Questions and Answers.pdf
PDF 53 KB Posted
- Attached to
- Air Compressors and Dryers Federal contract opportunity
- Solicitation number
- FA9101-20-Q-0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1730 Shop Air Compressor and Dryer Specification 21Jun2019-Attachment_Data-Sheet.pdf | ||
| Questions and Answers for FA9101-20-Q-0002-Service Air Procurement 4Dec2019.pdf | ||
| CAGI Fixed Speed Datasheet 10-11 rev8.pdf | ||
| Questions and Answers for FA9101-20-Q-0002-Service Air Procurement 3Dec2019.pdf | ||
| Questions and Answers for FA9101-20-Q-0002.pdf | ||
| Updated SOW.pdf | ||
| 1730 Shop Air Compressor and Dryer Specification 17Oct19.pdf | ||
| FA9101-20-Q-0002 Air Compressors & Dryers - Combined Synopsis.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
1. Can you please verify the temperatures?
The temperatures stated, (32oF to 115oF) were meant to reflect the extreme operating and non-operating conditions at the installation point. We will ventilate and/or heat this location prior to and during operation, therefore we agree 35oF to 105oF would be the more appropriate ambient operating temperatures.
2. Will a skid be sufficient for the solid base?
Intent is for the units to be mounted on one platform/skid of the vendors design for ease of factory testing, shipping, and installation with identical interface connection points. Skid mount is acceptable.
3. Can you provide more clarity on the regulating controller statement?
This is a legacy statement to indicate the Compressors and Dryers would have digital programmable controls to “regulate” their functions as described in greater detail elsewhere in this specification.
4. Can you provide additonal information on the rotary screw design and cast iron requirement?
Further explanation provide in revised SOW. Delete “with controllable slide valve for turn down flow control.”
5. Can you provide additional information on the Pressure Dew Point readout?
This is a requirement that feeds into Pressure Dew Point (PDP) control verses timed control.
6. How will we quote the representative capable of responding to repair service calls>
The quote shall include the location and capability statement for this service organization so we can assess meeting this requirement.
7. Will there be technicians to be trained by one (1) serviceman?
Correct
8. How many air tanks are in the system and what is the total volume?
The system as currently configured has one air receiver just downstream of the proposed installation point. Receiver capacity is approximately 150 ft3.