Final CxA RFP GRPS - Multiple Sites 02052025.pdf
PDF 219 KB Posted
- Attached to
- GRPS Commissioning Services - Multiple Sites
- Solicitation number
- RFP-GRP-250000001312-1
- Issued by
- Kent County, Grand Rapids City, Michigan
About this file
This is a Request for Qualifications and Fee Proposal (RFP) issued by Grand Rapids Public Schools (GRPS) seeking a Commissioning Agent (Cx) for construction/renovation projects at Ken-O-Sha Elementary, Riverside Montessori, and New Aberdeen Elementary schools. The RFP was issued on February 7, 2025, with proposals due February 27, 2025 at 11:00am. The selection process includes interviews during the week of March 3, 2025, with selection/recommendation by March 7, finance approval by March 17, and board approval by March 24, 2025. A pre-proposal meeting will be held February 19, 2025 at 2:00pm at GRPS 900 Union Ave. The scope includes typical pre-construction and commissioning services, meeting with design partners, attending construction progress meetings, and issuing site visit progress reports and final commissioning reports.
Firms may propose on any individual project or combination of projects, with GRPS maintaining sole discretion to award separately or combined. Required insurance includes $1 million workers compensation, $5 million general liability, automobile liability coverage, and $2 million professional liability insurance. The selected firm must submit a staffing and fee proposal in Excel format detailing all reimbursable charges, billable hourly rates, and overhead & profit percentages. The firm must indicate if discounts are available for multiple project awards. Submissions require four hard copies plus one electronic PDF copy, along with various affidavits covering familial relationships, Iran business relationships, criminal background checks, non-collusion, and debarment status.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FACILITIES COMMISSIONING SERVICES
FOR CONSTRUCTION/RENOVATION OF
Ken-O-Sha Elementary Riverside Montessori
New Aberdeen Elementary
Awarded Separately or Combined at GRPS Sole Discretion
GRAND RAPIDS PUBLIC SCHOOLS
Request for Qualifications and Fee Proposal(s)
Issued by:
The Ad Hoc Committee Professional Service Contractor Selection
Proposal Due Date: February 27 @ 11:00am Issuing Office: Grand Rapids Public School District
Office of Facilities Management & Planning
This is a Qualification Based Selection Process. Complete submittal of information requested in this document is essential to the selection process. Failure to provide this information may result in not being considered for the award of a contract.
February 7, 2025
GENERAL INFORMATION
A. Purpose- Procure Commissioning Services for GRPS 2023 Bond Program
Grand Rapids Public Schools (GRPS) seeks professional Commissioning Agent (Cx) expertise to give design input and execute its construction projects.
To obtain the highest quality project within the time and budget allocations, GRPS seeks PSCs for the above noted school buildings through this Qualification-Based
Selection (QBS) process. This selection process articulates the district goals, reflects our guiding principles and provides openness and consistency so that all qualified firms receive fair consideration. The remainder of this Request For Qualifications
(RFQ) identifies specifics regarding each of the above noted school building renovation projects.
GRPS invites you to submit a lump sum price proposal package (“Proposal”) for the Services required in this RFP in accordance with this letter and the following documents that are attached hereto, made a part hereof, and form the Contract Documents that may result from this RFP. The Owner is committed to commissioning its facilities to ensure that all systems are well-designed, complete and functioning properly, and that the Owner’s staff has adequate system documentation and training.
B. RFP Schedule:
The district seeks to promote potential efficiencies of awarding multiple projects to a single Commissioning Agent (Cx). In addition to typical pre-construction and commissioning services, the scope of work for all PSCs includes, but is not limited to, meeting with design partners, attending construction progress meetings, and issuing site visits progress and, at completion, full commissioning reports. The CA firm will be required to work closely with the AE and CM to estimate and balance scope, budget, and construction phasing options.
Selection & Design Timeline
RFP Issuance: February 7, 2025
Proposals Due: February 27, 2025
Interviews: Week of March 3, 2025
Selection/Recommendation: March 7, 2025
Finance Approval: March 17, 2025
Board Approval: March 24, 2025
A Pre-Propsal Meeting will be held:
February 19, 2025 2:00pm GRPS 900 Union Ave
C. Issuing Office
This RFP is issued by the GRPS Department of Facilities Management & Planning, hereinafter referred to as the issuing office. The Director of this department and point of contact for this Request for Qualifications and Fee Proposal is:
Dale Cammenga
Director of Design, Construction and Renovation
Grand Rapids Public Schools Service Building
900 Union NE
Grand Rapids, Michigan 49503
D. Contract Award
Contract award will be undertaken by GRPS with the Professional(s) whose qualifications and proposal(s) the issuing office determines to be in the District’s best interest. [C103-2015 Consultant Contract] will be the basis of this agreement with
[C203-2017 Scope of Cx Services].
Respondents must confirm their compliance with the terms of this agreement in their proposal. Any specific exceptions or requested modifications must also be noted in your response. Exceptions and/or modifications will be considered as part of the evaluation and GRPS will evaluate such modifications relative to its best interest and consistency with the project goals.
E. Submittal Requirements – Firm, Team and Approach
Submit Four (4) hard copies to address and person named above, and one electronic
PDF copy via email to Dale Cammenga at CammengaD@grps.org
Executive Summary – One [1] page maximum
Summarize your strong points and describe how your experience will benefit the
GRPS efforts to budget, schedule, and manage the listed projects.
Design Phase Begins:
Bid
Underway
Varies by Project
Construction: Varies by Project
Occupancy: Varies by Project
Business Organization - One [1] page maximum
State the full name and address of the organization and, if applicable, the branch office, consultants, or other subordinate elements that will provide or assist in providing the service.
Indicate whether you operate as an individual, partnership, or corporation; if as a corporation, include the state in which you are incorporated. State the names of the principals of your firm.
Firm Experience – Five [5] pages maximum
Provide examples of up to five similar projects completed by the firm for educational clients within the past ten (10) years.
Statement of the Problem and Summary of Approach – Three [3] pages maximum
State in succinct terms your understanding of the major issues of this project. Identify specifically how your firm will meet the project goals and GRPS expectations.
Briefly describe how you intend to address the main issues of the project.
Work Plan / Schedule – Three [3] pages maximum (per project proposed)
Include a time-related chart, show events, tasks, and decision points in your work plan, from selection through overall completion of the program. Discuss how your work will be coordinated and how you intend to interface with Grand Rapids Public
School District, the Construction Manager and the rest of the project team. Provide a review schedule between the A/E, CM, and Owner.
Manpower and Team - No page limit (per project proposed)
The firm must staff a project team with the qualifications and expertise necessary to undertake a project of this scope, ready to begin work immediately upon notice to proceed. Include the number of executive and professional personnel by skill and qualification that will be employed in the work. Describe their role in the project.
Identify key participants, including major consultants, with name, resumes, qualifications and relevant experience. You must indicate a percentage of time which each key participant will allocate to this project and coordinate this information with your fee proposal. Include a listing of their current project responsibilities and the dates that they will be available to begin work on this project.
Resumes with qualifications for key individuals must be provided. Include a brief description of three [3] major projects in which each individual has been instrumental (may be projects completed for other firms but be certain to identify the firm). Up to one page per individual.
Diversity and Inclusion Practice / Program – No page limit
Describe your firm’s efforts to promote participation of MBE/WBE/disadvantaged contractors as members of your project team. Share your firm’s Diversity and
Inclusion plan and indicate your methods to seek disadvantaged firm’s participation in the construction of our projects. Indicate the average percent participation of such firms in the 5 example projects presented in your proposal.
F. Submittal Requirements – Fee (separate sealed envelope – 3 hard copies)
You are requested to submit a Staffing and Fee excel document on the format provided for the scope of work described above for each individual project or group of projects proposed. Your fee proposal must also reflect and include detail for all expected reimbursable charges and the billable hourly rates for your team members assigned to our project. Be sure in include your fee percentage for Overhead & Profit on the first page where indicated. All other information will auto-populate from the following workbook tabs for staff and reimbursables. Input staff name, hourly rates, and projected hours per month where indicated on staffing tab. Input rates and units for reimbursables on construction support tab. Be sure to include rates / costs for insurance and bonding.
Any costs you expect to invoice to GRPS beyond your Fee (staff, GCs, support expenses, etc.) must be identified in cost workbook.
Firms are permitted to propose on any one or combination of any of the above projects. Please clearly indicate if a discount is available should your firm be selected for more than one project.
Your firm will be working closely with the design firma Construction Manager retained by GRPS. Close collaboration between your firm and the CM is expected on a weekly basis during Pre-construction your efforts will include weekly updated opinions of cost, project development schedule, constructability advice, and forecasting any supply chain or unusual lead time issues.
The submittal requirements are:
➢ Email and hand deliver your Fee proposal to:
Dale Cammenga, Director of Design, Construction, Renovation 900 Union NE Grand Rapids, MI 49503 CammengaD@grps.org
➢ Qualification submittals are due no later than February 27, 2025 at 11:00AM.
Your submittal should be prepared simply and economically, providing a straightforward comprehensive description of the professional’s ability to meet the requirements of the request. Submittals must be signed by an official authorized to bind the professional to its provisions.
Your submittal will be considered a contract document. Submittals must remain valid for a minimum of sixty [60] days.
mailto:Smarta@grps.org
H. Incurring Costs
GRPS is not liable for any cost incurred by the professional prior to issuance of a contract.
I. Required Forms:
1. Familial Disclosure Affidavit 1 page
2. Iran Disclosure Affidavit 1 page
3. Criminal Background Disclosure 1 page
4. Non-Collusive Affidavit 1 page
5. Debarrment & Suspension Certification 1 page 6 Detailed Proposal Form
J. Project Overview & Scope:
1. Overview and Objectives (attach A1) 2 pages
2. Scope of Services (attach A2) 5 pages
K. Project Schematic Design
1. Aberdeen narrative 90 pages
2. Aberdeen schematic design drawings 6 pages
3. Riverside schematic design drawings 67 pages
4. Ken O Sha narrative 4 pages
5. Ken O Sha schematic design layout 1 page
INSURANCE REQUIREMENTS
The firm must acquire and continuously maintain during the period in which the consultant is performing services pursuant to this Contract, and provide the GRPS with acceptable proof of the following type and amounts of insurance coverage:
1. Statutory Workers Compensation Insurance
Each Accident $ 1,000,000 Disease-Policy Limit $ 1,000,000 Disease-Each Employee $ 1,000,000
2. Comprehensive General Liability Insurance with separate limits of not less than $1,000,000 per accident coverage against bodily injury and $1,000,000 per accident coverage against property damage, or with a combined single limit against both bodily injury and property damage of not less than $5,000,000 per occurrence. This coverage shall include a contractual liability endorsement.
3. Comprehensive Owned and Non-Owned Automobile Liability Insurance with the same minimum limits of coverage as that required for the Comprehensive General Liability Insurance.
4. Professional Liability Insurance coverage with an annual aggregate limit of not less than $2,000,000.
The Grand Rapids Public School District and Plante Moran Realpoint, it’s Owner’s Representative, must be named as additional insured by endorsement to the Comprehensive General Liability Policy. Certificates of insurance evidencing that the consultant has secured all of the foregoing insurance must be provided to the Grand Rapids Public School District. A minimum of thirty [30] days notice to the GRPS prior to the cancellation of, or change in, any such insurance shall be endorsed on each policy and noted on each certificate.
Fair Employment Practices Agreement
Equal Opportunity [Affirmative Action Employer]
The Grand Rapids Public School District, as an Equal Opportunity/Affirmative Action Employer, complies with federal and state laws prohibiting discrimination, including Title IV and Title VII [with amendments] of the 1964 Civil Rights Act, Title IX of the Educational Amendment of 1972, Section 504 of the Rehabilitation Act of 1973, Veterans Readjustment Act of 1974 as amended 28 USSC 20-12 and the Americans With Disabilities Act of 1990. It is the policy of the School Board that no person, on the basis of race, sex, height, weight, color, religion, national origin, or ancestry, age, marital status, disability, or veteran status, shall be discriminated against in employment, educational programs and activities, or admission.
Inquiries or complaints should be addressed to Frederica Williams, 1331 Martin Luther King Jr. St. SE, PO Box 117, Grand Rapids, Michigan 49501- 0117.
SWORN STATEMENT OF FAMILIAL RELATIONSHIP
As required by Section 1267 of the Revised School Code – MCL 380.1267
STATE OF MICHIGAN
COUNTY OF
, being duly sworn, deposes and says:
That (The “Bidder”) has bid for an improvement to the following described project located in Kent County, Michigan, which is owned by the Grand Rapids Public Schools:
Project Name:
That the following is a statement of disclosure of any familial relationship that exists between the owner or any employee of the Bidder and any member of the Grand Rapids Public Schools Board of Education or Superintendent, as required pursuant to Section 1267 of the Revised School Code, as amended.
1. That there are no such familial relationships existing at this time.
OR
2. That a familial relationship exists between an owner employee of the Bidder who is the relationship of _____________________________________ , who is a member of the
Board, the Superintendent.
Deponent _________________________________________
Subscribed and sworn to before me this _____ day of _________________, 20_____
Acting in:
My commission expires: ________________
IRAN BUSINESS RELATIONSHIP
AFFIDAVIT
Effective April 1, 2013 all bids, proposals, and/or qualification statements received in the State of Michigan must comply with the “Iran Economic Sanctions Act”. The following certification is to be signed and included at time of submittal.
Certification
Pursuant to the Michigan Iran Economic Sanctions Act, 2012 P.A. 517, by submitting a bid, proposal or response, Respondent certifies, under civil penalty for false certification, that it is fully eligible to do so under law and that it is not an “Iran linked business” as the term is defined in the Act.
Signature Title
Company
Criminal Background Affidavit
The undersigned, the owner or authorized officer of the below-named Firm, pursuant to the criminal background compliance certification requirements of Grand Rapids Public Schools (the “School District”) hereby represents and warrants that the Firm has performed and/or will perform sufficient criminal background checks, including at a minimum, an Internet Criminal History Tool (“ICHAT”) check, for all of its owners, employees, agents, representatives, contractors and/or other personnel who will be on any School District premises to carry out the services contemplated by the Contract Documents. The Firm further hereby certifies that no owner, employee, agent, representative, contractor and/or other personnel of the Firm will be on any School District premises if they are a registered criminal sexual offender under the Sex Offenders Registration Act, Public Act 295 of 1994, or have been convicted of “Listed Offense” as defined under Section 722 of the Sex Offenders Registration Act, MCL 28.722.
The Firm further acknowledges that if it is found to have submitted a false certification or otherwise fails to comply with the requirements of this certification, the School District may immediately terminate the Contract.
FIRM:
Name of FIRM
By: _________________________
Its: _________________________
STATE OF ____________)
)ss.
COUNTY OF __________)
This instrument was acknowledged before me on the _____ day of _____, 20__, by ________________. , Notary Public ______________ County _________, My Commission Expires: _________
Acting in the County of: __________
NON-COLLUSIVE AFFIDAVIT
STATE OF MICHIGAN )
) SS
COUNTY OF ________)
______________________ , being duly sworn, deposes and says that:
1. The proposal has been arrived at by the consultant independently and has been submitted without collusion with, and without any agreement, understanding, or planned common course of action with, any other vendor of materials, supplies, equipment, or services described in the request for proposals, designed to limit independent bidding or competition; and,
2. The contents of the proposal have not been communicated by the consultant or its employees or agents to any person not an employee or agent of the consultant or its surety on any bond furnished with the proposal and will not be communicated to any such person prior to the official opening of the proposal.
Signature of Consultant
STATE OF ___________________)
)SS.
COUNTY OF __________ )
This instrument was acknowledged before me on the ______ day of _____, 20__, by
_________________, Notary Public
_________ County ____________, My Commission Expires: _________
Acting in the County of: __________
DEBARMENT AND SUSPENSION CERTIFICATION
The bidder, under penalty of perjury, certifies that, except as noted below, he/she or any other person associated therewith in the capacity of owner, partner, director, officer, manager:
• Is not currently under suspension, debarment, voluntary exclusion, or determination of ineligibility by any Federal agency;
• Has not been suspended, debarred, voluntarily excluded or determined ineligible by any Federal agency within the past 3 years;
• Does not have a proposed debarment pending; and
• Is not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or Local) in any matter involving fraud or official misconduct within the past 3 years.
If there are any exceptions to this certification, insert the exceptions in the following space:
Exceptions will not necessarily result in denial or award, but will be considered in determining bidder responsibility. For any exception noted above, indicate below to whom it applies, initiating agency, and dates of action.
Notes: Providing false information may result in criminal prosecution or administrative sanctions. The above certification is part of the Bid.
Signing this document on the signature portion thereof shall also constitute signature of this Certification.
Signature Title
Company Date
File details come from the government source that posted it. Updated .