 55 Work items state 300 SF of Abate WI 55 Encapsulate is not a single area with interferences.
Contractor has not been advised what areas will be selected and therefore no idea as to the extent of interference removal in way of selected area to price.
Can interferences be treated with a CFR and CR to be determined upon location(s) selected?
How does contractor price an unknown work scope?
This Optional item is related to another Optional Item, WI- 29, Inspect for Presence of Lead Based Paint. Both items are place in the spec based on the CG experience from another cutter. The interferences listed in the specs are the known interferences based on the anticipated areas where the possibilities of lead paint exist. KTR should price based on what is listed in both specs, up to 300 sq/ft of abatement and encapsulation, and listed interferences with the final price being adjusted based on the actual square footage needed upon activation.
Question 14: Lead Dust, Clean Work Item 30 Work Item states “clean and remove lead dust contamination ….up to 750 SF” Is there a known contamination associated with this work item? What action would cause this work item be activated? Also the note box states the 750SF will be broken into several smaller areas..And interferences are stated in 3.1.4, however, Contractor has no idea what areas will be selected and therefore no idea as to the extent of interference removal in way of selected area to price. Can interferences be treated with a CFR and CR to be determined upon location(s) selected?
How does contractor price an unknown work scope?
This Optional item is related to another Optional Item, WI- 29, Inspect for Presence of Lead Based Paint. This item is place in the spec based on the CG experience from another cutter. The interferences listed in the specs are the known interferences based on the anticipated areas where the possibilities of lead dust exist. KTR should price based on what is listed in the specs, up to 750 sq/ft of clean up and listed interferences with the final price being adjusted based on the actual square footage needed upon activation