CGC_SAGINAW_VENDOR_QUESTIONS_-_AMEND_0004.docx

DOCX document 18 KB Posted

Attached to
CGC SAGINAW Drydock Repairs
Solicitation number
HSCG85-16-Q-P45019
Issued by

About this file

CGC SAGINAW VENDOR QUESTONS AMENDMENT 0004

View the file

Other files

File Type Posted
CGC_SAGINAW_AMEND_0004.docx DOCX document
CGC_SAGINAW_AMEND_0003.docx DOCX document
CGC_SAGINAW_VENDOR_QUESTIONS_-_AMEND_0003.docx DOCX document
CGC_SAGINAW_AMEND_0002.docx DOCX document
CGC_SAGINAW_VENDER_QUESTIONS.docx DOCX document
CGC_SAGINAW_Attachment_2_-_SCHEDULE_OF_SUPPLIES_For_Amend_-_2.docx DOCX document
CGC_SAGINAW_SPEC_REV-2.pdf PDF
AMEND_0001_SAGINAW.docx DOCX document
SAGINAW_FY16_DD_-_SOLICITATION_AMENDMENT.docx DOCX document
CGC_SAGINAW_Attachment_3_-_GOVERNMENT_PROPERTY_REPORT.docx DOCX document
SAGINAW_(WLIC_160B)_DD_SPEC.pdf PDF
CGC_SAGINAW_Attachement_5_-_PAST_PERFORMANCE_INFORMATION_FORM.docx DOCX document
CGC_SAGINAW_Attachement_4_-_Request_for_Clarification.docx DOCX document
SAGINAW_FY16_DD_-__SOLICITATION.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question 13: LBP Abate; LBP Encapsulate Work Item 47 & 55 Work items state 300 SF of Abate WI 55 Encapsulate is not a single area with interferences.

Contractor has not been advised what areas will be selected and therefore no idea as to the extent of interference removal in way of selected area to price.

Can interferences be treated with a CFR and CR to be determined upon location(s) selected?

How does contractor price an unknown work scope?

This Optional item is related to another Optional Item, WI- 29, Inspect for Presence of Lead Based Paint. Both items are place in the spec based on the CG experience from another cutter. The interferences listed in the specs are the known interferences based on the anticipated areas where the possibilities of lead paint exist. KTR should price based on what is listed in both specs, up to 300 sq/ft of abatement and encapsulation, and listed interferences with the final price being adjusted based on the actual square footage needed upon activation.

Question 14: Lead Dust, Clean Work Item 30 Work Item states “clean and remove lead dust contamination ….up to 750 SF” Is there a known contamination associated with this work item? What action would cause this work item be activated? Also the note box states the 750SF will be broken into several smaller areas..And interferences are stated in 3.1.4, however, Contractor has no idea what areas will be selected and therefore no idea as to the extent of interference removal in way of selected area to price. Can interferences be treated with a CFR and CR to be determined upon location(s) selected?

How does contractor price an unknown work scope?

This Optional item is related to another Optional Item, WI- 29, Inspect for Presence of Lead Based Paint. This item is place in the spec based on the CG experience from another cutter. The interferences listed in the specs are the known interferences based on the anticipated areas where the possibilities of lead dust exist. KTR should price based on what is listed in the specs, up to 750 sq/ft of clean up and listed interferences with the final price being adjusted based on the actual square footage needed upon activation