SF 30 - Amendment 0001

Text of this file

RPM1012917

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Title: Power Plant Modernization

The purpose of this amendment is to provide responses to questions/RFIs, provide clarifications and incorporate Small Business Subcontracting Plan information. SEE SUMMARY OF CHANGES and ATTACHMENT 3 - AMENDMENT 1 - RFIs

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X HQ0034-12-R-0004

X 9B. DATED (SEE ITEM 11)

09-Dec-2011

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-Dec-2011

CODE

WHS - ACQUISITION DIRECTORATE

2521 SOUTH CLARK STREET, SUITE 3000

ARLINGTON VA 22202

HQ0034 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL: TEL:

HQ0034-12-R-0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by full text:

AMENDMENT 1

1) The submission date/time for proposals is January 20th, 2012 at 3:00pm EST as indicated in Box 13A. The 4:00 delivery time listed in Box 10(h) is incorrect. Delivery address is as follows:

WHS/Acquisition Directorate Attn: Dennis Luquette 2521 S. Clark Street, Suite 3000 Arlington, VA 22202

2) Add the following to Section H – Special Contract Requirements:

Small Business Subcontracting Plan: In accordance with FAR clause 52.219-9 Alternate II - Small Business Subcontracting Plan, all other than small business offerors are required to submit a Small Business Subcontracting Plan with its offer. The final Small Business Subcontracting Plan shall be incorporated by reference into the resulting contract.

3) Add the following to Section L – Instructions to Offerors:

Small Business Subcontracting Plan (not applicable to Small Business Offerors):

Offerors shall submit a small business subcontracting plan satisfying the requirements in FAR 52.219-9, Alt II and DFARS 252.219-7003. In addition to the requirements of FAR clause 52.219-9 Alt II, the small business subcontracting plan shall address affirmatively all other small business subcontracting requirements in FAR Part

19.7. The small business subcontracting plan shall be submitted separately from the Small Business Participation Plan (Phase Two, Subfactor 5), which applies to both small and other than small businesses. The Subcontracting Plan is not a requirement for evaluation in source selection, but rather, a requirement for basis of award to an other than small business. The small business subcontracting plan will be included with the Phase Two offer and a final small business subcontracting plan shall be incorporated into the resulting contract.

4) The deadline for submitting RFIs/questions for Phase One is no later than 3:00pm EST on January 6, 2012.

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 DD Form 254 Draft 4 29-NOV-2011 Attachment 2 EXHIBITS A & B - Past

Performance Project Data & Questionnai

3 05-DEC-2011

to:

HQ0034-12-R-0004

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 DD Form 254 Draft 4 29-NOV-2011 Attachment 2 EXHIBITS A & B - Past

Performance Project Data & Questionnai

3 05-DEC-2011

Attachment 3 Amendment 1 - RFIs 4 28-DEC-2011

(End of Summary of Changes)

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .