ATTACHMENT_12_17G230005-1_SUPPLEMENTAL_FIRST_ARTICLE_GUIDANCE.pdf

PDF 54 KB Posted

Attached to
C-17 Globemaster III Ground Handling Cradle Federal contract opportunity
Solicitation number
FA8526-18-R-0027
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

Attachment 12

View the file

Other files for this federal contract opportunity

Other files attached to C-17 Globemaster III Ground Handling Cradle, newest first.
File Type Posted
FA852618R00270001.pdf PDF
Atch_1._Present_PastPerformance_FACTS_Sheet.docx DOCX document
Atch_2._Client_Authorization_Letter.docx DOCX document
Atch_4._Consent_Letter.docx DOCX document
Atch_3._Transmittal_Letter.docx DOCX document
ATTACHMENT_7_Form_158_FD2060-18-34899.pdf PDF
ATTACHMENT_9_IUID_CDRL_-_C-17_PSE_DD_FORM_1423-1.pdf PDF
ATTACHMENT_11_Bidder_Notice_on_PN_17G230005-1_Signed_JBS.pdf PDF
ATTACHMENT_10_CDRLs_A001,_A002,_A003_3_Aug_18.pdf PDF
ATTACHMENT_8_Form_DD1653_FD20601834899.doc DOC document
Atch_5._Cross_Reference_Matrix.docx DOCX document
FA852618R0027.pdf PDF
ATTACHMENT_13_MaintenancePlatformGFPModuleAttachment.xlsx XLSX spreadsheet
Atch_6_Past_Performance_Questionnaire.docx DOCX document
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUPPLEMENTAL FIRST ARTICLE GUIDANCE/REQUIREMENTS* :

NSN 1730-01-250-9737BA, P/N 17G230005-1

Revised: 29 Jan 2018

1) Complete waiver of First Article applies only to suppliers with successful past production and/or FAT of 17G230005-1 within the last 48 months. Waiver applies to actual producers of the item in question.

Prior pass-through vendors are not exempt, and are required to produce the item IAW standard definitions for same.

2) Failure to pass the ATP (DWG 17G236001) and/or pre-ATP tests contained/referenced in the TDP, shall be grounds for failure of First Article Testing.

3) Supplemental to the contractor First Article Test Plan (including schedule), one additional data item is required prior to testing:

a. Test Tooling Stress & Deflection Analysis Report incl. supporting BOM and "sketches" documenting contractor unique test tooling to be employed in testing cradle IAW ATP and contractor FATP.

(1) CDRL 17G230005-1 A002

(2) Delivery: In accordance with the contract schedule

(3) Approval: See CDRL

4) Items failing to pass FAT testing will be returned to/retained by the contractor pending disposition by the contractor.

NOTE: Any subsequent retest involving dimensional re-inspection, load tests as contained in the ATP or Form-Fit-Function Tests may entail testing at either the Contractor facility or at a Government facility (as appropriate), involving more thorough verification of compliance with all requirements, dependent upon the degree and nature of the judged non-compliance noted in the initial FAT attempt. Any such re-testing would be subject to contract negotiation.

5) The First Article test at the contractor facility will be witnessed by the Government Program Engineer, Program Manager, Contract Officer, QAR, and Boeing technical rep or combination thereof (some may waive attendance). At minimum, the QAR and Government Program Engineer will witness the contractor test.

* See related FIRST ARTICLE REQUIREMENTS document for subject NSN in/from PRPS dated 25 Jan 2018 (or subsequent) and related CDRLs and item TDP for balance of FA requirements/ conditions.

NOTE: This version supersedes prior version dated 2011/09/15.