Middough Inc. • Middough Building • 1901 East 13 th Street, Suite 400 • Cleveland, OH 44114 www.middough.com
PROPERTY OF THE UNITED STATES GOVERNMENT- FOR OFFICIAL USE ONLY
Do not remove this notice – Properly destroy documents when no longer needed
North and South Stairwell Dilution Venting
AJ Celebrezze Federal Building
1240 E. Ninth Street
Cleveland, Ohio 44114
Project Specification Manual
Bid Documents
May 19, 2016
Volume 1 of 1 http://www.middough.com/
North & South Stairwell Dilution Venting ROH00425
Anthony J. Celebrezze Federal Building 05/19/16
TABLE OF CONTENTS TOC - 1
PROPERTY OF THE UNITED STATES GOVERNMENT – FOR OFFICIAL USE ONLY
TABLE OF CONTENTS
Number SECTION TITLE
DIVISION 01 - GENERAL REQUIREMENTS
011000 SUMMARY
011400 WORK RESTRICTIONS
013100 PROJECT MANAGEMENT AND COORDINATION
013200 CONSTRUCTION PROGRESS DOCUMENTATION
013300 SUBMITTAL PROCEDURES
013525 FIRE PREVENTION AND PROTECTION IN CONSTRUCTION,
ALTERNATION AND DEMOLITION
014000 QUALITY ASSURANCE & CONTROL REQUIREMENTS
014200 REFERENCES
015000 TEMPORARY FACILITIES
015930 SECURITY REGULATIONS
015950 SAFETY AND HEALTH
016000 PRODUCT REQUIREMENTS
017000 EXECUTION REQUIREMENTS
017310 CUTTING AND PATCHING
017320 SELECTIVE DEMOLITION
017350 FIRE PREVENTION PRECAUTIONS FOR HOT WORK
017419 CONSTRUCTION NONHAZARDOUS WASTE MANAGEMENT AND
DISPOSAL
017700 CLOSEOUT PROCEDURES
017810 PROJECT RECORD DOCUMENTS
017822 OPERATION AND MAINTENANCE DOCUMENTATION
018200 DEMONSTRATION AND TRAINING
TABLE OF CONTENTS TOC - 2
DIVISION 02
028200 ASBESTOS ABATEMENT
DIVISION 04 - MASONRY
042000 UNIT MASONRY
DIVISION 05 - METALS
051200 STRUCTURAL STEEL FRAMING
053000 METAL DECKING
054000 COLD-FORMED METAL FRAMING
055000 METAL FABRICATIONS
061053 MISCELLANEOUS ROUGH CARPENTRY
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
072100 THERMAL INSULATION
074113.13 FORMED METAL ROOF PANELS
074213.13 FORMED METAL WALL PANELS
076200 SHEET METAL FLASHING AND TRIM
077200 ROOF ACCESSORIES
078110 SPRAYED FIRE-RESISTIVE MATERIALS
078413 PENETRATION FIRESTOPPING
079200 JOINT SEALANTS
DIVISION 08 – DOORS AND WINDOWS
081113 HOLLOW METAL DOORS AND FRAMES
087100 DOOR HARDWARE
TABLE OF CONTENTS TOC - 3
DIVISION 21 – FIRE SUPPRESSION
211315 SPRINKLER SYSTEM MODIFICATIONS
DIVISION 22 – PLUMBING
221316 SANITARY WASTE AND VENT PIPING
DIVISION 23 - HVAC
230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
230593 TESTING, ADJUSTING AND BALANCING FOR HVAC
230713 DUCT INSULATION
230800 COMMISSIONING OF HVAC
233113 METAL DUCTS
233300 AIR DUCT ACCESSORIES
233416 CENTRIFUGAL HVAC FANS
233713 DIFFUSERS, REGISTERS AND GRILLES
DIVISION 26 - ELECTRICAL
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS
262416 PANELBOARDS
262923 VARIABLE-FREQUENCY MOTOR CONTROLLERS
263600 TRANSFER SWITCHES
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
283104 FIRE ALARM SYSTEM MODIFICATION
SUMMARY 01 10 00 - 1/3
SECTION 01 10 00 – SUMMARY
PART 1 - GENERAL
1.1 PROJECT INFORMATION
A. Project Name and Location:
North & South Stairwell Dilution Venting
Anthony J. Celebrezze Building
1240 East Ninth Street
Cleveland, Ohio 44199
B. Project Summary Description:
1. New stairwell dilution ventilation system designed to mitigate smoke into stairwells during fire and smoke condition
2. Project consists of new supply and exhaust ductwork risers encased in fire rated wrap installed in existing north and south shafts adjacent to stairwell, new supply and exhaust fans installed on roof and associated fire alarm modifications.
C. Architect: The term Architect refers to the project designer. The Architect's status relative to the construction will be stated in writing by the Contracting Officer prior to the pre-construction conference. The project was designed by:
Middough Inc., Phone: 216-367-6170
1901 East 13th Street, Suite 400
Cleveland, Ohio 44114
D. Project Delivery Method: Traditional (GC)
E. Fire Protection Consultants
Jensen Hughes Associates
Mike Ferreira
410-737-8677
F. Asbestos and Lead Survey conducted by others: Asbestos abatement is included in this contract -see Section 028200 Asbestos Abatement.
SUMMARY 01 10 00 - 2/3
G. The Contracting Officer for the project:
Katie Musselman:
Phone:(317) 308-4414
8899 E 56TH ST Room: Column 123B, INDIANAPOLIS IN 46216-1000
1.2 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in the existing building to after hours (6:pm to 6:30am), Monday through Friday, unless otherwise indicated. Coordinate starting time with GSA Property
Management.
1. Coordinate deliveries and waste removal through GSA, C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Owner not less than three days in advance of proposed utility interruptions.
2. Obtain Owner's written permission before proceeding with utility interruptions.
D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
1. Notify Owner not less than two days in advance of proposed disruptive operations.
2. Obtain Owner's written permission before proceeding with disruptive operations.
E. Nonsmoking Building: Smoking is not permitted within the building or within 50 feet (16 m) of entrances, operable windows, or outdoor-air intakes.
F. Controlled Substances: Use of tobacco products and other controlled substances Project site is not permitted.
1.3 WORK UNDER SEPARATE CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract or other contracts.
Coordinate the Work of this Contract with work performed under separate contracts.
1.5 MISCELLANEOUS PROVISIONS
SUMMARY 01 10 00 - 3/3
A. Work in existing facilities shall correspond in all respects with the existing conditions to which it connects, or to similar existing conditions, in materials, workmanship and finish.
B. Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of Work under the Contract.
Work out of alignment where exposed by removal of existing work shall be called to the attention of GSA. Necessary corrective work shall be as directed.
1. Replacements of existing conditions that are removed shall match similar existing conditions.
2. Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting Officer.
3. Conditions remaining in place, which are damaged or defaced during the Work, shall be restored to the condition existing at time of award of Contract.
4. Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.
C. Existing structures will remain in place.
D. Removed items indicated to remain the property of the Government shall be stored on site where directed by the Contracting Officer.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 011000
WORK RESTRICTIONS 01 14 00 - 1/3
SECTION 01 14 00 - WORK RESTRICTIONS
PART 1 - GENERAL
1.1 CONTRACTOR USE OF PREMISES
A. The Contractor will review and document the existing conditions surrounding the project premises. Provide documentation to the Government prior to the commencement of any construction activity.
B. During the construction period, the Contractor shall have full use of the designated premises for construction operations, including full use of the indicated work site, limited only by the
Government's right to perform work or retain other contractors to perform work on portions of the project.
C. The Contractor shall limit use of the premises to the work in areas indicated, and to allow for
Government occupancy and public use.
1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which Work is indicated.
2. Keep driveways and entrances serving the premises clear and available at all times to the
Government, Government employees and to visitors. Do not use these areas for parking or storage of materials.
3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.
4. Maintain existing building in a safe and weather-tight condition throughout the construction period. Repair damage caused by construction operations to the satisfaction of the government. Take precautions to protect the building, its occupants and the public during the construction period. A representative of the Contractor shall be available to arrive on site within one (1) hour of notice should an emergency occur.
5. Keep public areas, such as hallways, stairs, lobbies and toilet rooms, free from accumulation of waste material, rubbish, construction debris and construction materials.
6. Space on the premises will be made available for the Contractor's storage and related activities, provided that its use will not interfere with operations of the Government.
Arrange and gain approval for use of this space through the Contracting Officer.
7. Use of the existing loading dock facilities will be shared with Government activities on a first-come-first-served, wait-your-turn basis. The loading dock is available for the delivery of materials, tools, and supplies between the hours of 5:30: a.m. 5:30 p.m.
8. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or designated to be salvaged as Government property, shall become the property of the Contractor and shall be removed from the site. Storage or sale of excess salvageable materials and equipment is not permitted on site.
9. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into the building. When not required for powering unloading operations, turn off engines when docked.
WORK RESTRICTIONS 01 14 00 - 2/3
10. Smoking is not permitted in or around the building, see Facilities Management
Regulation (FMR) Case 2008-102—3. Also see Code of Federal Regulations (CFR) 41
CFR Part 102-74.
11. No parking will be available on site during working hours for building occupants. The
Contractor and Contractor's employees shall make their own arrangements for vehicle parking off site.
12. Cell Phones: Contractor is to provide company cell phone during this contract. All cell phones to be “on vibrate” at all times. If a telephone begins audibly ringing, the building guards will take the cell phone and hold until the end of the working day prior to the con-tractor leaving the property. Cell phones are only permitted in construction area and contractor’s office space.
13. No apparatus with an open flame is allowed to be used within the facility without the prior receipt of a burn permit. Contact the Field Office to obtain burn permits. Burn permits are required for each separate occurrence.
14. Permits: Refer to FAR 52.236-7
15. The work shall be sequenced to minimize disruption to building occupants, visitors, and maintenance activities. To the greatest extent feasible, demolition work should not take place until supplies are on hand to perform new work.
16. Coordinate with the GSA Building Manager and the COR for site access.
17. Coordinate with the GSA Building Manager and the COR on correct response procedures for any building system alarms occurring during or resulting from the construction process.
18. All building systems outside the immediate construction area shall be kept fully operational during normal working hours.
19. Protect building site from flying debris.
1.2 GOVERNMENT OCCUPANCY
A. The Government will occupy the site and the existing building during the entire period of construction. Cooperate with the Government's representatives during construction operations to minimize conflicts, mitigate noise, and facilitate Government usage. Perform the Work in a manner that does not interfere with the Government's operations.
B. The Government reserves the right to occupy, place, and install equipment in completed areas of the building prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. The Government's installation of equipment and partial occupancy shall not constitute acceptance of the total Work.
1. Prior to partial Government occupancy, mechanical and electrical systems for the space shall be fully operational, and required inspections and tests shall be successfully completed. Upon occupancy, the Government will operate and maintain mechanical and electrical systems serving the occupied portions of the building.
2. Upon occupancy, the Government will assume responsibility for maintenance and custodial service for the occupied portions of the building.
PART 2 - PRODUCTS (Not Applicable)
WORK RESTRICTIONS 01 14 00 - 3/3
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 011400
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 1/7
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:
1. General project coordination.
2. Coordination drawings.
3. Conservation.
4. Administrative and supervisory personnel.
5. Conferences and meetings.
6. Cleaning and protection.
1.2 GENERAL PROJECT COORDINATION
A. Coordination of Trades: Coordinate construction operations included in the various sections of the
Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation. Keep pipes, ducts, conduit, and the like as close as possible to ceiling slab, walls, and columns to take up a minimum amount of space.
Locate pipes, ducts, and equipment so that they do not interfere with the intended use of eyebolts and other lifting devices. Assure all controls can be reached and operated.
1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the Work depends on installation of other components before or after that part.
2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.
3. Minimize roof penetrations.
B. Notification: Prepare and distribute memoranda to each party involved, outlining special procedures required for coordination. Include notices, reports and meeting minutes as part of the memoranda.
C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work.
Administrative procedures include but are not limited to the following:
1. Preparation of schedules.
2. Installation and removal of temporary facilities.
3. Security packages and systems by others (i.e. U.S. Marshals Service (USMS), Federal
Protective Service (FPS), tenants, etc.)
4. Audio Visual (AV) and technology requirements and packages for tenants and/or end users.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 2/7
5. Telecommunication, data, internet and other tele-work systems for GSA, tenants and/or end users.
6. Delivery and processing of submittals.
7. Progress meetings.
8. Project closeout activities.
9. Startup and adjustment of systems.
1.3 CONSERVATION
A. Coordinate conservation of energy, water and materials in the conduct of construction operation.
Salvage materials and equipment involved in the performance of, but not incorporated into, the
Work.
B. Waste Management Plan: Establish a program to maximize recycling of waste materials. Program shall include the following:
1. Designation of a waste management coordinator.
2. Identification of recyclable materials.
3. Identification of available local recycling firms and agencies to receive recyclable materials.
4. Establishment of quantity goals for collection of each recyclable material.
5. Designation of one or more locations on the project site for collection, sorting and temporary storage of recyclable materials.
6. Means and schedule for transporting and delivery of recyclable materials to recycling firms and agencies.
7. Implementation of the Waste Management Plan: Contractor's waste management coordinator shall provide on-site instruction of workers in the identification, separation and handling of recyclable materials, and shall manage the process for the duration of the
Contract.
a. Contractor shall lay out and define specific areas to facilitate separation of materials for recycling, and shall maintain collection bins clearly marked to avoid contamination of the recyclable materials.
b. The waste management coordinator shall report monthly, in writing, the quantity of each recyclable material collected during the previous month and cumulatively to date, compared to the quantity goal, and other points of interest. Copies of each report shall be distributed to each significant stakeholder of the project, including the
Government.
1.4 ADMINISTRATIVE AND SUPERVISORY PERSONNEL
A. The Contractor shall provide administrative and supervisory personnel for proper performance of the Work.
B. Project Coordinator: Provide a full-time project coordinator, experienced in the administration and supervision of building construction, including all systems required in the project. The project coordinator shall be authorized to act as the coordinator of construction activities, including but not limited to the following:
1. Scheduling and sequencing of Work.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 3/7
2. Sharing access to work spaces.
3. Installations.
4. Protection of work.
5. Cutting and patching.
6. Selections for compatibility.
7. Preparation of coordination of drawings.
8. Inspection and tests.
9. Temporary services and facilities.
C. Safety and Health Officer: Provide a safety and health officer whose duties shall consist of developing and implementing safety and health programs specified in Division 1 Section "Safety and Health."
D. Provide a waste management coordinator whose duties shall consist of developing and implementing a program for maximizing recycling of waste.
1.5 CONFERENCES AND MEETINGS
A. Preconstruction Conference: The government shall schedule a preconstruction conference before starting construction at a time and place convenient to the Contractor. The conference shall review responsibilities and personnel assignments.
1. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and shall minimally include representatives of the following parties:
a. Government.
b. Architect.
c. Major design consultants.
d. Contractor.
e. Major subcontractors.
f. Major suppliers.
g. Other concerned parties.
2. Agenda: Subjects for discussion shall include items of significance that could affect progress, including but not limited to the following:
a. Tentative construction schedule.
b. Critical work sequencing.
c. Designation of responsible personnel.
d. Procedures for processing field decisions and Change Orders.
e. Procedures for processing Applications for Payment.
f. Distribution of Contract Documents.
g. Submittal of Shop Drawings, Product Data, and Samples.
h. Preparation of Record Documents.
i. Use of the premises.
j. Parking availability.
k. Office, work, and storage areas.
l. Equipment deliveries and priorities.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 4/7
m. Safety procedures.
n. First aid.
o. Security.
p. Housekeeping and progress cleaning.
q. Working hours.
r. Energy and resource efficiency / sustainability
s. Waste management
t. Commissioning
B. Progress Meetings: The Government or designee shall conduct progress meetings at the Project
Site at regular intervals. Dates of meetings shall be coordinated with preparation of the payment request.
1. Attendees: In addition to the Contractor's and Government's representatives, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.
a. Contractor's Construction Schedule: Review progress since the last progress meeting.
Determine where each activity is in relation to the Contractor's Construction
Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do
so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time. Provide 2 week schedule look ahead.
b. Review the present and future needs of each entity present, including but not limited to the following:
1) Interface requirements.
2) Time.
3) Sequences of operations.
4) Status of submittals.
5) Deliveries.
6) Off-site fabrication.
7) Access.
8) Site utilization.
9) Temporary facilities and controls.
10) Hours of work.
11) Hazards and risks.
12) Housekeeping and progress cleaning.
13) Quality and work standards.
14) Change Orders.
15) Documentation of information for payment requests.
16) Updating of Record Documents.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 5/7
3. Schedule Updating: The Contractor shall revise the Contractor's Construction Schedule after each progress meeting where revisions to the schedule have been made or recognized.
The revised schedule shall be issued concurrently with the report of each meeting.
C. Project Closeout Conference: GSA will schedule and conduct a Project closeout conference, at a time convenient to Contractor, CM and Architect, but no later than 90 days prior to the scheduled date of Substantial Completion.
Attendees: Authorized representatives of GSA, CM, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
1. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:
a. Preparation of record documents.
b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.
c. Coordination of final commissioning requirements and submittal of written warranties.
d. Requirements for completing sustainable design documentation.
e. Requirements for preparing operations and maintenance data.
f. Requirements for delivery of material samples, attic stock, and spare parts.
g. Requirements for demonstration and training.
h. Preparation of Contractor's punch list.
i. Procedures for processing Applications for Payment at Substantial Completion and for final payment.
j. Submittal procedures.
k. Coordination of separate contracts, if any.
l. GSA's partial occupancy requirements.
m. Installation of GSA's furniture, fixtures, and equipment.
n. Responsibility for removing temporary facilities and controls.
2. Minutes: Entity conducting meeting will record and distribute meeting minutes within 3 working days. Meeting Minutes should be uploaded or documented within ePM.
1.6 UTILITY SERVICE INTERRUPTIONS
A. Utility Service Interruption Plan: Within 4 calendar days from Notice to Proceed (NTP)
Contractor shall submit a utility service interruption plan for the project. Plan shall include dates and times of each scheduled interruption, with estimated period of outage, list of existing equipment that will be affected by the interruption, proposed sequence of equipment shut-down and start-up, and responsible personnel.
1. Keep interruptions and periods of interruption to a minimum.
2. Schedule interruptions during times when the facility is unoccupied.
3. Plan must be approved in writing by the Building Manager and the Government or the
Government's representative. If not approved, consult with the Building Manager, and revise and resubmit the plan until approved.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 6/7
B. Coordination of Interruptions: Sufficiently in advance of each scheduled utility interruption, the
Contractor shall issue a notice to all affected parties, confirming each provision of the interruption, or canceling and rescheduling. Coordinate with the Building Manager and Government's representative, and confirm that the responsible personnel are prepared to execute the shut-down and start-up of affected existing equipment, prior to each interruption.
1.7 SUBMITTALS
A. Subcontract List: Within 7 calendar days from Notice to Proceed (NTP) prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, and telephone number of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
4. Coordination Drawings: Comply with the shop drawing requirements specified in Division
1 Section "Submittal Procedures".
B. Waste Management: Within 10 calendar days after commencement of construction, submit the waste management plan, followed by monthly implementation reports.
C. Staff Names: Within 10 calendar days after commencement of construction, submit a list of principal staff assignments, including the superintendent and other primary personnel at the Project site. Identify individuals by name, duties and responsibilities, home address, and business and home telephone numbers.
1. Post copies of this list in ePM, in the project meeting room, temporary field office and at each temporary telephone location.
D. Utility Service Interruptions: No later than 4 calendar days prior to the first planned interruption, submit the utility service interruption plan, followed by confirmed scheduled shut-down notices at least 3 calendar days prior to each interruption.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION
3.1 GENERAL COORDINATION PROVISIONS
A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.
1. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
2. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of uncovering completed construction for that purpose.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 7/7
B. Construction in Progress: Keep construction in progress, and adjoining materials in place, clean during handling and installation. Apply protective coverings where required for protection from damage or deterioration.
C. Completed Construction: Clean completed construction, and provide maintenance, as frequently as necessary to prevent damage or soiling or other deterioration through the remainder of the construction period. Adjust and lubricate operable components as necessary to assure operability without damage.
D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging or otherwise deleterious conditions during the construction period. Such conditions include but are not limited to the following:
1. Excessive static or dynamic loading.
2. Excessive internal or external pressures.
3. Excessively high or low temperatures.
4. Thermal shock.
5. Excessively high or low humidity.
6. Pollution and air contamination.
7. Water or ice.
8. Chemicals and solvents.
9. Light.
10. Radiation.
11. Puncture.
12. Abrasion.
13. Heavy traffic.
14. Soiling, staining, and corrosion.
15. Bacteria.
16. Rodent and insect infestation.
17. Combustion.
18. Electrical current.
19. High-speed operation.
20. Improper lubrication.
21. Unusual wear or other misuse.
22. Contact between incompatible materials.
23. Destructive testing.
24. Misalignment.
25. Excessive weathering.
26. Unprotected storage.
27. Improper shipping or handling.
28. Theft or vandalism.
END OF SECTION 013100
CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 1/2
SECTION 01 32 00 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes certain schedules and reports required for documenting the progress of construction during performance of the Work.
B. Coordinate the timing for preparation and processing of schedules and reports with the performance of other construction activities, and maintain a consistent and logical correlation between updated schedules and reports.
C. All construction progress documentation should be created and transmitted electronically into
GSA’s electronic Project Management (ePM) database system.
1.2 SCHEDULE OF INSPECTIONS AND TESTS
A. Prepare and submit a schedule of inspections, tests and similar services required by the Contract
Documents within 10 calendar days after issuance of the Notice to Proceed.
B. Contractor shall coordinate the schedule of inspections and tests with the Construction Schedule and other related documents. Prepare the schedule in tabular form, including but not limited to the following information:
1. Specification section number.
2. Description.
3. Identification of applicable standards.
4. Identification of methods to be used.
5. Number of inspections, tests or similar services.
6. Time schedule or time span.
7. Responsible entity.
8. Requirements for taking samples.
9. Unique characteristics.
C. Distribution: Submit in ePM electronic copies of the schedule of inspection and tests to the
Contracting Officer, entities designated by the Contracting Officer, and each party involved in performance of portions of the Work where inspections, tests and similar serviced are required.
1.3 SCHEDULE OF SUBMITTALS
A. Prepare and submit a schedule of submittal required by the Contract Documents within 14 calendar days after issuance of the Notice to Proceed.
B. Contractor shall create in ePM the schedule of submittals and other related documents. Prepare the schedule in tabular form, including but not limited to the following information:
CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 2/2
1.4 REPORTS
A. Daily Construction Reports: Prepare electronic daily construction report recording the following information concerning but not limited to events at the site. All daily reports are to be uploaded to
GSA’s e-PM Include:
1. List of subcontractors at the site.
2. List of separate contractors at the site.
3. Count of personnel at the site.
4. High and low temperatures, general weather conditions.
5. Accidents.
6. Meetings and significant decisions.
7. Unusual events (see D. Unusual Event Reports below).
8. Stoppages, delays, shortages, and losses.
9. Emergency procedures.
10. Orders and requests of governing authorities.
11. Change Orders received or implemented.
12. Services connected or disconnected.
13. Equipment or system tests and startups.
14. Partial completions or occupancies.
15. Summary of all work performed.
B. Material Location Reports: At not more than weekly intervals, prepare a comprehensive list of materials delivered to and stored at the site. The list shall be cumulative, showing materials previously reported plus items recently delivered. Include a statement of progress on and delivery dates for materials or items or equipment fabricated or stored away from the site. Within 30
Calendar days submit copies of the list to the Contracting Officer (CO) or Contracting Officer's
Representative (COR).
C. Field Correction Reports: When the need to take corrective action requires a departure from the
Contract Documents, prepare a detailed report. Include a statement describing the problem and recommended changes. Indicate reasons the Contract Documents cannot be followed. Within [X]
Calendar days submit a copy to the Contracting Officer or Contracting Officer's representative for approval.
D. Unusual Event Reports: When an event of an unusual and significant nature occurs at the site, prepare a detailed report. List the chain of events, persons participating, response by the
Contractor's personnel, evaluation of the results or effects, and similar pertinent information.
Within 2 Calendar days submit a copy to the Contracting Officer or Contracting Officer's representative immediately. Advise the Contracting Officer or Contracting Officer's representative in advance when such events are known or predictable.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION (Not applicable)
END OF SECTION 013200
SUBMITTAL PROCEDURES 01 33 00 - 1/7
SECTION 01 33 00 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes certain administrative and procedural requirements for shop drawings, coordination drawings, schedules, samples and certain other quality assurance submittals.
B. This section does not include requirements for the following submittals that are included in their specific sections:
1. Inspection and test reports specified in Division 1 Section "Quality Control."
2. Warranties specified in Division 1 Section "Product Requirements."
3. Closeout submittals specified in Division 1 Section "Closeout Procedures."
4. Record documents specified in Division 1 Section "Project Record Documents."
5. Operation, maintenance and instruction manuals specified in Division 1 Section "Operation and Maintenance Documentation."
6. Reports, schedules and other submittals specified in Division 1 Section "Construction
Progress Documentation".
C. Shop drawings, coordination drawings and schedules are further categorized and defined as follows:
1. Shop drawings include drawings and schedules prepared for specific parts of the project, except for coordination drawings.
2. Coordination drawings are specified in Division 1 Section "Project Management and
Coordination."
3. Product data includes manufacturer's standard catalogs, pamphlets and other printed materials that show and describe materials and items, and includes but is not limited to the following:
a. Product specifications.
b. Installation instructions.
c. Color charts.
d. Catalog cuts.
e. Rough-in diagrams and templates.
f. Wiring diagrams.
g. Performance curves.
h. Operational range diagrams.
i. Mill reports.
D. Other quality assurance submittals include materials specifically prepared for the project, except drawings and schedules, and include but are not limited to the following:
1. Design data and calculations.
2. Certifications of compliance or conformance.
3. Manufacturer's instructions and field reports.
SUBMITTAL PROCEDURES 01 33 00 - 2/7
E. Approvals do not supersede requirements of the contract documents.
1.2 GENERAL SUBMITTAL REQUIREMENTS
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities and with the Submittal Schedule specified in Division 1 Section
"Construction Progress Documentation". Unless otherwise specified, submittals shall be transmitted via GSA’s electronic Project Management (ePM) system as PDF electronic files to
GSA according to the contractor’s approved construction schedule and submittal schedule. .
Transmit each submittal sufficiently in advance of the scheduled performance of related construction activities to avoid delaying the Work, allowing for the review times specified for submittals.
1. Coordinate each submittal with other submittals and related activities that require sequential scheduling, to allow for testing, purchase, fabrication and product delivery in a timely manner.
2. Schedule transmittal of different categories of submittals for the same element of Work and for different elements of related parts of the Work at the same time. Notwithstanding the foregoing sentence, the Contractor shall provide a complete submittal package for each
Division of the specification so as to enable the Government to review the related sections together. Coordinate submittals to enable approvals and acceptances so as not to inhibit orderly progress of the Work.
3. Post electronic submittals as PDF electronic files directly to the ePM system specifically established for the Project. GSA will return annotated file. Annotate and retain one copy of file as an electronic project record document file.
4. Allow sufficient time for submittal review, corrections following the initial review, and re-submittal review before activities scheduled after the submittal approval.
5. Failure on the part of the Contractor to indicate approval or acceptance on submittals prior to submission to Contracting Officer will result in their being returned to the Contractor without being acted upon.
6. Any resubmission required after Government review shall be made within 10 calendar days after return of the submittal, unless specifically authorized otherwise by GSA.
7. Submittals which are determined to be incomplete or otherwise substandard will be returned to the Contractor with no further review. Delays due to incomplete or rejected submittals will not be excused.
8. Construction will not be allowed to proceed if submittals are not received in a timely manner, and will not result in an extension to the Contractor's Construction Schedule.
9. Failure by the Contractor to provide the required submittals in a timely manner may result in withheld payments until submittals are up-to-date.
10. Maintain one complete set of submittals at project site.
11. Maintain an organized submittal register at project site. This will be an agenda item for progress meetings.
12. The contractor to schedule and allow a minimum of ten working days for the
Architect/Engineer submittal review. The comment period initiates upon the receipt of the submittal by the office performing the primary review. The period commences upon issue of the submittal by the office performing the primary review. In the event the architect/engineer receives an extraordinary lengthy or complex submittal whose review may not be able to be accomplished within the stipulated submittal review period, architect/engineer to notify the Construction Manager Agency (CMa) in writing with a
SUBMITTAL PROCEDURES 01 33 00 - 3/7
request for extended review period within 3 working days of receipt of the submittal. Such submittals may include structural steel, curtain wall, or complex systems requiring coordination with other systems.
B. Submittal Identification and Information: Identify and incorporate information in each electronic submittal file as follows:
1. Assemble each submittal item into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each submittal item.
2. Name file with submittal number or other unique identifier, including revision identifier.
a. File name shall use Contract number and Specification Section number followed by a decimal point and then a sequential number (e.g., LNHS-061000.01). Re-submittals shall include an alphabetic suffix after another decimal point (e.g., LNHS-
061000.01.A).
3. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by GSA.
4. Transmittal Form for Electronic Submittals: Use software-generated form from electronic project management software acceptable to GSA.
a. Project name.
b. GSA project number.
c. Date.
d. Name and address of Architect.
e. Name of Contractor.
f. GSA contract number.
g. Name of firm or entity that prepared submittal.
h. Names of subcontractor, manufacturer, and supplier.
i. Category and type of submittal.
j. Submittal purpose and description.
k. Specification Section number and title.
l. Specification paragraph number or drawing designation and generic name for each of multiple items.
m. Drawing number and detail references, as appropriate.
n. Location(s) where product is to be installed, as appropriate.
o. Related physical samples submitted directly.
p. Indication of full or partial submittal.
q. Transmittal number, numbered consecutively.
r. Submittal and transmittal distribution record.
s. Other necessary identification.
5. Include the following information as keywords in the electronic file metadata:
a. Project name.
b. GSA project number.
c. Contract number.
d. Number and title of appropriate Specification Section.
e. Specification paragraph number and generic name of each item.
SUBMITTAL PROCEDURES 01 33 00 - 4/7
f. Manufacturer name.
g. Product name and model number.
1.3 SHOP DRAWINGS AND COORDINATION DRAWINGS
A. Submit originally prepared information, drawn accurately to scale. Do not reproduce Contract
Documents or copy standard printed materials as the basis for Shop Drawings and Coordination
Drawings.
B. Include at minimum the following information on Shop Drawings and Coordination Drawings:
1. Dimensions.
2. Identification of products and materials.
3. Compliance with specified standards.
4. Notation of coordination requirements.
5. Notation of dimensions established by field measurements.
6. Highlighted or encircled deviations from the Contract Documents.
C. Sheet size: Except for templates, patterns and similar full-size drawings, submit Shop Drawings and Coordination Drawings on sheets of at least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 40 inches (750 by 1000 mm).
D. Submittals: Unless otherwise indicated, submit one electronic file (.pdf) of each drawing submittal through ePM. The file will be marked with action taken and returned.
E. Distribution: When submittal is approved or accepted, Contractor shall prepare final electronic files, for the following purposes.
1. One file shall be marked and retained as a "Record Document."
2. Unless otherwise requested, one file shall be provided to the Contracting Officer.
3. Additional prints shall be provided to the entities involved in the construction.
4. Prints will be included in the Operation and Maintenance manuals.
1.4 PRODUCT DATA
A. Collect Product Data into a single submittal for each system or element of construction. Mark each copy to show specific product choices and options applicable to the project. Product Data shall include the following information, where applicable:
1. Manufacturer's printed recommendations.
2. Compliance with recognized trade association standards.
3. Compliance with recognized testing standards.
4. Applicability of testing agency labels and seals.
5. Notation of dimensions verified for fit by field measurements.
6. Notation of coordination requirements.
B. Preliminary Submittal: Prior to submittal of complete Product Data, submit a preliminary single copy of that part of Product Data when selection of options is required, such as for color charts.
SUBMITTAL PROCEDURES 01 33 00 - 5/7
Preliminary submittal will be returned, with selection noted, for the Contractor's use in subsequent submittals.
C. Submittals: Unless otherwise indicated, submit one electronic copy of each Product Data submittal. One original copy will be retained and a copy will be marked with action taken and returned to the contractor.
D. Distribution: When submittal is approved or accepted, Contractor shall distribute copies for the following purposes:
1. One copy shall be marked and retained as a "Record Document."
2. Additional copies shall be provided to the manufacturers, subcontractors, suppliers, installers, governing authorities and others as required for performance of the applicable construction activities.
3. Copies required for operation and maintenance manuals
1.5 SAMPLES
A. Submit full-size, fully fabricated samples, cured and finished in the manner specified. Samples shall be physically identical to the material or product proposed for use.
B. Mount, display, or package samples to facilitate review of kind, color, pattern, texture and other qualities indicated, as a final check of these characteristics with other elements and for comparison of these characteristics with those of the actual component delivered and installed.
C. Where variation in color, pattern, texture or other characteristic is inherent in the material or product, submit at least 3 multiple units that show approximate limits of the variations.
D. Refer to other specification sections for requirements for samples that illustrate workmanship, fabrication techniques, and details of assembly, connections, operations and similar construction characteristics.
E. Refer to other specification sections for samples to be returned to the Contractor for incorporation in the Work. Such samples must be in undamaged condition at time of use.
F. Preliminary Submittal: Where color, pattern, texture or similar characteristics are specified to be selected from a manufacturer's range of standard choices, submit a preliminary single set sample of available choices prior to submittal of the complete sample. Preliminary submittal will be returned, with selection noted, for the Contractor's use in subsequent submittals.
G. Submittals: Unless otherwise indicated and except for field samples or mock-ups of full-size physical examples erected on-site or elsewhere, submit not less than [Edit] three (3) or [_X_] sets of each sample submittal. One copy will be marked with action taken and returned. Comply with requirements in the individual specification section for field samples and mockups.
H. Distribution: Except for field samples or mockups, when submittal is approved, Contractor shall distribute approved copies for the following purposes:
1. One copy shall be marked and retained as a "Record Document" at the Project Site, and shall be available for comparison throughout the course of construction activity.
SUBMITTAL PROCEDURES 01 33 00 - 6/7
2. Additional copies shall be provided to manufacturers, subcontractors, suppliers, installers, governing authorities and others as required for performance of the applicable construction activities.
1.6 OTHER QUALITY CONTROL SUBMITTALS
A. Submit other quality control submittals in compliance with requirements in the individual specification sections, including Division 1.
B. Certifications: Submit notarized certifications indicating compliance with specified requirements.
Certifications shall be signed by an individual authorized to sign on behalf of the Contractor.
1.7 REVIEW ACTION ON SUBMITTALS
A. For electronic submittals,
1. Submit electronic submittals via ePM as PDF electronic files.
a. GSA will return annotated file. Annotate and retain one copy of file as an electronic
Project record document file.
B. Compliance with specified characteristics is the Contractor's responsibility, and is not part of the
Contracting Officer's review and indication of action taken.
The contract documents shall prevail in case of review action conflict.
C. Submittals without approval or acceptance shall not be used.
D. Action Stamp:
1. For paper or non-electronic submittal: Each submittal will be stamped with a uniform action stamp. The stamp shall be marked to indicate one of the following actions taken:
a. For electronic submittal: Provide a digital signature with digital certificate on electronically submitted certificates and certifications where indicated. For notarized signature if required, provide paper copies for signature.
b. Final Unrestricted Release: Where marked "Approved" or "Accepted", the work covered by the submittal may proceed, provided it complies with the requirements of the Contract Documents.
c. Final But Restricted Release: Where marked "Approved " or "Accepted" "As Noted", the work covered by the submittal may proceed, provided it complies with the notations or corrections on the submittal and with the requirements of the Contract
Documents.
d. Return for Re-submittal: Where marked "Not Approved" or "Not Accepted", Revise and Resubmit", do not proceed with the work covered by the submittal, including purchasing, fabrication, delivery or any other activity. Revise or prepare a new submittal according to the notations on the submittal or on the return transmittal.
Resubmit without delay, repeating as necessary to obtain a final release action mark.
e. No Action: Where a submittal is for the record or for information or for another purpose not requiring review action, the submittal may not be returned or may be returned and marked "Action Not Required."
SUBMITTAL PROCEDURES 01 33 00 - 7/7
E. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. For equipment, include the following in addition to the above, as applicable:
a. Wiring diagrams showing factory-installed wiring.
b. Printed performance curves.
c. Operational range diagrams.
d. Clearances required to other construction, if not indicated on…