CGC WILLIAM TATE FY11 DS SPECIFICATION REV-1.doc
DOC document 1 MB Posted
- Attached to
- CGC WILLIAM TATE FY11 DOCKSIDE REPAIRS
- Solicitation number
- HSCG85-11-Q-P45T71
About this file
Specification Rev1/April 12 2011
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30_Amendment_A00002_.doc | DOC document | |
| 175-WLM_930_1_2_-_K1.dwf | DWF file | |
| 175-WLM_930_1_2_-_K1 pdf - Adobe Acrobat Standard.pdf | ||
| SF30 Amendment A00002 .doc | DOC document | |
| SF30 Amendment A00001 .doc | DOC document | |
| CGC WILLIAM TATE FY11 DS RFQ.pdf | ||
| CGC WILLIAM TATE FY11 DS - SPECIFICATION R-0.pdf | ||
| CGC WILLIAM TATE FY11 DS SCHEDULE.xls | XLS spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC WILLIAM TATE (WLM-175) DOCKSIDE AVAILABILITY 2011
USCGC WILLIAM TATE (WLM 560)
175 FOOT COASTAL BUOY TENDER
SPECIFICATION FOR DOCKSIDE REPAIRS
Developed By: Miguel K. Augustin (Rev-1, 12 April 2011)
TABLE OF CONTENTS
iiiRevisions Record ivConsolidated List of References viiConsolidated List of Government-furnished Property ixConsolidated List of Critical Inspection Items xPrincipal Characteristics
1General Requirements
9WORK ITEM 1: Tanks (Potable Water), Clean and Inspect
11WORK ITEM 2: Circuit Breakers (60 Hz), Inspect and Test
15WORK ITEM 3: Compressed Air Receivers , Clean, Inspect , and Test
WORK ITEM 4: Single Point Davit, Level 2 Inspect and Repair 22WORK ITEM 5: Grey Water Piping , Clean and Flush
WORK ITEM 6: Sewage Piping , Clean and Flush WORK ITEM 7: Main Diesel Engine (MDE) Exhaust Stack Uptakes , Commercial Clean WORK ITEM 8: Ship Service Diesel Generator (SSDG) Exhaust Piping , Commercial Clean WORK ITEM 9: SW Heat Exchangers , Clean , Inspect and Hydro WORK ITEM 10: Tanks (Fuel), Preserve “ 100% WORK ITEM 11: Warping Capstan, Level 2 Inspect and Repair 44WORK ITEM 12: Hydraulic Power Unit Insulation Valves, Install
WORK ITEM 13: Crossdeck Winches, Overhaul WORK ITEM 14: Hydraulic Inhaul Winch, Overhaul WORK ITEM 15: Propulsion Shaft Bulkhead Seals , Upgrade WORK ITEM 16: Deck Covering ( Electrical Matting ) , Renew WORK ITEM 17: Tanks (Potable Water), Preserve 100% WORK ITEM 18: Tanks ( Potable Water ), Preserve “ Partial ” WORK ITEM 19: Hydraulic Chain Stoppers, level 2 Inspect and Repair WORK ITEM 20: Window Wiper Modifications, Install WORK ITEM 21: Deck Covering (Wet/Dry), Renew WORK ITEM 22: Oil Containment Coaming Renewal WORK ITEM 23: Raised Scuttle Replacement WORK ITEM 24: Engine Room Bilge , Clean and Inspect WORK ITEM 25: Decks - Exterior, Preserve ( “MIL-Spec/ Flight Deck” System) WORK ITEM 26: Buoy Cane, Inspect and Repair
Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
| DATE |
| REV# |
| WORK ITEM# |
| CHANGES MADE |
| 05APR11 |
| 1 |
| 4 |
| Modified entire spec |
| 05APR11 |
| 1 |
| 26 |
| Added WI 26 |
| 08 APR11 |
| 1 |
| 21 |
| Updated paragraph 3.2.3 |
| 12 APR11 |
| 1 |
| 11 |
| Modified entire spec |
| 12 APR11 |
| 1 |
| 12 |
| Added OEM and Phone number in GFP Table. Revised paragraph 3.5 (flushing). |
| 12 APR11 |
| 1 |
| 13 |
| Modified entire spec |
| 12 APR11 |
| 1 |
| 14 |
| Modified entire spec |
| 12 APR11 |
| 1 |
| 19 |
| Modified entire spec |
| 12 APR11 |
| 1 |
| 21 |
| Modified entire spec |
| 12 APR11 |
| 1 |
| 26 |
| Modified entire spec |
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
Consolidated List of References
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free or charge. Other Government documents may be accessed – free of charge – as follows:
· MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
· Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
· Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws:: www.gpoaccess.gov The Government is aware of the following internet web links where contractors may procure commercial specifications:
· American Welding Society (AWS): http://www.awspubs.com/index.php
· ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
· NFPA: http://www.nfpa.org
· SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 201-001, Rev C, Machinery Spaces Arrangment Coast Guard Drawing 175 WLM 243-202, Rev F, Propulsion Shaft Arrangement Coast Guard Drawing 175 WLM 244-001, Rev -, 4.48” ND Type Bulkhead Seal Coast Guard Drawing 175 WLM 256-001, Rev H, Seawater Cooling System Diagram Coast Guard Drawing 175 WLM 256-003, Rev D, Seawater Cooling System FR 61 Forward Coast Guard Drawing 175 WLM 256-004, Rev J, Seawater Cooling System Arrangements and Details Coast Guard Drawing 175 WLM 256-005, Rev -, Z-Drive Lube Oil Heat Exchanger Tube Bundle, Replacement and Piping Mods Coast Guard Drawing 175 WLM 256-012, Rev A, Auxiliary Seawater System Piping Mods Coast Guard Drawing 175 WLM 259-001, Rev A, Combustion Exhaust Diagram Coast Guard Drawing 175 WLM 259-005, Rev C, Combustion Exhaust A&D, Hull Block 970 Coast Guard Drawing 175 WLM 320-001, Rev U, Electrical One-line Diagram Coast Guard Drawing 175 WLM 320-007, Rev P, Power System Deck Plan 01 Level and Above Coast Guard Drawing 175 WLM 533-006, Rev D, Independent Tank Potable Water Hb 950 Coast Guard Drawing 175 WLM 549-001, Rev D, Onboard Lubrication Requirements Coast Guard Drawing 175 WLM 551-001, Rev H, Compressed Air System Diagram Coast Guard Drawing 175 WLM 556-008, Rev-, Isolation Valves for Deck Machinery Hydraulic Power Unit Coast Guard Drawing 175 WLM 573-050, Rev A, Hydraulic Piping Installation for Chain Stopper Coast Guard Drawing 175 WLM 573-051, Rev B, Chain Stopper Structural Modifications for Hydraulic Roller Assembly Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage and Waste Water System Diagram Coast Guard Drawing 175 WLM 601-001, Rev L, General Arrangement and Inboard and Outboard Profiles Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Plans Coast Guard Drawing 175 WLM 625-001, Rev K, Windows and Portlights Coast Guard Drawing 175 WLM-74-1, Rev A, Radiographic Inspection Hull Welds Coast Guard Drawing 175 WLM-900-1, Rev B, Hull Block Plan Coast Guard Drawing 175-WLM 167-1, Rev -, Structural Closures Coast Guard Drawing 175-WLM 320-1, Rev U, Electrical One-Line Diagram Coast Guard Drawing 175-WLM 506-8, Rev -, Oil Containment Coamings Coast Guard Drawing 175-WLM 635-1, Rev -, Hull Thermal & Acoustic Insulation Schedule Coast Guard Drawing 175-WLM 549-001, Rev D, Onboard Lubrication Requirements Coast Guard Drawing 175-WLM 573-001, Rev K, Buoy Deck Arrangement Coast Guard Drawing 175-WLM 593-001, Rev G, Sewage & Waste Water System Diagram Coast Guard Fleet Drawing FL-2605-29, Rev H, Chain Stopper System – Rising Sheave Assembly Coast Guard Fleet Drawing FL-2605-30, Rev B, Chain Stopper Plate for Hydraulic Roller Assembly Coast Guard Drawing 175 WLM-930-001, Rev K, Sheet 2, Hull 930 Panels
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and Color Manual Coast Guard Technical Publication (TP) 3498, Section A, Feb 2008, Buoy Chain Winch Coast Guard Technical Publication (TP) 3613, Tab 243-B, Bulkhead Seal Coast Guard Technical Publication (TP) 3619, 13-AUG-98, Manufacturers Instruction Book-SWBS Group(s) 324 Coast Guard Technical Publication (TP) 3627, Mar 2007, SWBS 556, Tab 556A - Deck Equipment Hydraulic Power Unit Coast Guard Technical Publication (TP) 3631, Mar 2007, Manufacturer’s Instruction Book-SWBS Group(s) 573-581, Section B, Cross Deck Winch Coast Guard Technical Publication (TP) 3632, Feb 2001, Chapter 583, Section C, Technical Manual for Slewing Arm Davit Model D6000CT Coast Guard Technical Publication (TP) 3632, Section 582-A, Sep 1999, Manufacturer's Instruction Book-SWBS Groups 582-583, Aft Capstan Coast Guard Technical Publication (TP) 3939, Apr 2007, Section 573-A, Rising Sheave Chain Stopper Coast Guard Technical Publication (TP) 4609, July 2006, Wynn Installation and Operation Manual Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 6341, Jan 2009, Install New Deck Covering Systems Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC STD SPEC 0740), Jan 2009, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Auxiliary Machine Systems Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), Jan 2009, Temporary Hull Accesses Surface Forces Logistics Command (SFLC) Naval Engineering Directive (NED) 5735-01, Inspection and Test Procedure For Buoy Chain Winch Model CW-1 Onboard WLM 551-564 and WLB 201-215, May 2010
OTHER REFERENCES
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System Components - Health Effects ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2008, Occupational Safety and Health Standards for Shipyard Employment Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety Administration, Department Of Transportation Commercial Item Description (CID) A-A-59588, Jul 2005, Rubber Silicone DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric MIL-PRF-24667, Jun 2005, Coating system, Non-Skid, for Roll or Spray Application MIL-PRF-900, Mar 1991, Rubber Gasket Material, 45 Durometer Hardness MIL-STD-1689, Nov 1990, Fabrication, Welding and Inspection of Ships Structure National Electrical Manufacturers Association (NEMA) Stds, Pub. No. AB4, 2003, Guidelines for Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and Industrial Applications
QPL-24667, May 2006, Qualified Product List of Products Qualified under Performance Specification MIL-PRF-24667, Coating system, Non-Skid, for Roll or Spray Application Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), Jan 2009, Install New Deck Covering Systems The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2004, Near-White Blast Cleaning Underwriters Laboratories Inc. (UL) 489, May 2002, Molded Case Circuit Breaker Wartsila Defense, Inc. Technical Manual for Type ND Seal
Consolidated List of Government-furnished Property
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
| WORK ITEM |
| MTI |
| ITEM DESCRIPTION |
| NSN/PN |
| QTY |
| ESTIMATED COST |
($/Unit)
| 4 |
| Y |
| Winch Assembly |
| NSN: 2030015051581 |
| 1 ea. |
| 17,454.50 |
| 4 |
| N |
| Swing Brake Seal Kit |
| NSN: 2030013512820 |
| 2 ea |
| 138.80 |
| 4 |
| N |
| Swing Brake Disc & Bearing Kit |
| NSN: 2030013499486 |
| 2 ea |
| 937.70 |
| 12 |
| N |
| Check Valve, In-line |
| PN: 123A-6 PL4354 (CPV MFG, Inc/800-386-8830) |
| 3 ea. |
| 400.00 |
| 14 |
| N |
| Roller bearing Unit |
(for Para. 3.2.1, Task #4)
| NSN:3130-01-504-4363 |
| 2 ea. |
| 4,012.00 |
| 14 |
| N |
| Grease seal |
(for Para. 3.2.1, Task #5)
| NSN:5330-01-462-5544 |
| 4 ea. |
| 79.25 |
| 14 |
| N |
| Level wind pivot bushing |
(for Para. 3.2, Task #6)
| PN:7101-573-1 PC-17 (Marinette Marine) |
| 1 ea. |
| 392.00 |
| 14 |
| N |
| Level wind thrust bearing |
(for Para. 3.2.1, Task #6)
| PN:7101-573-1 PC-16 (Marinette Marine) |
| 2 ea. |
| 249.00 |
| 14 |
| N |
| Hand Pump |
(for Para. 3.2.1, Task #7)
NSN:4320-01-015-9422
PN:P-18 (Enerpac, LTD_
| 1 ea. |
| 218.76 |
| 14 |
| Y |
| Level wind hydraulic cylinder |
(for Para. 3.2.1, Task #8)
| NSN: 3040-01-441-3721 |
| 1 ea. |
| 7,423.00 |
| 14 |
| N |
| 3:1 Pilot Ratio, Vented Counterbalance Valve Assembly |
(For Para. 3.2.1, Task #17)
| PN: CWEA-LHN (Sun Hydraulics Corp) |
| 1 ea |
| 98.70 |
| 14 |
| N |
| Fully Adjustable Needle Valve |
(for Para. 3.2.1, Task #17)
| PN: NFDC-LAN (Sun Hydraulics Corp) |
| 1 ea |
| 48.75 |
| 14 |
| Y |
| **Hydraulic Motor |
(for Para. 3.2.1, Task #21)
| NSN: 4320-01-441-3721 |
| 1 ea |
| 23,998 |
| 15 |
| N |
| Seal, Bulkhead Shaft (entire seal) H76287-01 |
| PN: OC 0000-01-LG9-4521 |
| 4 ea. |
| 20 |
| N |
| Wynn Window Wiper Assemblies, Straight Line, Type C |
| ACN: 2090-01-LG9-1208, |
-1209, -1210, -1211, -1212, -1213, -1214, -1215, -1216, -1217, -1218
| 11 ea. |
| 1,000.00 |
| 20 |
| N |
| Controllers |
| #1000 Model 1001 |
| 11 ea. |
| 2,000.00 |
| 23 |
| Y |
| Scuttle, 1.5” Raised, 18” dia, steel, w/coaming |
| NIN: 007275458 |
| 1 ea. |
| $937.25 |
| 26 |
| N |
| DCV |
| 2MP2220CHB3L24QQ0A |
| 1 ea. |
| $4000 |
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter
Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000_STD, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item Title
| 4 |
| Single Point Davit, Level 2 Inspect and Repair |
| 13 |
| Crossdeck Winches, Overhaul |
| 14 |
| Hydraulic Inhaul Winch, Overhaul |
| 16 |
| Deck Covering ( Electrical Matting ) , Renew |
| 19 |
| Hydraulic Chain Stoppers, level 2 Inspect and Repair |
26 Buoy Crane, Inspect and Repair
PC_175_WLM_310
Principal Characteristics
175' WLM BUOY TENDER
Physical Characteristics
| Length Overall |
| 174' 8" |
| Length between Perpendiculars |
| 155' 1" |
| Depth |
| 14' 8" |
| Maximum Beam |
| 36' 0" |
| Designed Draft |
| 8' 0" |
| Mast Height (Above 8' Waterline) |
| 58' 8" |
| Frame Spacing |
| 20" |
| Full Load Displacement |
| 906.42 long tons |
| Light Load Displacement |
| 840 long tons |
| Minimum Op Condition Displ |
| 870 long tons |
Machinery Characteristics
| Main Propulsion |
| Two Caterpillar 3508 DITA V-8 diesel; 999 BHP ea @ 1500 RPM |
Two Ulstein 360 degree steerable Z-Drives, 403 SRPM @ 1600 ERPM
| Reduction Gears |
| Two Z-Drive units, Cardan shafting; 3.973:1 gear ratio |
| Shaft Seal |
| John Crane Type ND |
| Shaft Bearings |
| Five pedestal mounted, Cooper split roller bearings |
| Number of Propellers |
| 2 |
| Number of Blades |
| 4 |
| Diameter |
| 57.1" |
| Rudders |
| None; Z-drive |
| Ship's Service Generators |
| Three Caterpillar Model 3406 DITA Turbocharged; 285KW, 450V, 60 Hz, 1800 RPM |
| Emergency Diesel Generator |
| One Caterpillar Model 3406 DIT 210 KW, 24V, 60 Hz, 1800 RPM |
Tank Capacities
| Diesel Oil Capacity (100%) |
| 16,385 gal |
| Fresh Water Capacity (100%) |
| 7,339 gal |
| Lubricating Oil (100%) |
| 86 gal |
00000_0310_FLT
REC_0000_FLT_ Commercial Project @ CG Facility (1209) General Requirements
1. SCOPE
1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability.
2. REFERENCES
Coast Guard Drawings None.
Coast Guard Publications Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes Other References Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety Administration, Department Of Transportation
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:
· Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.4 HW disposal. The Contractor shall be responsible for all hazardous wastes generated by work under this contract. Label and package all hazard wastes in 49 CFR-approved containers, and in accordance with all other applicable Federal, state, and local laws and regulations. In addition, comply with applicable parts of 40 CFR 262, applicable to handling of hazardous wastes.
3.4.1 Along with the Government, the Contractor shall be contractually considered the co-generator of all hazardous wastes; be aware that the Government will make available its facility’s EPA Generator Identification (ID) Number for manifesting of hazardous wastes.
3.4.2 The Contractor shall identify, arrange, and be responsible for the turnover of all hazardous wastes, within the confines of the Coast Guard shore facility, to the facility’s HM/HW Coordinator. Notify the ship’s HW Coordinator prior to any transfers of HW from ship to shore.
3.4.3 The Contractor shall prepare a manifest of hazardous waste to be reviewed and signed by the HM/HW Coordinator. Contact the HM/HW Coordinator for turnover of any hazardous waste; in addition, notify the COTR 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.4.4 The Contractor shall be aware of the following:
3.4.4.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COTR or KO-approval.
3.4.4.3 Local environmental regulations at the Government facilities may be more stringent than in many jurisdictions. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with, the local and state regulations.
3.4.4.4 Coast Guard facilities do not have Facilities Response Plans (see 33 CFR 154 Subpart F). It is the Contractor’s responsibility to furnish the Facility Response Plan (FRP) when required for over-the-water liquids transfers to and from vessels. This requirement is applicable to transfers to/from vessels with an oil/fuel capacity of 250 barrels or more.
4. NOTES
4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address: http://www.uscg.mil/directives/cim.asp
4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 0000 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
| Location of Work (incl. frame #’s) |
| Area (sqft) |
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).
Verify surface anchor profile using ASTM D4417-Methods B or C against COMDTINST M10360.3. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
| DATE & TIME |
| ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…) |
| LOCATION (Frame & Deck, relation to equipment, etc.) |
| TEMPERATURE |
| % REL. HUMID-ITY |
| DEW PT. |
| SURFACE |
| AMBIENT |
| ΔT |
| DP - Surface |
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
| Location of Work (Frame References) |
| Area (sqft) |
| SURFACE PREPARATION METHOD |
| PROFILE ACHIEVED (mils) |
| Min |
| Max |
| Mean |
| SSPC-SP-10/NACE No. 2 |
| ( |
| SSPC-SP-12/NACE No. 5 |
| ( |
| SSPC-SP-3 |
| ( |
| SSPC-SP-11 |
| ( |
| SSPC-SP-11 (inaccessible area) |
| ( |
| Brush-blasting (non-metallic substrate) |
| ( |
Abrasive Manufacturer and Sieve Size: _________________________________
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile Replica Tape Here
Reading:__________ mils Place Surface Profile Replica Tape Here
Reading:__________ mils Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils Place Surface Profile Replica Tape Here
Reading:__________ mils Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils Place Surface Profile Replica Tape Here
Reading:__________ mils Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils Place Surface Profile Replica Tape Here
Reading:__________ mils Place Surface Profile Replica Tape Here
Reading:__________ mils
Place Surface Profile Replica Tape Here
Reading:__________ mils Place Surface Profile Replica Tape Here
Reading:__________ mils Place Surface Profile Replica Tape Here
Reading:__________ mils
Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
| Location of Work (incl. frame #’s) |
| Area (sqft) |
| SURFACE PREPARATION METHOD |
| PROFILE ACHIEVED (mils) |
| Min |
| Max |
| Mean |
| SSPC-SP-10/NACE No. 2 |
| ( |
| SSPC-SP-12/NACE No. 5 |
| ( |
| SSPC-SP-3 |
| ( |
| SSPC-SP-11 |
| ( |
| SSPC-SP-11 (inaccessible area) |
| ( |
| Brush-blasting (non-metallic substrate) |
| ( |
Abrasive Manufacturer and Sieve Size: _________________________________
Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
| Reading: |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| Reading: |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| Reading: |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| Reading: |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| Reading: |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| Reading: |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| Reading: |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| Reading: |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| Reading: |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| Reading: |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
Mean Mil Reading (IAW ASTM D4417-Method B) for above 10 readings (by column):
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| _____ mils |
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
| Location of Work (incl. frame #’s) |
| Area (sqft) |
SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15
| DATE |
| TEST LOCATIONS |
| CONDUCTIVITY |
(microsiemens/cm)
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
| Coating Mfg |
| Product Name |
| Batch # |
| Induction Time |
| Coating System Sequence (Primer/Touchup/3rd Coat, etc.) |
Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2
| SPOT |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| AVERAGE VALUE |
*BASE METAL READING (BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
Location (Frame Reference): ___________________
| SPOT |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| Overall Avg. DFT |
| ADJUSTMENTS |
| Avg. BMR |
| Deviation |
| Before Adjustments |
| After Adjustments |
Avg.
| SPOT |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| Overall Avg. DFT |
| ADJUSTMENTS |
| Avg. BMR |
| Deviation |
| Before Adjustments |
| After Adjustments |
Avg.
| SPOT |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| Overall Avg. DFT |
| ADJUSTMENTS |
| Avg. BMR |
| Deviation |
| Before Adjustments |
| After Adjustments |
Avg.
| Application Method (Airless, Conventional Spray, Rolled) |
| Average DFT |
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
12314_DLA_0209_FLT
REC_12314_FLT/175’ WLM (ALL) (0310)
WORK ITEM 1: Tanks (Potable Water), Clean and Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
| TYPE OF TANK |
| LOCATION |
| CAPACITY - 100% |
(gallons)
LOW SUCTION
(gallons)
| Potable Water |
| 1-94-0-W |
| 2,167 |
| 68 |
| Potable Water |
| 2-36-1-W |
| 5,172 |
| 163 |
1.2 Government-furnished property.
None.
2. REFERENCES
Coast Guard Drawings Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Plans Coast Guard Drawing 175 WLM 533-006, Rev D, Independent Tank Potable Water Hb 950 Coast Guard Publications None.
Other References American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System Components - Health Effects American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities
3. REQUIREMENTS
3.1 General. The Contractor shall refer to Coast Guard drawings 175 WLM 601-003 and 175 WLM 533-006 for guidance. The Contractor shall notify the Dockmaster prior to filling or draining the potable water tank(s), when this item is being executed in a drydock availability. The Contractor shall accomplish the following for the tank(s) designated in paragraph 1.1 (Intent):
3.1.1 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs, to demonstrate existing operational condition. Submit a CFR.
3.1.2 Tank content removal. Remove and dispose of all fluids and/or residues in accordance with all applicable Federal, state, and local regulations.
3.1.3 Tank cleaning. Remove tank cover(s); clean tank interior surfaces free of all foreign materials, such as sediment or sludge. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.1.4 Inspection. Visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas, if any.
· Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
· Tank level indicator (TLI) and/or float switch condition (if applicable).
· Sounding tube and striker plate condition.
· Suction and discharge piping condition.
· Fastener material and condition (correct fastener material is stainless steel).
3.2 Tank closing. The Contractor shall ensure that the tank(s) remain open for approximately 24 hours after completion of the tasks specified above. Notify the COTR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to ANSI/NSF 61. Renew all stud cotton grommets (as applicable) upon reinstallation of manhole cover(s).
3.3 Tank disinfecting. After all other work involving the potable water system and tank closing have been completed, the Contractor shall disinfect and treat the affected potable water tank(s) and associated disturbed piping and components, as necessary, to meet or exceed the requirements of AWWA C652. After tank disinfecting; remove and dispose of all treated water in accordance with all Federal, state and local regulations.
NOTE
Ensure that no one enters the tanks once disinfection is completed.
3.4 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by Coast Guard personnel) of all designated tank TLIs to prove satisfactory operating condition. Submit a CFR.
4. NOTES
This section is not applicable to this work item.
32123_JSP_0309_175
WORK ITEM 2: Circuit Breakers (60 Hz), Inspect and Test
1.1 Intent. This work item describes the requirements for the Contractor to inspect and test circuit beakers (60 Hz) located on the Switchboards.
1.2 Government-furnished property.
None.
2. REFERENCES
Coast Guard Drawings Coast Guard Drawing 175-WLM 320-1, Rev U, Electrical One-Line Diagram Coast Guard Publications Coast Guard Technical Publication (TP) 3619, 13-AUG-98, Manufacturers Instruction Book-SWBS Group(s) 324 Other References National Electrical Manufacturers Association (NEMA) Stds, Pub. No. AB4, 2003, Guidelines for Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and Industrial Applications Underwriters Laboratories Inc. (UL) 489, May 2002, Molded Case Circuit Breaker
3. REQUIREMENTS
3.1 General. The Contractor shall provide skilled technicians, portable instrument standards and all necessary equipment to inspect and test circuit breakers designated in the work item. The Contractor may remove the circuit breakers from the vessel to a shoreside test facility. If this is done the Contractor shall exercise extreme care in transporting and reinstalling the circuit breakers to original operating condition on Switchboard.
3.1.1 Prior to any wiring disconnection and removal of circuit breakers, the Contractor shall record all wiring information, trip setting adjustments, and equipment locations necessary for use in later reinstallation. Retain all mounting and connecting hardware for later reuse. Submit a CFR.
3.1.2 Disconnect and remove the circuit breakers listed in the Table 1& 2. Coordinate the disconnection and removal of the circuit breakers with the COTR to minimize disruption of power. Temporarily cover or insulate switchboard or panel board openings created by the removal of circuit breakers to prevent personnel contact with energized conductors.
3.1.3 The Contractor shall notify the COTR 48 Hours prior to start work on this item.
3.2 Inspection requirement. The Contractor shall inspect all circuit breaker wire connectors, screws and plating and submit a CFR.
3.2.1 Surface burn marks and hairline cracks are acceptable but shall not deteriorate the mold surface or impair physical strength. Cracks are not permitted in wall section between phase and a ground plane when there is a conducting part in contact with the wall section. Cracks shall not exceed 0.75 inch in length, and in no case should be greater than 50 percent of the length of the surface in which the crack appears. Submit a CFR.
3.3 Circuit breaker testing. The contractor shall test circuit breakers listed in the Table 1&2 in accordance with the National Electrical Manufacturers Association (NEMA) AB 4 or UL 489 Molded Case Circuit Breakers. The test shall include, at a minimum:
· Mechanical Operation
· Insulation Resistance
· Individual Pole Resistance
· Inverse-Time Over current Tripping
· Instantaneous Over current Tripping
· Rated Hold-In Current (Note: Perform this test only on the circuit beakers which are tripping under normal load condition. The Coast Guard Inspector will identify the circuit beakers).
3.4 Circuit breaker data sheet. The contractor shall provide data sheet of each circuit breaker testing with the following information:
· Circuit Breaker Model and Serial Number
· Circuit Breaker Service
· Circuit Breaker Visual Condition
· Test Voltage/Test Amperes
· Type of Test/Test Method/Test Date/Name of Test Laboratory
· Result of Testing
3.5 Contractor’s option for circuits breaker renewal. The Contractor may elect to renew circuit breakers in lieu of testing (due to high cost of labor for testing or non available near by testing facilities) at no additional cost to the government. Ensure that all circuit breakers shall be UL 489 Certified.
TABLE 1 – circuit breaker list
| quantity |
| DESCRIPTION |
| siemens Part NO |
| service |
| location |
| 1 |
| 800 AF, 400 AMP |
| AS8AEXBA06DU4 |
| SS Switchboard Emergency Switchboard Bus Tie |
| Emergency Switchboard, 450 Volt Section |
| 1 |
| 800 AF, 375 AMP |
| AS8AEXBA06DU4 |
| Emergency Generator |
| Emergency Switchboard, 450 Volt Section |
| 2 |
| 800 AF, 500 AMP IT |
| PART No. ITE ED63M125 |
| Port/STBD Z-Drive Back Up Hydraulic LO Pump |
| Emergency Switchboard, 450 Volt Section |
| 2 |
| 125 AF, 125 AMP |
| ED63M125 |
| Fire Pump No.1&2 |
| Emergency Switchboard, 450 Volt Section |
| 1 |
| 125 AF, 100 AMP |
| ED63M100 |
| Engine Room Vital Panel |
| Emergency Switchboard, 450 Volt Section |
| 1 |
| 125 AF, 100 AMP |
| ED63M100 |
| Main Deck Vital Panel |
| Emergency Switchboard, 450 Volt Section |
| 1 |
| 125 AF, 20 AMP |
| ED63M020 |
| Chart Room Vital Panel |
| Emergency Switchboard, 450 Volt Section |
| 1 |
| 125 AF, 35 AMP |
| ED63M035 |
| Emergency Switchboard 120 Volt ABT |
| Emergency Switchboard, 450 Volt Section |
TABLE 2– circuit breaker list
| quantity |
| DESCRIPTION |
| siemens Part NO |
| service |
| location |
| 1 |
| 800 A, F400 AT |
| RL-AS8EAGXBA06E |
| Shore Power |
| Main Switchboard |
| 3 |
| 800 AF, 520 AT |
| RL-AS8EAEXBA06DUA |
| SSDG No.1,2&3 |
| Main Switchboard |
| 2 |
| 800 AF -Non Automatic |
| RL-AS8EXXXBXXXE |
| Bus Tie 1S-2S & 2S-3S |
| Main Switchboard |
| 1 |
| 800 AF, 700 AT |
| RL-AS8EAEXBA06DU4 |
| Distribution CB |
| Main Switchboard |
| 2 |
| 800 AF, 500 IT |
| PART No. ITE ED63M125 |
| Port /Stbd Z Drive, Backup Hydraulic/Lo Pump |
| Main Switchboard |
| 1 |
| 800 AF, 400 AT |
| RLAS8EAEXBA06DU4 |
| HPU Control Panel |
| SS Switchboard |
| 4 |
| 125 AF, 100 AT |
| ED23M100 |
| Engine Room Power Panels (P2&P5).First Platform Fwd Power Panel (P6) |
| SS Switch Board |
| 2 |
| 125 AF, 80 AT |
| ED23M080 |
| Pump Room Power Panel (P4) &02 Level Power Panel (P19) |
| SS Switchboard |
| 1 |
| 125 AF,125 AT |
| ED23M125 |
| Galley Power Panel (P10) |
| SS Switchboard |
| 1 |
| 250 AF, 200 AT |
| FXD63M200 |
| O1 Level Vent/Heater Panel (P17) |
| SS Switchboard |
| 2 |
| 125 AF, 50 AT |
| ED23M050 |
| Main&Lower Deck Vent Power Panel (P7 & P20) |
| SS Switchboard |
| 2 |
| 125 AF, 125 AT |
| ED23M125 |
| ABT(FF Control Panel) |
| SS Switchboard |
| 1 |
| 125 AF, 25 AT |
| ED23M025 |
| Galley Power Panel |
| SS Switchboard |
| 3 |
| 125 AF, 100 AT |
| ED23M100 |
| SS Switchboard, Engine Room Power Panel (P1), Main Deck Vital Power Panel (P8) |
| SS Switchboard |
| 1 |
| 125 AF, 20 AT |
| NOED23M020 |
| Chart Room Vital Panel (P15) |
| SS Switchboard |
| 1 |
| 125 AF, 35 AT |
| ED23M035 |
| Emergency Switchboard |
| SS Switchboard |
| 1 |
| 700 AT |
| PART No. XXX RL-AS8EAGXBA06E |
| SCR Drive |
| SS Switchboard |
| 1 |
| 125 AF, 50 AT |
| ED23M050 |
| Capstan |
| SS Switchboard |
| 1 |
| 125 AF, 100 AT |
| ED23M100 |
| RHIB Crane Hydraulic Power Unit |
| SS Switchboard |
| 9 |
| 125 AF, 100 AT |
| ED23M100 |
| Misc Power Panels |
| SS Switchboard |
3.6 Circuit Breaker Installation. After all testing is complete, reinstall circuit breakers using previously recorded wiring information to its original operating condition and Coast Guard TP 3619.
3.7 Operational test-post repairs. After completion of the work, the Contractor shall witness an operational test (by Coast Guard personnel) of all circuit breakers to prove satisfactory operating condition. Submit a CFR.
3.7.1 Operate each Circuit Breaker “ON” and “OFF” several times to exercise the circuit breaker and ensure that mechanical linkages are free.
3.7.2 Direction of Rotation Test – Perform a direction of rotation test on each new and disturbed three-phase motor circuit.
4. NOTES
This section is not applicable to this work item.
55100_MWC_0709_FLT
REC_55100_FLT_175 WLM (ALL) (0709)
WORK ITEM 3: Compressed Air Receivers , Clean, Inspect , and Test
1.1 Intent. The work item describes the requirements for the Contractor to clean, inspect, and test the below designated air receivers:
| SERVICE |
| LOCATION |
| QTY |
| OPERATING PRESSURE (psi) |
| Ship’s Service |
| 3-61-0-E |
| 2 |
| 250 |
| Ship’s Whistle |
| 02-52-1-Q |
| 1 |
| 140 |
2. REFERENCES
Coast Guard Drawings Coast Guard Drawing 175 WLM 551-001, Rev H, Compressed Air System Diagram Coast Guard Publications Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes Other References None.
3. REQUIREMENTS
3.1 General.
3.1.1 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences):
· Gauge lines
· Brackets
· Piping
3.1.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the compressed air system, to demonstrate existing operational condition. Submit a CFR.
3.2 Cleaning and inspection. The Contractor shall clean and inspect each designated air receiver (see paragraph 1.1 (Intent)) as follows.
3.2.1 System blowdown. Blowdown the air receivers and collect the blowdown (condensate) into a separate container for inspection.
3.2.2 Visual inspection. Visually inspect the blowdown (condensate) under a bright white light for oil or particulate contamination. Clean and visually inspect the internal and external surfaces of the air receiver for signs of corrosion, pitting, and other damage. Submit a CFR.
3.3 NDI. The Contractor shall perform NDI of the designated air receiver(s) in accordance with SFLC Std Spec 0740, Appendix C. Refer to Coast Guard Drawing 175 WLM 551-001 for guidance.
NOTE
Testing shall be accomplished by ultrasonic (UT), magnetic particle (MT), or hydrostatic testing. The Contractor may select either method to satisfy testing requirements.
3.3.1 Hydrostatic testing.
3.3.1.1 Isolate the air receiver by disconnecting all piping, relief valves, and pressure switches. Install pipe plugs/caps to prevent system contamination and in accordance with manufacturer’s testing procedures.
3.3.1.2 After all authorized repairs, hydrostatically test the air receiver using clean fresh water in accordance with SFLC Std Spec 0740, Appendix C and manufacturer’s recommended procedures. In the event a test pressure is not listed on the applicable drawing, test to 1½-times the nominal operating system pressure and hold for five minutes. Be aware that no leakage or permanent deformation of pressure-containing parts is permissible. Repair all leaks and discrepancies found. Submit a CFR.
CAUTION!
Instruments and equipment that might be damaged by clean fresh water shall be excluded from hydrostatic pressure test.
3.3.1.3 After testing, drain and thoroughly dry the air receivers with warm air. Dispose of testing fluids in accordance with all applicable Federal, state, and local regulations. Reconnect all disconnected piping and restore system. Renew any disturbed gaskets.
NOTE
Do not drain any fluids, including fresh water, into any space, bilge, or exterior location.
3.3.2 Ultrasonic and magnetic particle testing. Ultrasonic and magnetic particle testing shall be in accordance with in accordance with SFLC Std Spec 0740, Appendix C. Submit a CFR.
3.4 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by Coast Guard personnel) of the compressed air system to prove satisfactory operating condition. Submit a CFR.
3.5 Surface preservation. The Contractor shall prepare and coat the receiver exterior surfaces, using the system specified for “Machinery, Operating Temperatures Under 200 oF” in COMDTINST M10360.3, Appendix B (Cutter and Boat Interior Painting Systems). Select finish/top coat color to match previous paint scheme.
3.6 Data plates. The Contractor shall affix an anodized aluminum test data plate with epoxy resin cement to each air receiver. The data plate shall be engraved with ¼-inch high letters, stating the following:
· Receiver name / number.
· Hydrostatic test pressure (if applicable).
· Date of inspection / test.
· Testing facility.
3.7 Documentation. The Contractor shall provide documentation to the Coast Guard Inspector certifying each air receiver tested. Documentation shall include the receiver name / number, method of testing, hydrostatic test pressure (if applicable), date of inspection / test, and testing facility.
4. NOTES
4.1 Air receiver definition. An air receiver is a pressure vessel for the storage of air at 600 psig and below.
58300_SPD_Level2_ANK_0411_175
WORK ITEM 4: Single Point Davit, Level 2 Inspect and Repair
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to inspection and repair of the Single Point Davit (SPD).
1.2 Government-furnished property.
| MTI |
| ITEM DESCRIPTION |
| NSN/PN |
| QTY |
| ESTIMATED COST |
($/UNIT)
| N |
| Swing Brake Seal Kit |
| NSN: 2030013512820 |
| 2 ea |
| 138.80 |
| N |
| Swing Brake Disc & Bearing Kit |
| NSN: 2030013499486 |
| 2 ea |
| 937.70 |
| Y |
| Winch Assembly |
| NSN: 2030015051581 |
| 1 ea. |
| 17,454.50 |
2. REFERENCES
Coast Guard Drawings
None.
Coast Guard Publications
Coast Guard Technical Publication (TP) 3632, Feb 2001, Chapter 583, Section C, Technical Manual for Slewing Arm Davit Model D6000CT Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Auxiliary Machine Systems
Other References
None.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph:
· 3.2.1 (Inspection and repair task particulars – Task #1).
3.1.2 Technical Representative.
Not applicable.
3.1.3 Protective measures.
Not applicable.
3.1.4 Interferences.
None.
3.1.5 Work coordination. The Contractor shall coordinate this work item with all other weight handling -associated jobs that are included in this specification package.
3.1.6 Reference documents. The Contractor shall perform all work in accordance with SFLC Std Spec 5000 and CG TP-3632, as applicable.
3.2 Inspection and repair task particulars.
ADDITION REQUIREMENTS
| # |
| TASK TYPE |
| QTY |
| COMPONENT OR ASSEMBLY |
| APPENDIX AND PARA. FROM 5000_STD |
| OTHER |
| 1 |
| Operate and Inspect |
| 1 |
| SPD |
| 3.2.1 |
| Submit (CIR). |
| 2 |
| Preserve |
| 1 |
| SPD Exterior Surfaces |
| 3.2.3 |
| 3 |
| Renew |
| 1 |
| External Hose Assembly |
| C2.2 |
| Submit CFR. |
| 4 |
| Renew |
| 1 |
| Wire Rope Assembly |
| D2.2 |
| Nominal diameter: 5/8 inch |
Nominal strength: EIPS
Total length of rope required: Template length to match existing.
End fitting type: Poured spelter.
Submit CFR.
| 5 |
| Renew |
| 1 |
| Winch Assembly |
| N/A |
| Install GFP winch assembly only if a Change Request has been authorized and released. |
| 6 |
| Service and Inspect |
| 2 |
| Swing Drive Brake |
| 3.2.3 |
| Reassemble with components provided in GFP kits. |
| 7 |
| Groom and Lubricate |
| 1 |
| SPD |
| 3.2.6 |
| Perform all maintenance specified in Chapter 4 of TP-3632. |
| 8 |
| Final Operational And/Or Weight Test |
| 1 |
| SPD |
| B2.7 |
| After completion of all other work, perform the operational and weight testing for this system. Main Hoist test weights are as follows: |
Static: 6,000 (+300 -0) pounds Dynamic: 5000 (+265 -0) pounds Rated: 4,000 (+0 -200) pounds
CT Operational Test: 1,000 (+50 -000) pound Submit a CFR.
| 9 |
| Fabricate and Install |
| 1 |
| Label plate |
| B2.9 |
3.3 Special requirements for various components. If a Change Request has been authorized for additional work on any of the components listed in Table 1 below, the Contractor shall refer to the corresponding Appendix or paragraph of SFLC Std Spec 5000, as applicable.
TABLE 1 – SPECIAL REQUIREMENTS
| Component |
| Appendix & Paragraph in sflc std spec 5000 |
Fluids
C2.1
Hose assemblies
C2.2
Piping and tubing
C2.3
Valves and manifolds
C2.4
Gages
C2.5
Gas charged accumulators
C2.6
Heat exchangers and fluid coolers
C2.7
Systems
C2.8
Fastener assemblies
D2.1
Wire rope assemblies
D2.2
Brakes and clutches
D2.3
Open gearing and gear reducers
D2.4
4. NOTES
59320_DLA_0209_FLT
REC_59320_FLT_175’ WLM (ALL) (0309)
WORK ITEM 5: Grey Water Piping , Clean and Flush
1.1 Intent. This work item describes the requirements for the Contractor to clean the grey water piping system.
1.2 Government-furnished property.
None.
2. REFERENCES
Coast Guard Drawings Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage and Waste Water System Diagram Coast Guard Publications Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General Requirements Other References ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems
3. REQUIREMENTS
3.1 General. The Contractor shall clean approximately 200 linear feet of grey water system piping, including condensate drain lines, shown on Coast Guard Drawing 175 WLM 593-001
3.1.1 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences):
· Grey water pumps.
3.1.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.2 Contamination prevention. The Contractor shall take all precautions to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations.
3.3 Cleaning plan. The Contractor shall establish a plan for cleaning the designated piping system, listing the step by step procedures necessary to ensure that all foreign debris is removed from the piping system.
NOTE
Although the Coast Guard prefers pressurized water as the cleaning fluid, the Contractor may propose chemical cleaning as an alternative, providing that the proposed chemical cleaning agent conforms to DOD-STD-2187 (where applicable), is environmentally safe, and pre-approved by the COTR. Due to the fact that sewage system piping has historically been difficult to clean by pressure washing only, chemical cleaning is usually required to successfully complete the cleaning process. The Contractor shall submit a MSDS to the COTR for all chemicals proposed for use.
3.3.1 Procedure requirements. Ensure that the procedure includes the following:
· Methods of cleaning.
· All safety precautions required during cleaning operations.
· List of qualified personnel who will operate machinery or handle chemicals (see paragraph 3.8 (Personnel qualification) herein).
· Locations in the grey water piping where cleaning will take place, and any additional fittings necessary.
· Sequence of each location that ensures all piping sections will be cleaned and all foreign debris removed.
3.3.2 Plan submittal.