Tooling_Pre-Proposal_Day_July_21_Questions.pdf

PDF 44 KB Posted

Attached to
B-2Tooling Move Federal contract opportunity
Solicitation number
FA8224-16-R-0054
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Tooling Pre-Proposal Conference July 21 Questions

View the file

Other files for this federal contract opportunity

Other files attached to B-2Tooling Move, newest first.
File Type Posted
Tooling_Pre-Proposal_Day_July_14_Questions.pdf PDF
B-2_Pre-Proposal_Conference_PowerPoint.pdf PDF
Registration_Form.xlsx XLSX spreadsheet
Freeport_end.PNG PNG image
Soliciation.pdf PDF
PWS.pdf PDF
GENERAL_INFORMATION.pdf PDF
QASP_B2_Tooling_Move_2.pdf PDF
Notice_of_Pre-Proposal_Day.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B-2 Tooling Move Pre-Proposal Conference July 21, Questions and Answers:

Will the contractor have to unload the vans when they reach Tooele?

o Tooele will have all the equipment to unload the vans, the contractor will not need to do it.

Will the Government stack and palletize the shelving?

o Yes, all shelving will be palletized by government workers.

Is there a part/tracking number to each item?

o Yes, there is an 1149 form attached to all of the equipment to help with inventory.

Trucks will be provided with a master copy of all the items that have been loaded on their trucks.

Is custom rigging needed?

o No, the rigging is pretty standard.

What does Tooele want moved first?

o Hill Air Force Base has negotiated with Tooele Army Depot that the larger items will be moved first so that there will be more space to accommodate the move.