CGC WILLIAM TATE FY11 DS - SPECIFICATION
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30_Amendment_A00002_.doc | DOC document | |
| 175-WLM_930_1_2_-_K1.dwf | DWF file | |
| CGC WILLIAM TATE FY11 DS SPECIFICATION REV-1.doc | DOC document | |
| 175-WLM_930_1_2_-_K1 pdf - Adobe Acrobat Standard.pdf | ||
| SF30 Amendment A00002 .doc | DOC document | |
| SF30 Amendment A00001 .doc | DOC document | |
| CGC WILLIAM TATE FY11 DS RFQ.pdf | ||
| CGC WILLIAM TATE FY11 DS SCHEDULE.xls | XLS spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC WILLIAM TATE (WLM 560)
175 FOOT COASTAL BUOY TENDER
SPECIFICATION FOR DOCKSIDE REPAIRS
Developed By: Miguel K. Augustin
(Rev-0, 15 February 2011)
USCGC WILLIAM TATE (WLM-175) DOCKSIDE AVAILABILITY 2011
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ....................................................................................................................................... iii
Consolidated List of References ................................................................................................................ iv
Consolidated List of Government-furnished Property .............................................................................. vii
Consolidated List of Critical Inspection Items .......................................................................................... ix
Principal Characteristics ............................................................................................................................. x
General Requirements
WORK ITEM 1: Tanks (Potable Water), Clean and Inspect
WORK ITEM 2: Circuit Breakers (60 Hz), Inspect and Test
WORK ITEM 3: Compressed Air Receivers , Clean, Inspect , and Test
WORK ITEM 4: Single Point Davit, Level 2 Inspect and Repair ............. Error! Bookmark not defined.
WORK ITEM 5: Grey Water Piping , Clean and Flush
WORK ITEM 6: Sewage Piping , Clean and Flush
WORK ITEM 7: Main Diesel Engine (MDE) Exhaust Stack Uptakes , Commercial Clean
WORK ITEM 8: Ship Service Diesel Generator (SSDG) Exhaust Piping , Commercial Clean
WORK ITEM 9: SW Heat Exchangers , Clean , Inspect and Hydro
WORK ITEM 10: Tanks (Fuel), Preserve “ 100%
WORK ITEM 11: Warping Capstan, Level 2 Inspect and Repair
WORK ITEM 12: Hydraulic Power Unit Insulation Valves, Install
WORK ITEM 13: Crossdeck Winches, Overhaul
WORK ITEM 14: Hydraulic Inhaul Winch, Overhaul
WORK ITEM 15: Propulsion Shaft Bulkhead Seals , Upgrade
WORK ITEM 16: Deck Covering ( Electrical Matting ) , Renew
WORK ITEM 17: T anks (Potable Water), Preserve 100%
WORK ITEM 18: Tanks ( Potable Water ), Preserve “ Partial ”
WORK ITEM 19: Hydraulic Chain Stoppers, level 2 Inspect and Repair
WORK ITEM 20: Window Wiper Modifications, Install
WORK ITEM 21: Deck Covering (Wet/Dry), Renew
WORK ITEM 22: Oil Containment Coaming Renewal
WORK ITEM 23: Raised Scuttle Replacement
WORK ITEM 24: Engine Room Bilge , Clean and Inspect
WORK ITEM 25: Decks - Exterior, Preserve ( “MIL-Spec/ Flight Deck” System) iii (Rev-0)
Revisions Record
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
Consolidated List of References
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution.
All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free or charge. Other Government documents may be accessed – free of charge – as follows:
MIL/DOD/CID Specifications: http://www.assistdocs.com/search/search_basic.cfm
Commandant Instruction Manuals: http://www.uscg.mil/directives/default.asp
Public Laws, Code of Federal Regulations, U.S Codes, and other Federal Government laws::
www.gpoaccess.gov
The Government is aware of the following internet web links where contractors may procure commercial specifications:
American Welding Society (AWS): http://www.awspubs.com/index.php
ANSI, ASTM, IEEEE, NFPA, ASME, SAE Standards: http://www.techstreet.com/
NFPA: http://www.nfpa.org
SSPC Standards and pictorial guides: http://shopping.netsuite.com/sspcmarketplace
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 201-001, Rev C, Machinery Spaces Arrangment
Coast Guard Drawing 175 WLM 243-202, Rev F, Propulsion Shaft Arrangement
Coast Guard Drawing 175 WLM 244-001, Rev -, 4.48” ND Type Bulkhead Seal
Coast Guard Drawing 175 WLM 256-001, Rev H, Seawater Cooling System Diagram
Coast Guard Drawing 175 WLM 256-003, Rev D, Seawater Cooling System FR 61 Forward
Coast Guard Drawing 175 WLM 256-004, Rev J, Seawater Cooling System Arrangements and Details
Coast Guard Drawing 175 WLM 256-005, Rev -, Z-Drive Lube Oil Heat Exchanger Tube Bundle, Replacement and Piping Mods
Coast Guard Drawing 175 WLM 256-012, Rev A, Auxiliary Seawater System Piping Mods
Coast Guard Drawing 175 WLM 259-001, Rev A, Combustion Exhaust Diagram
Coast Guard Drawing 175 WLM 259-005, Rev C, Combustion Exhaust A&D, Hull Block 970
Coast Guard Drawing 175 WLM 320-001, Rev U, Electrical One-line Diagram
Coast Guard Drawing 175 WLM 320-007, Rev P, Power System Deck Plan 01 Level and Above
Coast Guard Drawing 175 WLM 533-006, Rev D, Independent Tank Potable Water Hb 950
Coast Guard Drawing 175 WLM 549-001, Rev D, Onboard Lubrication Requirements
Coast Guard Drawing 175 WLM 551-001, Rev H, Compressed Air System Diagram
Coast Guard Drawing 175 WLM 556-008, Rev-, Isolation Valves for Deck Machinery Hydraulic Power Unit
Coast Guard Drawing 175 WLM 573-050, Rev A, Hydraulic Piping Installation for Chain Stopper
Coast Guard Drawing 175 WLM 573-051, Rev B, Chain Stopper Structural Modifications for Hydraulic Roller
Assembly
Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage and Waste Water System Diagram
Coast Guard Drawing 175 WLM 601-001, Rev L, General Arrangement and Inboard and Outboard Profiles
Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Plans http://www.assistdocs.com/search/search_basic.cfm http://www.uscg.mil/directives/default.asp http://www.gpoaccess.gov/ http://www.awspubs.com/index.php http://www.techstreet.com/ http://www.nfpa.org/ http://shopping.netsuite.com/sspcmarketplace v (Rev-0)
Coast Guard Drawing 175 WLM 625-001, Rev K, Windows and Portlights
Coast Guard Drawing 175 WLM-74-1, Rev A, Radiographic Inspection Hull Welds
Coast Guard Drawing 175 WLM-900-1, Rev B, Hull Block Plan
Coast Guard Drawing 175-WLM 167-1, Rev -, Structural Closures
Coast Guard Drawing 175-WLM 320-1, Rev U, Electrical One-Line Diagram
Coast Guard Drawing 175-WLM 506-8, Rev -, Oil Containment Coamings
Coast Guard Drawing 175-WLM 635-1, Rev -, Hull Thermal & Acoustic Insulation Schedule
Coast Guard Drawing 175-WLM 549-001, Rev D, Onboard Lubrication Requirements
Coast Guard Drawing 175-WLM 573-001, Rev K, Buoy Deck Arrangement
Coast Guard Drawing 175-WLM 593-001, Rev G, Sewage & Waste Water System Diagram
Coast Guard Fleet Drawing FL-2605-29, Rev H, Chain Stopper System – Rising Sheave Assembly
Coast Guard Fleet Drawing FL-2605-30, Rev B, Chain Stopper Plate for Hydraulic Roller Assembly
COMDINST M6240.5, COAST GUARD WATER SUPPLY AND WASTEWATER DISPOSAL MANUAL
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and Color
Manual
Coast Guard Technical Publication (TP) 3498, Section A, Feb 2008, Buoy Chain Winch
Coast Guard Technical Publication (TP) 3613, Tab 243-B, Bulkhead Seal
Coast Guard Technical Publication (TP) 3619, 13-AUG-98, Manufacturers Instruction Book-SWBS Group(s)
Coast Guard Technical Publication (TP) 3627, Mar 2007, SWBS 556, Tab 556A - Deck Equipment Hydraulic
Power Unit
Coast Guard Technical Publication (TP) 3631, Mar 2007, Manufacturer’s Instruction Book-SWBS Group(s)
573-581, Section B, Cross Deck Winch
Coast Guard Technical Publication (TP) 3632, Feb 2001, Chapter 583, Section C, Technical Manual for
Slewing Arm Davit Model D6000CT
Coast Guard Technical Publication (TP) 3632, Section 582-A, Sep 1999, Manufacturer's Instruction Book-
SWBS Groups 582-583, Aft Capstan
Coast Guard Technical Publication (TP) 3939, Apr 2007, Section 573-A, Rising Sheave Chain Stopper
Coast Guard Technical Publication (TP) 4609, July 2006, Wynn Installation and Operation Manual
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 6341, Jan 2009, Install New Deck
Covering Systems
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 0740 (SFLC STD SPEC 0740), Jan 2009, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Auxilary
Machine Systems
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Auxiliary
Machine Systems
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), Jan 2009, Temporary
Hull Accesses
Surface Forces Logistics Command (SFLC) Naval Engineering Directive (NED) 5735-01, Inspection and Test
Procedure For Buoy Chain Winch Model CW-1 Onboard WLM 551-564 and WLB 201-215, May 2010 vi (Rev-0)
OTHER REFERENCES
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities
American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System
Components - Health Effects
ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
Code of Federal Regulations (CFR) Title 29, Part 1915, Jul 2008, Occupational Safety and Health Standards for Shipyard Employment
Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters
Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency
Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation
Commercial Item Description (CID) A-A-59588, Jul 2005, Rubber Silicone
DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems
MIL-D-18873, Jul 1982, Deck Covering Magnesia Aggregate Mixture
MIL-D-21631, Dec 1990, Deck Covering, Latex Concrete
MIL-D-23134, Jul 1999, Deck Underlay and Covering, Insulating, Magnesia Aggregate Mixture
MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric
MIL-PRF-24667, Jun 2005, Coating system, Non-Skid, for Roll or Spray Application
MIL-PRF-3135, Nov 1986, Deck Covering Underlay Materials
MIL-PRF-900, Mar 1991, Rubber Gasket Material, 45 Durometer Hardness
MIL-STD-1689, Nov 1990, Fabrication, Welding and Inspection of Ships Structure
National Electrical Manufacturers Association (NEMA) Stds, Pub. No. AB4, 2003, Guidelines for Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and Industrial Applications
Naval Ship's Technical Manual (NSTM) Chapter 634, Dec 2001, Deck Covering
NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation
Details
QPL-24667, May 2006, Qualified Product List of Products Qualified under Performance Specification MIL-
PRF-24667, Coating system, Non-Skid, for Roll or Spray Application
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2007, Cork and
Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), Jan 2009, Install New
Deck Covering Systems
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard
SSPC-SP 10/NACE No.2, 2004, Near-White Blast Cleaning
Underwriters Laboratories Inc. (UL) 489, May 2002, Molded Case Circuit Breaker
Wartsila Defense, Inc. Technical Manual for Type ND Seal vii (Rev-0)
Consolidated List of Government-furnished Property
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
12 N Check Valve, In-line PN: CPV 123A-6 PL4354 3 ea. 400.00
N Roller bearing Unit
(for Para. 3.2, Task
#6)
NSN:3130-01-504-4363 2 ea. 4,012.00
N
Grease seal
(for Para. 3.2, Task
#7)
NSN:5330-01-462-5544 4 ea. 79.25
N
Level wind pivot bushing
(for Para. 3.2, Task
#8)
PN:7101-573-1 PC-17 1 ea. 392.00
N
Level wind thrust bearing
(for Para. 3.2, Task
#8)
PN:7101-573-1 PC-16 2 ea. 249.00
N
Hand Pump
(for Para. 3.2, Task
#9)
NSN:4320-01-015-9422
PN:P-18
1 ea. 218.76
Y Level wind hydraulic cylinder
(for Para. 3.2, Task
#10)
NSN: 3040-01-441-3721 1 ea. 7,423.00
Y Hydraulic motor
(for Para. 3.2, Task
#19)
NSN: 4320-01-445-2248 1 ea. 23,994.00
15 N Seal, Bulkhead Shaft
(entire seal) H76287-
PN: OC 0000-01-LG9-4521 4 ea.
20 N Wynn Window Wiper
Assemblies, Straight
Line, Type C
ACN: 2090-01-LG9-1208,
-1209, -1210, -1211, -1212, -1213, -1214, -1215, -1216, -1217, -1218
11 ea. 1,000.00
20 N Controllers #1000 Model 1001 11 ea. 2,000.00 23 Y Scuttle, 1.5” Raised, 18” dia, steel, w/coaming NIN: 007275458 1 ea. $937.25 viii (Rev-0)
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter ix (Rev-0)
Consolidated List of Critical Inspection Items
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000_STD, paragraph
3.2.6.5 (Inspection report particulars)):
Work
Item Title 4 Single Point Davit, Level 2 Inspect and Repair
13 Crossdeck Winches, Overhaul
14 Hydraulic Inhaul Winch, Overhaul
16 Deck Covering ( Electrical Matting ) , Renew
19 Hydraulic Chain Stoppers, level 2 Inspect and Repair x (Rev-0)
PC_175_WLM_310
Principal Characteristics
175' WLM BUOY TENDER
PHYSICAL CHARACTERISTICS
Length Overall 174' 8"
Length between Perpendiculars 155' 1"
Depth 14' 8"
Maximum Beam 36' 0"
Designed Draft 8' 0"
Mast Height (Above 8' Waterline) 58' 8"
Frame Spacing 20"
Full Load Displacement 906.42 long tons
Light Load Displacement 840 long tons
Minimum Op Condition Displ 870 long tons
MACHINERY CHARACTERISTICS
Main Propulsion
Two Caterpillar 3508 DITA V-8 diesel; 999 BHP ea @
1500 RPM
Two Ulstein 360 degree steerable Z-Drives, 403
SRPM @ 1600 ERPM
Reduction Gears Two Z-Drive units, Cardan shafting; 3.973:1 gear ratio
Shaft Seal John Crane Type ND
Shaft Bearings Five pedestal mounted, Cooper split roller bearings
Number of Propellers 2
Number of Blades 4
Diameter 57.1"
Rudders None; Z-drive
Ship's Service Generators Three Caterpillar Model 3406 DITA
Turbocharged; 285KW, 450V, 60 Hz, 1800 RPM
Emergency Diesel Generator One Caterpillar Model 3406 DIT 210 KW, 24V, 60
Hz, 1800 RPM
TANK CAPACITIES
Diesel Oil Capacity (100%) 16,385 gal
Fresh Water Capacity (100%) 7,339 gal
Lubricating Oil (100%) 86 gal xi (Rev-0)
1 (Rev-0)
00000_0310_FLT
REC_0000_FLT_ Commercial Project @ CG Facility (1209)
General Requirements
1. SCOPE
1.1 Intent. This item describes the general requirements to be followed by the Contractor while conducting this availability.
2. REFERENCES
COAST GUARD DRAWINGS
None.
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3C, Change 1, Jun 2006, Coatings and
Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 33 CFR, 2008, Navigation and Navigable Waters
Code of Federal Regulations (CFR) Title 40, Chapter I, 2008, Environmental Protection Agency
Code of Federal Regulations (CFR) Title 49, Chapter I, 2008, Pipeline and Hazardous Materials Safety
Administration, Department Of Transportation
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
2 (Rev-0)
Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.
3.4 HW disposal. The Contractor shall be responsible for all hazardous wastes generated by work under this contract. Label and package all hazard wastes in 49 CFR-approved containers, and in accordance with all other applicable Federal, state, and local laws and regulations. In addition, comply with applicable parts of 40 CFR
262, applicable to handling of hazardous wastes.
3.4.1 Along with the Government, the Contractor shall be contractually considered the co-generator of all hazardous wastes; be aware that the Government will make available its facility’s EPA Generator Identification
(ID) Number for manifesting of hazardous wastes.
3.4.2 The Contractor shall identify, arrange, and be responsible for the turnover of all hazardous wastes, within the confines of the Coast Guard shore facility, to the facility’s HM/HW Coordinator. Notify the ship’s HW
Coordinator prior to any transfers of HW from ship to shore.
3.4.3 The Contractor shall prepare a manifest of hazardous waste to be reviewed and signed by the HM/HW
Coordinator. Contact the HM/HW Coordinator for turnover of any hazardous waste; in addition, notify the
COTR 24 hours prior to any waste removals, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.4.4 The Contractor shall be aware of the following:
3.4.4.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the
Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast
Guard facility without COTR or KO-approval.
3.4.4.3 Local environmental regulations at the Government facilities may be more stringent than in many jurisdictions. As with all environmental regulations, it is the Contractor's responsibility to research, prepare for, and comply with, the local and state regulations.
3.4.4.4 Coast Guard facilities do not have Facilities Response Plans (see 33 CFR 154 Subpart F). It is the
Contractor’s responsibility to furnish the Facility Response Plan (FRP) when required for over-the-water liquids transfers to and from vessels. This requirement is applicable to transfers to/from vessels with an oil/fuel capacity of 250 barrels or more.
4. NOTES
4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may be accessed at the following URL address: http://www.uscg.mil/directives/cim.asp
4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 0000 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
http://www.uscg.mil/directives/cim.asp
3 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
Vessel Name: _______________________ Hull Number: ______________ CLIN No.: _____________ Work Item Title: ________________________________________________ Specific Area Being Preserved: ___________________________________________________________
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating manufacturer(s).
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down
(maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10…).
Verify surface anchor profile (1.5-3.5 mils for abrasive-blasted steel surfaces; 1.0 mil (minimum) for power-tool cleaned surfaces; 1.0-1.5 mils for abrasive-blasted aluminum surfaces); and 1.5 –2.5 for surfaces to be coated w/single coat of inorganic zinc). Conduct 5 sets of 3 readings for the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Measure soluble salt conductivity (5 measurements per 1000 sqft) – maximum threshold: 70 microsiemens/cm for non-submerged surfaces and 30 microsiemens/cm for submerged surfaces.
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application:_________/_________; Return to service or removal from environment controls: _______/_______
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
Name of QP-1 or NACE-Certified Inspector: __________________________________________ Cert. No.: ____________ Signature of Inspector: _______________________________________ Date:_______________ Time: _________
4 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
Vessel Name: _______________________ Hull Number: ______________
CLIN No.: _____________ Work Item Title: ________________________________________________
(Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat)
DATE &
TIME
ENTER ACTIVITY
(Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION
TEMPERATURE
% REL.
HUMIDITY
SIGNATURE
OF
INSPECTOR DEW
POINT SURFACE AMBIENT
ΔT
| DP - Surface
Name of QP-1 or NACE-Certified Inspector: __________________________________________ Cert. No.: ____________ Signature of Inspector: _______________________________________ Date:_______________ Time: _________
5 (Rev-0)
QA-3 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG)
Vessel Name: _______________________ Hull Number: ______________
CLIN No.: _____________ Work Item Title: ________________________________________________
Location of Surface Profile Measurements: ___________________________________________________________
SURFACE PREPARATION
METHOD
PROFILE
(mils)
Min Max Avg.
SSPC-SP-10/NACE No. 2
SSPC-SP-12/NACE No. 5
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
Abrasive Manufacturer and Sieve Size: _________________________________
Place Surface Profile Replica Tapes In The Spaces Provided Below, To Serve As Permanent QA record. Maintain separate log for each area/location. When an Area Is Divided Into Separate Sections, Maintain A Separate Log for Each Section.
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Place Surface Profile
Replica Tape Here
Reading:__________ mils
Average Mil Reading (IAW ASTM D4417-Method C) for above 15 readings: ______________
Name of QP-1 or NACE-Certified Inspector: __________________________________________ Cert. No.: ____________ Signature of Inspector: _______________________________________ Date:_______________ Time: _________
6 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
Vessel Name: _______________________ Hull Number: ______________
CLIN No.: _____________ Work Item Title: ________________________________________________
Location of Work (including frame numbers): _______________________________________
Area (square feet): ____________
DATE TEST LOCATIONS CONDUCTIVITY
(microsiemens/cm)
Name of QP-1 or NACE-Certified Inspector: __________________________________________ Cert. No.: ____________ Signature of Inspector: _______________________________________ Date:_______________ Time: _________
7 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
Vessel Name: _______________________ Hull Number: ______________
CLIN No.: _____________ Work Item Title: ________________________________________________
Coating Manufacturer: ___________________Product Name: _______________________Batch Number: ____________ Induction Time: _______________________________________________________________ Coating System Sequence (Indicate Whether: Primer, Touch-Up Primer, Barrier Coat, 3rd Coat…): __________________
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC PA-2
SPOT 1 2 3 4
5 AVERAGE
VALUE
*BASE METAL
READING (BMR)
*Required, If Magnetic Pull-Of (Type I/Banana) Gauge Is Used.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Location (Frame Reference): ___________________
SPOT 1 2 3 4 5
Overall Avg. DFT
ADJUSTMENTS
1 Avg. BMR Deviation 3 Before
Adjustments After Adjustments
Avg.
Application Method (Airless, Conventional Spray, Rolled):____________________
Average DFT: __________________________________________________________
Name of QP-1 or NACE-Certified Inspector: __________________________________________ Cert. No.: ____________ Signature of Inspector: _______________________________________ Date:_______________ Time: _________
8 (Rev-0)
12314_DLA_0209_FLT
REC_12314_FLT/175’ WLM (ALL) (0310)
WORK ITEM 1: Tanks (Potable Water), Clean and Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
TYPE OF TANK LOCATION
CAPACITY - 100%
(gallons)
LOW SUCTION
(gallons) Potable Water 1-94-0-W 2,167 68 Potable Water 2-36-1-W 5,172 163
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Plans
Coast Guard Drawing 175 WLM 533-006, Rev D, Independent Tank Potable Water Hb 950
COAST GUARD PUBLICATIONS
None.
OTHER REFERENCES
American National Standards Institute/NSF International (ANSI/NSF) 61, 2008, Drinking Water System
Components - Health Effects
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2002, Disinfection of Water-Storage Facilities
3. REQUIREMENTS
3.1 General. The Contractor shall refer to Coast Guard drawings 175 WLM 601-003 and 175 WLM 533-006 for guidance. The Contractor shall notify the Dockmaster prior to filling or draining the potable water tank(s), 9 (Rev-0) when this item is being executed in a drydock availability. The Contractor shall accomplish the following for the tank(s) designated in paragraph 1.1 (Intent):
3.1.1 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all designated tank TLIs, to demonstrate existing operational condition.
Submit a CFR.
3.1.2 Tank content removal. Remove and dispose of all fluids and/or residues in accordance with all applicable
Federal, state, and local regulations.
3.1.3 Tank cleaning. Remove tank cover(s); clean tank interior surfaces free of all foreign materials, such as sediment or sludge. Remove all persistent residues, taking care not to damage the tank coating system. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.1.4 Inspection. Visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a
CFR including the following, as applicable:
Tank structural condition.
Inaccessible areas, if any.
Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
Tank level indicator (TLI) and/or float switch condition (if applicable).
Sounding tube and striker plate condition.
Suction and discharge piping condition.
Fastener material and condition (correct fastener material is stainless steel).
3.2 Tank closing. The Contractor shall ensure that the tank(s) remain open for approximately 24 hours after completion of the tasks specified above. Notify the COTR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to ANSI/NSF 61. Renew all stud cotton grommets (as applicable) upon reinstallation of manhole cover(s).
3.3 Tank disinfecting. After all other work involving the potable water system and tank closing have been completed, the Contractor shall disinfect and treat the affected potable water tank(s) and associated disturbed piping and components, as necessary, to meet or exceed the requirements of AWWA C652. After tank disinfecting; remove and dispose of all treated water in accordance with all Federal, state and local regulations.
NOTE
Ensure that no one enters the tanks once disinfection is completed.
3.4 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by
10 (Rev-0)
Coast Guard personnel) of all designated tank TLIs to prove satisfactory operating condition. Submit a CFR.
This section is not applicable to this work item.
11 (Rev-0)
32123_JSP_0309_175
WORK ITEM 2: Circuit Breakers (60 Hz), Inspect and Test
1.1 Intent. This work item describes the requirements for the Contractor to inspect and test circuit beakers (60
Hz) located on the Switchboards.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 175-WLM 320-1, Rev U, Electrical One-Line Diagram
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 3619, 13-AUG-98, Manufacturers Instruction Book-SWBS
Group(s) 324
OTHER REFERENCES
National Electrical Manufacturers Association (NEMA) Stds, Pub. No. AB4, 2003, Guidelines for
Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and
Industrial Applications
Underwriters Laboratories Inc. (UL) 489, May 2002, Molded Case Circuit Breaker
3. REQUIREMENTS
3.1 General. The Contractor shall provide skilled technicians, portable instrument standards and all necessary equipment to inspect and test circuit breakers designated in the work item. The Contractor may remove the circuit breakers from the vessel to a shoreside test facility. If this is done the Contractor shall exercise extreme care in transporting and reinstalling the circuit breakers to original operating condition on Switchboard.
3.1.1 Prior to any wiring disconnection and removal of circuit breakers, the Contractor shall record all wiring information, trip setting adjustments, and equipment locations necessary for use in later reinstallation. Retain all mounting and connecting hardware for later reuse. Submit a CFR.
3.1.2 Disconnect and remove the circuit breakers listed in the Table 1& 2. Coordinate the disconnection and removal of the circuit breakers with the COTR to minimize disruption of power. Temporarily cover or insulate http://www.techstreet.com/ http://www.techstreet.com/ http://www.techstreet.com/ http://www.techstreet.com/cgi-bin/detail?product_id=1173948
12 (Rev-0) switchboard or panel board openings created by the removal of circuit breakers to prevent personnel contact with energized conductors.
3.1.3 The Contractor shall notify the COTR 48 Hours prior to start work on this item.
3.2 Inspection requirement. The Contractor shall inspect all circuit breaker wire connectors, screws and plating and submit a CFR.
3.2.1 Surface burn marks and hairline cracks are acceptable but shall not deteriorate the mold surface or impair physical strength. Cracks are not permitted in wall section between phase and a ground plane when there is a conducting part in contact with the wall section. Cracks shall not exceed 0.75 inch in length, and in no case should be greater than 50 percent of the length of the surface in which the crack appears. Submit a CFR.
3.3 Circuit breaker testing. The contractor shall test circuit breakers listed in the Table 1&2 in accordance with the National Electrical Manufacturers Association (NEMA) AB 4 or UL 489 Molded Case Circuit Breakers. The test shall include, at a minimum:
Mechanical Operation
Insulation Resistance
Individual Pole Resistance
Inverse-Time Over current Tripping
Instantaneous Over current Tripping
Rated Hold-In Current (Note: Perform this test only on the circuit beakers which are tripping under normal load condition. The Coast Guard Inspector will identify the circuit beakers).
3.4 Circuit breaker data sheet. The contractor shall provide data sheet of each circuit breaker testing with the following information:
Circuit Breaker Model and Serial Number
Circuit Breaker Service
Circuit Breaker Visual Condition
Test Voltage/Test Amperes
Type of Test/Test Method/Test Date/Name of Test Laboratory
Result of Testing
3.5 Contractor’s option for circuits breaker renewal. The Contractor may elect to renew circuit breakers in lieu of testing (due to high cost of labor for testing or non available near by testing facilities) at no additional cost to the government. Ensure that all circuit breakers shall be UL 489 Certified.
13 (Rev-0)
TABLE 1 – CIRCUIT BREAKER LIST
QUANTITY DESCRIPTION SIEMENS PART NO SERVICE LOCATION
1 800 AF, 400
AMP AS8AEXBA06DU4
SS Switchboard Emergency
Switchboard Bus Tie
Emergency Switchboard, 450
Volt Section
1 800 AF, 375
AMP AS8AEXBA06DU4 Emergency Generator
Emergency Switchboard, 450
Volt Section
2 800 AF, 500
AMP IT ITE ED63M125
Port/STBD Z-Drive Back Up Hydraulic LO
Pump
Emergency Switchboard, 450
Volt Section
2 125 AF, 125
AMP ED63M125 Fire Pump No.1&2
Emergency Switchboard, 450
Volt Section
1 125 AF, 100
AMP ED63M100 Engine Room Vital
Panel Emergency
Switchboard, 450 Volt Section
1 125 AF, 100
AMP ED63M100 Main Deck Vital Panel
Emergency Switchboard, 450
Volt Section
1 125 AF, 20
AMP ED63M020 Chart Room Vital
Panel Emergency
Switchboard, 450 Volt Section
1 125 AF, 35
AMP ED63M035
Emergency Switchboard 120 Volt
ABT
Emergency Switchboard, 450
Volt Section
TABLE 2– circuit breaker list quantity DESCRIPTION siemens Part NO service location
1 800 A, F400 AT RL-AS8EAGXBA06E Shore Power Main Switchboard
3 800 AF, 520
AT
RL-
AS8EAEXBA06DUA SSDG No.1,2&3 Main Switchboard
2 800 AF -Non Automatic RL-AS8EXXXBXXXE Bus Tie 1S-2S & 2S-3S Main Switchboard
1 800 AF, 700
AT RL-AS8EAEXBA06DU4 Distribution CB Main Switchboard
2 800 AF, 500 IT ITE ED63M125
Port /Stbd Z Drive, Backup Hydraulic/Lo Pump
Main Switchboard
1 800 AF, 400
AT RLAS8EAEXBA06DU4 HPU Control Panel SS Switchboard
4 125 AF, 100
AT ED23M100
Engine Room Power Panels (P2&P5).First Platform Fwd Power
Panel (P6)
SS Switch Board
2 125 AF, 80 AT ED23M080 Pump Room Power SS Switchboard
14 (Rev-0)
Panel (P4) &02 Level Power Panel (P19)
1 125 AF,125 AT ED23M125 Galley Power Panel (P10) SS Switchboard
1 250 AF, 200
AT FXD63M200 O1 Level Vent/Heater
Panel (P17) SS Switchboard
2 125 AF, 50 AT ED23M050
Main&Lower Deck
Vent Power Panel (P7 & P20)
SS Switchboard
2 125 AF, 125
AT ED23M125 ABT(FF Control Panel) SS Switchboard
1 125 AF, 25 AT ED23M025 Galley Power Panel SS Switchboard
3 125 AF, 100
AT ED23M100
SS Switchboard, Engine Room Power
Panel (P1), Main Deck Vital Power Panel (P8)
SS Switchboard
1 125 AF, 20 AT NOED23M020 Chart Room Vital Panel (P15) SS Switchboard
1 125 AF, 35 AT ED23M035 Emergency Switchboard SS Switchboard
1 700 AT RL-A58EAGXBAD6E SCR Drive SS Switchboard 1 125 AF, 50 AT ED23M050 Capstan SS Switchboard
1 125 AF, 100
AT ED23M100 RHIB Crane Hydraulic
Power Unit SS Switchboard
9 125 AF, 100
AT ED23M100 Misc Power Panels SS Switchboard
3.6 Circuit Breaker Installation. After all testing is complete, reinstall circuit breakers using previously recorded wiring information to its original operating condition and Coast Guard TP 3619.
3.7 Operational test-post repairs. After completion of the work, the Contractor shall witness an operational test (by Coast Guard personnel) of all circuit breakers to prove satisfactory operating condition. Submit a CFR.
3.7.1 Operate each Circuit Breaker “ON” and “OFF” several times to exercise the circuit breaker and ensure that mechanical linkages are free.
3.7.2 Direction of Rotation Test – Perform a direction of rotation test on each new and disturbed three-phase motor circuit.
15 (Rev-0)
55100_MWC_0709_FLT
REC_55100_FLT_175 WLM (ALL) (0709)
WORK ITEM 3: Compressed Air Receivers , Clean, Inspect , and Test
1.1 Intent. The work item describes the requirements for the Contractor to clean, inspect, and test the below designated air receivers:
SERVICE DESIGNATION LOCATION QTY
OPERATING
PRESSURE (PSI)
Ship’s Service 3-61-0-E 2 250 Ship’s Whistle 02-52-1-Q 1 140
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 551-001, Rev H, Compressed Air System Diagram
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Jan 2009, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Jan 2009, Welding and Allied Processes
OTHER REFERENCES
None.
3.1 General.
16 (Rev-0)
3.1.1 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5
(Interferences):
Gauge lines
Brackets
Piping
3.1.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the compressed air system, to demonstrate existing operational condition.
Submit a CFR.
3.2 Cleaning and inspection. The Contractor shall clean and inspect each designated air receiver (see paragraph
1.1 (Intent)) as follows.
3.2.1 System blowdown. Blowdown the air receivers and collect the blowdown (condensate) into a separate container for inspection.
3.2.2 Visual inspection. Visually inspect the blowdown (condensate) under a bright white light for oil or particulate contamination. Clean and visually inspect the internal and external surfaces of the air receiver for signs of corrosion, pitting, and other damage. Submit a CFR.
3.3 NDI. The Contractor shall perform NDI of the designated air receiver(s) in accordance with SFLC Std Spec
0740, Appendix C. Refer to Coast Guard Drawing 175 WLM 551-001 for guidance.
NOTE
Testing shall be accomplished by ultrasonic (UT), magnetic particle (MT), or hydrostatic testing. The
Contractor may select either method to satisfy testing requirements.
3.3.1 Hydrostatic testing.
3.3.1.1 Isolate the air receiver by disconnecting all piping, relief valves, and pressure switches. Install pipe plugs/caps to prevent system contamination and in accordance with manufacturer’s testing procedures.
3.3.1.2 After all authorized repairs, hydrostatically test the air receiver using clean fresh water in accordance with
SFLC Std Spec 0740, Appendix C and manufacturer’s recommended procedures. In the event a test pressure is not listed on the applicable drawing, test to 1½-times the nominal operating system pressure and hold for five minutes. Be aware that no leakage or permanent deformation of pressure-containing parts is permissible. Repair all leaks and discrepancies found. Submit a CFR.
CAUTION!
Instruments and equipment that might be damaged by clean fresh water shall be excluded from hydrostatic pressure test.
3.3.1.3 After testing, drain and thoroughly dry the air receivers with warm air. Dispose of testing fluids in accordance with all applicable Federal, state, and local regulations. Reconnect all disconnected piping and restore system. Renew any disturbed gaskets.
17 (Rev-0)
NOTE
Do not drain any fluids, including fresh water, into any space, bilge, or exterior location.
3.3.2 Ultrasonic and magnetic particle testing. Ultrasonic and magnetic particle testing shall be in accordance with in accordance with SFLC Std Spec 0740, Appendix C. Submit a CFR.
3.4 Operational test – post repairs. After completion of work, the Contractor shall witness an operational test (by
Coast Guard personnel) of the compressed air system to prove satisfactory operating condition. Submit a CFR.
3.5 Surface preservation. The Contractor shall prepare and coat the receiver exterior surfaces, using the system specified for “Machinery, Operating Temperatures Under 200 oF” in COMDTINST M10360.3, Appendix B
(Cutter and Boat Interior Painting Systems). Select finish/top coat color to match previous paint scheme.
3.6 Data plates. The Contractor shall affix an anodized aluminum test data plate with epoxy resin cement to each air receiver. The data plate shall be engraved with ¼-inch high letters, stating the following:
Receiver name / number.
Hydrostatic test pressure (if applicable).
Date of inspection / test.
Testing facility.
3.7 Documentation. The Contractor shall provide documentation to the Coast Guard Inspector certifying each air receiver tested. Documentation shall include the receiver name / number, method of testing, hydrostatic test pressure (if applicable), date of inspection / test, and testing facility.
4.1 Air receiver definition. An air receiver is a pressure vessel for the storage of air at 600 psig and below.
18 (Rev-0)
58300_SPD_Level2_ANK_0810_175
WORK ITEM 4: Single Point Davit, Level 2 Inspect and Repair
1.1 Intent. This work item describes the requirements for the Contractor to perform Single Point Davit Level 2 maintenance.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
None.
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 3627, Mar 2007, SWBS 556, Tab 556A - Deck Equipment
Hydraulic Power Unit
Coast Guard Technical Publication (TP) 3632, Feb 2001, Chapter 583, Section C, Technical Manual for
Slewing Arm Davit Model D6000CT
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Jan 2009, Auxiliary
Machine Systems
OTHER REFERENCES
None.
3.1 GENERAL
19 (Rev-0)
3.1.1 Wash down, visually inspect, and operationally test the Allied Model D6000CT Single Point Davit
(SPD) including the Control Console and Hydraulic Power Unit (HPU) onboard the cutter. The contractor shall submit a Condition Found Report (CFR) to the Coast Guard Inspector with the inspection and test results identifying any deficiencies that may require immediate attention for continued safe operation of the davit. The report shall also identify and recommend any maintenance required to the davit and its components to extend operation until the next scheduled overhaul (2 years). Do not remove any bushings for inspection. Inspect all bushings in place.
3.1.2 In the presence of the Coast Guard Inspector, inspect and test all affected equipment and systems to document original condition. Submit a Critical Inspection Report (CIR) noting any discrepancies in equipment and system operation. Use CG Tech Pub 3632 for guidance. Ship’s force will operate all machinery.
NOTE: The Coast Guard will launch the Rigid Hull Inflatable Boat (RHIB)
3.2 TAG-OUT – Secure, isolate, and tag-out all affected mechanical, piping, and electrical systems in accordance with the General Requirements.
3.3 DAVIT INSPECTION
3.3.1 Wash down and thoroughly clean the entire davit and associated components with fresh water and detergent. Verify that the load rating is clearly identified on the SPD and that a test plate is present and identifies that last date of testing.
3.3.2 Perform a “walk around” visual inspection of the davit structure and pedestal for cracks, deformation, and corrosion. Visually inspect welds on davit structure, boom, and pedestal for cracks, damage, or corrosion.
Visually check that all bolts are secured and properly torqued in accordance with CG Tech Pub 3632. Ensure there is no gasket on the pedestal.
3.3.3 Perform a visual inspection of all hoisting fittings on the davit (release hook or release mechanism) and ensure that the release latch locks and releases freely without binding. Inspect sheave for wear with groove gage.
Inspect sheave’s pivot pins and bushings for wear. Inspect sheave housing for cracked welds, damage or deterioration. Inspect antitwo block switch assembly for damage, frayed wires, or loose connections.
3.4 WIRE ROPE REMOVAL – Remove and dispose of wire rope and end fitting from the davit by paying out the entire length from the drum in accordance with all federal, state, and local laws and regulations. Remove down stop control assembly. Remove wire rope from the drum by tapping out the cable wedge at the bitter end connection. Retain quick release hook or hook release mechanism (for (Rigid Hull Inflatable) RHIB’s with lifting frame) for reuse.
3.4.1 Inspect sheave in accordance with enclosed Figure “Sheave Inspection” and submit a CFR.
3.5 SWING ASSEMBLY – Visually inspect the swing gear and pinion for excessive wear and damage.
Check that the pinion gear caps and cap screws are secured. Change oil in accordance with CG Tech Pub 3632.
3.5.1 Inspect swing motor and stop valve for leakage.
3.5.2 Overhaul swing brake in accordance with CG Tech Pub 3632.
3.6 Clean and inspect the hand pump.
20 (Rev-0)
3.7 CT WINCH ASSEMBLY – Wire brush winch drum and inspect surface for cracks, wear, damage or corrosion. Change oil in accordance with CG Tech Pub 3632.
3.8 HYDRAULIC POWER UNIT (HPU)
3.8.1 Renew fluid level in tank is full (100 gallons capacity) and renew all filters in accordance with CG Tech
Pub 3627. Renew tank vent filter, pressure filter, and return filter. Remove sump magnet, clean, and reinstall.
Tank is located in compartment 3-88-0-E. Submit a CFR.
3.8.2 Inspect welds of HPU frame and welding of frame to deck for cracks or corrosion. Check Coupling
(motor to pump) for alignment and wear. Inspect motor and pump shock mounts for wear or loose hardware.
Check the electric motor resistance reading. Submit a CFR.
3.8.3 Start HPU or activate Ship’s central hydraulic system. Verify that davit supply pressure is 2500 psig minimum. Verify that operating pressure and flow at control console is, 34 GPM at 2500 psig maximum. Check pressure settings, make adjustments in accordance with CG Tech Pub 3627. Check full load motor amperage draw, voltage, and frequency and submit a CFR. Relief valve is set at 2750 psig. Check the setting of the SPD relief valve. Adjust as required.
3.8.4 Visually check for leaking connections, worn or damaged hoses and fittings, or any other defect.