RFP FA8533-08-R-22907

72kW/90 kVA GENERATOR SET

Questions and Answers (Second Set) 13 April 2009

Question 1) CDRL A0004 reference is to SOW paragraph 3.1.3 and 3.7.1.1 for Contractors Progress Status and Management Report. SOW paragraph 3.1.3 references Program Schedule, not status reports. Referenced paragraph 3.7.1.1 does not exist in the current CDRL. What are the correct references for this CDRL in the current SOW?

Answer 1) The CDRL in question, referencing Data Item Description DI-MGMT-80227, section 5 entitled "Contract Reference" should read "SOW Para. 3.1.3" not "SOW Para. 3.1.3 and 3.7.1.1".

Question 2) SOW paragraph 3.7.2 lists DI-ALSS-81350/T as a requirement for CDRL C001. Search of the ASSIST database for this document shows no results. Is this reference correct and if so, where may we find this document?

Answer 2)In section SOW paragraph 3.7.2 states "DI-ALSS-81350/T LMI Summary worksheet for Hand Tools List; Standard Modified Hand Tools List"; the DID reference is a typo, it should read "DI-ALSS-81530/T LMI Summary worksheet for Hand Tools List; Standard Modified Hand Tools List". The correct DID reference, as noted on the provisioning CDRL, is DI-ALSS-81530/T; this DID is available on Assist.

Question 3) The revised SOW dated 8 OCT 2008, totaling 10 pages, ends with section 3.7.3. The previous SOW, dated 7 FEB 2007, included section 3.8 Quality Assurance Provisions, which included warranty requirements.

The pricing for CLIN 0006 on page 12 of 64 of the Solicitation still includes reference to the warranty requirement 3.8.2 which has been removed from the updated SOW. Would you please clarify for me as to whether the pricing for this CLIN and CLINs 1001, 2001, 3001, 4001 and 5001 are to include warranty costs or not. If so, could you please describe the expected warranty coverage?

Answer 3) Please see Amd 0005 dated 13 April 2009 to RFP FA8533-08-R-22907 which incorporates clause 52.246-17, WARRANTY OF SUPPLIES OF A NONCOMPLEX NATURE. A warranty shall be included with each production GPU, to include all production units applicable to CLINs 0006, 1001, 2001, 3001, 4001, and 5001.

Other files for this federal contract opportunity

Other files attached to 72kW Ground Power Unit, newest first.
File Type Posted
FA853308R22907______0005.doc DOC document
PD08WRGBGEA04_Amd_01.doc DOC document
FA853308R22907 QA 9 Mar 09.doc DOC document
FA853308R22907______0004.doc DOC document
DoD_5230 25_(export_controlled).pdf PDF
FA853308R22907______0003.doc DOC document
GPU Schedule to Offerors.xls XLS spreadsheet
SOW8Oct08.doc DOC document
72kW Memorandum to Offerors.pdf PDF
FA853308R22907______0002.pdf PDF
72KW Clarification.doc DOC document
GPU viewing.pdf PDF
Answers to offeror's questions.pdf PDF
FA853308R22907______0001.pdf PDF
Attch_1_FACTS_Sheet.doc DOC document
Attch_4_Transmittal_Ltr.doc DOC document
SOW1.pdf PDF
RFP.pdf PDF
PD08WRGBGBEA04.pdf PDF
Pkg AFMC158.pdf PDF
Exhibit D.pdf PDF
Gen Eng Notes.pdf PDF
Attch_2_Client_Ltr.doc DOC document
GPU Cost Volume to Offerors.xls XLS spreadsheet
Exhibit A.pdf PDF
Attch_5_Questionnaire_Performance.doc DOC document
Exhibit C.pdf PDF
Exhibit B.pdf PDF
EDL.pdf PDF
Attch_3_Tracker.doc DOC document
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .