GLEN_13-1403_SOW_Addendum.pdf
PDF 47 KB Posted
- Attached to
- B500 HVAC Federal contract opportunity
- Solicitation number
- GLEN13-1403_Solicitation
About this file
SOW Addendum
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFI_Questions_3_Jul_2018.docx | DOCX document | |
| FA255018R1012_GLEN_13-1403_Amendment_002.pdf | ||
| M-101_-_MECHANICAL_DUCTWORK_FLOOR_PLAN_13-1403.PDF | ||
| Amendment_002_Information.pdf | ||
| Amendment_Information.docx | DOCX document | |
| 1_GLEN131403_SOW.pdf | ||
| 4_GLEN131403_AF_Form_66.xls | XLS spreadsheet | |
| 0_FA2550-18-R-1012.pdf | ||
| 3_Specifications.pdf | ||
| 5_Wage_Determination.pdf | ||
| 2_GLEN131403_Drawings.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Addendum 1
Project Number: GLEN 13-1403
Repair HVAC, B500
Schriever AFB, Colorado
12 June 2018
GLEN 19-2102
1.0 BACKGROUND:
An amendment for a SOW Addendum is necessary due to changes to the requirement.
2.0 SCOPE OF WORK:
The Contractor shall provide all labor, tools, and materials to complete all work represented by these changes. The Contractor shall still adhere to the original contract documents, including the original Statement of Work and the USACE final design Drawings and Specifications. All material and testing requirements from the original contract scope remain unchanged. The Contractor shall provide the Government with complete construction, and warranty for this project, to include both original and modified requirements.
3.0 MODIFIED REQUIREMENTS:
5.2.1 Demolition:
a. Demolish existing relief and return air dampers and actuators as indicated on the project drawings M-101.
b. Demolish the existing outside air and economizer dampers and actuators as indicated on the project drawings.
c. Demolish existing condensing unit CU-SSB-101 as shown project drawing M-101.
d. Demolish existing insulation on chilled water and steam lines in the mechanical room.
5.2.2 New Work:
a. Install new relief air damper actuator and return air camper actuator as indicated on the project drawings.
b. Install new outside air and economizer dampers as indicated on the project drawings.
c. Install new condensing unit comparable to the existing unit CU-SSB-101and associated valves and fittings.
d. Install new CO2, humidity, and differential pressure sensors as indicated on the project drawings. Update control sequence and graphics as necessary. Current controls contractor in B500 is HSQ.
e. Repair any damage to the facility and/or landscaping that is caused by the contractor.
f. Replace pipe insulation on chilled water and steam lines in the mechanical room.
g. Repaint piping on chilled water and steam lines in the mechanical room.
h. Replace relief air damper and return air damper. See keyed notes 1 & 2 on project drawing M-101.