Summary of SP2658 - Sewer Lateral Beach Restrooms Construction Contract
This document is the Construction General Conditions document for the City of Santa Monica's SP2658 Sewer Lateral Beach Restrooms project. The City of Santa Monica is soliciting electronic bids for construction work related to sewer lateral installations at beach restroom facilities. Bids must be submitted through the City's online vendor portal (OpenGov) at https://procurement.opengov.com/portal/santa-monica-ca by 5:00 p.m. on Friday, November 20, 2026. The bid opening will be conducted electronically, with all submitted bids viewable to the public immediately following the close of bidding. The General Conditions outline the administrative and operational requirements governing the construction contract, including the contractor's obligations for supervision, schedule management, quality control, inspections, and completion milestones including Substantial Completion and Final Completion.
The General Conditions establish comprehensive requirements for contractor performance, including provisions for labor, materials, workmanship, and compliance with all applicable codes and regulations. The contractor is responsible for all costs associated with the work, including labor, materials, equipment, permits, licenses, and taxes, with no adjustment to the contract sum except through formal change orders. Specific performance requirements include maintenance of daily reports, submission of construction schedules using the critical path method, and continuous update of as-built documents. The contract incorporates performance and payment bonds, insurance requirements, and indemnification provisions. Contractor delays are classified as either Compensable Delay (entitling the contractor to time and cost adjustments), Excusable Delay (time extension only), or Unexcused Delay (no relief), with strict notice and documentation requirements for all delay claims. The document does not specify the contract value, funding source, or incumbent contractor information.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION
GENERAL CONDITIONS
Sewer Lateral Beach Restrooms
SP2658
Public Works | General Conditions Construction | April 2022 i | P a g e
GENERAL CONDITIONS
TABLE OF CONTENTS
ARTICLE 1 – GENERAL PROVISIONS
1.1 DEFINITIONS
1.2 OWNERSHIP AND USE OF DOCUMENTS
1.3 AUTHORITY OF CITY
1.4 INTERPRETATION OF CONTRACT DOCUMENTS
ARTICLE 2 – CITY
2.1 INFORMATION AND SERVICES PROVIDED BY CITY
2.2 ACCESS TO PROJECT SITE
2.3 CITY'S RIGHT TO STOP THE WORK
2.4 CITY’S RIGHT TO CARRY OUT THE WORK
ARTICLE 3 – CONTRACTOR
3.1 REVIEW OF THE SITE, CONTRACT DOCUMENTS AND FIELD CONDITIONS
3.2 SUPERVISION AND CONSTRUCTION PROCEDURES
3.3 RESPONSIBILITY FOR THE WORK
3.4 LABOR, WORKMANSHIP, MATERIALS AND MANUFACTURED ITEMS
3.5 CONTRACTOR'S WARRANTY
3.6 CONSTRUCTION METHODS AND PROCEDURES
3.7 TAXES
3.8 LEGAL REQUIREMENTS
3.9 SUPERINTENDENT/PROJECT STAFF
3.10 SCHEDULES REQUIRED OF CONTRACTOR
3.11 DOCUMENTS AND SAMPLES AT PROJECT SITE
3.12 INTENTIONALLY LEFT BLANK SUBMITTALS
3.13 TRADE NAMES, SUBSTITUTIONS
3.14 DAILY REPORTS BY CONTRACTOR
3.15 CUTTING AND PATCHING
3.16 ACCESS TO THE WORK
3.17 ROYALTIES AND PATENTS
3.18 PERMITS AND LICENSES
3.19 DIFFERING SITE CONDITIONS
3.20 INSPECTIONS
Public Works | General Conditions Construction | April 2022 ii | P a g e
3.21 INDEMNIFICATION, STOP NOTICES
3.22 PARKING
3.23 USE OF THE PROJECT SITE AND CLEAN UP
3.24 ENVIRONMENTAL CONTROLS
ARTICLE 4 – ADMINISTRATION OF THE CONTRACT
4.1 CONTRACT ADMINISTRATION BY CITY, DESIGN CONSULTANT AND CONSTRUCTION MANAGER
4.2 CLAIMS
ARTICLE 5 – SUBCONTRACTORS
5.1 CONTRACTOR'S AWARD OF SUBCONTRACTS
5.2 SUBCONTRACTUAL RELATIONS
5.3 CONTINGENT ASSIGNMENT OF SUBCONTRACTS
ARTICLE 6 – CONSTRUCTION BY CITY OR BY SEPARATE CONTRACTORS
6.1 CITY'S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE CONTRACT….………………………
6.2 MUTUAL RESPONSIBILITY
6.3 CITY’S RIGHT TO CLEAN UP
ARTICLE 7 – CHANGES
7.1 CHANGES
7.2 CHANGE ORDERS AND CHANGE ORDER REQUESTS
7.3 FIELD ORDERS
7.4 DISPUTES REGARDING CHANGES
ARTICLE 8 – CONTRACT TIME
8.1 COMMENCEMENT OF THE WORK
8.2 PROGRESS AND COMPLETION
8.3 DELAY
ARTICLE 9 – PAYMENTS AND COMPLETION
9.1 SCHEDULE OF VALUES
9.2 PROGRESS PAYMENT
9.3 APPLICATION FOR PAYMENT
9.4 CERTIFICATE FOR PAYMENT
9.5 DEPOSIT OF SECURITIES IN LIEU OF RETENTION AND DEPOSIT OF RETENTION INTO ESCROW
9.6 BENEFICIAL OCCUPANCY
9.7 SUBSTANTIAL COMPLETION
9.8 FINAL COMPLETION AND FINAL PAYMENT
Public Works | General Conditions Construction | April 2022 iii | P a g e
ARTICLE 10 – PROTECTION OF PERSONS AND PROPERTY
10.1 SAFETY PRECAUTIONS AND PROGRAMS
10.2 SAFETY OF PERSONS AND PROPERTY
10.3 EMERGENCIES
ARTICLE 11 – INSURANCE AND BONDS
11.1 CONTRACTOR'S INSURANCE
11.2 BOND REQUIREMENTS
ARTICLE 12 – DEFECTIVE WORK
12.1 UNCOVERING OF WORK
12.2 CORRECTION OF DEFECTIVE WORK AND GUARANTEE TO REPAIR PERIOD
12.3 ACCEPTANCE OF DEFECTIVE WORK
ARTICLE 13 – STATUTORY REQUIREMENTS
13.1 NONDISCRIMINATION/EQUAL OPPORTUNITY
13.2 STATE LABOR LAW
13.3 PAYROLL RECORDS
13.4 APPRENTICES
13.5 WORK DAY
Public Works | General Conditions Construction | April 2022 1 | P a g e
ARTICLE 1 – GENERAL PROVISIONS
1.1 DEFINITIONS
Terms appearing in the Contract Documents with initial capitalization shall have the meanings set forth below:
1.1.1 ACCEPTANCE: The point after Final Completion when Contractor has fully performed all of the requirements of the Contract Documents and the Work is accepted by City in writing.
1.1.2 ADDENDA, ADDENDUM: Written or graphic information (including, without limitation, Drawings or Special Provisions and Technical Specifications) prepared and issued by Division Manager or its designee prior to the receipt of Contractor’s Bid, which modify or interpret the Bid Documents by additions, deletions, clarifications or corrections.
1.1.3 ALLOWABLE COSTS: Costs for which reimbursement is allowed under Article
7.2.5 of these General Conditions and for which reimbursement is allowed under other provisions of the Contract Documents, that may be added by Change Order to the Contract Sum for Extra Work or deducted by Change Order from the Contract Sum for Deleted Work.
1.1.4 ALTERNATE(S): Those portions of the Bid setting forth the price(s) for optional or alternative items of Work not covered by the Base Bid.
1.1.5 APPLICABLE CODE REQUIREMENTS: All applicable federal, state and municipal laws, statutes, building codes, ordinances and regulations of governmental authorities having jurisdiction over the Project, Work, Site, Contractor or City.
1.1.6 APPLICATION FOR PAYMENT: An itemized application for payment prepared and submitted by Contractor for review and approval by City, which is prepared, submitted and accompanied by supporting documentation in accordance with the requirements of the Contract Documents.
1.1.7 APPROVE, APPROVED or APPROVAL: Whether capitalized or not capitalized, shall mean, unless otherwise stated, either an express approval contained in a written statement signed by the approving individual or entity or deemed approved in accordance with the terms, conditions and procedures set forth in the Contract Documents. All such approvals by or on behalf of City (including, without limitation, approvals by Construction Manager) may be granted or withheld in the sole discretion of City.
1.1.8 AS-BUILT DOCUMENTS: The Contract Documents showing the condition of the Work as actually built, including, without limitation, the locations of mechanical, electrical, plumbing, HVAC or similar portions of the Work that are shown diagrammatically in the Contract Documents approved by City. These documents are maintained by Contractor on the Site and delivered, along with an electronic version of the set, to City upon Final Completion.
Public Works | General Conditions Construction | April 2022 2 | P a g e
1.1.9 BASE BID: The sum stated in the Bid to perform the Work, exclusive of any Alternate(s).
1.1.10 BENEFICIAL OCCUPANCY: City's right, at its option and convenience, to occupy or otherwise make use of all or any part of the Work prior to either Substantial Completion, Final Completion, or Acceptance.
1.1.11 BID: Contractor’s written bid proposal submitted to City for the Project in response to City’s Notice Inviting Bids.
1.1.12 BID DOCUMENTS: The following collection of documents are designated as the Bid Documents:
(i) Notice Inviting Bids.
(ii) Instructions to Bidders.
(iii) Blank Bid Form.
(iv) Construction Contract between City and Contractor.
(v) General Conditions.
(vi) Special Provisions and Technical Specifications.
(vii) Plans and Drawings.
(viii) Bidding Addenda.
(ix) Reports, Supplements, Attachments, Modifications, and Exhibits attached to the above items.
1.1.13 CERTIFICATE FOR PAYMENT: The form for approval by the Construction Manager of Contractor's Application for Payment.
1.1.14 CHANGE: Whether capitalized or not, when used in reference to changes in the Work is a generic term encompassing additions, deletion, alterations or changes in the Work, which may or may not involve Extra Work and for which Contractor may or may not be entitled to a Change Order under the terms of the Contract Documents.
1.1.15 CHANGE ORDER: A written instrument signed by City, or by City and Contractor, describing a Change to the Work of Contractor.
Public Works | General Conditions Construction | April 2022 3 | P a g e
1.1.16 CHANGE ORDER REQUEST: Contractor's written request for an adjustment in the Contract Sum or Contract Time due to a Change resulting in Extra Work or Deleted Work.
1.1.17 CITY: City of Santa Monica, a municipal corporation.
1.1.18 CLAIM: A written demand or assertion by City or Contractor seeking, as a matter of right, an interpretation of the Contract Documents, adjustment of the Contract Sum or Contract Time, payment of money, recovery of damages, resolution of a disputed interpretation of the Contract Documents, or other relief. A Claim does not include, and the procedures for processing of Claims do not apply to the following:
(i) Penalties or forfeitures prescribed by statute or regulation imposed by a governmental agency.
(ii) Tort claims for personal injury or death.
(iii) False claims liability under California Government Code Section 12650, et seq.
(iv) Defects in the Work first discovered by City after final payment by City to Contractor.
(v) Stop notices.
(vi) The right of City to specific performance or injunctive relief to compel performance of any provision of the Contract Documents.
1.1.19 CLIENT DEPARTMENT: Department or Division of City of Santa Monica identified as the end user of the facilities.
1.1.20 COMPENSABLE DELAY: A Delay for which Contractor may be entitled under the Contract Documents to both an extension of the Contract Time and an adjustment of the Contract Sum for additional compensation. "Compensable Delay" means any Delay to the path of activities that is critical to Contractor’s Substantial Completion of the Work within the Contract Time, which Delay is all of the following:
(i) Solely due to Changes requested by City that adds time, but can’t be worked around or re-sequenced but does not involve Extra Work.
(ii) Not due, in whole or in part, to the fault or negligence or breach of Contractor or any Subcontractor or Sub-subcontractor, of any Tier.
(iii) Not concurrent with another Excusable Delay or any Unexcused Delay.
1.1.21 CONSTRUCTION CONTRACT: The written contract executed between City and Contractor for construction of the Project.
Public Works | General Conditions Construction | April 2022 4 | P a g e
1.1.22 CONSTRUCTION MANAGER: The individual, partnership, corporation, joint venture or other legal entity under contract with City to perform construction management services for the Project. The term "Construction Manager" means Construction Manager or Construction Manager's authorized representative, or, alternatively, City's authorized representative if City does not contract for construction management services for the Project.
1.1.23 CONSTRUCTION SCHEDULE: The graphical representation of Contractor’s as-planned schedule for performance of the Work, prepared in accordance with the requirements of the Contract Documents and that provides for Substantial Completion of the Work within the Contract Time.
1.1.24 CONTRACT DISPUTE: A dispute, other than a dispute listed in Section 14.2.1 (Non-Contract Disputes) of the Construction Contract, arising out of or related to the Construction Contract or the interpretation, enforcement or breach thereof.
1.1.25 CONTRACT DISPUTE RESOLUTION PROCESS: The process of resolution of Contract Disputes, and, upon election of City, disputes as set forth in Section 14 (Dispute Resolution) of the Construction Contract.
1.1.26 CONTRACT DOCUMENTS: The following collection of documents are designated as contract documents:
(i) The Notice Inviting Pre-Qualification Statements, Pre-Qualification Statement, and Pre-Qualification Checklist (if applicable).
(ii) Executed Construction Contract between City and Contractor.
(iii) Notice Inviting Bids.
(iv) Instructions to Bidders.
(v) Bidding Addenda.
(vi) Contractor's Bid.
(vii) General Conditions.
(viii) Special Provisions and Technical Specifications.
(ix) Performance and Payment Bonds.
(x) Insurance Forms.
(xi) Plans and Drawings.
Public Works | General Conditions Construction | April 2022 5 | P a g e
(xii) Reports listed in the Bidding Documents.
(xiii) Supplements, Attachments and Exhibits attached to the above items.
(xiv) Notice to Proceed
(xv) Modifications.
(xvi) Change Orders.
(xvii) Field Orders.
1.1.27 CONTRACT SUM: The total amount of compensation stated in the Construction Contract that is payable to Contractor for the performance of the Work in accordance with the Contract Documents.
1.1.28 CONTRACT TIME: The total number of days set forth in the Construction Contract within which Substantial Completion of the Work must be achieved by Contractor, including approved extensions of time permitted under the terms of the Contract Documents.
1.1.29 CONTRACTOR: The individual or firm under contract with City to serve as the General Contractor for construction of the Project. The term "Contractor" means Contractor or Contractor's authorized representative.
1.1.30 CONTRACTOR MARKUP: The additional sum or deductive credit provided for under the Construction Contract for Contractor’s profit and overhead on Extra or Deleted Work for which a Change Order is required to be executed under the Contract Documents adjusting the Contract Sum.
1.1.31 DAY: Whether capitalized or not, unless otherwise specifically provided, means calendar day. NOTE: For Federally-funded projects DAY, whether capitalized or not, is considered WORKING DAY and is defined as any day, except weekends and legal holidays.
1.1.32 DEFECTIVE WORK: Work by Contractor that is unsatisfactory, faulty, omitted, incomplete, deficient or does not conform to the Applicable Code Requirements, the Contract Documents, the directives of City or the requirements of any inspection, reference standard, test, code or approval specified in the Contract Documents.
1.1.33 DELAY: Whether capitalized or not, includes any circumstances involving disruption, hindrance, or interference in the performance of the Work.
Public Works | General Conditions Construction | April 2022 6 | P a g e
1.1.34 DELETED WORK: Work that is eliminated due to a Change in the Work requested by City or Contractor for which City is entitled to a deductive adjustment in the Contract Sum.
1.1.35 DESIGN CONSULTANT. The individual(s) or firm(s) under contract with City to provide design or engineering services for the Project and are responsible for preparing the Contract Documents for the Project. The term "Design Consultant" means Design Consultant or Design Consultant's authorized representative.
1.1.36 DRAWINGS: The graphic and pictorial portions of the Contract Documents showing the design, location, and dimensions of the Work, generally including plans, elevations, subparagraphs, details, schedules and diagrams. The Drawings are outlined in the Drawing Index. The term “Drawings” may be used interchangeably with "Plans."
1.1.37 ESCROW AGENT: A state or federally chartered bank in the State of California which holds securities pursuant to an escrow agreement as set forth in Article 9.5 of these General Conditions.
1.1.38 EXCUSABLE DELAY: A Delay for which Contractor may be entitled under the Contract Documents to an extension of time, but not compensation. "Excusable Delay" means any delay to the path of activities that is critical to Substantial Completion of the Work within the Contract Time caused by conditions beyond the control or foreseeability, and without the fault or negligence of Contractor or its Subcontractors or Sub-subcontractors, of any Tier, such as, but not limited to: war, embargoes, fire, unavoidable casualties, unusual delays in transportation, national emergency, and stormy and inclement weather conditions that are unusual and unseasonable and in which the Work cannot continue. Without limitation to the foregoing, the financial inability of Contractor or any Subcontractor or Sub-subcontractor, shall not be deemed conditions beyond Contractor's control or foreseeability. Contractor may claim an Excusable Delay only if all Work on a critically scheduled activity is stopped for more than six (6) hours of a normal eight (8) hour working day, or if three to six hours are lost in one working day, then it may be claimed for one-half day. A Compensable Delay shall, to the extent that it is concurrent with an Excusable Delay, be conclusively deemed an Excusable Delay.
1.1.39 EXISTING IMPROVEMENTS: All improvements located on the Site as of the date of execution of the Construction Contract, whether above or below the surface of the ground, including but not limited to existing buildings, utilities, infrastructure improvements and other facilities.
1.1.40 EXTRA WORK: Additional Work or costs due to a Change in the Work that is not described in or reasonably inferable from the Contract Documents and for which Contractor is entitled to an adjustment of the Contract Sum under the terms of the Contract Documents. Extra Work shall not include additional Work or costs arising from Contractor’s failure to perform any of its duties or obligations under the Contract Documents or arising from errors, omissions, conflicts, ambiguities, lack of coordination
Public Works | General Conditions Construction | April 2022 7 | P a g e or noncompliance with Applicable Code Requirements in the Contract Documents with respect to which Contractor has assumed responsibility in connection with its obligation to conduct a careful review of the Bid Documents and Contract Documents.
1.1.41 FIELD ORDER: A written instrument signed by the Construction Manager that requests performance of Work in one of the following categories:
(i) Over which there is a dispute as to whether the Work is or is not Extra Work.
(ii) Involving Extra Work which City requests be performed without a unilateral Change Order adjustment to the Contract Sum or Contract Time and before all terms of an adjustment to the Contract Sum or Contract Time are fully agreed upon by City and Contractor.
The purpose of a Field Order is to direct performance of Work, which may be disputed, and, whether or not it expressly so states, shall not be construed as an acknowledgment by City that the Work described constitutes a Change or Extra Work if that is in fact not the case.
1.1.42 FINAL COMPLETION: The point at which:
(i) Work is completed to the satisfaction of City in accordance with the Contract Documents, including minor corrective or completion items.
(ii) All requirements of the Contract Documents entitling Contractor to final payment shall have been performed by Contractor (including, without limitation, delivery of all warranties and guarantees, equipment operation and maintenance manuals, as-built drawings and schedules and certificates required prior to occupancy).
(iii) All approvals and acceptances shall have been made pursuant to Applicable Code Requirements.
(iv) All rubbish, tools, scaffolding and surplus materials and equipment have been removed from the Site.
1.1.43 FRAGNET: A “Fragnet”, sometimes referred to as “time impact analysis,” is a contemporaneous, fragmentary scheduling network, which graphically identifies the sequencing of all critical and non-critical new activities and/or activity revisions affected by a Change Order Request, Field Order or Change Order, with logic ties to all affected existing activities noted on the Construction Schedule. Its objective is to isolate and quantify any time impact of a specific issue, determine and demonstrate any such specific Delay in relation to past and/or other current Delays and to provide a method for incorporating adjustments to the Contract Time into the Construction Schedule.
1.1.44 GENERAL CONDITIONS: That portion of the Contract Documents relating to the administrative procedures to be followed by Contractor in carrying out the Work.
Public Works | General Conditions Construction | April 2022 8 | P a g e
1.1.45 HAZARDOUS SUBSTANCES: Refers to, without limitation, the following: any chemical, material or other substance defined as or included within the definition of hazardous substances, hazardous wastes, extremely hazardous substances, toxic substances, toxic material, restricted hazardous waste, special waste, or words of similar import under any Environmental Law.
1.1.46 LOSSES: Any and all losses, costs, liabilities, Claims, damages, liquidated damages, actions, judgments, settlements, expenses, fines and penalties. "Losses" do not include attorneys' fees.
1.1.47 MODIFICATION: A document other than a Change Order, approved by City Attorney and signed by City and Contractor, agreeing to alter, amend or modify the Contract Documents.
1.1.48 NON-COMPENSABLE DELAY: An (I) Unexcused Delay, and (ii) an Excusable Delay that is not also a Compensable Delay.
1.1.49 NOTICE OF AWARD: Written notice issued by City notifying Contractor of issuance of the Construction Contract.
1.1.50 NOTICE TO PROCEED: Written notice issued by City to Contractor to begin the Work.
1.1.51 PERFORMANCE BOND, PAYMENT BOND: The performance and payment bonds to be provided by Contractor for the Project.
1.1.52 PLANS: The graphic and pictorial portions of the Contract Documents showing the design, location and dimensions of the Work, generally including plans, elevations, subparagraphs, details, schedules and diagrams. The term “Plans” may be used interchangeably with "Drawings."
1.1.53 PRE-CONSTRUCTION MEETING: A meeting held with the Project Team prior to beginning construction in order to review Contract Documents and clarify roles, responsibilities and authority of the Project Team.
1.1.54 PROJECT: The total construction, of which the Work performed by Contractor under the Contract Documents may be the whole or part and which may include Work performed by City’s own forces or by Separate Contractors.
1.1.55 PROJECT TEAM: Collectively, the Contractor, City, Design Consultant, Separate Contractors, Construction Manager and other consultants and contractors providing professional and technical consultation for the design and construction of the Project.
Public Works | General Conditions Construction | April 2022 9 | P a g e
1.1.56 RECORD DOCUMENTS: The term “Record Documents” refers to the As-Built Documents, warranties, guarantees and other documents required to be submitted by Contractor as a condition of Final Completion.
1.1.57 REQUEST FOR INFORMATION: A written instrument, prepared by Contractor, which requests an interpretation or clarification in the Work or a response to a question concerning the Work. A Request for Information does not entitle Contractor to an adjustment in the Contract Sum unless it requires Extra Work and Contractor requests and is entitled to such an adjustment in accordance with the provisions of the Contract Documents.
1.1.58 REQUEST FOR INFORMATION RESPONSE: A written instrument, usually prepared by the Design Consultant, which sets forth an interpretation or clarification in the Work or a response to a Contractor question concerning the Work.
1.1.59 SCHEDULE OF VALUES: A detailed, itemized breakdown of the Contract Sum, which provides for a fair and reasonable allocation of the dollar values to each of the various parts of the Work.
1.1.60 SEPARATE CONTRACTOR: A person or firm under separate contract with City or other entity performing other Work at the Site.
1.1.61 SITE: The physical site located within City where the Project is to be constructed, including all adjacent areas for staging, storage, parking and temporary offices.
1.1.62 SPECIAL PROVISIONS AND TECHNICAL SPECIFICATIONS: The portion of the Contract Documents consisting of the written requirements for materials, equipment, standards, skill, quality for the Work and performance of related services. These provisions may also contain amendments, deletions or additions to the General Conditions.
1.1.63 STATEMENT OF CONTRACT DISPUTE: The Contractor’s written statement prepared in accordance with Section 14.3 (Submission of Contract Dispute) of the Construction Contract required as a condition of its initiating the Contract Dispute Resolution Process.
1.1.64 SUBCONTRACTOR: A person or firm that has a contract with a Contractor to perform a portion of the Work. The term "Subcontractor" includes suppliers and vendors performing Work on site, and is referred to throughout the Contract Documents as if singular in number and means a Subcontractor or an authorized representative of the Subcontractor.
1.1.65 SUB-SUBCONTRACTOR: A person or firm that has a contract with a Subcontractor to perform a portion of the Work. The term "Sub-subcontractor" includes suppliers and vendors, performing Work onsite, and is referred to throughout the Contract
Public Works | General Conditions Construction | April 2022 10 | P a g e
Documents as if singular in number and means a Sub-subcontractor or an authorized representative of the Sub-subcontractor.
1.1.66 SUBCONTRACTOR/SUB-SUBCONTRACTOR MARKUPS: The sum allowable under the Construction Contract for Subcontractor and Sub-subcontractor profit and overhead on Extra or Deleted Work for which Contractor is entitled to a Change Order under the Contract Documents adjusting the Contract Sum.
1.1.67 SUBMITTALS: All shop drawings, samples, exemplars, product data and other submittals required to be submitted by Contractor under the Contract Documents.
1.1.68 SUBSTANTIAL COMPLETION, SUBSTANTIALLY COMPLETE: The point at which the Work is sufficiently complete to be occupied and utilized by City for its intended purpose, and Contractor has fulfilled its obligations under the Contract Documents as determined by City, except for minor punchlist items which do not impair City's ability to so occupy and utilize the Project.
1.1.69 SUPERINTENDENT: The person appointed by Contractor, subject to approval by City, to supervise and coordinate Contractor's own forces and Subcontractors in all aspects of the Work.
1.1.70 TIER: The contractual level of a Subcontractor with respect to Contractor. For example, a first-tier Subcontractor is under subcontract with Contractor. A Sub-subcontractor under subcontract with a first-tier Subcontractor, is in the second tier, and so on.
1.1.71 UNEXCUSED DELAY: Any Delay in the path of activities that is critical to Substantial Completion of the Work within the Contract Time resulting from causes other than Excusable Delay or Compensable Delay. An Unexcused Delay shall not entitle Contractor to either an extension of the Contract Time or an adjustment of the Contract Sum. A Compensable Delay or Excusable Delay shall, to the extent it is concurrent with an Unexcused Delay, be conclusively deemed an Unexcused Delay.
1.1.72 WORK: All labor, materials, equipment, services, permits, licenses and taxes, and all other things necessary for Contractor to perform its obligations and complete the Project, including, without limitation, any changes or additions requested by City, in accordance with the Contract Documents and all Applicable Code Requirements.
1.2 OWNERSHIP AND USE OF DOCUMENTS
1.2.1 All originals, copies and electronic forms of Drawings, Plans, specifications, shop drawings, samples, reports, schedules and other materials or documents prepared for the Project (including, without limitation, the Contract Documents) shall not be used by Contractor, or any Subcontractor or Sub-subcontractor, of any Tier, for any purpose other than performance of the Work. Contractor, Subcontractors and Sub-subcontractors are granted a limited license, revocable at will by City, to use and reproduce applicable
Public Works | General Conditions Construction | April 2022 11 | P a g e portions of the Contract Documents appropriate to and for use in the execution of their Work under the Contract Documents; provided however, that such use shall not be construed in derogation of Owner’s rights to use and ownership under this provision.
1.2.2 Contractor shall keep on the Site of the Project, at all times, a complete set of City approved, permitted Contract Documents for use by City.
1.2.3 Proposed Changes or refinements and clarifications will be provided to Contractor in the form of PDF electronic files. Contractor shall, at its own expense and without adjustment to the Contract Sum, do all reproduction and distribution of such files as necessary for the complete pricing of the Change and for performance of the Work.
1.2.4 Contractor shall take all necessary steps to assure that a provision is included in all contracts with Subcontractors and Sub-subcontractors, of every Tier, who perform Work on the Project, protecting and preserving City’s rights to ownership and use of documents as set forth in this Article 1.2.
1.3 AUTHORITY OF CITY
1.3.1 The Design Consultant shall, upon request, make recommendations to City and the Construction Manager concerning the quality or acceptability of Work performed.
1.3.2 City, in its sole discretion, will interpret the Contract Documents and make the determination of whether or not Contractor has fulfilled the requirements of the Contract Documents. Such interpretations and decisions of City shall be final and binding upon Contractor.
1.4 INTERPRETATION OF CONTRACT DOCUMENTS
1.4.1 The Contract Documents are complementary and what is required by one shall be as binding as if required by all.
1.4.2 In general, the Drawings will show dimensions, positions, and kind of construction;
and the Special Provisions and Technical Specifications will define materials, quality and standards. Any Work called for on the Drawings and not mentioned in the Special Provisions and Technical Specifications, or vice versa, shall be performed as though fully set forth in both. Work not particularly detailed, marked or specified, shall be the same as similar parts that are detailed, marked or specified.
1.4.3 Unless otherwise stated in the Contract Documents, technical words and abbreviations contained in the Contract Documents are used in accordance with commonly understood construction industry meanings and non-technical words and abbreviations are used in accordance with their commonly understood meanings.
1.4.4 The Contract Documents may omit modifying words such as "all" and "any," and articles such as "the" and "an." If a modifier or an article is not included in one statement
Public Works | General Conditions Construction | April 2022 12 | P a g e and appears in another it is not intended to affect the interpretation of either statement.
The use of the word "including," when following any general statement, shall not be construed to limit such statement to specific items or matters set forth immediately following such word or to similar items or matters whether or not non-limiting language (such as "without limitation," "but not limited to," or words of similar import) is used with reference thereto, but rather shall be deemed to refer to all other items or matters that could reasonably fall within the broadest possible scope of such general statement.
1.4.5 Whenever the context so requires, the use of the singular number shall be deemed to include the plural and vice versa. Each gender shall be deemed to include the other gender, and each shall include corporation, partnership, trust, or other legal entity whenever the context so requires. The captions and headings of the various subdivisions of the Contract Documents are intended only as a matter of reference and convenience and in no way define, limit, or prescribe the scope or intent of the Contract Documents or any subdivision thereof.
1.4.6 Any cross-references indicated between various subparagraphs or Drawings and Documents are provided for the convenience of Contractor and shall not be deemed to be all-inclusive.
1.4.7 Unless specifically noted to the contrary, it is the intention of the Contract Documents that all Work, equipment, casework, mechanical, electrical and similar devices of whatever nature, be completely installed, hooked-up, made operational and made functional for the purpose such are intended, and that all costs therefor be included in the Contract Sum.
1.4.8 Figured dimensions on scale Drawings and on full size Drawings shall govern over scale Drawings without figured dimensions. The Drawings shall not be scaled to determine dimensions, and (except in the case of diagrammatic Drawings) shall be calculated from figures shown on the Drawings. Obvious discrepancies between scale and figured dimensions, not marked "not to scale," must be brought to the Construction Manager's attention before proceeding with the Work affected by the discrepancy.
1.4.9 If there is a conflict between or among any of the Contract Documents, Contractor shall immediately bring such conflict to the attention of City, whose decisions regarding such conflict shall be final and binding as to the requirements of the Contract Documents.
In the event of any conflicts between or among the Applicable Code Requirements, the more stringent shall govern. In resolving any conflict in the Contract Documents, the highest standard of quality and skill, the most stringent requirements, and the most specific provision of the Contract Documents shall govern and shall be required in the performance of the Work.
1.4.10 The general character of the Work is shown in the Contract Documents, but Changes, modifications, clarifications and refinements may be made in details when needed to more fully explain the Work. Provided that they is a logical evolution of the Bid Documents that were bid by Contractor or were reasonably inferable as necessary to
Public Works | General Conditions Construction | April 2022 13 | P a g e provide a completed and fully operational system, facility or structure, the same shall be considered part of the scope of the Work to be performed without adjustment in the Contract Sum or the Contract Time.
1.4.11 Where on any Drawing a portion of the Work is drawn out and the remainder is indicated in outline, the drawn-out parts shall apply also to all other like portions of the Work. Where ornament or other detail is indicated on starting only, such detail shall be continued throughout the course of parts in which it occurs and shall also apply to all other similar parts in the Work unless otherwise indicated.
1.4.12 For convenience, the Special Provisions and Technical Specifications are arranged in various trade subparagraphs, but such segregation shall not be considered as limiting the Work of any subcontract or trade. Contractor shall be solely responsible for all subcontract arrangements of Work regardless of the location or provision in the Special Provisions and Technical Specifications.
1.4.13 Contractor will provide all necessary labor, equipment, transportation and incidentals required to complete the Work, even if the Contract Documents do not describe the Work in complete detail.
1.4.14 Drawings and diagrams for mechanical, plumbing and electrical Work shall be considered as diagrammatic only, not to be used for any structural guidance or physical layout, unless specifically detailed or dimensioned, and Contractor shall be responsible to provide any and all numbers and lengths of mechanical, plumbing or electrical fittings, wire, conduit, connections, attachments or similar materials needed to complete the Work, at no adjustment to the Contract Sum or Contract Time, whether or not they exceed the numbers of such pieces or the lengths indicated by the Drawings.
ARTICLE 2 – CITY
2.1 INFORMATION AND SERVICES PROVIDED BY CITY
2.1.1 City will furnish one electronic/digital (set) of the Contract Documents or portions thereof free of charge.
2.1.2 Except as otherwise provided in the Special Provisions and Technical Specifications and Article 3.18 herein, City shall obtain and pay for any permits, easements and governmental approvals for the use or occupancy of permanent structures required in connection with the Work.
2.1.3 Requests for Information Responses, Approvals and decisions required of City, Design Consultant or Construction Manager under the Contract Documents shall be provided by City, Design Consultant or Construction Manager to Contractor upon request in a timely manner in order to avoid unreasonable Delay in the orderly and sequential progress of the Work. Notwithstanding the foregoing, failure by City, Design Consultant, Construction Manager or City’s other consultants to provide Request for Information Response, Approvals or decisions shall not be considered as a basis for Contractor to
Public Works | General Conditions Construction | April 2022 14 | P a g e seek adjustment in the Contract Time until seven (7) Days after Contractor has delivered written notice to City and to the person from whom such information, Approval or decision is needed, stating the following:
(i) You are hereby notified that certain information, approval or decision described herein has not been provided in accordance with this provision and if not provided within seven (7) Days from this notice may result in additional cost or a request for time extension due to Delay;.
(ii) A detailed description of the information, approval or decision required.
(iii) The date by which the information, approval or decision must be received so as to not result in Delay to the Project, which shall in no event be earlier than seven (7) Days after the date of City’s receipt of such notice.
2.2 ACCESS TO PROJECT SITE
2.2.1 City will make available, no later than the date designated in the current Construction Schedule accepted by City, the lands and facilities upon which the Work is to be performed, including such access and other lands and facilities designated in the Contract Documents, for use by Contractor.
2.3 CITY'S RIGHT TO STOP THE WORK
2.3.1 If Contractor fails to correct Defective Work as required by Article 12.2, fails to perform the Work in accordance with the Contract Documents, or violates any Applicable Code Requirement, City may direct Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated by Contractor. Contractor shall not be entitled to any adjustment of Contract Time or Contract Sum as a result of any such order.
City shall have no duty or responsibility to Contractor or any other party to exercise the right to stop the Work.
2.4 CITY’S RIGHT TO CARRY OUT THE WORK
2.4.1 If Contractor fails to carry out the Work in accordance with the Contract Documents, fails to provide sufficient labor, materials, equipment, tools and services to maintain the Construction Schedule, or otherwise fails to comply with any requirement of the Contract Documents, and fails within the time specified in the Contract Documents, after receipt of notice from City to promptly commence and thereafter diligently continue to completion the correction of such failure, City may, without prejudice to other remedies City may have, correct such failure at Contractor's expense. In such case, City shall be entitled to deduct from payments then or thereafter due Contractor the cost of correcting such failure, including compensation for the additional services and expenses of City and City's consultants made necessary thereby. If payments then or thereafter due Contractor are not sufficient to cover such amounts, Contractor shall pay the additional amount to City.
Public Works | General Conditions Construction | April 2022 15 | P a g e
ARTICLE 3 – CONTRACTOR
3.1 REVIEW OF THE SITE, CONTRACT DOCUMENTS AND FIELD CONDITIONS
3.1.1 Contractor acknowledges that it is satisfied as to character, quality, and quantities of surface and subsurface materials or obstacles to be encountered insofar as reasonably ascertainable from a careful inspection of the Site (including, without limitation, Existing Improvements on the Site) and from the geological investigation reports, data and similar information made available to Contractor by City. Any failure by Contractor to take such information or conditions into consideration will not relieve Contractor from responsibility for estimating the difficulty and cost of successfully completing the Work within the Contract Sum and Contract Time.
3.1.2 Contractor warrants and represents that it has carefully reviewed and compared the Bid and Bid Documents prior to submitting its Bid and executing the Contract. Based upon its careful review, Contractor agrees that it shall not be entitled, and conclusively waives any right, to an adjustment in the Contract Sum or Contract Time for any additional or unforeseen costs or Delay in the performance of Work due to conditions in Contract Documents constituting errors, omissions, conflicts, ambiguities, lack of coordination or noncompliance with Applicable Code Requirements, if such conditions were either discovered by Contractor or could have been reasonably discovered by Contractor or its Subcontractors or Sub-subcontractors, of every Tier, in the exercise of care and diligence in the review of the Bid Documents.
3.1.3 If Contractor discovers what it perceives to be errors, omissions, conflicts, ambiguities, lack of coordination or noncompliance with Applicable Code Requirements in the Contract Documents, then Contractor shall, before proceeding with the Work affected, notify City or the Construction Manager in writing within two (2) Days stating both of the following:
(i) A detailed description of the conditions discovered.
(ii) Contractor’s request for clarification, further details or correction of the Contract Documents.
Failure by Contractor to provide written notice within the period of time required shall result in Contractor waiving any right to adjustment in the Contract Sum or Contract Time on account thereof.
Public Works | General Conditions Construction | April 2022 16 | P a g e
3.1.4 Contractor shall submit written notice thereof to City if, in Contractor’s opinion, City, Design Consultant or Construction Manager furnishes additional written or verbal instructions, information or directions that Contractor considers constitute additional Work or Delay for which Contractor believes it is entitled to an adjustment of the Contract Sum or Contract Time. Such notice shall be provided prior to performance of the Work affected by such instruction, information or direction and seven (7) Days after Contractor first received such instruction, information or direction. Failure to provide such written notice in the manner required by this provision shall constitute a waiver by Contractor of the right to any adjustment to the Contract Sum or Contract Time by reason of such instruction, information or direction.
3.1.5 Field measurements shall be taken and existing field conditions verified by Contractor, and carefully compared with the Contract Documents and other information known to Contractor before commencing the Work. Contractor shall promptly report in writing to the Construction Manager any errors, inconsistencies, or omissions discovered.
3.1.6 If Contractor or any Subcontractor or Sub-subcontractor, of every Tier, performs any portion of the Work which it knows, or in the exercise of care and diligence should have known, involves an error, omission, conflict, ambiguity, lack of coordination or noncompliance with Applicable Code Requirements, without notifying and obtaining the written Approval of City or before obtaining a written clarification, interpretation, instruction or decision from City, Design Consultant or Construction Manager, then any Work that is performed that is not in conformance with the clarifications, interpretation, instruction or decision of City, Design Consultant or Construction Manager shall be removed or replaced and Contractor shall be responsible for the resultant Losses with no adjustment in the Contract Sum or Contract Time.
3.1.7 City does not impliedly or expressly warrant, and assumes no responsibility for, the accuracy, suitability or completeness of the Bid Documents, Contract Documents or of the data, opinions or recommendations contained or expressed in any information, data or reports provided to Contractor relating to the following conditions at the Site: geological, soils, hydrologic, groundwater, Hazardous Substances, surface and subsurface obstructions, surface and subsurface utilities or Existing Improvements. Existing Improvements at the Site, for which no specific description is made on the Drawings, but which could be reasonably assumed to interfere with the satisfactory completion of the Work, shall be removed and disposed of by Contractor, but only upon the specific direction and control of City. Without limitation to the foregoing, and notwithstanding any information provided by City pertaining to groundwater elevations and/or geological and soils conditions encountered, it is understood that it is Contractor’s responsibility to determine and allow for the elevation of groundwater, and the geological and soils conditions at the date of performance of the Work and any difference between elevation of groundwater and the geotechnical and soils conditions shown in the information provided by City and groundwater and the geotechnical and soils conditions actually encountered will not be considered as a Differing Site Condition or as a basis for an adjustment to the Contract Sum or Contract Time.
Public Works | General Conditions Construction | April 2022 17 | P a g e
3.2 SUPERVISION AND CONSTRUCTION PROCEDURES
3.2.1 Contractor shall supervise, coordinate and direct the Work using Contractor's best skill and attention and shall provide supervision sufficient to assure proper coordination and timely completion. Contractor shall be solely responsible for and have control over construction means, methods, techniques, safety, sequences, procedures and the coordination of all portions of the Work.
3.2.2 Contractor shall be responsible for the accurate layout of all portions of the Work and shall verify all dimensions on the Drawings and shall report to City any discrepancies before proceeding with related Work.
3.2.3 Contractor may be assigned working space adjacent to the Site, and all field offices, materials and equipment shall be kept within this area. Contractor shall be responsible for leaving the space in as good condition as Contractor found it, or restoring it to the condition it was in prior to Contractor commencing the Work.
3.2.4 Contractor shall be responsible to City for acts and omissions of Contractor's agents, employees, and of Contractor’s Subcontractors and Sub-subcontractors, of every Tier, and their respective agents and employees. Unless otherwise stated in the Contract Documents, references to Contractor, when used in reference to an obligation bearing upon performance of the Work, shall be deemed to include Contractor’s Subcontractors and Sub-subcontractors of every Tier.
3.2.5 Contractor shall not be relieved of its obligation to perform the Work in accordance with the Contract Documents by the act(s) or omission(s) by City in the administration of the Contract, or by tests, inspections or Approvals required or performed by persons or firms other than Contractor.
3.3 RESPONSIBILITY FOR THE WORK
3.3.1 Contractor shall be in charge of and responsible for all portions of the Work of the Contract, and shall be responsible for conforming such portions to the requirements of the Contract Documents and readying such portions to receive subsequent Work.
3.3.2 Contractor shall at all times maintain good discipline and order among its employees and Subcontractors. Contractor shall provide competent, fully qualified personnel to perform the Work, and shall ensure that each Subcontractor and Sub-subcontractor engaged on the Site arranges the storage of materials and equipment and performance of its Work so as to interfere as little as possible with Separate Contractors or other persons engaged in work for City on the Site.
3.3.3 During the installation of Work, Contractor shall insure that existing facilities, fences, and other structures are all adequately protected. Upon Final Completion of all Work, all facilities that may have been damaged shall be restored to a condition acceptable to City.
Public Works | General Conditions Construction | April 2022 18 | P a g e
3.3.4 Contractor is responsible for the security of the Site and all Work provided under the terms of this Contract, as well as all Work provided by Separate Contractors that occurs on the Site at any time prior to Final Completion and Acceptance of the Work by City.
3.4 LABOR, WORKMANSHIP, MATERIALS AND MANUFACTURED ITEMS
3.4.1 Contractor shall provide and pay for all labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work. Unless otherwise provided in the Contract Documents or otherwise Approved by the Construction Manager, all articles, equipment and materials incorporated in the Work shall be new, of good quality, undamaged and not defective.
3.5 CONTRACTOR'S WARRANTY
3.5.1 Contractor warrants to City that all materials and equipment used in or incorporated into the Work will be of good quality, new and free of liens, Claims and security interests of third parties; that all labor, installation, materials and equipment used or incorporated into the Work will be of good quality and free from defects; and that the Work will conform with the requirements of the Contract Documents and Applicable Code Requirements. If required by City, Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment. Manufactured items installed in the Work and not specifically covered in the Contract Documents are to be installed in strict accordance with manufacturers' current printed instructions.
3.5.2 All materials to be incorporated in the Work shall be protected from damage during delivery, storage, and handling, and after installation until Acceptance of the Work, and Contractor shall, without charge to City, be responsible for all damage due to Contractor's failure to provide such proper protection.
3.6 CONSTRUCTION METHODS AND PROCEDURES
3.6.1 The methods and procedures adopted by Contractor shall be such as to secure a quality of Work satisfactory to City and to enable completion of the Work in the time agreed upon. If at any time such methods and procedures appear inadequate, City may order Contractor to improve their character or increase efficiency, and Contractor shall conform to such order; but the failure of City to order such improvement of methods or increase of efficiency will not relieve Contractor from its obligation to perform the Work in accordance with the Contract Documents or within the Contract Time.
3.6.2 If the Contract Documents give specific instructions concerning construction means, methods, techniques, sequences or procedures, Contractor shall be fully and
Public Works | General Conditions Construction | April 2022 19 | P a g e solely responsible for the Site safety for implementing such means, methods, techniques,…