FASTC CONTRACT 03 (Design Pack 4)
BID QUESTIONS SPREADSHEET
Government Assigned Number
QUESTION ANSWER
33 There is reference to several sensitive sites such as 44NT0210. I could not find a document that had descriptions of these sites in them. Please advise.
Refer to Environmental Impact Statement (EIS) for descriptions of the sensitive sites. The EIS is a public document and can be found on the Department of State website at the following URL:
https://2009-2017.state.gov/documents/organization/241072.pdf
Volume I-B Sheet CJ.04.1.04 shows 3’-0” wide concrete stoops and leadwalks from the sidewalks to the modular building doors. Sheet L.04.1.23 shows 4’ wide aggregate landing and path from the sidewalks to the modular building doors.
Please confirm the material to be used from the modular building doors to the sidewalks.
In the case of discrepancies for pedestrian walkway dimensions and materials, all work shall be provided in accordance with the Landscape (L series) Drawings. The Landscape Drawings will be revised in Addendum B to provide concrete leadwalks as opposed to aggregate. CJ-series drawings will be revised to coordinate with the Landscape Drawings.
Volume I-B Sheet A.04.1.03 at south east corner of Mock Embassy compound there is a note calling for a 10’ high simulated modular concrete wall. Please provide structural drawings and specifications for this work.
The simulated concrete wall is to be provided as a delegated design included in the Modular Training Structures specification. Further description will be added ot the specification via forthcoming addendum.
Volume I-B Sheet A.04.1.03 Mock Embassy site plan shows in plan view & elevation, two double gates with side panels. Please provide structural drawings and specifications for this work.
The compound gates are to be provided as a delegated design included in the Modular Training Structures specification. Further description will be added ot the specification via forthcoming addendum.
Volume I-B Sheet A.04.2.01 The exterior stairs at MOUT training area do not show any foundations. Please provide foundation design to support exterior stairs and landings.
Foundations will be provided for the exterior steel stairs for Addendum B.
Volume II Sheet CJ.09.101 shows 3’-0” wide concrete sidewalks from existing doorways to new sidewalk. Sheet L.09.1.24 calls for 4’-0” wide concrete sidewalks.
Please confirm with of sidewalks from doorway to new sidewalk.
See Response to question # 35 above
Volume I-A Sheet A.00.4.00 – Accessories Legend; Keynote AC34 is noted as a shower curtain rod. Detail 2 references AC34 and looks to be a mop hook in utility room. Please confirm Keynote AC34 is to be a mop hook.
AC 34 is a mop hook. Drawings and specifications will be revised accordingly via addendum.
Volume II Sheet A.22.4.07 – Detail 3 Room 22.107 shows AC26 & AC27 point toward the lavatory counter. Elevation 12 does not show these items. Please confirm AC26 & AC27 are not required.
At that location AC26 and AC27 are not required. They are located within the space, just on the opposing walls. Drawing are being revised via Addendum B
Volume II Sheet A.22.4.07 – Detail 3 Room 22.107 & 22.108 shows AC35 (combo dispenser/waste). Elevation 10 call-out shows this as an AC27 (waste only). Please confirm this is to be AC35 (combo).
Confirmed, this is to be AC35 a combo unit.
Volume II Sheet A22.4.17 shows rectangles in floor space between banks of lockers in Mens and Womens Locker Rooms. Please advise what this is to represent.
Rectangles shown are lockerroom benches and they are NIC.
44 Volume II Sheet QF.22.4.01 Equipment List shows item #76 & 77 as millwork items. No details are provided.
Cashier stations are to be solid surface millwork similar to item 71 as detailed on the Architetcural drawings. Additional details will be provided via forthcoming addendum.
45 Volume IV Sheet S.51.1.02, Are the non-stair walls on a footing or a thickened slab? Typical walls section noted near Grid C:13 references a column detail.
The non-stair walls shown on the plan are on a thickened slab. The section cut should refer to 3/S.00.5.01.
46 Volume IV Sheet S.51.1.02, What is TOF elevation for the stair tower? The top of footing elevation for the stair tower is -1’-0”.
Government Assigned Number
QUESTION ANSWER
Spec Section 04 2200 - 2.12 makes reference to corefill insulation in the CMU, however the drawings do not call this out anywhere. Please confirm corefill insulation is not required.
Confirmed, corefill insulation is not required. The specification has been revised by Addendum B.
Spec Section 04 2200 - 2.6.L, integral water repellant is noted to be added to the mortar, however, integral water repellant is not required to be part of the concrete masonry unit mix design. Please confirm integral water repellant is not required in the CMUs and only to be included in the mortar.
Integral water repellant is to included within the concrete masonry unit mix design. The specifcation has been revised by Addendum B
In order to allow interested subcontractors and suppliers adequate time to assemble the best possible pricing for the project, we request an extension of at least 2 weeks. This is made for the following reasons:
•Overall size and complexity of the drawings •Design elements of the project that are done by the contractor, such as the pre-fabricated bridges •Short time between the site visit and the proposal due date •Slower document distribution due to SBU requirements
The due date for Step 2 proposals is extended to April 21, 2017 at 12:
00pm, Philadelphia local time. It should be noted that the deadline for questions related to amendment materials remains cob April 5, 2017.
Reference drawing CJ.06.5.03, Section C1. For the 1’-0” Walls at the ends of the sand pit is there a footing required under this wall? If so, please provide details.
Also, what is the reinforcing steel required in these walls?
Footing and reinforcing steel have been added to a revised Sheet CJ.
06.5.03 provided with Addendum B.
51 Reference drawing CJ.06.5.03, Section B2. Please provide any steel reinforcing details required in the two cattle guard areas at the ends of each sand pit.
Reinforcing steel has been added to a revised Sheet CJ.06.5.03 provided with Addendum B.
Reference drawing CJ.06.5.04. Please provide the following:
a. Is any reinforcing required in the concrete steps and top slab?
b. Please provide dimensions and concrete reinforcing details for the concrete parapet.
c. What is the required depth of the VDOT RW-2 retaining wall into the ground as dictated by the soil conditions?
Sheet CJ.06.5.04 has been revised and provided with Addendum B to include the following:
a)Reinforcing steel has been added to Sheet CJ.06.5.03.
b)Concrete parapet to be used is VDOT Standard MB-7F and attached to RW-2 wall in like fashion as the VDOT standard detail illustrates the #8 bar connection to the 18” footing.
c)The RW-2 wall extends 2’ below finished grade.
53 Reference drawing CJ.06.5.05. For the 8” concrete on the slopes is there any reinforcing steel required?
Reinforcing steel mat has been added to a revised Sheet CJ.06.5.05 provided with Addendum B.
54 Reference drawing CJ.06.5.07, Parallel Rails details. What is the required tie spacing and size to support the #4 longitudinal rebar shown?
Reinforcing steel has been updated on a revised Sheet CJ.06.5.07 provided with Addendum B.
55 Reference drawing CJ.06.5.08. Please provide any concrete reinforcing details required for the concrete abutments.
Reinforcing steel has been added to a revised Sheet CJ.06.5.08 provided with Addendum B.
56 Reference drawing CJ.06.5.10. Is any reinforcing steel required in the 8” concrete section at the base of the fording water and on the 5:1 concrete slope?
Reinforcing steel mat has been added to a revised Sheet CJ.06.5.10 provided with Addendum B.
57 Reference drawing CJ.06.5.12, Logs Plan details. What is the required tie spacing and size to support the #4 longitudinal rebar shown?
Reinforcing steel has been updated on a revised Sheet CJ.06.5.12 provided with Addendum B.
Government Assigned Number
QUESTION ANSWER
Reference drawing CJ.00.5.01. The note for the concrete pavement references drawings CJ.01.1.01, CJ.01.1.08 and CJ.01.1.09. These drawings could not be found in the drawing set. Please provide clarification on where these drawings are located.
Sheet CJ.00.5.01 has been revised in Addendum A to correct the sheet references.
Reference drawing S.22.3.01, sections 2, 3, and 11. For the 4” floating slab, the detail refers to Jack Upmounts and to refer to specifications. Specifications on this item could not be found. Please provide specification information for the jack upmounts.
Refer to revised specifications issues with Addendum A
Reference drawing A.04.1.01. At the entrances to the MOUT structures there is a typical note that says “Conc Step, See L Series, TYP”. When referencing the L Series drawing for the MOUT (L.04.1.23) at the entrance doors to the MOUT structures there is a 4’ wide compacted aggregate path or 4’ wide compacted aggregate pad. Please confirm we are to include what is shown on the L series drawing and there are no concrete steps at the MOUT structures.
Steps have been added in Addendum B.
Reference drawing A.04.1.03. At the entrances to the Mock Embassy structures there is a typical note that says “Stoop at Entrances TYP, see S-Series”. The S Series drawing for the Mock Embassy (S.4.1.03) do not show any concrete stoops.
Please confirm there are to be crushed gravel surrounding the Mock Embassy structures per the L series drawings.
All entries at the Mock Embassy and the MOUT are to have concrete stoops. Drawings will be revised accordingly via Addendum B.
Reference drawing 2/S.04.1.03 and 1/A.04.1.04. Both details indicate a Modular Simulated Wall with no details on the construction of this wall. Further referencing specification section 13 34 25 as reference on 1/A.04.1.04 there is no mention of this wall and any requirements for it in the specification. Please provide construction details and specification information for this wall.
The simulated concrete wall is to be provided as a delegated design included in the Modular Training Structures specification. Further description will be added ot the specification via forthcoming addendum.
Reference drawing CJ.09.1.01 and CJ.09.5.02. For the 50’ x 24’ pre-fabricated bridge shown on these drawings there is no design or elevations of the abutments required for the bridge support. Please provide design and details for the bridge abutments.
Reference Specification Section 34 8000, Division 34 Transportation in Volume IV of the Project Manual. All foundations for the prefabricated bridge are the responsibility of the Contractor and should be based on available nearby geotechnical data gathered for other structures in previously released packages. Since the foundation design will depend on the selected prefabricated structure, none are provided. Contractor should take note of the Scope Validation Period associated with this element of work.
Government Assigned Number
QUESTION ANSWER
Reference drawings S.09.1.02 through S.09.1.08, and drawing S.09.1.12. For the free standing façade structures there are footings/piers indicated on the drawings, but there is no reference to what size each pier is. The column size is labeled (i.e C2.10, C3.10), but there are no Px.10 indications on the foundation plans for which size pier is to be used. Furthermore, the Concrete Pier Schedule on S.09.1.12 has the diameter or size of the piers but no depth. Also, there is no pier for the C5.10 and C6.10 columns as indicated on the foundation plans. To summarize the following information is needed:
d. Pier size for each of the foundations for the free-standing façade structures
e. Depth of pier sizes P1.10, P2.10, P3.10, and P4.10
f. Size of pier for column labeled C5.10 and C6.10
There are no sub sections A,B,C in the question. The answer for D,E,F are as follows:
Pier designations are indicated on the foundation plan notes located on S.
09.1.02 through S.09.1.08, based on facade height. Pier types for all columns including columns C5.10 and C6.10 are determined this way.
The length and width of the piers are indicated in the pier schedule on S.
09.1.12. Minimum depths below grade are also provided in the schedule updated for Addendum A.
Reference drawing S.09.1.09 showing Huts A through E and Shed A. Please confirm that these buildings do not require a slab on metal deck. If no slab on metal deck is required for these roofs please provide typical detail for angle at perimeter and metal decking without concrete fill as this does not exist on the typical details on drawing S.00.5.07.
Huts A through E and Shed A will have no roof. CMU wall will be free-standing and shall be detailed as such.
Reference drawing S.22.1.01. The note for the grease interceptor opening states to reference detail 16/S.00.5.01. Detail 16/S.00.5.01 does not exist. Please advise what detail is to be used at the opening for the grease interceptor.
The 16/S.00.5.01 reference has been replaced by reference to 6/S.
00.5.02 on S.22.1.01 for Addendum B.
Reference detail 12/L.22.5.01 and 13/S.22.3.01. The L series drawing shows a wall drain and stone behind the retaining wall, whereas the S series does not. Please advise if the wall drain and stone is required behind all the retaining walls at the Fitness Center per the L series drawing.
Wall drain and stone shall be provided as required by the L series drawings. Structural drawing details describe structural scope and do not include this drain where it may be present. Refer also to keynote #28 on Sheet C.22.1.03.
Drawing CJ.03.1.02 indicates a 400’ x 200’ Ram Pad, but the Ram Pad Typical Section on drawing CJ.00.5.01 indicates a 300’ width. Please confirm that the dimensions shown on drawing CJ.03.1.02 are the correct design dimensions.
The 400’x200’ dimension shown on Sheet CJ.03.1.02 is correct.
Reference drawing S.36.1.01. Based upon the concrete pier schedule on this sheet and scaling the drawing the piers for the parking canopy are 4’ W x 4’ L x 8’ Deep.
The notation on the foundation plan for the P1.36 has two elevations – (0’-0”) and (-6’-0”). Please confirm the bottom of the pier elevation should be changed to (-8’ -0”).
The initial design for the bottom of pier elevation shall be -8-0" for all piers supporting the pre-engineered canopy. The foundation plan will be updated to reflect this for Addendum B.
Reference details 1, 2, 3, 6, 11, 12, 12, 14, and drawing A.00.5.09, they all reference for 06 16 00 WRB, but specification 06 16 00 doesn’t list a product for the WRB, please specify?
Specification information for Weather Resistent Barrier has been added to 06 1600 in Addendum B.
73 Reference details 1-4/A.005.08, please clarify if the classroom canopies are to be standing seam or corrugated metal roofing.
The roofs at the classrom building canopies are to be corrugated metal roofing per 07 6100 except that the profile shall be 16 Gauge with 7/8" thick sine wave corrugations. The specification will be revised accordingly in a forthcoming addendum.
Government Assigned Number
QUESTION ANSWER
Reference drawing S.51.1.24, Sheet Note 8. This note specifies that the max joint spacing for concrete walls is 70’-0”. This conflicts with detail 3/S.51.6.14 where the maximum joint spacing is listed as 24’-0”. Please confirm the max spacing of wall joints is 24’’-0”.
The maximum joint spacing is 70’-0” as shown on the plans. Detail 3/S.
51.6.14 will be changed to match for Addendum B.
Reference specification 13 34 25 2.1.A.4.c – Heating, the specifications for the modular training structure call for heat. Please clarify what the specific requirements for providing heat, are all units to receive unit heaters or only certain units?
Provide VRF Heat Pump units in Type B Modular units only for partial conditioning (approx. 45 BTU/hr per square foot). Provide dedicated Split Systems / VRF unit for each of two (2) CER Rooms at this venue for full 72F/50% RH conditioning. Further details to be provided in forthcming addendum
76 Reference drawings A.04.1.01 and A.04.1.2 – please specify the difference between a type B1 and B2 modular training unit?
Please refer to previous response to Question #5 and revised drawings issued with Addendum A
Reference drawing EP.04.1.02 through EP.04.1.05 regarding traffic signal hand holes. These drawings indicate that the hand holes are to be 4’x4’x4’ at a minimum per P100. Are these intended to be pre-cast hand holes similar to the telecom and electrical structures? Is there a list of all the required structures for this area?
Additionally, the conduit sizes connecting these hand holes are not indicated.
Please provide the required conduit sizes.
The hand holes are pre-cast similar to Telecom and Electrical structures.
There is no list of these typical structures. The conduit size shall be governed by General Note #5, indicating 2” Conduit, UNLESS otherwise specifically indicated on the plans.
Multiple drawings reference all supply and return ductwork to be Minimum 18GA and to have 1” acoustic liner (Example M32.1.01). Does this apply to ductwork labeled outside air (OA) that has been conditioned and feeding Terminal units to be treated as supply duct?
YES, this applies to OA duct. Further clarification will be provided in forthcoming addendum.
Multiple drawings show liner (L1 Tag or dashes) on supply air/return ductwork and not on other ductwork on drawings that call for liner on all supply/return ductwork (Example A09 Central Warehouse M23.1.01). Is duct liner only to be provided on ductwork indicated with and L1 Tag or dashes, or per the notes referencing all ductwork?
Lining is to be per drawings as shown. Specific clarifications to verbiage and missing ducts requiring lining will be provided in forthcoming addendum.
Is it a requirement to have all ductwork, both rectangular and round, that is indicated to have elastomeric internal liner to be double wall construction (per specifications on Metal ducts 233113.2.4.A.4 and 233113.2.4.C.8 and drawing M.
00.5.02 detail 3 note 6)? Typically this is only used for a fiberglass liner application.
Yes, all internally lined ductwork shall have double wall lining per P100, 5.3.5.9, even if elastomeric or non-fibrous. NOTE: Fiberglass duct liner is not acceptable.
Multiple buildings show low pressure round run outs to diffusers indicated to be internally lined (example M.32.1.01). Is this to be a double wall spiral product per the duct liner specifications referenced in question 37 above?
This is correct within the classroom buildings. Clarifications will be provided in forthcoming addendum..
Reference drawing CJ.09.1.01: Note in lower left corner of the sheet states that all driveways proposed within the rural simulation driving track shall be constructed with 6” of aggregate base material. Drawing CJ.00.5.01 contains a typical roadway section for the rural simulations alley with a prescribed pavement section per Inset C which consists of 8” of compacted aggregate. Please clarify the required depth of aggregate base material for these roadways.
Driveways are those perpendicular access roads from the mainline roadway to the Huts (A-E) and Shed (A). These shall be 6” depth as noted on CJ.09.1.01 while the mainline roadway depths shall be 8” per Inset C, Sheet CJ.00.5.01.
Government Assigned Number
QUESTION ANSWER
Volume IV Sheet 53.1.01, Door 53.103 [Weapons Vault] shows a Class 5 vault door and day gate. Volume I-A Sheet A.00.6.02 Door Schedule – Venue 53 – R07 shows Door 53.103 as HM door & frame with hardware. Please confirm a vault door is required for this location. Please confirm correct door size.
Door schedule has been revised via addendum.
Solicitation (C201) Section V.B.3 states “Contracting Officer may exercise the option by written notice to the Contractor within 60 calendar days of award.”
Construction Contract 3 (C101) Section II.A.(4) Options states “…Unless otherwise specified, all options may be exercised within 90 days of Contract award.” Please confirm the award period for Options will be within 60 calendar days after Contract award.
As stated at the Pre-Proposal Conference, GSA will decide which options will be exercised at the time of award.
85 Volume III Sheet A.36.1.01, Detail 2 refers to Spec Section 13 3440 for the parking canopy. This spec section does not exist. Please issue spec section 13 3440.
Specification section 13 3440 CARPORTS has been added via Addendum B
Volume II Sheet L.22.1.61 Planting Plan shows 8 canopy trees. Tree schedule on L.22.5.61 shows a quantity of 4 canopy trees. Please confirm a quantity of 8 canopy trees is required.
8 Canopy trees are required.
Volume II Sheet G.23.0.01 refers to the boundaries to Bid Option 7 – Central Warehouse, which includes boiretention pond 501 along Kemper Avenue and the storm line along the new drive including structures D4-507, 507A, 509 and 502 that falls within the Option 7 boundaries. Spec Section 01 2400 – 3.2.G.5. refers to only bioretention pond 503 and related piping to D4-502 to be part of Option 7. Please revise G.23.0.01 boundaries or revise Spec Section 01 2400 – 3.2.G.5 to reflect intended definition of Option 7.
The Extents line indicated on G.23.0.01 is to serve as a point of reference for the option description in 01 2400. Only the work included in the options descriptions in 01 2400 is to be included in the option. All other work is to be part of the base bid. Bioretention pond 501 and associated piping is not included in the options description and therefore shall be part of the base bid.
89 Volume I Sheet A.00.6.20 – Venue 22 – A08 – Room22.108 shows CT-1 as ceiling finish. Please confirm this is correct.
The ceiling finish is PNT. Finish schedule has been revised via Addendum B
Government Assigned Number
QUESTION ANSWER
Volume 4 Drawing B.51.1.01 - Are there any lateral load limits on the geothermal wells that are located within the building footprint of venue RO4 – 100M Outdoor Range? If the wells are installed prior to the structural steel, there could be significant loads imposed during the steel erection.
There are no lateral load limits available from either the International Ground Source Heat Pump Association (IGSHPA) or the UK Ground Source Heat Pump Association (GSHPA). However, there is some limited risk of damage to constructed boreholes following the placement of the structural steel load. We have discussed this potential risk with knowledgeable geotechnical engineers who have advised that us there should be no reliance on the boreholes to resist the lateral loads from the steel structure. In addition, presuming that the in-situ soil strength is sufficient, on its own, to resist bearing failure from the lateral load with adequate factor of safety, the contractor should demonstrate that the construction sequencing does not change the conditions during temporary works.
We also wish to point out that the headering / conveyance piping would be expected to have less tolerance to lateral loads than the vertical heat exchange piping and boreholes (due to the nature of electrofusion jointing along the headering pipes). In our experience, the headering piping is connecting after the placement of the structural steel, thus avoiding the impact of the placement of the steel on the headering piping. We recommend that the construction sequence be reviewed to identify if there is a potential risk to the integrity of the heading piping.
91 Volume 1, Part B, Drawing CJ.04.4.03 – Please provide a thickness and gradation for the ballast at the railroad crossing.
VDOT Standard 21A should be used as the substitute for railroad ballast and be 12” inches in thickness under the rail ties. Sheet CJ.04.4.03 has been updated to clarify and provided with Addendum B.
92 Volume 1, Part A, Drawing C.00.5.02 – Please provide the gravel thickness for the D05 West Access Road.
The D05 West Access Road pavement section shall be 14” of 21-A. Refer to revised Sheet C.00.5.02, Addendum B.
Is it intended that the materials for site grading designated as select fill and select material at various locations in the plans and specs are meant to be imported material or meant to be found on site?
If select materials are present on site the material may be used in construction. Additionally, with concurrence of the A/E and Government, the Contractor may borrow from areas within the LOD for select material and spoil unsuitable material so long as the requirements of the specifications are met and all grades match the finished grade at completion of the contract.
94 Is there a detail for the Hill Climb shown on page CJ.06.1.01 in volume 1? Is it the same as the hill climb shown on CJ.06.1.02?
The Hill Climb obstacle shown on Sheet CJ.06.1.02 is detailed on Sheet CJ.06.5.05. The Hill Climb shown on Sheet CJ.06.1.01 is a natural hill climb. The only Contractor work proposed is to clear undergrowth and provide the circuit through the woods over a naturally steep portion of existing terrain.
There are crash walls at D02A and D02B. The Civil drawings say refer to CJ-series sheets. There don’t seem to be CJ series drawings associated with these venues.
Ref. C.31.1.01 and C.32.1.03.
Reference Sheet CJ.03.1.02 for location of MB-7F barrier for D02A. The Crash Wall at D02B will be included in Package 3 scope via an ASI and should be considered “existing” for the purposes of this bid.
Government Assigned Number
QUESTION ANSWER
Is there a profile view of the retaining wall at the Urban Steps shown on page CJ.
06.5.04? also, the VDOT Standard reference doesn’t show rebar. What is the assumption on Rebar for the wall?
The profile has been added to a revised Sheet CJ.06.5.04 provided with Addendum B. The top of the wall profile has been shown to follow the top of the steps. In accordance with VDOT Standard RW-2, no reinforcing steel is required for the wall.
Ballistic Shooting Stalls (aka Firing Line Dividers) please advise which of the capability options should be priced in proposal: handgun or rifle rated dividers, and clear or solid color, or clear upper and solid lower panels should be provided in the dividers. These options create a potentially large variance in pricing.
Refer to revised specification issued in Addendum B
98 Please confirm if any of the optional items noted in specification 15-1310 I. are required to be priced into this project? Refer to revised specification issued in Addendum B
Drawing A.51.3.01 detail 4 Please confirm the required overall length of the overhead ballistic containment baffle sections (i.e. how many 4ft long panels to join together to create the desired full sections). Are the 11 inclined sections of 4x4 AR500 baffle panels between the two of the trap and the horizontal section each 8ft long? Is the horizontal section above the firing line 20ft long?
This has been addressed in Addendum B. See detail 1/A.51.5.12 for 25M panel dimensions. Overall baffle length is length of range end wall minus ½” each side (minus 1” total). 25M range is 100’-0” minus 1” = 99’-11” =
(12) 8’-0” panels + (1) 3’-11” panel. The horizontal baffle above the firing line is 20’-0” long. This has been updated per A/A.51.5.12 25 M Range Firing Wall Elevation. This has been addressed in Addendum B
Drawing A.51.3.01 detail 1 and 3 and drawing A.51.5.11 detail APlease confirm the required overall length of the overhead ballistic containment baffle sections (i.e.
how many 4ft long panels to join together to create the desired full sections). Are the 9 inclined sections of 4x4 AR500 baffle panels between the toe of the bullet trap (0 yard line) and the horizontal safety ceiling each 40ft long? Drawing A.51.5.11 detail 2 shows a ‘100m baffle section’ at 16ft long, but this doesn’t scale to the elevations and larger sections. Is the horizontal section 24ft long?
See detail 2/A.51.5.11 for 100M panel dimensions. Overall baffle length is length of range end wall minus ½” each side (minus 1” total). 100M range is 201’-0” minus 1” = 200’-11” = (12) 16’-0” panels + (1) 8’-11” panel. The horizontal baffle above the firing line is 22’-9” long. This has been updated per A/A.51.5.11 100 M Range Firing Wall Elevation. This has been addressed in Addendum B
101 Drawing A.51.5.11 detail A please confirm if the height of 3/8” AR500 steel plate above/behind the rubber media berm bullet trap in the 100m range is 7ft6in
Height of steel plate behind the bullet trap on the 100M range end wall is 8’-11””. This plate will run the full height of the wall above the target berm from the Bottom of Baffle elevation of 8’-4”. This has been addressed in Addendum B
Drawing A.51.5.12 detail A please confirm if the height of the 3/8” AR500 steel plate on the wall above/behind the rubber media berm bullet traps in the 25m ranges is 7ft 6in
Height of steel plate behind the bullet trap on the 25M range end wall is 3’ -10 1/2” from the 25 Meter TO Steel Plate elevation of 8’-3”. This has been addressed in Addendum B
Please confirm if the user will require a master targetry control computer in each range (to be able to operate all lanes or groups of lanes ‘in-unison’ and/or from pre-programmed scenarios)? If a master target control is required, is this computer to be located in the range control room, or a wireless handheld unit in the respective range?
Refer to revised specification issued in Addendum B
104 Refer to Package 4, Volume 2 Drawing, Sheet L22.1.21, Please provide a detail for the paving section on the asphalt service drive.
Refer to civil drawings, revised via addendum B for vehicular paving at service drive.
Government Assigned Number
QUESTION ANSWER
105 Drawing A22.4.04 indicates steel tubes at the Cafe Servery. These are not indicated on the structural drawings. Please provide details.
These tubes are called out under 05 50 00 and therefore do not appear on the structural drawings. These tubes are to be provided as supplementary support, if needed, to achieve the deflection criteria for partition walls defined in 09 10 00. Per 05 50 00, the tubes are to be located and sized by a professional engineer in order to meet these criteria.”
The term “Proposed” is used in various locations on the documents including CJ.
03.1.01 thru 03, CJ.04.4.04 thru 05, CJ.04.1.01 thru 05, CS.23.1.04, regarding gravel, sidewalks, ditches, traffic signalization, speed bumps, dumpsters, trash compactors, parking stripes. Are these to be excluded from the bid?
On C-series and CJ-series drawings the term “proposed” refers to work that IS INCLUDED in the scope of this bid as it pertains to gravel, sidewalks, ditches, traffic signals, speed bumps, and parking striping.
Dumpsters and Trash Compactors shown on CS.23.1.04 are NOT INCLUDED. The keynote will be revised in a forthcoming addendum.
Drawing CJ.06.5.03 indicates cattle guards. Section B2 indicates a structure below the grating that appears to be concrete, but it is not indicated. If so, is this precast or cast-in- place? Please provide details.
Reference Note 2, Sheet CJ.06.5.03 which indicates “concrete baths.”
For clarification purposes, all concrete elements in the Off Road Obstacle Areas shall be VDOT Class A4 concrete.
108 Reference bid option 3, are the ACT and gypsum board ceilings shown drawing A.
22.4.05 to be include in the base bid or bid option 3?
The ACT and gypsum board ceilings shown on A.22.4.05 are not included in the description of Option 3 in Specification 01 2400 and are therefore to be included in the base bid.
Reference drawing A.00.6.01 and A.22.1.01. Door 22.100.1 appears on sheet A.
22.1.01, but is missing from the door schedule, please specify what is to be provided for this door.
Door 22.100.1 does not exisit at A08. There is door E22.1.01.1, with the "E" designating that it is an exterior door. This is scheduled on A.00.6.01.
For Venue 23 and 53, both buildings are specified as pre-engineered metal buildings. At both the standing seam metal roofing and metal wall panels reference specification 13 34 19, but that specification references back to the drawings for the standing seam metal roofing and metal wall panels. Please confirm that we must provide the Centria Standing Seam Metal Roofing specified in 07 61 00 and the Metal Panels specified in 07 42 13 to match the other buildings.
The metal wall panel and roof system at A09 and R07 are to be part of the pre-engineered metal building system. The roof at A09 and R07 is not required to be by Centria, unless Centria is the roofing system used by the proposed metal Buiding System Manufacturer and if complies with all performance requirements. Specification section 13 3419 has been revised via Addendum B to provide additional information for the Metal Building System roof system and wall panels.
111 Reference drawings A.22.1.02, A.22.4.01, and A.22.5.01, please specify the exterior wall partition type behind the metal panels.
On the 2nd floor of A08 there is no partition beind the insulated metal panels; it is exposed.
112 Reference details 5&8/A.51.5.03, currently a wedge of wood blocking is required, to simplify this detail can the wood blocking be changed to insulation?
Alternate details and substitutions will be considered after award in accordance with 01 2500.
Detail 2/A.00.5.07 indicates a rake detail in which the rake becomes a shallow parapet. However, the wall sections do not show this condition. Please verify that there is no parapet at the rake conditions of the roof.
Detail 2/A.00.5.07 is correct, at A09/R07 the roof rake includes a shallow parapet or curb following the roof slope as described in the detail.
The RFP requires that we identify the Project Manager, Construction Superintendent and Project Scheduler in the technical response, please confirm these individuals need to be dedicated to the Contract 3 project.
The Project Manager and Construction Superintendent must be dedicated to the Contract 3 Project.
116 Please confirm that none of the buildings have any blast requirements. None of the buildings in Package 4 are required to be designed for blast.
Government Assigned Number
QUESTION ANSWER
Reference detail 4/A.32.4.00, the typical soffit assembly lists “AVB”, we assume this is an air vapor barrier, but there is no specification for an air vapor barrier, please clarify what is to be included for this item.
Refer to specification section 07 2700 AIR BARRIERS added via Addendum B.
Reference detail 4/A.32.4.00, there appears to be either a piece of stub steel or LGMF support left of the light fixture with no designation, please clarify what is to be included for this item.
Refer to details on A.00.5.14 as referenced from the RCP on A.32.1.11
Please clarify the following questions regarding the exterior wall cold metal framing at the classroom buildings:
a. Per the manufacturer recommendation, double studs are required at the joints for attachment, please confirm this is correct.
b. The manufacturer indicated the maximum metal panel length is 16’. The distance between the joints shown on the drawings is much larger. Please provide revised elevations showing correct joint spacing so the correct backup framing can be included.
a. A double stud behind vertical panel joints is correct.
b. The ispecifications are being revised via addendum to indicate an "embossed" finish at the metal panel. The BOD metal wall panel manufacturer can furnish embossed metal panels in 37' lengths. The joint spacing shown on the drawings is correct.
Reference Specification Section 13 34 20 – Metal Pedestrian Bridges, Section 2.2 D. For the chain link fencing at the pedestrian bridge there is missing information that needs to be filled in. Please provide.
Additional information has been provided to the specification as revised via Addendum B
Reference details 5&6/S.31.5.32, which are typical of all the classrooms buildings.
a. Please clarify if the canopies are to receive metal roof decking and corrugated metal roofing or just corrugated metal roofing.
b. If only corrugated metal roofing is required, the manufacturer recommends a center support, please specify if required.
a. Canopies are to receive corrugated metal roofing only.
b.The corrugated roofing shall be 16 gage, 7/8" thick sine wave corrugations. the specifcation will be revised accordingly via forthcoming addendum
Reference detail 12/A.09.5.01 shows a piece of bent plate supporting the corrugated metal roofing, but the structural detail 5/S.09.1.03, doesn’t show this plate. Please clarify if required and specify a size.
Bent plate is required. It is a 1/4" thick continuous bent plate at 4 1/2" H x 4" W.
The Pedestrian Bridge specification (Section 133420) indicates that manufacturers need to be pre-approved by the architect 5 days prior to the bid. What documentation must be supplied in order for the architect to review and approve?
Information as outlined in specification section 133420 shall be provided including documentation relevant to sections 1.1.C, 1.1.D, 2.4.A, 3.2.A.
Specification will be edited so that submittal information is not required before bidding for Addendum B.
Sheet A.09.1.07 indicates that the span length of the pedestrian bridge is 90’, however specification section 133420 indicates that it is 75’. Please confirm 90’ is the correct span.
E04 pedestrian bridge span shall be 89’ and will be updated on A.09.1.07 and specification section 133420 for Addendum B.
There does not appear to be a section view provided for the pedestrian bridge.
Please confirm that it is a half-through truss (open at the top) and does not require roofing, as there is a reference to it potentially being required in specification section 133420.
No roofing is required at the E04 pedestrian bridge. Clarification for this has been added to specification section 133420 for Addendum B.
Please clarify the safety system requirements for the pedestrian bridge. Vertical pickets are required per the specification. Fencing is referenced in the spec as well.
These are somewhat redundant safety systems, and typically only one or the other is required.
Fencing requirements have been revised in specification section 133420 for Addendum B.
Government Assigned Number
QUESTION ANSWER
130 Please confirm that the pedestrian bridge only needs to be galvanized and does not require painting as well.
Confirmed, sand blasting and galvanizing are the only finishes used for steel at the E04 pedestrian bridge. No painting is required.
Reference detail 1/A.09.4.03 issued with Addendum 1 showing the typical façade section. This detail indicates a smaller second pier or concrete enclosure at the base of the façade structural steel support framing. This smaller pier or enclosure is not detailed or sized on any drawings. Please provide details for this pier or enclosure.
Dimensioning and reinforcing for the secondary pier are provided in the E04 venue specific typical structural details, in detail 8/S.09.2.01 of Addendum A.
133 Reference drawing A.35.101. The detail for the carport references specification section 13 34 20 which does not exist. Please provide specification for 13 34 20.
Specification section 13 3440 CARPORTS has been added via Addendum B
Reference drawing M.51.1.02 for the items labeled as RD-B along column line 12.
Per the RCP plan on A.51.1.21, these are called out to be Radial Diffusers and to reference the M-series drawings. The M series drawings do not provide any further details for the radial diffusers except on M.51.1.02. Please provide further details for the radial diffusers.
This is as indicated on the diffuser schedule. Specifications will be updated in this Addendum B.
136 Reference drawing A.00.6.01 and A.22.1.01, doors 22.102.5 and 22.102.06 are shown on the floor plans, but are missing from the door schedule, please clarify. See response to question # 109 above
138 Reference A.04.1.03, please provide a section cut with details for the 10’ tall simulated modular container wall.
The simulated concrete wall is to be provided as a delegated design included in the Modular Training Structures specification. Further description will be added ot the specification via forthcoming addendum.
139 Reference A.04.1.03 and S.04.1.03, please provide foundation details for the two gates at the mock embassy. Typical foundation detail will be provided on S.04.1.03 for Addendum B.
Some of the venue bathrooms follow the toilet accessory schedule (Spec. 10 2813-
3) and list the mirror as AC 28 “SST Frame Mirror”, while other venue bathrooms do not list the type of mirror. Please confirm which venue bathroom mirrors are AC 28 “SST Frame Mirror”.
Confirmed all venues to have SST frame mirror (AC 28)
Addendum A was issued on 3/24/17 with a Package 4 Construction Documents listings of included documents. Please provide the following landscape drawings that are listed in Addendum A, but were not uploaded in the zip file on FedBizOpps:
L.00.1.61, L.22.1.21, L.22.1.61, L.22.2.01, and L.22.2.02.
The referenced sheets are being issued with Addendum B
142 Sheet L.09.1.26 specifies an Armag unit. However, no details or specifications are provided. Please confirm that this is not part of Contract 3 scope.
An Explosives Storage Magazine unit is to be provided at venue 09.
Specification 13 6000 "EXPLOSIVES STORAGE MAGAZINE" will be issued with Addendum B
Reference drawing L.09.1.25 specifies a 4’x4’ and 7’x4’ compacted aggregate pad.
However, the arrow does not point to anything. Please specify quantity and location of these compacted aggregate pads.
Those 2 notes should be deleted. The aggregate pads are located on the street side of those buildings only.
Reference sheets L.09.1.64 and L.09.5.61. L.09.1.64 calls for PL-5A planting soil mix. However, the planting legend on L.09.1.64 and L.09.5.61 do not specify what is PL-5A. Please specify what planting mix is included in PL-5A.
Refer to specification section 32 9200
145 Reference sheet L.22.1.21 and C.22.1.03. Please provide detail of the asphalt service drive.
For pavement section, refer to revised Detail #3, Sheet C.00.5.02 provided in Addendum B.
Government Assigned Number
QUESTION ANSWER
Reference sheet CS.23.1.04, note 6 refers to sheet L.00.5.02 for road end barrier details. However, sheet L.00.5.02 does not exist. Please provide detail for road end barrier.
Refer to revised Keynote #6, Sheet CS.23.1.04 provided in Addendum B.
See also sheet L.00.5.01 as revised in Addendum A
147 Note #11 on C.09.1.06 specifies a drop arm gate that appears to be outside Contract 3 LOD. Please confirm this is not part of Contract 3 scope.
The gate construction required by Note #11 IS INCLUDED in the scope of this bid. Refer to revised Keynote #11, Sheet C.09.1.06 provided in Addendum B.
Drawing M.00.9.01 Building Automation System Architecture shows a requirement to provide JACE panels and network switches at the list sown in Note 2. Regarding that list:
2.g. T03*** - I do not believe this venue included a JACE in the previous phase.
2.i. T05*** - I do not believe this venue included a JACE in the previous phase.
2.k. R03b* - This is part of Package 4, however there are no Mechanical Plans or Control drawings provided. Please provide a control drawing or list of systems/points to be integrated to BMS.
2.w. D02-1 Wet Track*** - Please provide a control drawing or list of systems/points to be integrated to BMS.
2.x. D02-2 Wet Track*** - Please provide a control drawing or list of systems/points to be integrated to BMS.
2.y. D02-3 Wet Track*** - Please provide a control drawing or list of systems/points to be integrated to BMS.
2.z. D03 Mock Embassy Structures*** - This is part of Package 4, however there are no Mechanical Plans or Control drawings provided. Please provide a control drawing or list of systems/points to be integrated to BMS.
Additionally, the “***” denotes “DOS to confirm requirement for JACE Panel”.
Please confirm if the BAS contractor is required to include a JACE and network switches in each of these *** venues in this bid, or if they are to be excluded until instructed otherwise.
2.g. - Revise T03*** to T03* and include a JACE Interface with Exhaust Fans 2.i. - Revise T05*** to T05* and include a JACE Interface with VRF Systems yet to be provided 2.k. - Interface with one, single VRF unit serving a CER located at this venue. Refer to typical points list for a CER split system / VRF unit.
2.w. - Specifications updated to indicate number of points expected.
2.x. - Specifications updated to indicate number of points expected.
2.y. - Specifications updated to indicate number of points expected.
2.z. - JACE Box / Boxes to be provided to integrate VRF split systems being provided at this venue. VRF systems are design build. Provide integration with two CER Room Split Systems at this venue.
where*** notes "DOS to confirm requirement for JACE Panel", these venues should be revised to include JACE Boxes and Network switches.
Refer to Addenda 002 drawing C.00.5.02, detail 6 references a PVC underdrain system. Can more information on the system, such as pipe size, length, spacing, etc., be provided?
Refer to revised Detail #6, Sheet C.00.5.02 provided in Addendum B.
Refer to revised Sheets C.51.1.03 and C.51.1.04 at Venue R02/R04 for length and spacing.