AFCEC_Fairchild_PBR_Overview_Slides_23_Oct_13_Final.pdf
PDF 545 KB Posted
- Attached to
- Fairchild AFB Performance Based Remediation Federal contract opportunity
- Solicitation number
- FA8903-14-R-0004
About this file
AFCEC Fairchild PBR Overview
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Air Force Civil Engineer Center I n t e g r i t y - S e r v i c e - E x c e l l e n c e
Kurt Lee
AFCEC/CZRY
23 October 2013
Air Force Performance Based
Remediation Overview
Overview
Air Force Restoration program was directed in FY11 to utilize the Performance Based Contracting methodology to accelerate clean up
To date, 27 Active Air Force PBRs worth $666.8M have been awarded
By the end of FY15, all CONUS Restoration programs will be covered under a PBR
Failure is not an option – we have to work together to ensure Milestones are met!
Working Together to Optimize Investment!
FY14 and FY15 PBRs
IRP and MMRP RC Planned vs. Actual
91 174
86 61 99 96 125
103 33
FY08 FY09 FY10 FY11 FY12 FY13 FY14
N um be r o f S ite s
IRP Planned MMRP Planned IRP Actual IRP Anticipated MMRP Actual MMRP Anticipated
I n t e g r i t y - S e r v i c e - E x c e l l e n c e 5
Active Air Force ERP RC Goals
509 403
61.5%
84%
91%
2013 2014 2015 2016 2017 2018 2019 2020 2021 Remaining Sites
Cu m ul at iv e
RC
S ite s
RC
S ite s b y
FY
RC Projection
Projected RC Cumulative Projected Total RC Target
90% 95%
491 Sites 323 Sites
Cumulative RC Progress for Combined IRP, MMRP and BD/DR
OSD Goal: Achieve 90% RC by 2018 and 95% by 2021
Total #Sites = 8143 (as of 20 June) 5
Program FY12 FY13 FY14 FY15 FY16 FY17 FY18
Total Program TOA $525.5 $529.2 $439.8 $413.4 $374.9 $381.2 $301.1
Total Program CTC ($M) $5,784.0 $5,214.0 $4,735.0 $4,310.2 $3,910.9 $3,590.0 $3,289.0
ERA Program Cost to Complete FY13-FY42
$0 $100,000,000 $200,000,000 $300,000,000 $400,000,000 $500,000,000
$600,000,000 EESOH MIS TOTAL REQUIREMENT BY YEAR - ABIDES 2013-
Oversight – the REAL Challenge!
FY FY+1 FY+2 FY+3 FY+4 FY+5 FY+6 FY+7 FY+8 FY+9 FY+10 FY+25 FY+30
Site 1 $2M $9M $9M $10M $2M $32M Site 2 $6M $9M $15M Site 3 $9M $10M $3M $2M $1M $1M $26M Site 4 $4M $9M $6M $5M $4M $1M $1M $30M Site 5 $10M $3M $3M $2M $18M Site 6 $3M $10M $3M $2M $.5M $.5M $19M Site 7 $2M $3M $5M Site 8 $2M $3M $5M Site 9 $2M $3M $3M $8M Site 10 $3M $4M $4M $11M Site 11 $2M $2M $2M $.5M $.5M $7M Site 12 $2M $9M $3M $3M $.5M $.5M $18M
TOA $34M $27M $29M $29M $20M $9M $6M $16M $10M $6M $M $4M $4M $193M
ASSESSMENT INVESTIGATION DECISION DOC CONSTRUCTION OPERATIONS MONITORING
FY FY+1 FY+2 FY+3 FY+4 FY+5 FY+6 FY+7 FY+8 FY+9 FY+10 FY+25 FY+30
PBC 1 $34M $27M $29M $29M $20M $9M $6M $16M $10M $6M $M $4M $4M $193M
PBC 2 $10M $12M $35M $10M $5M $2M $7M $8M $2M $M $5M $2M $6M $104M
PBC 3 $15M $25M $114M $88M $64M $26M $19M $7M $8M $2M $1M $3M $7M $379M
PBC 4 $32M $15M $5M $7M $3M $6M $8M $M $3M $5M $6M $2M $7M $99M
PBC 5 $20M $5M $5M $11M $5M $4M $24M $2M $6M $8M $2M $1M $2M $95M
PBC 6 $25M $3M $12M $10M $8M $9M $2M $1M $M $1M $3M $1.M $1.M $76M
PBC 7 $15M $32M $8M $9M $9M $7M $6M $5M $5M $5M $4M $3M $2M $110M
PBC 8 $5M $20M $7M $3M $6M $8M $M $3M $5M $6M $2M $7M $1M $73M
TOA $163M $153M $232M $177M $131M $74M $72M $48M $41M $33M $23M $24M $31M $1202M
A N
Y A
FB
ERA PROGRAM
Pre –negotiated locked-in CLINS Out-year
$9M $10M $2M
$2M $3M $2M $3M $3M
$38M +$4M
$33M +$6M ‐$1M
$28M ‐$6M ‐$9M +$9M ‐$10M +$10M ‐$2M +$2M $23M $11M $18M $6M $20M $4M $2M
ANY $38M $33M $28M $23M $11M $18M $6M $20M $4M $2M
+$4M +$6M ‐$1M ‐$6M ‐$9M +$9M ‐$10M +$10M ‐$2M +$2M
Level to FYDP TOAs
PBR Surveillance – the REAL Challenge!
PBR Philosophy
Winning offeror should have the expertise to have submitted an executable proposal
Some risk is transferred to the offeror and should be considered as part of the proposal
AF will not be receptive to cost and/or schedule changes from reasonably anticipated contingencies
Proposed schedule end date will be incorporated into contract as period of performance (POP) end date for SubCLIN.
Common Proposal Issues
Date discrepancies between MPS, IMS, and Technical Approach
IMS does not include sufficient time for requirement such as regulator reviews (30 days minimum, +20 days as needed) and AF technical reviews (30 days minimum)
Because proposed end date becomes SubCLIN POP, might not be float in schedule to overcome – could lead to a deficiency
Plan B will not achieve Objective in proposed timeframe (i.e., SC in 2019, Plan B will be implemented in 2018; if Plan B includes 3QTRs of clean sampling SC will not be achieved in 2019.)
Typical Early Execution Issues
Program Management Plan (PMP) Document Review Process Not implementing “Plan B” soon enough to meet
MPO
Success!
Air Force wants successful PBRs Cost – Stay within the cost you propose Schedule – Meet all timelines in proposals Performance – Keep your eye on the goals and let’s get there together!
Working Together to Optimize Investment!
File details come from the government source that posted it. Updated .