Garde_Arts_Center_Environmental_Cleanup_(Addendum_#1_Revision).pdf
PDF 234 KB Posted
- Attached to
- Garde Arts Center Environmental Cleanup
- Solicitation number
- 2026-05 CONL
- Issued by
- New London County, Connecticut
About this file
This is a bid document (Bid No. 2026-05 CONL) from the City of New London, Connecticut, for the Garde Arts Center Environmental Cleanup project. The bid encompasses environmental abatement and disposal services at multiple locations (10 Meridian Street, 14-16 Meridian Street, and 28 Meridian Street), including the removal of friable and non-friable asbestos, polychlorinated biphenyls (PCBs), lead-based paints, and interior/exterior materials. The project requires disconnecting existing utilities and follows Federal Davis-Bacon and Connecticut prevailing wage requirements. The bid was released on November 3, 2025, with a mandatory pre-proposal meeting on November 10, 2025, and responses due by November 21, 2025, at 10:00 am.
The bid includes three alternate bid options with line items for mobilization, various types of asbestos and PCB abatement, and waste disposal, all priced as lump sum quantities. The City offers a 15% local vendor preference and has employment goals requiring 25% local workforce participation, with 50% priority given to New London residents and including 25% female and minority representation. The project also requires a 10% apprenticeship workforce for state-licensed trades. Insurance requirements are comprehensive, with minimum coverage limits including $1 million per occurrence for bodily injury and property damage, and $2 million aggregate. Liquidated damages are set at $1,000 per day, and a 5% retainage will be held. Bidders must submit various forms including non-collusion affidavits, equal employment opportunity certifications, and a bid bond.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2026-05_CONLGarde_Arts_wages_with_docs_10-31-25.pdf | ||
| Garde_Arts_Abatement_Project_Bid_Package_1027.pdf | ||
| Payment_&_Performance_Bonds__(1).docm | DOCM document | |
| Sample_Contract_(w_Liquidated_Damages_and_Retainage_Language).docx | DOCX document | |
| Sample_Contract.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For more information, please visit our online supplier portal, located at https://procurement.opengov.com/portal/newlondonct
City of New London
13 Masonic St.
New London, CT 06320
GARDE ARTS CENTER ENVIRONMENTAL CLEANUP
Project ID: 2026-05 CONL
RELEASE DATE: November 3, 2025
RESPONSE DEADLINE: November 21, 2025, 10:00 am
Please refer to the project timeline in this document for all important deadlines.
#2026-05 CONL
Title: Garde Arts Center Environmental Cleanup
Table Of Contents
1. Introduction
2. Submission of Proposals
3. Guaranty or Surety
4. Award
5. Other Requirements
6. Contract
7. Delivery
8. Saving Clause
9. Advertising
10. Rights
11. Scope of Work
12. Price Proposal
13. Vendor Submission Forms
Attachments:
A - Garde Arts Abatement Project Bid Package_1027
B - 2026-05 CONLGarde Arts wages with docs 10-31-25
1. Introduction
1.1. Summary & Special Instructions
The Work includes the following major items:
a. Abatement and disposal of friable and non-friable asbestos containing building materials, polychlorinated biphenyls
(PCBs) containing building materials with concentrations <50 and ≥50 parts per million (ppm) and lead-based paints.
b. Remove and dispose of materials located at the site where noted on the drawings and in accordance with requirements indicated on Drawings and in Specifications.
c. Disconnecting existing utilities including, but not limited to, water, electricity, and natural gas as needed to facilitate the work. This includes coordination with individual utility companies and the City as required.
• Federal Davis-Bacon wages and CT Prevailing wages apply.
• Liquidated damages- $1,000 / day
• Retainage- 5%
1.2. Timeline
Release Project Date: November 3, 2025
Pre-Proposal Meeting (Mandatory): November 10, 2025, 10:00am
10 Meridian Street, New London, CT 06320
Question Submission Deadline: November 14, 2025, 3:00pm
Response Submission Deadline: November 21, 2025, 10:00am
Via Zoom or in-person in the office of the
Purchasing Agent, 13 Masonic Street, New
London, CT 06320.
2. Submission of Proposals
2.1. Response Submission
Submit Electronic Responses via the City of New London's e-Procurement Portal https://procurement.opengov.com/portal/newlondonct
2.2. Questions
Bidders shall submit all inquiries regarding this bid via the City of New London's e-Procurement Portal, located at https://procurement.opengov.com/portal/newlondonct. Please note the deadline for submitting inquiries. All answers to inquiries will be posted on the City of New London's e-Procurement Portal. Bidders may also click “Follow” on this bid to receive an email notification when answers are posted. It is the responsibility of the bidder to check the website for answers to inquiries.
2.3. Addenda Notification and Acknowledgement
Addenda Notification: Bidders are required to register for an account via the e-Procurement Portal hosted by OpenGov.
Once the bidder has completed registration, they will receive addenda notifications to their email by clicking “Follow” on this project. Ultimately, it is the sole responsibility of each bidder to periodically check the site for any addenda at
2.4. Submission of Proposals
All Invitation for Bids issued by the City of New London (City) will bind Proposers to the terms and conditions listed below, unless specified otherwise in any individual Invitation for Bids.
Incorporated by reference into this contract are the provisions of Article IV., Section 2-66 through 2-71 and Section 2-73 of the Code of Ordinances of the City of New London.
The contractor agrees to comply with the Code of Ordinances as they exist on the date of the contract and as they may be adopted or amended from time to time during the term of this contract and any amendments thereto.
1. Proposals must be submitted on forms supplied by the City of New London or in the format requested in the specifications. Telephone, facsimile or e-mail proposals will not be accepted in response to a Invitation for Bids.
2. The date and time proposals are to be opened are given in each Invitation for Bids issued. Proposals received after the specified date and time of the proposal opening given in each Invitation for Bids will not be considered.
3. Incomplete proposal forms may result in the rejection of the proposal. Amendments to proposals received by the
Purchasing Agent after the date and time specified for the proposal opening shall not be considered. Proposals shall be computer prepared, typewritten or handwritten in ink. Proposals submitted in pencil shall be rejected. A person duly authorized to sign proposals for the proposer shall sign all proposals. Unsigned proposals shall be rejected.
4. Conditional proposals are subject to rejection in whole or in part. A conditional proposal is defined as one that limits, modifies, expands or supplements any of the terms and conditions and/or specifications of the Invitation for Bids.
5. Alternate proposals will not be considered. An alternate Proposal is defined as one that is submitted in addition to the proposer’s primary response to the Invitation for Bids.
6. Prices shall include delivery and transportation charges fully prepaid by the Contractor to the destination specified in the Invitation for Bids and subject only to cash discount.
7. Pursuant to Sections 12-412 and 12-412(1) of the Connecticut General Statutes, the City of New London is exempt from the payment of excise, transportation and sales taxes imposed by the Federal Government and/or the State. Such taxes must not be included in the proposal prices.
8. In the event of a discrepancy between the unit price and the extension, the unit price shall govern.
9. By its submission the Proposer represents that the proposal is not made in connection with any other Proposer submitting a proposal for the same commodity or commodities and is in all respects fair and without collusion or fraud.
10. All proposals will be opened virtually via OpenGov and ZOOM. The ZOOM link is https://us06web.zoom.us/j/89725259556?pwd=7u3kNN1NHmQy6a4EAOVXz8oJqmEpXu.1 Meeting ID: 897 2525 9556
Passcode: 2vUAF0 .
3. Guaranty or Surety
Bid bonds, performance bonds, and labor and material bonds will be required as specified below. Guaranty or surety may be in the form of certified check. Bonds must meet the following requirements: Corporation – must be signed by an official of the corporation above their official title and the corporate seal must be affixed over the signature; Firm or Partnership -must be signed by all of the partners and indicate they are “doing business as”; Individual – must be signed by the owner and indicated as “Owner”. The surety company executing the bond or countersigning must be licensed in Connecticut and an official of the surety company must sign the bond with the corporate seal affixed over the signature. Signatures of two
(2) witnesses for both the principal and the surety must appear on the bond. Power of attorney for the official signing the bond for the surety company must be submitted with the bond.
Bid Bond – Ten percent (10%) due at time of bid for all contract services and public works/construction projects that exceed twenty thousand dollars ($20,000.00)
Performance Bond – One hundred percent (100%) of contract price for projects that exceed fifty thousand dollars
($50,000.00).
Labor and Material Payment Bonds – One hundred percent (100%) of contract price for projects that exceed fifty thousand dollars ($50,000.00).
4. Award
1. Award of this contract will be made to the lowest responsible, qualified proposer and will be based on net cost and City specifications. The City of New London reserves the right to reject any and all bids or parts thereof, to waive any informality and to award this contract to other than the low proposer and to make multiple awards if deemed in the best interest of the City.
2. The City of New London allows a fifteen percent (15%) local vendor preference. A New London based business will be considered the lowest responsible proposer if it's proposal is within fifteen percent (15%) of the low proposer and it is willing to accept the award at the low proposal price. Any proposer claiming to be a New London based business must provide documentation that all of its motor vehicles are registered in New London and that payment of all of its property and motor vehicle taxes are current.
3. The City of New London may reject any bidder in default of any prior contract or guilty of misrepresentation or any bidder with a member of its firm in default or guilty of misrepresentation.
4. The Purchasing Agent may correct inaccurate awards resulting from clerical or administrative errors.
5. Other Requirements
1. The City has an employment preference goal that jobs be offered to local residents on public prevailing wage projects with thresholds great than $100,000 for renovation and $1,000,000 for new construction. For such projects, it is understood that contractors shall make a good faith effort to employ a participating workforce comprised of twenty-five
(25%) local residents of New London County, CT, with residents of the City of New London, CT getting a priority representing fifty percent (50%) of said participation, which will include twenty-five percent (25%) female and minority.
2. The City has an employee training preference goal that apprenticeship opportunities be made available for state licensed trades on public prevailing wage projects with thresholds greater than $100,000 for renovation and $1,000,000 for new construction. For such projects, it is understood that contractors shall make a good faith effort to employ a minimum of ten percent (10%) of the workforce per state licensed trade as apprentices and, of this number, a minimum of fifty percent (50) shall be in the first year of apprenticeship training.
6. Contract
1. The existence of a contract shall be determined in accordance with the requirements set forth above.
2. The Contractor shall not assign or otherwise dispose its contract or its right, title or interest, or its power to execute such contract to any other person, firm or corporation without the prior written consent of the City of New London.
3. Failure of a Contractor to deliver commodities or perform services as specified will constitute authority for the City of
New London to purchase these commodities or services on the open market. The contractor agrees to promptly reimburse the City of New London for excess cost of these purchases. The purchases will be deducted from the contracted quantities.
4. The Contractor agrees to hold the City of New London harmless from liability of any kind for the use of any copyrighted or uncopyrighted composition, secret process, patented or unpatented invention furnished or used in the performance of the Contract; Guarantee its products against defective material or workmanship; repair damages of any kind, for which it is responsible to the premises or equipment, to its own work or to the work of other contractors; obtain and pay for all licenses, permits, fees etc., and to give all notices and comply with all requirements of the City of New London, the State of Connecticut and the U.S. Government.
5. Insurance requirements generally apply to contract services, professional services and public works improvement/construction projects. The Contractor will carry commercial general liability insurance to protect the City of
New London from loss. The following minimum limits shall be met:
Bodily Injury and Property Damage – One million dollars ($1,000,000.00) each occurrence; two million dollars
($2,000,000.00) aggregate
Products or Completed Operations - One million dollars ($1,000,000.00) each occurrence; two million dollars
($2,000,000.00) aggregate
Professional Liability (Errors and Omissions) Coverage appropriate to the contractor’s operations – Two million dollars ($2,000,000.00) each occurrence
Commercial Automobile Coverage including owned, non-owned, leased and hired vehicles (if used on City of New London property) – One million dollars ($1,000,000.00) combined single limit for each accident.
Workers’ Compensation Coverage - Will be in accordance with State of Connecticut requirements at the time of
Proposal.
Any deductible or self-insured retention must be disclosed and any claim payments falling within the deductible shall be the responsibility of the contractor.
The CITY requires that these aggregate limits be maintained by the CONTRACTOR as required. It is the responsibility of the CONTRACTOR or his representative to notify the CITY if ever or whenever claims reduce the General Aggregate below $1,000,000.
The Contractor shall require all subcontractors to carry the same forms and minimum coverages that it is required to provide. Evidence of these coverages must be provided to the City of New London Purchasing Agent prior to the contractor or subcontractor coming onto the work site.
All insurance policies shall be endorsed to the City of New London, its officers and employees as additional insured, and shall not be reduced or cancelled without thirty (30) days prior written notice to the Purchasing Agent. The policy shall also include a subrogation of waiver. In addition, the contractor’s insurance shall be primary as respects the City of New
London, and any other insurance maintained by the City of New London shall be excess and not contributing insurance with the contractor’s insurance.
6. Notwithstanding any provision or language in this contract to the contrary, the Mayor may, without cause, terminate this contract for the City’s convenience upon approval by the City Council, whenever he/she determines that such termination is in the best interest of the City of New London. Any such termination shall be effected by delivery to the Contractor of a written notice of termination. The notice of termination shall be sent by registered mail to the Contractor address furnished to the City of New London for purposes of correspondence or by hand delivery. Upon receipt of such notice, the
Contractor shall both Immediately discontinue all services affected (unless the notice directs otherwise) and deliver to the
City of New London all data, drawings, specifications, reports, estimates, summaries, and such other information and materials as may have been accumulated by the Contractor in performing its duties under this contract, whether completed or in progress. All such documents, information and materials shall become the property of the City of New
London. In the event of such termination, the contractor shall be entitled to reasonable compensation as determined by the Mayor, however, no compensation for lost profits shall be allowed.
7. Delivery
1. All products and equipment delivered must be new unless otherwise stated in the proposal specifications.
2. All deliveries will be to the locations specified by the City of New London. The City of New London does not have a loading dock therefore all Contractors will be responsible for inside delivery without assistance from City of New London personnel.
3. Payment terms are net 45 days after receipt of goods or invoice, whichever is later, unless otherwise specified.
4. Charges against a Contractor shall be deducted from current obligations. Money paid to the City of New London shall be payable to the Treasurer, City of New London.
8. Saving Clause
The Contractor shall not be liable for losses or delays in the fulfillment of the terms of the contract due to wars, acts of public enemies, strikes, fires, floods, acts of God or any other acts not within the control of or reasonably prevented by the
Contractor. The contractor will give written notice of the cause and probable duration of any such delay.
9. Advertising
Contractors may not reference sales to the City of New London for advertising and promotional purposes without prior approval of the City of New London.
10. Rights
1. The City of New London has sole and exclusive right and title to all printed material produced for the City of New
London and the Contractor shall not copyright the printed matter produced under this contract.
2. The Contractor assigns to the City of New London all rights, title and interests in and to all causes of action it may have under Section 4 of the Clayton Act, 15 USC 15, or under Chapter 624 of the Connecticut General Statutes. This assignment occurs when the contractor is awarded the contract.
3. The Contractor agrees that it is in compliance with all applicable federal, state and local regulations, including but not limited to Connecticut General Statutes Section 7-148i. The Contractor also agrees that it will hold the City of New
London harmless and indemnify the City of New London from any action which may arise out of any act by the Contractor concerning lack of compliance with these laws and regulations. All purchases will be in compliance with Sections 22a-194 to 22a-194g of the Connecticut General Statutes related to product packaging.
4. This contract is subject to the provisions of Executive Order Number Three of Governor Thomas J. Meskill promulgated
June 16, 1971, the provision of Executive Order Number Seventeen of Governor Thomas J. Meskill promulgated February
15, 1973 and Section 16 of Public Act 91-58, nondiscrimination regarding sexual orientation, and the provisions of
Executive Order No. Sixteen of Governor John G. Rowland promulgated August 4, 1999 regarding Violence in the
Workplace Prevention Policy.
11. Scope of Work
11.1. Garde Arts Abatement & Renovation Project
Please refer to the "Attachments" section for project specifications and prevailing wage rates.
12. Price Proposal
10 MERIDIAN STREET
Line Item Description Quantity Unit of
Measure
Unit Cost Total
1 10 Meridian Street - Mobilization and Demobilization (*Not to exceed 5% of the total Bid price.)
1 Lump Sum
2 10 Meridian Street - Friable
Asbestos Pipe and/or Pipe Fitting
Insulation Abatement and Disposal
1 Lump Sum
Line Item Description Quantity Unit of
Measure
Unit Cost Total
3 10 Meridian Street - Non-Friable
Asbestos Interior Floor Tile &
Mastic, Exterior Window Glazing, and Exterior Roofing & Flashing
Tar Abatement and Disposal
1 Lump Sum
4 10 Meridian Street - Mixed
Asbestos and PCB-Containing <50 ppm Interior Plaster Walls/Ceilings and Transite Wall Paneling
Abatement and Disposal
1 Lump Sum
5 10 Meridian Street - Mixed Non-
Friable Asbestos and PCB-
Containing ≥50 ppm Skylight
Window Glazing Abatement and
Disposal
1 Lump Sum
6 10 Meridian Street - PCB-
Containing <50 ppm Interior
Plaster Walls, Ceilings, & Debris and Interior & Exterior Wood
Storefront Window/Door System
Abatement and Disposal
1 Lump Sum
7 10 Meridian Street - Interior Soil
Excavation and Disposal
(approximately 133 tons)
TOTAL
ALTERNATE BID NO. 1
14-16 Meridian Street
Line Item Description Quantity Unit of
Measure
Unit Cost Total
1 14-16 Meridian Street - Asbestos
Abatement and Disposal
1 Lump Sum
2 14-16 Meridian Street - EPA
Regulated Mixed Lead & PCB-
Containing Materials Abatement and Disposal
Line Item Description Quantity Unit of
Measure
Unit Cost Total
3 14-16 Meridian Street - EPA PCB-
Containing Materials ≥50 ppm
Abatement and Disposal
1 Lump Sum
4 14-16 Meridian Street - Solid (poly barriers, suits, PPE, etc.) and
Liquid (wastewater and decon water) PCB Remediation Waste
Disposal
ALTERNATE BID NO. 2
28 Meridian Street
Line Item Description Quantity Unit of
Measure
Unit Cost Total
1 28 Meridian Street - Asbestos
Abatement and Disposal
1 Lump Sum
2 28 Meridian Street - EPA
Regulated Mixed Lead & PCB-
Containing Materials Abatement and Disposal and Encapsulation at
28 Meridian Street
1 Lump Sum
3 28 Meridian Street - Solid (poly barriers, suits, PPE, etc.) and
Liquid (wastewater and decon water) PCB Remediation Waste
Disposal at 28 Meridian Street
13. Vendor Submission Forms
1. Non Collusion Affidavit of Prime Bidder *
Please download the below documents, complete, and upload.
• Non_Collusion-_Prime_Bidder...
*Response required
2. Non Collusion Affidavit of Subcontractor*
Please download the below documents, complete, and upload.
https://government-project.s3.us-west-2.amazonaws.com/179072/f801ff58-a3a5-422d-9aeb-94332d9c3dbe_Non_Collusion-_Prime_Bidder.pdf
Mark "N/A" if this does not apply.
• Non_Collusion_of_Subcontrac...
*Response required
3. Affirmative Action Policy Statements*
Please download the below documents, complete, and upload.
• Affirmative_Action.pdf
*Response required
4. Certification of Bidder Regarding Equal Employment Opportunity*
Please download the below documents, complete, and upload.
• EEO_Cert.pdf
*Response required
5. Vendor Registration Form
Please download the below documents, complete, and upload.
If you are already a vendor with the City, you only need to upload this if your information has changed.
• Vendor_Registration_Form.docx
6. W-9*
Please download the below documents, complete, and upload.
• Federal_W-9_Form_2024.docx
*Response required
7. Statement of Bidder's Qualifications*
Please download the below documents, complete, and upload.
• Statement_of_Qualifications...
*Response required
8. Bid Bond*
Please download the below documents, complete, and upload.
If you are submitting the bid bond in the form of a certified check, please upload an image of the certified check.
• Bid_Bond_Form.docm
*Response required
9. Certification on Non Segregated Facilities*
This Bidder certifies that he does not maintain or provide his employees any segregated facilities at any of his establishments, and that he does not permit his employees to perform their services at any location, under his control, where segregated facilities are maintained. The Bidder certifies further that he will not maintain or provide for his employees any segregated facilities at any of his establishments, and that he will not permit his employees to perform their services at any locations, under his control, where segregated facilities are maintained. The Bidder agrees that a breach of his certification will be a violation of the Equal Opportunity clause and any Contract resulting from acceptance of this Bid. As used in this certification, the term "segregated facilities" means any waiting rooms, work areas, restrooms and washrooms, restaurants and other eating areas, timeclocks, locker rooms and other storage or dressing areas, parking lots, drinking fountains, recreation or entertainment areas, transportation, and housing facilities provided for https://government-project.s3.us-west-2.amazonaws.com/179072/a59791d4-5b56-4ab0-a106-03be917f14e9_Non_Collusion_of_Subcontractor.pdf https://government-project.s3.us-west-2.amazonaws.com/179072/1932f320-823e-49fc-b128-deb35f4465d9_Affirmative_Action.pdf https://government-project.s3.us-west-2.amazonaws.com/179072/7e3a0915-e43b-4b93-89c0-49d581318c54_EEO_Cert.pdf https://government-project.s3.us-west-2.amazonaws.com/179072/b9e3d0b9-65f4-45db-b7ae-10ea68aacb73_Vendor_Registration_Form.docx https://government-project.s3.us-west-2.amazonaws.com/179072/dba7fe0c-0f3b-41a3-9c5e-a7b7c57d8259_Federal_W-9_Form_2024.docx https://government-project.s3.us-west-2.amazonaws.com/179072/e970f9b2-f8ac-4646-a79b-02439c2af81c_Statement_of_Qualifications.pdf https://government-project.s3.us-west-2.amazonaws.com/179072/496c5efe-66b8-4e29-ad6d-e0ce222359ae_Bid_Bond_Form.docm employees which are segregated by explicit directive or are, in fact, segregated on the basis of race, color, religion or national origin, because of habit, local custom or otherwise. The Bidder agrees that (except where he has obtained identical certification from proposed Subcontractors for specific time periods) he will obtain identical certifications from proposed Subcontractors prior to the award of Subcontracts exceeding $10,000 which are not exempt form the provisions of the Equal Opportunity clause; that he will retain such certifications in his files; and that he will forward the following notice to such proposed subcontractors (except where the proposed subcontractors have already submitted identical certifications for the specific time periods):
“Notice to prospective subcontractors of requirements for non-segregated facilities. A certification of non-segregated facilities must be submitted prior to the award of a subcontract exceeding the Equal Opportunity Clause. The certification may be submitted either for each subcontract or for all subcontracts during a period (i.e. quarterly, semi-annually, or annually).
Note: The penalty for making false statements in offers is prescribed in 18 U.S.C. Paragraph 1001.
☐ Please confirm
*Response required
10. Anti-Fracking Provision*
We hereby submit a bid for materials, equipment and/or labor for the City of New London. The Bid is for bid documents titled Bid No. 2026-05 CONL Garde Arts Center Environmental Cleanup. We hereby certify under penalty of perjury that no natural gas waste or oil waste will be used by the undersigned bidder or any contractor, sub-contractor, agent or vendor agent in connection with the bid; nor will the undersigned bidder or any sub-contractor, agent or vendor agent thereof apply any natural gas waste or oil waste to any road or real property within the City of New London as a result of the submittal of this bid if selected.
☐ Please confirm
*Response required
11. Additional Information
12. Is your company on the debarment list with the State of Connecticut?*
*Response required
13. Please upload Item 2 Sub-Bids from page 00410-LS-8*
*Response required