AMENDMENT 0001 TO SOLICITATION HSCG80-10-Q-PHMG99 DRYDOCK AND REPAIRS TO THE USCGC DRUMMOND (WPB-1323)

View the file

Other files

File Type Posted
SF300003DRUMMONDDD.doc DOC document
SF300002DRUMMONDDD.doc DOC document
RFQ DRUMMOND DD 04-13-10.doc DOC document
RFQ DRUMMOND DD 04-13-10.doc DOC document
DRUMMOND_DD_MSL_10R0.pdf PDF
DRUMMOND_(WPB_110B)_DD_MSL_10ER0_BLANK_ESTIMATE.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

DO-A3

PAGE

OF PAGES

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

29 APRIL 2010

4. REQUISITION/PURCHASE REQ. NO.

21-10-800PHMG99

5. PROJECT NO.

CGC DRUMMOND DRY DOCK

6. ISSUED BY CODE: CPD-C&P1-PBPL

SURFACE FORCES LOGISTICS CENTER

300 E. MAIN STREET, SUITE 600

NORFOLK, VA 23510-9102

POC: MR. LOUIS ROMANO (757) 628-4651

E-mail: Louis.J.Romano@uscg.mil

7. ADMINISTERED BY CODE:

8. NAME AND ADDRESS OF CONTRACTOR (No, street, county, state and Zip Code)

CODE: FACILITY CODE:

X
9a. AMENDMENT OF SOLICITATION NO.

HSCG80-10-Q-PHMG99_____________

9b. DATED (SEE ITEM 11)

22 APRIL 10 ________________________

10a. MODIFICATION OF CONTRACT NO.

10b. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENT OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of offers XX IS NOT extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning one copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (IF REQUIRED)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACT/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO DESCRIBED IN ITEM 14.

A. This change order is issued pursuant to: (Specify authority) The changes set forth in Item 14 are made in the contract order no in item 10A.

B. The above numbered contract/order is modified to reflect the administrative changes (such as changes in paying office, appropriation data, etc.) set forth in Item 14 pursuant to the authority of FAR 43.103(b).

C. This supplemental agreement is entered into in pursuant to authority of:

D. Other (Specify type of modification and authority)

E. IMPORTANT: Contractor ( is not, ( is required to sign this document and return _1____ copies to the issuing office.

14. Description of amendment/modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible)

HSCG80-10-Q-PHMG99

DRYDOCK REPAIRS, USCGC DRUMMOND (WPB-1323)

Subject solicitation is amended as follows:

1. Far Clause 52.212-5 has been revised and the new effective date is APR 2010. See pages 11 thru 16 in the revised solicitation provided with this amendment.

2. Delete the 22 March 2010/REV 0 Specifications for Drydock Repairs issued on 22 April 2020; refer to REV 1 Specifications for Drydock Repairs, dated 28 April 2010 provided with this amendment, to price out your offer. Note the Revisions Record on page vi to see the list of revised work items as a result of questions submitted by prospective offerors.

3. After a review of the work items, the following clarifications are provided to all prospective offerors:

A. In work item 19, the maximum rated RPM required for “B” class vessels addressed in paragraph 3.2.2 is 500 RPM’s.

B. The area(s) in work item 65 that are to be renewed and coated with new capastic fairing are shown in the applicable drawings in the work item specification.

C. The area(s) for work item 31 and work item 65 requiring the renewal of the CAPAC anode and associated capastic fairing are shown on the applicable drawings in the work item(s) specification. There will NOT be any GFP provided for work item number 65.

D. For work item number 55, the specification requires that the insulation is to be carried down to the stringer 11L, as per the applicable drawing. Also the lower termination of insulation on bulkheads 31-1/2 and 33 is also 11L as called out in the applicable drawing.

4. All other terms and conditions remain unchanged. The due date for offers remains unchanged at May 13, 2010 at 2:00PM, EST.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type/Print)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type/Print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED

16B. UNITED STATES OF AMERICA

BY_LR_________________________________

(Signature of Contracting Officer)

16C. DATE SIGNED

04/29/10___________